POSITIVE RESULTS FROM SMELTER SCOPING
STUDY
PERTH, AUSTRALIA Mirabela Nickel Limited (TSX: MNB, ASX: MBN)
is pleased to announce that a scoping study for a nickel sulphide smelter at its
Santa Rita project has returned positive results with preliminary cost
estimates as follows:
Capital expenditure – US$254m
Operating cost – US$111/t of concentrate
As a
result of these encouraging results, the Company is proceeding with a full feasibility
study to build a smelter at Santa Rita. A smelter would provide the
following major benefits:
-
Substantial increase in nickel payability
-
Increase in payability for credits for
Cu, Co, Au and PGEs.
-
Savings on transport costs
-
Optimization of mine, concentrator and
smelter circuit
“The
scoping study indicates that a smelter at Santa Rita could be an important
value proposition for the Company,” said Managing Director Nick
Poll. “It’s all about making the most of the economies of
scale that are available to us and Santa Rita now has the third largest
open-cut, nickel sulphide mining reserve in the world. A smelter would
allow the Company to capture the revenue and operating benefits of downstream
processing, whilst reducing transport costs. We believe that the demand
for nickel matte, the smelter product, is even stronger than the demand for
nickel concentrate, so a smelter would also strengthen the Company’s
strategic position in the nickel market,” he said.
“At
this stage, we are working through the options and implications of a smelter in
detail. We remain focused on producing nickel concentrate, starting in
2009, from the currently planned operation for at least the first few
years,” said Mr Poll.
The
results of the smelter study coincide with today’s announcement of new drilling results that extend
mineralization about 120m down dip of the recently announced open-cut mining
reserve, with composite intersections up to 135m grading 0.83% nickel located
in the Southern high grade zone of the Santa Rita deposit. The occurrence of such
thick mineralization is very encouraging and is expected to increase the
open-pit mining reserve.
The
positive smelter study has come on the back of several announcements in the
past month, including the first mining reserve at Santa Rita, an updated CAPEX for
the planned increase in capacity of the concentrator to 4.6mtpa and the mandating
of debt financing.
Study details
WorleyParsens,
a leading specialist in pyrometallurgical processing, completed the scoping
study using the following Mirabela assumptions:
·
230ktpa concentrate throughput rate
·
12% nickel concentrate grade
·
25,000t of nickel a year output
The
above assumptions are consistent with an expected 6.0mtpa production rate from
the Santa Rita mine.
Whilst
the current planned capacity of Santa Rita is 4.6mtpa for 18,500t of nickel
output, it is expected that this will be increased to 6mtpa for 25,000t of
nickel within the first few years of operation due to continued growth of the
resource.
The
scoping study costs are estimated to within +/- 50% and used a Brazilian Real
exchange rate of R$2.05 to the US dollar.
WorleyParsons
has been commissioned to proceed with the feasibility study, a team has been
appointed and work is underway. The project will be split into two
stages. Stage one is expected to cover preliminary test work,
thermodynamic modelling, conceptual engineering and estimation of capital cost
to within +/- 30% for a cost of about A$2m. Stage two will cover more
detailed engineering and estimation of capital cost to within +/- 15%. It
is expected Stage one will be completed in Q3 2008 and Stage two in Q3 2009.
It is expected that a smelter would take about 2 years to construct.
Background
Mirabela Nickel
is listed on the Australian and Toronto
stock exchanges. With a proven and probable mining reserve of 84mt at
0.61% Ni and growing, Santa Rita is the world’s largest greenfields
nickel sulphide discovery in the last 12 years and the third largest open-cut
nickel sulphide mining reserve. Exploration is continuing to increase the
in-pit reserves and determine underground mining potential below 500m deep, as
mineralization appears to continue well below current drilling.
Construction of a
nickel sulphide concentrator commenced in November 2007 and is progressing
well. The plant is expected to produce 18,500t a year of nickel in a sulphide
concentrate from one open-cut mine starting from mid 2009. At this rate
of production the project is expected to have a mine life of at least 18
years. Studies are underway to increase nickel production to 25,000t a
year.
Nick Poll
Managing Director
Contact details
Australia contact: Toronto contact (media):
Nick Poll,
Managing Director Eric Tang, Porter Novelli
Telephone: +61 8
9324 1177 Telephone:
+1 (416) 422-7200
nickp@mirabela.com.au eric.tang@porternovelli.com
Australia contact (media):
Caroline
de Mori, Purple Communications
Telephone:
+61 8 9485 1254
cdemori@purplecom.com.au
Caution
Regarding Forward Looking Statements: There
can be no assurance that an expanded mineral resource or reserve will be
established at the Santa Rita Project. The forward-looking statements
made in this news release are based on assumptions and judgments of management
regarding future events and results. Such forward-looking statements, including
but not limited to those with respect to the construction and development of
a 18,500 tonnes per year and subsequently a 25,000 tonnes per
year nickel sulphide concentrator and a nickel smelter at the Santa
Rita Project and the required capital expenditures and estimated future
production and operating cash costs involve known and unknown risks,
uncertainties, and other factors which may cause the actual results, performance
or achievements of the Company to be materially different from any anticipated
future results, performance or achievements expressed or implied by such
forward-looking statements. Such factors include, among others, the actual
market prices of nickel, the actual results of current exploration, the
actual results of future mining, processing and development activities, changes
in project parameters as plans continue to be evaluated, as well as
those other factors disclosed in the Company's filed documents.
www.mirabela.com.au
***
The new Spam Act commenced on 10 April 2004. This Act is aimed at
reducing the amount of unauthorised emails you receive. You have been
receiving e-mails containing information and news releases from us on behalf of
our clients because you are an important contact of Purple Communications, a
boutique stakeholder communications consultancy. If you do not wish
to receive such emails from Purple, please click mailto: purple@purplecom.com.au
subject=UNSUBSCRIBE or reply to this email and put UNSUBSCRIBE in the subject
line and we will not email you again.
If you do not reply, we will continue sending you relevant news
and information via email. However, all future emails will allow you to
unsubscribe.
Issued by
Purple
Communications
Level 3, 28 Kings Park Road, WEST PERTH WA 6005
Ph: 08 9485
1254 Fax: 08 6263 0455
purple@purplecom.com.au