January 14, 2008                                                                                                              

TSX: BAJ

 

PRESS RELEASE

 

BAJA MINING ORDERS LONG LEAD ITEMS

 

Baja Mining Corp. (the “Company”) is pleased to announce that it has placed orders for the Construction Camp and several critical path items, with long delivery times, in order to keep the overall schedule on track for start-up of the Boleo copper-cobalt project at Santa Rosalia, Mexico

 

Construction Camp

The anticipated peak work force during construction is anticipated to be approximately 2,500 people.  The construction camp will be built in two phases, with the first phase being able to accommodate 1,000 workers.  The company has now awarded the contract for the construction of the first phase of the camp, with expected completion in the second quarter of 2008.  With over 100 people currently on site, the early delivery of the main camp will enable the accelerated pace of construction to continue.  All of the water for the camp and construction, prior to startup of the process plant, will be provided by a reverse osmosis desalination plant which has also been purchased.  It is anticipated that the second phase of the camp, with capacity for up to 2,200 workers, will not be required until 2009.

 

Acid Plant and Power Generation Facilities

The Acid Plant and Power Cogeneration (cogen) Plant are both critical path items in the construction schedule.  Accordingly, to ensure their timely availability in 2009, the Company has placed the order for a 46 megawatt turbine and generator (TG) set which has been identified as the single longest lead item.  The cost of this TG package is approximately US$10 million. Delivery is expected in 18-22 months.   The Cogen Plant is an integral part of the acid plant and utilizes heat recovered from the burning of sulphur to generate power.  When fully operational, it is anticipated that this facility will provide almost all of the power required for the mine and process plant.  In addition, the Company has issued a “Letter of Award and Limited Authorization to Proceed” to SNC-Lavalin Engineers & Constructors Inc. for basic engineering and procurement services for the 2400 tonnes per day acid plant, complete with heat recovery system and the 46 MW turbo generator package.  The parties are currently working on concluding a definitive agreement for all services; however work has commenced based on the award. 

 

Site Activities

Baja Mining Corp. is pleased to advise that site work at the Boleo project, Santa Rosalia, Mexico is proceeding on a timely basis for the start of construction.  Initial work over the past several months consisted of a cactus removal, quarantine and relocation program at the proposed plant location and construction camp site in accordance with our environmental permits. The Company and the local authorities of Santa Rosalia have also been working in a cooperative effort to remediate the town’s existing landfill, located on the Company’s land, and to develop a controlled facility in a new location to the north on land being donated by the Company for such purpose.  In addition, geo-technical drilling and testwork has been ongoing for the last few months at the process plant and tailings dam locations to enable an early start of construction.  The Company will be continuing to place orders for long lead items over the next few months.

 

ON BEHALF OF THE BOARD OF DIRECTORS OF

BAJA MINING CORP.

 

“John W. Greenslade”

 

JOHN W. GREENSLADE, PRESIDENT

 

For further information please contact John Greenslade, President, at (604) 685-2323

 

Some of the statements contained in this release are forward-looking statements, such as statements that describe the Company’s timing of placement of and expected number of construction workers on site, expected timing of delivery of long lead items, such as the acid plant, expect, and other statements.  Since forward-looking statements are not statements of historical fact and address future events, conditions and expectations, forward-looking statements by their nature inherently involve unknown risks, uncertainties, assumptions and other factors well beyond the Company’s ability to control or predict.  Actual results and developments may differ materially from those contemplated by such forward-looking statements. Material factors that could cause actual revenues to differ materially from those contained in such forwarding-looking statements include (i) fluctuations on the prices of copper, cobalt, zinc and manganese, (ii) interpretation of contract terms, (iii) accuracy of the Company’s and consultants’ projections, (iv)  the Company’s ability to finance, receive permits for, obtain equipment, construct and develop the El Boleo Project, (v) the effects of weather; operating hazards; adverse geological conditions and global warming, (vi) impact of availability of labor, materials and equipment; and (vii) changes in governmental laws, regulations, economic conditions or shifts in political attitudes or stability.

 

These forward-looking statements represent the Company’s views as of the date of this release. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.  Readers should not place undue reliance on any forward-looking statements.

 

 

------------------------------------------------------

To unsubscribe from this mailing list, please send a blank e-mail to:

 

 

 

VanEck Vectors Global Alternative Energy ETF

DEVELOPMENT STAGE
CODE : BAJ.TO
ISIN : CA05709R1038
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Baja Mining is a zinc and copper development stage company based in Canada.

Baja Mining develops zinc, copper, cobalt and manganese in Mexico.

Its main asset in development is BOLEO in Mexico.

Baja Mining is listed in Canada, in Germany and in United States of America. Its market capitalisation is 1.7 millions as of today (US$ 1.5 millions, € 1.1 millions).

Its stock quote reached its highest recent level on December 31, 2007 at 2.57, and its lowest recent point on January 24, 2014 at 0.01.

Baja Mining has 47 442 200 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of VanEck Vectors Global Alternative Energy ETF
1/23/2015Baja Mining's long-delayed and almost dead El Boleo finally ...
12/19/2006New Analysis
Annual reports of VanEck Vectors Global Alternative Energy ETF
2008 Annual report
2007 Annual Report
Financings of VanEck Vectors Global Alternative Energy ETF
8/21/2012Reports on Status of Stage I Financing and Provides Corporat...
9/13/2007Announces CDN$45+ Million Private Placement
Option Grants of VanEck Vectors Global Alternative Energy ETF
1/12/2012[Baja Mining Corp.] Amends Stock Option Plan and Extends Boa...
Nominations of VanEck Vectors Global Alternative Energy ETF
11/14/2012[Baja Mining Corp.] Appoints Interim CFO
5/16/2012[Baja Mining Corp.] Announces Resignation of Greenslade, App...
4/18/2012[Baja Mining Corp.] Announces Resignation of Gerald Prosalen...
4/17/2012Announces Resignation of Gerald Prosalendis From Board
12/15/2011Hires New Officers; Completes Second Draw on Senior Debt
2/3/2011Appoints Wolf Seidler to Board
6/3/2009Appoints Michael Shaw as COO
9/6/2007Welcomes New Vice President - Engineering & Construction
Financials of VanEck Vectors Global Alternative Energy ETF
11/14/2013Files Third Quarter 2013 Financial Results
8/15/2013Files Second Quarter 2013 Financial Results
5/16/2013Reports Standstill Extension and Files 2013 First Quarter Fi...
4/3/2013[Baja Mining Corp.] Baja Mining Files 2012 Financial Results
Project news of VanEck Vectors Global Alternative Energy ETF
12/23/2013(Boleo)Test - Boleo Project Schedule and Corporate Update
8/8/2013(Boleo)Boleo Project Receives Further Funding and Baja Mining Inter...
5/13/2013(Boleo)Boleo Project Receives Further Funding and Baja Mining Inter...
5/13/2013(Boleo)Boleo Project Receives Further Funding and Baja Mining Inter...
4/29/2013(Boleo)Interest in Boleo Project Reduced to 20.9 Percent
11/2/2012(Boleo)[Baja Mining Corp.] Announces Additional Funding For Boleo P...
10/19/2012(Boleo)[Baja Mining Corp.] Reports No Damages to Boleo Project Due ...
10/15/2012(Boleo)Announces Further Funding for Boleo Project
10/5/2012(Boleo)[Baja Mining Corp.] Announces Additional Funding Provided fo...
6/22/2012[Baja Mining Corp.] Thanks Shareholders for Their Support an...
1/18/2012(Boleo)Announces Further Draw of US$ 100 Million of Senior Debt for...
1/3/2012(Boleo)[Baja Mining Corp.] Provides Update on Governance and Boleo ...
1/3/2012(Boleo)Provides Update on Governance and Boleo Project
8/4/2011(Boleo)provides Project Update at Boleo
6/16/2011(Boleo).: Secretary of Economy of Mexico Lays First Stone at Minera...
3/9/2010Files Updated Technical Report & Amended Financial Statement...
10/28/2009(Boleo)Provides Project Update
6/17/2009(Boleo)Achieves Key Milestone in Development of Manganese Metal Pro...
5/14/2009(Boleo)Selects ICA Fluor as EPCM Contractor & Restarts Boleo Engine...
2/3/2009(Boleo)Provides Project and Company Update
4/18/2008(Boleo)Welcomes Kores as Development Partner at El Boleo
8/21/2007(Boleo)Receives Essential Land Use Permits
Corporate news of VanEck Vectors Global Alternative Energy ETF
12/4/2013Comments on Trading in Shares
8/14/2013(Boleo)Provides Update on Boleo Technical Report
6/26/2013Company Update - AGM and SRK Report
6/26/2013Signs Option Agreement
6/3/2013Reports Standstill Extension
4/18/2013Provides Annual Meeting Information
4/12/2013Provides Standstill and Funding Update
2/12/2013Korean Consortium Provides Phase 2 Funding Commitment, Baja ...
1/31/2013[Baja Mining Corp.] Reports Technical Report Developments
1/25/2013(Boleo)[Baja Mining Corp.] Provides Boleo Project Financing Update
1/24/2013(Boleo)Provides Boleo Project Financing Update
11/7/2012[Baja Mining Corp.] Announces Further Standstill Extension
9/27/2012[Baja Mining Corp.] Announces Standstill Extension and Updat...
9/4/2012[Baja Mining Corp.] Provides Update on Stage II Funding Deci...
8/24/2012[Baja Mining Corp.] Reports Waiver to Standstill Agreement
8/13/2012[Baja Mining Corp.] Resignations of Messrs. Waisberg and Mar...
8/7/2012[Baja Mining Corp.] Signs Second Standstill Agreement with L...
8/7/2012Signs Second Standstill Agreement With Lenders
8/1/2012[Baja Mining Corp.] Announces Director Resignations
7/27/2012[Baja Mining Corp.] Class Action Commenced Against Baja
7/26/2012(Boleo)[Baja Mining Corp.] Secures US$90 million Interim Funding fr...
7/13/2012[Baja Mining Corp.] Provides Update
6/20/2012[Baja Mining Corp.] to Hold Annual General and Special Meeti...
6/20/2012[Baja Mining Corp.] Obtains Standstill Agreement from Lender...
6/18/2012[Baja Mining Corp.] Disclosure Challenged by Louis Dreyfus
6/14/2012[Baja Mining Corp.] Confirms Availability of Meeting Materia...
6/14/2012Confirms Availability of Meeting Materials
6/4/2012[Baja Mining Corp.] Provides Guidance On Shareholder Meeting...
6/4/2012Provides Guidance on Shareholder Meeting Resolutions
5/30/2012[Baja Mining Corp.] Provides Update on Liquidity and Corpora...
5/25/2012[Baja Mining Corp.] Receives Request for Arbitration from Lo...
5/7/2012[Baja Mining Corp.] Announces Update on Progress of Funding ...
5/7/2012[Baja Mining Corp.] Announces Board Appointments
5/7/2012Announces Update on Progress of Funding Solution
4/25/2012[Baja Mining Corp.] Provides Update on Cost Controls, Fundin...
4/23/2012(Boleo)Provides Update For Costs of the Boleo Project; Announces Di...
4/4/2012[Baja Mining Corp.] Shareholders Vote to Keep the Current Bo...
4/3/2012Shareholders Vote to Keep the Current Board
3/29/2012(Boleo)Announces Further US$ 80 Million Draw of Senior Debt for Bol...
3/28/2012(Boleo)Provides Update on Boleo ProjectSubject: [Baja Mining Corp.]...
3/26/2012[Baja Mining Corp.] Urges Shareholders: Vote the Gold Proxy
3/23/2012[Baja Mining Corp.] Reports Support From Glass Lewis, A Lead...
3/22/2012[Baja Mining Corp.] Comments on ISS Recommendation
3/22/2012Comments on ISS Recommendation
3/6/2012[Baja Mining Corp.] Receives Response from BCSC Regarding Ba...
3/5/2012[Baja Mining Corp.] Alerts Shareholders: Mount Kellett Final...
3/2/2012[Baja Mining Corp.] Advises Shareholders: Don't Trust the Mo...
2/27/2012[Baja Mining Corp.] Provides Initial Response to Dissident C...
2/23/2012Files Complaint Regarding Mount Kellett's Trade Disclosure
2/14/2012[Baja Mining Corp.] Advises Shareholders: Mount Kellett's 15...
2/9/2012[Baja Mining Corp.]Files Management Information Circular And...
2/9/2012Files Management Information Circular and Exposes Mount Kell...
1/18/2012(Boleo)Announces Further Draw of US$ 100 Million of Senior Debt for...
1/9/2012[Baja Mining Corp.] Calls Requisitioned Special Meeting for ...
1/9/2012Calls Requisitioned Special Meeting for April 3, 2012
12/19/2011[Baja Mining Corp.] Receives Letter Requisitioning a Shareho...
12/15/2011[Baja Mining Corp.] Hires New Officers; Completes Second Dra...
11/28/2011(Boleo)Schedules Conference Call to Provide Boleo Project Update
9/7/2011(Boleo)[Baja Mining Corp.] Baja Mining Commences Underground Mining...
9/7/2011(Boleo)Commences Underground Mining at Boleo
6/16/2011issued today
5/9/2011(Boleo)[Baja Mining Corp.] Announces Commencement of Mining Activit...
4/11/2011(Boleo)[Baja Mining Corp.] Annouces First Concrete at Boleo and Pro...
4/11/2011(Boleo)Announces First Concrete at Boleo and Provides Construction ...
3/9/2010Files Base Shelf Prospectus
9/14/2009Commences Trading on US OTCQX
8/20/2008To Take First Delivery of Mining Equipment
7/28/2008 Receives $90 Million & Ramps-up Construction Activities
7/4/2008 Releases Video Presentation on Korean Financing Closing
7/2/2008Completes Unprecedented Financing and Provides Transaction D...
6/25/2008Provides Financing Update
6/3/2008[Baja Mining Corp.] Closes Transaction with Korean Consortiu...
5/9/2008 Welcomes Tom Ogryzlo as Chairman of the Board
4/23/2008Launches New Multimedia Presentations - Now Online!
3/27/2008 Presents at AMEX Precious and Base Metals Conference
1/14/2008Project Update and Ordering of Long Lead Items
11/13/2007 Secures US$64 Million Equipment Lease with Caterpillar Fina...
10/16/2007Closes Brokered Tranche of $45 Million Placement; Receives S...
10/11/2007 Notifies 2005 Warrant Holders of Near Term Expiry Date
9/4/2007Signs Bridge Loan Facility with Endeavour Mining Capital
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (BAJ.TO)FRANKFURT (B1Y.F)
0.035+0.00%0.003+0.00%
TORONTO
CA$ 0.035
03/14 15:59 -
0%
Prev close Open
0.040 0.035
Low High
0.035 0.035
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.035 -12.50%
Volume 1 month var.
913,500 -12.50%
24hGold TrendPower© : -15
Produces
Develops Cobalt - Copper - Manganese - Zinc
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/5/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
error

 

 

THE REQUESTED URL IS UNCORRECT

VanEck Vectors Global Alternative Energy ETF profile | VanEck Vectors Global Alternative Energy ETF news | VanEck Vectors Global Alternative Energy ETF market Indicators | VanEck Vectors Global Alternative Energy ETF projects and resources | VanEck Vectors Global Alternative Energy ETF valuation | Go to VanEck Vectors Global Alternative Energy ETF properties | VanEck Vectors Global Alternative Energy ETF corporate presentation | VanEck Vectors Global Alternative Energy ETF annual report | VanEck Vectors Global Alternative Energy ETF management | VanEck Vectors Global Alternative Energy ETF interactive charts | VanEck Vectors Global Alternative Energy ETF free charts | VanEck Vectors Global Alternative Energy ETF TORONTO | VanEck Vectors Global Alternative Energy ETF FRANKFURT | VanEck Vectors Global Alternative Energy ETF Other OTC
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !