Canadian Zinc Corp

Published : June 05th, 2009

Prairie Creek Metallurgical Results

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Click for moreClick for more

CANADIAN ZINC CORPORATION
Suite 1710 - 650 West Georgia Street, Vancouver, BC, V6B 4N9

Tel: (604) 688-2001
Fax: (604) 688-2043

Toll free: 1-866-688-2001

CANADIAN ZINC REPORTS POSITIVE METALLURGICAL TEST RESULTS FOR PRAIRIE CREEK MINE

Vancouver, British Columbia, June 4, 2009 - Canadian Zinc Corporation (TSX: CZN; OTCBB: CZICF) reports recent positive results from ongoing (Phase 5) metallurgical testing relating to its planned Prairie Creek zinc/lead/silver mine in the Northwest Territories of Canada.

In late 2008 a 530 kg representative rock sample of mineralized vein material was extracted from multiple headings within the underground workings at the Prairie Creek Mine.  The sample was composited at SGS Lakefield Research for large scale locked cycle testing with the objective of producing representative concentrates, tailings and process effluents using the actual proposed process flow sheet for the Prairie Creek Mine. This flow sheet has been presented in the Project Description Report, dated May 2008, submitted as part of the applications for operating permits, which are presently the subject of Environmental Assessment being carried out by the Mackenzie Valley Environmental Impact Review Board ("MVEIRB").

 

In addition, a large volume of representative mine water was also collected at that time and shipped to SGS Lakefield for use in the same locked cycle tests to better simulate actual site operating conditions.

 

Metallurgical Test Results:

 

Heavy Liquid Separation:

 

Previous metallurgical studies incorporated a Heavy Liquid Separation ("HLS") process applied to the Run of Mine (ROM) feed to optimize the existing mill at the Prairie Creek Mine by enhancing the metal grade entering into the flotation process, and thus reducing the amount of waste being needlessly processed.  HLS is used in the laboratory to simulate the process of Dense Media Separation ("DMS") which will be undertaken on a commercial scale.

 

A composite ROM sample was stage crushed to a nominal � inch size.  The composite was then screened at 14 mesh with the minus � inch and plus 14 mesh processed through a HLS plant.  This resulted in 41% of the ROM composite being rejected as waste with a loss of only 2.5% total lead and 4.4% total zinc metal values.  Waste rejection from the previous DMS studies averaged ~30%.  The higher number in this recent case is a significant improvement but may relate to the inherent variability of dilution in the mining of mineralized vein structures to collect the bulk sample.  The HLS test result is consistent with the previous studies in that it demonstrated that a significant increase in mill throughput and grade can be achieved with a minimal loss of economic metals of less than 5%.

 

The results of the HLS (DMS) test work are presented in the following table:

 

Product

Weight

Assays %

g/t

% Distribution

 

%

PbT

ZnT

Pbox

Znox

Ag

PbT

ZnT

Pbox

Znox

Ag

Minus1/2" +14m HLS Sink

31.9

28.3

26.9

6.44

4.48

453

73.27

57.13

49.95

42.04

59.52

Minus 14m

27.1

11.0

21.3

6.81

5.64

339

24.23

38.49

44.95

45.03

37.90

Minus1/2" +14m HLS Float

41.0

0.75

1.6

0.51

1.07

15.2

2.50

4.38

5.10

12.93

2.57

ROM comp head (calc)

100

12.31

15.00

4.11

3.40

242

100

100

100

100

100

 

 

 

 

 

 

 

 

 

 

 

 

Mill Feed after HLS

59.0

20.35

24.33

6.61

5.01

401

97.5

95.6

94.9

87.1

97.4

T= total sulphide and oxide

 

The HLS enhanced plant mill feed was then combined, mixed, and crushed to 10 mesh in preparation for the locked cycle flotation test work.

 

Locked Cycle Flotation Tests:

 

After crushing and grinding the HLS enhanced mill feed was delivered into a locked cycle flotation test where concentrates of lead sulphide, zinc sulphide and lead oxide were generated.  No separate zinc oxide flotation was completed since previous metallurgical studies indicated low concentrate grades and low recoveries for zinc oxide.

 

The locked cycle tests were designed to produce concentrates, tailings and effluent for engineering, marketing and environmental studies and in using active means. The reagent scheme used in the locked cycle tests was developed from previous studies and slightly modified for use with the actual mine water.  Small scale batch tests were run prior to the locked cycle tests with the objective of optimizing selectivity between lead and zinc.

 

Three large-scale locked cycle tests were performed.

 

The test results indicate that the overall grade of the blended lead sulphide / oxide concentrate assayed 67% lead, with a 82% recovery of total lead in the plant feed, and the zinc sulphide graded 58% Zn with a 74% recovery of the total zinc in the plant feed. An average of 92.7% of the total silver values in the plant feed was recovered within the lead and zinc concentrates.

 

"The recent metallurgical tests generated very satisfactory simulated results of anticipated actual operations in the production mineral concentrates at the Prairie Creek Mine," said Alan Taylor, Chief Operating Officer of Canadian Zinc.

 

"The Phase 5 test results showed concentrate grades and recoveries similar to results of previous locked cycle tests, allowing for variations within the individual bulk samples, and confirmed anticipated concentrate grades and recoveries under simulated actual proposed milling operations and using representative actual mine water."  Mr. Taylor added.

 

The generated by-products of HLS reject and flotation tailings from the Phase 5 metallurgical tests are currently undergoing further study and characterization by Golder Paste Technology Ltd., of Sudbury, Ontario to assist in developing a new plan for the permanent disposal of paste tailings underground.  Similarly CEMI Labs of Burnaby are further testing various water treatment options on the process effluent generated from this phase of metallurgical testing to ensure a sound treatment scheme during the operation of the Prairie Creek mine.  Further study directed towards reducing the amount of certain deleterious elements within the concentrates, (eg. mercury, antimony and arsenic) to enhance payability, is also being examined.

 

The results of the test work will be used in pursuing marketing and treatment alternatives for the Prairie Creek concentrates and will also be incorporated into the Developers Assessment Report to be submitted to the Mackenzie Valley Environmental Impact Review Board later this year once Final Terms of Reference for the environmental assessment are issued.  The MVEIRB issued Draft Terms of Reference for comments to be submitted by June 12, 2009 and finalization shortly thereafter.

 

Proposed Operations at Prairie Creek Mine:

 

The proposed new operation at Prairie Creek utilizes the existing infrastructure and facilities that were built in the 1980s and which will be upgraded and enhanced to meet current-day environmental standards. 

 

The Mill, which is already constructed on site but never operated, will process 600-1,000 tonnes per day.  Ore will be crushed to a gravel-size and passed through a new DMS plant.  The lighter, uneconomic "gangue" minerals will create a waste rock aggregate.  The more dense material will be processed further by grinding and flotation to produce concentrates of lead sulphide, zinc sulphide and lead oxide.  No hazardous chemicals will be used in the process.

 

The existing large pond facility, originally intended in 1980 for tailings disposal, will be reconfigured, relined and recertified to form a two-celled Water Storage Pond.

 

Underground Tailings Disposal:

 

In recognition of concerns about tailings disposal, and following extensive research, Canadian Zinc has developed a new tailings management plan. The Company proposes to place all mill tailings permanently underground as paste backfill, together with approximately three quarters of the DMS waste rock and a cement binder.  The mix will solidify after placement into a form of concrete.   In this manner all mill flotation tailings will be backfilled into the voids in the underground mine with the waste rock aggregate.  The flotation tailings are expected to be non-acid generating with low sulphide content and excess buffering capacity.

 

The benefits of this new tailings management plan are that all tailings will be placed underground and there will be no permanent disposal of tailings on surface.

 

Qualified Person:

 

Alan Taylor, P.Geo., Chief Operating Officer & Vice President Exploration and a Director of Canadian Zinc Corporation, is the Company's non-independent Qualified Person for the purposes of NI 43-101 and has approved this press release.

The Prairie Creek Mine:

A major underground tunneling and Diamond drilling program led to the completion, in October 2007, of a Technical Report (the "Report") to National Instrument ("NI") 43-101 standards, which estimates that the Prairie Creek Property hosts total Measured and Indicated Resources of 5,840,329 tonnes grading 10.71% zinc, 9.90% lead, 161.12 grams silver per tonne and 0.326% copper. In addition, the Report confirms a large Inferred Resource of 5,541,576 tonnes grading 13.53% zinc, 11.43% lead, 215 grams per tonne silver and 0.514% copper and additional exploration potential.  The Measured and Indicated Resource is capable of supporting a mine life in excess of ten years at the planned 1,000 tonnes per day mining rate.

 

Cautionary Statement - Forward Looking Information

This press release contains certain forward-looking information, including, among other things, the expected completion of acquisitions and the advancement of mineral properties.  This forward looking information includes, or may be based upon, estimates, forecasts, and statements as to management's expectations with respect to, among other things, the completion of transactions, the issue of permits, the size and quality of mineral resources, future trends for the company, progress in development of mineral properties, future production and sales volumes, capital costs, mine production costs, demand and market outlook for metals, future metal prices and treatment and refining charges, the outcome of legal proceedings, the timing of exploration, development and mining activities, acquisition of shares in other companies and the financial results of the company.  There can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. The Company does not currently hold a permit for the operation of the Prairie Creek Mine.  Mineral resources that are not mineral reserves do not have demonstrated economic viability.  Inferred mineral resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves.  There is no certainty that mineral resources will be converted into mineral reserves.

 

Cautionary Note to United States Investors

The United States Securities and Exchange Commission ("SEC") permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce.  We use certain terms in this press release, such as "measured," "indicated," and "inferred" "resources," which the SEC guidelines prohibit U.S. registered companies from including in their filings with the SEC.

For further information contact:

John F. Kearney

Chairman

(416) 362- 6686

Suite 700, 220 Bay Street
Toronto, Ontario M5J 2W4

Alan Taylor

Vice President Exploration & Chief Operating Officer

(604) 688- 2001

Suite 1710 - 650 West Georgia Street , Vancouver, BC   V6B 4N9

Tel: (604) 688-2001      Fax: (604) 688-2043

Tollfree:1-866-688-2001

A more extensive description of the Company's activities is available on the Company's web site at  www.canadianzinc.com

E-mail: invest@canadianzinc.com   Website:  www.canadianzinc.com


Click for moreClick for moreClick for moreClick for more<
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Canadian Zinc Corp

DEVELOPMENT STAGE
CODE : CZN.TO
ISIN : CA1368021053
CUSIP : 136802-10-5
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Canadian Zinc is a zinc and silver development stage company based in Canada.

Canadian Zinc develops zinc, silver and gold in Fiji.

Its main asset in development is TUVATU in Fiji and its main exploration property is PRAIRIE CREEK in Canada.

Canadian Zinc is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 30.6 millions as of today (US$ 23.2 millions, € 20.1 millions).

Its stock quote reached its highest recent level on February 20, 2004 at CA$ 2.04, and its lowest recent point on December 04, 2015 at CA$ 0.06.

Canadian Zinc has 265 920 016 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Canadian Zinc Corp
2007 Annual Report
Financings of Canadian Zinc Corp
7/7/2016Announces Closing of $10,200,000 FInancing
8/1/2014CZN Closes $15.8 Million Bought Deal Financing
8/2/2013ANNOUNCES C$4 MILLION BOUGHT DEAL FLOW-THROUGH PRIVATE PLAC...
Nominations of Canadian Zinc Corp
6/13/2013Reports on Election of Directors at Annual General Meeting o...
Financials of Canadian Zinc Corp
5/17/2016Reports Financial Results for Q1 2016 and Operations Update
3/31/2016CZN Reports Financial Results for 2015
11/13/2015Reports Results for Third Quarter 2015
8/14/2015Reports Financial Results for Second Quarter 2015
3/31/2015Reports Financial Results for Fiscal 2014
11/15/2013CZN Reports Financial Results for Third Quarter 2013
8/13/2013Reports Financial Results for Second Quarter 2013
5/13/2013Reports Financial Results for First Quarter 2013
3/20/2013REPORTS FINANCIAL RESULTS FOR FISCAL 2012
8/10/2012Reports Financial Results for Second Quarter 2012
3/16/2012Reports Financial Results for Fiscal 2011
3/17/2011Reports Financial Results for Fiscal 2010
11/17/20092009 Third Quarter Results
8/17/2009Reports Second Quarter 2009 Results
5/16/20092009 First Quarter Results
8/8/2008Reports Second Quarter 2008 Results
5/15/2008First Quarter Results
Project news of Canadian Zinc Corp
4/19/2017Drilling Extends Mineralization at Lemarchant, NFLD
9/15/2016CZN Modifies 2016 Preliminary Feasibility Study
1/21/2014Engineering and Procurement Contracts awarded for Prairie Cr...
12/12/2013Assay Results of 2013 Drill Program at South Tally Pond
12/9/2013(Prairie Creek)Assay Results of 2013 Drill Program at Prairie Creek
9/18/2013(Prairie Creek)Granted Water Licence for Prairie Creek Mine
6/21/2013(Prairie Creek)CZN RECEIVES PERMITS FOR OPERATION OF PRAIRIE CREEK MINE
3/25/2013(Prairie Creek)RECEIVES PROPOSED WATER QUALITY CONDITIONS IN DRAFT WATER LI...
3/18/2013(Prairie Creek)Receives Draft Water Licence and Permits for Operation of Pr...
1/15/2013to Drill South Tally Pond Project, Newfoundland
1/8/2013(Prairie Creek)oration: Permitting Progress for Prairie Creek Mine
8/28/2012(Prairie Creek)and Government of Northwest Territories Advance Co-operation...
6/14/2012(Prairie Creek)oration: Minister Confirms Environmental Impact Review Not R...
5/15/2012(Prairie Creek)oration: Additional Permits Approved for Prairie Creek Mine ...
10/3/2011(Prairie Creek)Reports Success With Prairie Creek Exploration Drilling
9/26/2011(Prairie Creek)oration: Environmental Assessment of Prairie Creek Mine Ente...
8/22/2011(Prairie Creek)and Government of the Northwest Territories Sign Socio-Econo...
6/19/2011(Prairie Creek)and Liidlii Kue First Nation Sign Impact and Benefits Agreem...
6/8/2011(Prairie Creek)oration: Exploration Drill Program Commences at Prairie Cree...
2/28/2011(Prairie Creek)oration: Prairie Creek Mine Feasibility Study Commissioned
2/2/2011(Prairie Creek)CZN Obtains Permit Extension
1/24/2011(Prairie Creek)CZN Signs Agreement with NDDB
1/21/2011(Prairie Creek)and Nahanni Butte Dene Band Sign Impact and Benefit Agreemen...
9/2/2009(Tuvatu)Diamond Drilling Commences at Tuvatu
7/21/2009(Prairie Creek)Federal Minister Visits Prairie Creek Mine
6/5/2009(Prairie Creek)Prairie Creek Metallurgical Results
5/20/2009(Tuvatu)Tuvatu gold project option
8/21/2008Permitting Update
7/22/2008(Prairie Creek)Prairie Creek Permitting Update
6/11/2008(Prairie Creek)Submits Permit Applications for Production at the Prairie Cr...
Corporate news of Canadian Zinc Corp
8/10/2017Reports Financial Results for Q2 and Provides Project Update...
7/15/2016DEH CHO DRUM - July 14, 2016 Public voices thoughts on road
7/7/2016JULY 7, 2016: CANADIAN ZINC ANNOUNCES CLOSING OF $10,200,000...
6/29/2016JUNE 29, 2016: CANADIAN ZINC ANNOUNCES FILING OF FINAL PROSP...
6/21/2016JUNE 21, 2016: CANADIAN ZINC REPORTS ON ANNUAL GENERAL MEETI...
6/16/2016JUNE 16, 2016: CANADIAN ZINC ANNOUNCES C$8.0 MILLION UNDERWR...
6/16/2016JUNE 16, 2016: CANADIAN ZINC PRICES $8-MILLION OVERNIGHT OFF...
6/15/2016JUNE 15, 2016: CANADIAN ZINC ANNOUNCES PUBLIC EQUITY OFFERIN...
5/30/2016Minco Press Release First Quarter 2016 Financial Results
5/27/20162016 First Quarter Managements Discussion and Analysis
5/24/2016MAY 24, 2016: CANADIAN ZINC ANNOUNCES NEW NOMINEES TO BOARD ...
1/25/2016JANUARY 25, 2016: UPDATE ON RESEARCH PROGRAM TO INVESTIGATE ...
1/25/2016Canadian Zinc provides update on research program to investi...
12/2/2015DECEMBER 2, 2015: RESEARCH FUNDING AWARDED TO CANADIAN ZINC ...
12/2/2015Research Funding awarded to Canadian Zinc to investigate cen...
10/24/2015Sandstorm Gold Provides Asset Updates
10/23/2015Sandstorm Gold Provides Asset Updates
9/17/2015SEPTEMBER 17, 2015: MINERAL RESOURCES INCREASE AT PRAIRIE CR...
9/17/2015Canadian Zinc Corporation : Mineral Resources Increase at Pr...
8/14/2015AUGUST 14, 2015: CANADIAN ZINC REPORTS FINANCIAL RESULTS FOR...
8/14/2015Canadian Zinc Reports Financial Results for Second Quarter 2...
8/11/2015AUGUST 11, 2015: UNDERGROUND DRILL PROGRAM AT PRAIRIE CREEK ...
8/11/2015Canadian Zinc Corporation: Underground Drill Program at Prai...
3/31/2015MARCH 31, 2015: CANADIAN ZINC REPORTS FINANCIAL RESULTS FOR ...
3/31/2015Canadian Zinc Reports Financial Results for Fiscal 2014
3/26/2015MARCH 26, 2015: NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK...
3/26/2015(Prairie Creek)oration: New Mineral Resource Update at Prairie Creek Mine
1/29/20142014 Winter Drill Program Commences at South Tally Pond, NFL...
10/31/2013Drilling Extends Massive Sulphide Mineralization at Lemarcha...
10/31/2013oration: Drilling Extends Massive Sulphide Mineralization at...
9/16/2013Drill Program Underway for South Tally Pond, Newfoundland
9/12/2013and Messina Minerals Announce Agreement on Proposed Acquisit...
9/5/2013(Prairie Creek)CZN Receives Permits from Parks Canada for Prairie Creek Min...
9/4/2013(Prairie Creek)Commencing New Drill Program at Prairie Creek
8/20/2013Announces Closing of C$4 Million Bought Deal Flow-Through Pr...
8/1/2013announces C$4 million bought deal flow-through private place...
7/15/2013OtcbbJournal.com Sheds Light on Micro-Cap Companies Under th...
7/8/2013oration: Water Board Completes Regulatory Process; Water Lic...
5/31/2013Raises US$10.0 Million
5/10/2013oration: Annual General Meeting and Adoption of Advance Noti...
4/17/2013Completes Winter Drill Program at South Tally Pond
1/29/2013(Prairie Creek)First Operating Permit Received For Prairie Creek Mine:
1/25/2013CZN Submits Final Responses To Water Board Ahead Of Public H...
1/22/2013Submits Final Responses to Water Board Ahead of Public Heari...
1/15/2013to Drill Lemarchant Massive Sulphide Deposit at South Tally ...
10/31/2012Visit Canadian Zinc Booth # 418 Hard Assets San Francisco
9/24/2012Acquires Paragon Minerals Corporation
7/31/2012Announces Merger and Private Placement With Paragon Minerals...
6/27/2012(Prairie Creek)Reports Results of Prairie Creek Preliminary Feasibility Stu...
3/5/2012and Parks Canada Sign Renewed Memorandum of Understanding
2/29/2012Reports Significant Assay Results from Final Holes of 2011 D...
2/10/2012(Prairie Creek)Closes $4 Million Second Tranche of Zhongrun Private Placeme...
1/6/2012Announces the Closing of $5.1 Million Bought Deal Public Off...
12/30/2011Announces Closing of: $2.5 Million Private Placement of Flow...
12/9/2011Receives Environmental Approval
8/29/2011Federal Government Provides $3 Million Funding to Assist in ...
6/28/2011oration: Environmental Assessment Hearings Completed
3/26/2010Developers Assessment Report Filed
9/30/2009Vatukoula Finance - Operations Update
6/24/2009Gold Production Up at Vatukoula Mine
6/12/2009Vatukoula Approves Share Purchase
5/27/2009Normal Course Issuer Bid
2/24/20092009 Convention - Prospectors & Developers Association of Ca...
11/18/2008SULPHIDE VENT COMPLEX/FEEDER ZONE IDENTIFIED AT THE NORTH LE...
11/4/2008Memorandum of Understanding Signed With Nahanni Butte Dene B...
8/1/2008Memorandum Of Understanding Signed With Parks Canada
4/1/20082007 Year End Results
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CZN.TO)FRANKFURT (SRS.F)
0.115+4.55%0.017-5.56%
TORONTO
CA$ 0.115
09/10 16:58 0.010
4.55%
Prev close Open
0.110 0.110
Low High
0.110 0.115
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.115 -%
Volume 1 month var.
122,370 -%
24hGold TrendPower© : 11
Produces
Develops Gold
Explores for Copper - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 10/18/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :