Preliminary economic assessment for Long Canyon Project generates 64% IRR

09-34

 

Fronteer Development Group Inc. (FRG - TSX/NYSE Amex) is pleased to announce the completion of Long Canyon's first Preliminary Economic Assessment (PEA). The PEA is based on the project's March 2009 resource estimate and does not include the approximately 30,000 metres of subsequent drilling completed this year.  Long Canyon's initial PEA illustrates that the project is viable in today's cost environment and has a solid economic foundation to build upon.

 

The study, prepared by Mine Development Associates (MDA) of Reno, Nevada, and reviewed by AMEC Americas Limited, is based on an Indicated Mineral Resource of 4.8 million tonnes grading 2.4 g/t gold (363,000 gold ounces) and an Inferred Mineral Resource of 8.8 million tonnes grading 1.6 g/t gold (459,000 gold ounces) at a cutoff grade of 0.3 g/t gold. The PEA supports a financially robust open-pit, run-of-mine (ROM), heap-leach operation. At a 5% discount rate, and US$800/oz gold price, the project's pre-tax net present value (NPV) is US$145 million with a pre-tax internal rate of return (IRR) of 64% on an unleveraged 100% equity basis, and a pay-back period of 1.3 years.  

 

"This PEA confirms our view that Long Canyon is a straightforward project amenable to conventional, low-cost mining and extraction methods, the simplicity of which could shorten our lead time to production," says Troy Fierro, Fronteer Chief Operating Officer.  "In a short period of time, this asset has become a viable project, with mineralization open in every direction."

 

All dollar amounts in this release are stated in US currency. The disclosure set forth below is derived from the PEA unless otherwise expressly noted.

PEA highlights

Total gold produced

565,000 ounces

Average gold grade

2.15 g/t

Average annual gold production

93,000 ounces

Peak annual production

132,000 ounces

Life of mine

6 years

IRR (pre-tax)

64%

NPV (pre-tax)

$145 million

Discount rate

 5%

Pay-back period

1.3 years

Net cumulative cash flow (pre-tax)

$181 million

Direct cash costs

$351/oz

Initial capital expenditures including mining pre-strip, equipment, process, infrastructure & buildings, owners and miscellaneous costs

$66 million

 

Metallurgical recovery rate

87%

Long-term gold price

$800/oz

Note: This PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves at this time and as such there is no certainty that the preliminary assessment and economics set forth in the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. 

In management's view, such favourable economics at this early stage of project development provide a strong incentive for continued exploration, resource expansion and aggressive development. The results of this year's exploration/development program will be incorporated into an updated resource estimate in Q1 2010, followed by a revised economic analysis.

 

Fronteer believes there are excellent opportunities to refine various project elements and improve the economics through cost reduction and optimization, as outlined in the PEA. 


Project Description

The Long Canyon property is controlled by a joint venture, of which Fronteer (51%) is majority owner and operator.  Fronteer also has a 3% net smelter return (NSR) royalty on gold ounces produced from mineral lands that it contributed to the joint venture.  Approximately 84% of the ounces produced in the PEA model are attributable to this Fronteer NSR royalty. 

 

The construction phase of the Long Canyon Project is anticipated to take approximately one year. Processing facilities will be located near the leach pad.  Most of the buildings, including maintenance facilities, office and warehouse, would also be located at the mine site.


MINING PLAN

The PEA considers development of the Long Canyon project as an open-pit mine and ROM heap-leach operation. The pit is developed in five phases designed to provide sufficient ore for leaching and exploitation of Whittle pit shells that maximize the NPV of the deposit. Material grading better than the internal cut-off grade of 0.22 g/t gold was considered for open-pit mining.  

 

The forecast mine life is six years, during which time 9.4 million tonnes of ore will be mined and placed on the leach pad and 81.3 million tonnes of waste will be trucked to a waste dump. Throughout the life-of-mine, an estimated 565,000 ounces are produced at an average grade of 2.15 g/t gold. Better than average grades and more than 100,000 ounces per year are recovered in years 1, 2 and 5, with peak production of 131,000 and 132,000 ounces per year in years 2 and 5.

 

All mineralized material classified as Indicated and Inferred Mineral Resources was considered in the optimization and mine plan.


Metallurgy and Processing

The metallurgical component of the PEA was supervised by G.L. Simmons and supported by work carried out by McClelland Laboratories in Nevada. Gold production was estimated based on ultimate recovery and lagged recovery on an annual basis. Ultimate recoveries used are 88% and 80% for material grading above and below 1.25 g/t gold, respectively.  Total gold recovery from the leach pads averaged 87% during the life-of-mine.


Infrastructure

The PEA outlines the project's infrastructure and building requirements, which will include a single-use leach pad, carbon columns and electrowinning circuits, water wells, a waste-rock dump, access and haul roads, office buildings, shop & warehouse, and explosives magazine.  A 69 KV power transmission line must also be built connecting the mine site to existing power north of the mine. 


CAPITAL COSTS

The initial project capital costs of the Long Canyon project are estimated to be $66.0 million, primarily based on mining equipment and infrastructure. Sustaining capital through the life of mine would be an additional $6.0 million, which would be derived from cash flow and primarily (~75%) used for leach-pad expansions.


OPERATING COSTS

The following life-of-mine costs are expected for the operating phase of the project:

Items

Cost per tonne processed

Cost per ounce

Mining cost

$15.58

$259.52

Processing and refining cost

$2.12

$36.81

G&A (transport included)

$2.57

$42.76

Reclamation

$0.71

$11.78


SENSITIVITY ANALYSIS

The following sensitivity table demonstrates that the project has robust economics across a range of gold-price scenarios.

Gold price

IRR (pre-tax)

NPV (5%, pre-tax)

Pay back

$700

45%

$96 million

1.5 years

$800 (base case)

64%

$144 million

1.3 years

$900

82%

$193 million

1.1 years

$1000

100%

$241 million

1.0 years

 


NEXT STEPS/RECOMMENDATIONS

Fronteer's 2009 exploration/development work-plan includes recently completed infill and step-out drilling, as well as ongoing engineering, environmental, hydrological, metallurgical, land and legal programs. Subsequent work activities will lead to continued refinement of project input parameters in the following areas: 

  • Resources: Resource expansion represents the most significant opportunity for enhancing project economics. Additional delineation and infill drilling will increase the confidence of resource estimates. This will enable conversion of resources from Inferred to Measured and Indicated categories, which will in turn provide for a higher conversion rate of resources to reserves.
  • Geotechnical: On-going geotechnical studies will provide slope parameters for pit designs to ensure safe and optimal pit walls.
  • Processing: Ongoing metallurgical testing of materials representative of the deposit needs to be completed to confirm recoveries; preliminary metallurgical testing relied on near-surface samples. Metallurgical findings from composites taken from three cross-sections are expected to be reported during Q1 2010. 
  •  Permitting: Permitting strategies are currently being developed and all baseline data are being collected to support permit submission.

Preparation of PEA

The PEA has been prepared with input from MDA, G.L. Simmons and McClelland Laboratories. 

 

MDA is a geology and engineering consultancy firm with extensive experience in resource exploration, development and operating projects.

 

G.L. Simmons has more than 30 years of mineral and gold processing experience. Mr. Simmons formerly served as Senior Technical Director, Metallurgy&Technology, Newmont Mining Corp.

 

An updated National Instrument 43-101 Technical Report will be filed on SEDAR within 45 days of this press release and will include a summary of the PEA.

 

Qualified Person

The PEA was prepared under the supervision of Dr. Michael Gustin, P.G., Mr. Thomas Dyer, P.E., and Mr. Gary Simmons, each of whom are "qualified persons," as such term is defined in National Instrument 43-101, and have each read and confirmed that this news release fairly and accurately reflects the contents of the PEA report. Christopher Lee, P. Geo., Chief Geoscientist for Fronteer, is the Company's designated Qualified Person for this news release and has reviewed and validated that the information contained in the release is consistent with that provided by the QPs responsible for the PEA.

 

ABOUT FRONTEER

We intend to become a significant gold producer. Our solid financial position and strengthened operational team give us the ability to advance our key gold projects through to production. Our future potential production platform includes our Long Canyon, Sandman and Northumberland projects - all located in Nevada, one of the friendliest gold-mining jurisdictions in the world. Our robust pipeline also includes 40% interest in an emerging copper-gold mineral district in northwestern Turkey. In addition, Fronteer has 100% ownership of Aurora Energy Resources, developer of one of the largest uranium deposits not currently in production. For further information on Fronteer visit www.fronteergroup.com or contact:

 

Mark O'Dea, Ph.D, P.Geo, President and CEO, Fronteer Development Group
Troy Fierro, COO, Fronteer Development Group
Richard Moritz, Director, Investor Relations
Glen Edwards, Director, Communications
Phone 604-632-4677 or Toll Free 1-877-632-4677
info@fronteergroup.com

Long Canyon mineral resource estimation
as of February 9, 2009. The Long Canyon mineral resource estimation was completed by MDA. The resources were modelled and estimated by evaluating the drill data statistically and utilizing three-dimensional lithologic solids provided by Fronteer to interpret mineral domains on cross sections spaced at 50-metre intervals throughout the extent of the Long Canyon mineralization. The mineral domain interpretations were then rectified on cross sections spaced at 10-metre intervals. The modeled mineralization was analyzed statistically to establish estimation parameters, and gold grades were estimated by inverse-distance methods into a block model with 5 metre (width) x 10 metre (length) x 3 metre (height) blocks that were coded to the mineral domains by the 10-metre mineral domain polygons. All modelling of the diluted resources was performed using Gemcom Surpac� software. Quality-control data generated during the various drill programs conducted at Long Canyon were independently reviewed by MDA as part of the resource study. The person responsible for the resource estimate on behalf of MDA is Michael Gustin, Ph.D., P. Geo, a Qualified Person as defined by National Instrument 43-101Further details of the estimation procedure are available in the updated NI 43-101 report posted on SEDAR (http://www.sedar.com/).

This PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves at this time and as such there is no certainty that the preliminary assessment and economics set forth in the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Except for the statements of historical fact contained herein, certain information presented constitutes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and Canadian securities laws. Such forward-looking statements, including but not limited to, those with respect to potential expansion of mineralization, potential size of mineralized zone, and size and timing of exploration and development programs, estimated project capital and other project costs  and the timing of submission and receipt and availability of regulatory approvals involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievement of Fronteer to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such factors include, among others, risks related to international operations and joint ventures, the actual results of current exploration activities, conclusions of economic evaluations, uncertainty in the estimation of mineral resources, changes in project parameters as plans continue to be refined, future prices of uranium, environmental risks and hazards, increased infrastructure and/or operating costs, labour and employment matters, and government regulation and permitting requirements as well as those factors discussed in the section entitled "Risk Factors" in Fronteer's Annual Information form and Fronteer's latest Form 40-F on file with the United States Securities and Exchange Commission in Washington, D.C. Although Fronteer has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Fronteer disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, other than as required pursuant to applicable securities laws. Accordingly, readers should not place undue reliance on forward-looking statements.

FRG - TSX �2009 Fronteer Development Group | fronteergroup.com
FRG - NYSE Amex Subscribe |
Suite 1650, 1055 West Hastings, Vancouver, BC V6E 2E9
Data and Statistics for these countries : Turkey | All
Gold and Silver Prices for these countries : Turkey | All

Fronteer Gold

DEVELOPMENT STAGE
CODE : FRG.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Fronteer Gold is a gold exploration company based in Canada.

Fronteer Gold develops gold and uranium in Canada, and holds various exploration projects in Canada, in Mexico and in Turkey.

Its main assets in development are MICHELIN (UNDERGROUND) and MICHELIN (OPEN PIT) in Canada and its main exploration properties are GROUSE CREEK, OLYMPIC, REEF, BUFFALO CANYON, GOLD SPRINGS, DIXIE LAKE, RAINBOW PROJECT, INDA LAKE, SANDMAN, JACQUES LAKE (UNDERGROUND), JACQUES LAKE (OPEN PIT), NASH, INDA, GEAR, INDA - UNDERGROUND, INDA - OPEN PIT, GEAR - UNDERGROUND, GEAR - OPEN PIT and KLONDIKE NORTH in Canada, SANTA CRUZ PROJECT, PASCO CANYON and ROSE MINE in Argentina, BUNCE, FIREBALL RIDGE, GREEN MONSTER, HAYS CANYON, JPW, WEST PEQUOP, HALILAGA, TRINITY SILVER, AGI DAGI - DELI ZONE, LONG CANYON, NORTHUMBERLAND, AGI DAGI, YUNTDAG and HUM in Turkey, BAZA, ARABIA, GYPSUM VALLEY, PEQUOP SOUTH, LENOID and SINTER in Spain and SWISS BANK in Mexico.

Fronteer Gold is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 2.2 billions as of today (US$ 2.3 billions, € 1.6 billions).

Its stock quote reached its lowest recent point on December 31, 2004 at CA$ 0.30, and its highest recent level on April 08, 2011 at CA$ 14.78.

Fronteer Gold has 150 571 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Fronteer Gold
2006 Annual report
Financials of Fronteer Gold
3/29/2011reports year-end results
8/12/2010Gold Reports Strong Second Quarter Financial Results and Sig...
5/12/2010Continues to report strong financial results and advancement...
11/16/2009reports third quarter results
8/14/2009reports second quarter and first half 2009 results
11/14/2008reports third quarter results
8/14/2008reports second quarter results
5/14/2008reports first quarter 2008 results
Project news of Fronteer Gold
1/12/2011(Long Canyon)reports interim resource estimate for Long Canyon gold depos...
1/18/2011(Long Canyon)Step-Out Drilling at Long Canyon Expands Deposit by 200 Metr...
8/18/2010Drilling along northern extension intersects 44.2 metres of ...
8/9/2010(Northumberland)Gold continues to intersect high-grade gold at Northumberlan...
8/3/2010(Northumberland)Second high-grade zone returns 7.10 g/t gold over 37.4 metre...
7/20/2010(Long Canyon)Drilling Along Northern Extension of Deposit Intersects 64 M...
6/21/2010(Sandman)Drilling hits 2.35 ounces/ton gold and 33.18 ounces/ton silv...
6/9/2010(Long Canyon)Drilling returns 16.4 g/t gold over 21.2 metres
6/7/2010(Sandman)New high-grade drill results and expanded Plan of Operations
5/19/2010(Long Canyon)New resource estimate
4/14/2010(Halilaga)Drilling returns 308 metres of 0.34 g/t gold and 0.30% coppe...
4/5/2010(Halilaga)Reports metallurgical results and 2010 work-program
3/25/2010(Sandman)Near-surface oxide gold intercepts highlight open-pit potent...
3/5/2010(Sandman)Drilling returns 1.23 ounces per ton gold over 24.8 feet at ...
3/1/2010(Northumberland)Initial Northumberland metallurgical testing reports gold re...
2/22/2010(Halilaga)New drilling expands Halilaga copper-gold porphyry in northw...
2/18/2010(Northumberland)Drilling further defines high-grade gold
2/2/2010(Long Canyon)Drilling returns 3.94 grams per tonne gold over 77.7 metres ...
1/25/2010(Sandman)Sandman delivers more high-grade gold to Fronteer's Nevada p...
1/11/2010(Sandman)Sandman gold project on track to potential production decisi...
1/6/2010(Agi Dagi)& Teck complete the sale of the Agi Dagi & Kirazli gold proj...
12/21/2009(Long Canyon)Drilling advancing Long Canyon gold deposit to feasib ility
12/9/2009(Northumberland)Drilling highlights large high-grade zone at Northumberland ...
12/4/2009(Michelin (open Pit))Independent study: Michelin Uranium Project to generate regi...
12/1/2009(Long Canyon)Preliminary economic assessment for Long Canyon Project gene...
10/5/2009(Long Canyon)Long Canyon extends 100 metres to the north, returning 6.57 ...
10/1/2009(Long Canyon)Step-out drilling at Long Canyon extends gold mineralization...
9/17/2009(Long Canyon)Long Canyon deposit expansion ramps up: step-out drilling re...
8/20/2009(Long Canyon)provides global update on its development-stage gold pro jec...
8/12/2009(Long Canyon)Emerging zone returns more wide intervals of gold at Long Ca...
8/5/2009(Sandman)High-grade gold intersected in footwall zone of Sandman gold...
7/16/2009(Northumberland)initiates permitting for underground access at Northumbe rla...
6/30/2009(Long Canyon)Metallurgical drilling returns 4.15 grams per tonne gold ove...
6/23/2009(Jacques Lake)reports 87.5% uranium recovery from Aurora's pilot plant te...
6/16/2009(Sandman)Ongoing work-program underlines strong production potential ...
6/11/2009(Long Canyon)Long Canyon column-leach tests return gold recoveries averag...
6/1/2009(Sandman)Sandman gold project returns 25.58 grams per tonne gold over...
1/26/2009(Long Canyon)Drilling returns 5.32 grams per tonne gold over 25.4 metres ...
1/19/2009(Agi Dagi - Deli Zone)Discovery of additional gold zone underlines open-ended pote...
12/29/2008(Long Canyon)Drilling returns 9.03 grams per tonne gold over 25.8 metres ...
12/23/2008(Halilaga)Regional drilling at Halilaga intersects new areas of coppe...
12/8/2008Shallow drilling demonstrates high-grade nature of mineraliz...
11/20/2008(Northumberland)Drilling strengthens continuity at Fronteer's Northumberland...
11/18/2008(Long Canyon)Drilling continues to extend gold mineralization at Long Can...
11/12/2008(Agi Dagi - Deli Zone)JV update: Drilling begins at Agi Dagi gold project
9/29/2008(Long Canyon)Drilling extends strike 400 metres at Fronteer's Long Canyon...
9/24/2008(Long Canyon)Earns Majority Interest in Long Canyon Gold Project, Nevada
9/11/2008(Long Canyon)Drilling, road building unearth more near-surface gold at Fr...
8/19/2008(Long Canyon)discovers new high-grade gold zone at Long Canyon, Nevada
8/9/2008(Northumberland)reclassifies Northumberland resource ounces
7/29/2008(Long Canyon)hits more high-grade gold at Nevada property
6/5/2008(Northumberland)Northumberland gold deposit increases in size and significan...
3/11/2008(Labrador Iocg)Nunatsiavut government considers proposed change
2/15/2008(Long Canyon)Drilling extends strike of high-grade gold at Nevada propert...
Corporate news of Fronteer Gold
4/7/2011Announces Completion of Acquisition by Newmont
3/20/2011ISS Proxy Advisory Services and Glass Lewis & Co. Recommend ...
2/1/2011completes sale of uranium assets to Paladin Energy
1/24/2011reports objectives, work plan and budget for 2011
6/28/2010Provides mid-year update on advancement of its key gold proj...
4/26/2010expands gold portfolio in Nevada with acquisition ...
3/29/2010Strong year-end results
1/6/2010Exceptional gold intercepts expand mineralization at Long Ca...
12/9/2009Agreement signed for the sale of the Agi Dagi and Kirazli go...
9/24/2009and Teck announce proposed sale of projects to Alamos
6/10/2009to subscribe for six million units of East Asia Minerals
6/2/2009grants option to International Enexco on Loomis gold pro per...
3/3/2009acquires additional shares and now owns 92.1% of Aurora Ener...
1/23/2009launches formal bid for Aurora Energy Resources Inc.
12/22/2008announces intention to acquire Aurora Energy Resources I nc.
11/5/2008hits more gold 'off-trend' in Nevada's Eastern Great Basin
6/18/2008finalizes Newmont deal to fast-track Nevada gold project to ...
4/18/2008 to hold Annual General Meeting in Toronto, May 6
4/8/2008Nunatsiavut Government's three-year moratorium to allow uran...
3/28/2008 reports fiscal 2007 results
3/25/2008's global exploration program aims to double gold resource b...
2/25/2008's Aurora exceeds annual resource target, adds four projects
4/5/2007Closes C$5,870,500 Over-Allotment Option
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (FRG.TO)AMEX (FRG)
14.78+0.07%29.88+0.10%
TORONTO
CA$ 14.78
04/08 16:38 0.010
0.07%
Prev close Open
14.77 14.71
Low High
14.71 14.84
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  14.78 -%
Volume 1 month var.
5,867,254 -%
24hGold TrendPower© : 34
Produces
Develops Uranium
Explores for Copper - Gold - Indium - Silver - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/19/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :