Golden Queen provides a construction update and updates its capital cost estimates
Published : March 27, 2014
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Golden Queen provides a construction update and updates its capital cost estimates

Photograph 1 - Concrete pouring near completion at warehouse area (CNW Group/Golden Queen Mining Co. Ltd.)

New Total Capital Expenditure Estimate of $141 Million Including $7 Million Spent to Date

VANCOUVER, March 27, 2014 /CNW/ - Golden Queen Mining Co.  Ltd.  (News - Market indicators) (OTCQX:GQMNF) (the "Company") is pleased to provide an update on the construction underway on its Soledad Mountain Project (the "Project") and its expected capital costs for the construction of the Project. (Amounts are shown in U.S. dollars).

Costs incurred on construction of the Project since July 2013 to date, including access roads and site preparation are largely in-line with the feasibility study cost estimates provided in a news release dated October 25, 2012; a copy of which is available on the Company's website and on SEDAR.

One of the Company's priorities in Q4 2013 and Q1 2014 has been to complete detailed engineering designs for construction and update cost estimates for the major turn-key projects. The feasibility study capital cost estimates were prepared in 2012 and were therefore out of date by around 18 months by the end of 2013. These detailed designs are either well under way or have essentially been completed, and the Company has now received updated cost estimates for all of the turn-key projects.

The typical increase in cost estimates for the turn-key projects is mostly a result of design changes from the feasibility study.  "The time between the feasibility study and the start of construction has provided us with the opportunity to re-evaluate the designs and we have made a number of improvements which we believe will enhance the efficiency and reliability of the processing operation" said H. Lutz Klingmann, President.

Workshop-Warehouse: The Company received a proposal for the construction of the workshop-warehouse from a local contractor in late-2013.  This was the first of the turn-key projects and the contract price was in line with the feasibility study cost estimate.

Crushing-Screening Plant: The contractor has just completed the design for the crushing-screening plant as a turn-key project with numerous adjustments to the feasibility-level design, to improve the operability of the plant both from an operating and a maintenance point of view.  The plant now includes an agglomeration drum and provision has been made for a possible future increase in plant throughput and this has added to the cost of the plant.

Stacking and Conveying System: The feasibility study employed a stacking and conveying system design completed in 2005. The current design has evolved substantially over the past year to a fully-automated system with a significant increase in the reliability of the overall system.  Especially the power distribution along the system has evolved with a separate transformer and motor control package for each unit of the system.  Each of the grass hopper conveyors now includes dust control covers over the conveyors and all functions of the stacker are now controlled by radio remote control.

Phase 1 Heap Leach Pad: The Phase 1 heap leach pad has been designed as a permanent, single-use pad with external solution collection and management systems.  Crushed and agglomerated ore will be conveyed to the heap and stacked with a radial stacker.  The Company has received an updated cost estimate for the construction of the Phase 1, Stage 1 pad and this, after allowance for the construction of the overland conveyor system and peripheral roads in 2013, is lower than the feasibility study cost estimate.

Merrill-Crowe Plant: The current design includes an increase in solution flow rates of 50% decided upon as part of an overall design review for the Project.  The increase in solution flow rates has been accommodated in the original Merrill-Crowe plant footprint. Costs are elevated due to an increase in the size of the equipment in the plant.

Assay Laboratory: The assay laboratory has been changed from a laboratory assembled from three pre-fabricated modules to a laboratory constructed on site.

Water Supply (Supply from Production Wells & Distribution): Both the design and the cost estimates for the water supply from two production wells were re-done from first principles by a consulting engineering firm based in Bakersfield.  The design for the feasibility study was inadequate and this was reflected in a cost estimate that was significantly lower than the current cost estimate.

The construction period will also be longer than the 12 months assumed in the feasibility study. As a result, the Company increased its EPCM (engineering, procurement and construction management), pre-production overhead and general site support cost estimates.

The key cost increases from the feasibility study estimates are shown in the table below:

   
Turn-Key Project Cost Increase from
2012 Feasibility Study
Workshop-Warehouse $0.1 million
Crushing-Screening Plant $2.7 million
Stacking and Conveying System $3.9 million
Phase 1 / Stage 1 Heap Leach Pad ($1.0 million)
Merrill-Crowe Plant $1.8 million
Assay Laboratory $0.4 million
Water Supply (Supply from Production Wells & Distribution) $2.3 million
Total Impact of Turn-Key Projects Revised Cost Estimates $10.2 million

Approximately 50% of capital expenditures are comprised of turn-key projects that will be awarded as fixed-price contracts. These contracts will therefore provide price protection during the construction period. The Company has selected and is working with contractors with significant experience and excellent reputations.

The updated designs and other cost updates have raised the total estimated capital cost to build the Project to $114 million. This includes a contingency of 15% of estimated construction costs, or approximately $15 million. The 2012 feasibility study had a cost estimate of $79 million and unallocated costs of $12 million for a total of $91 million.

In addition to the construction capital expenditures, the Company anticipates to require $10.5 million for working capital and approximately $17 million for mobile mining equipment. These estimates have not changed from the feasibility study. The Company's new estimate for the total capital required to bring the Project to production is $141 million (from $119 million in the feasibility study), of which $7 million has been spent to date.

CONSTRUCTION UPDATE

Phase 1 Construction

Work on the Phase 1 earthmoving projects was essentially completed in December 2013 with some final touch-up completed in January 2014. This included the pad where the workshop-warehouse is being constructed, the interconnecting roads including the main haul road between the area where the crushing-screening plant will be constructed and the east waste rock storage pad and the construction of safety berms as required by MSHA.

The Company awarded a contract for the construction of the workshop-warehouse and wash slab to a local contractor in late-2013.  A key milestone was achieved when the prepared pad was formally handed over to the contractor in mid-January to commence construction of the footings as illustrated in Photograph 1.

In addition, the Company has awarded contracts for the construction of the Phase 1 water supply and a guard shack and gate.

Phase 2 Construction

Phase 2 construction has commenced and will continue concurrently with the ongoing Phase 1 construction.

The Company anticipates completion of site preparation where the crushing-screening plant and the assay laboratory will be constructed in April.

The Company has awarded contracts for the construction of the septic system and leach field and a fuel storage facility.

A second key turn-key project is the assay laboratory.  Detailed designs have been completed and it is expected that a contract for the procurement and construction of the assay laboratory will be awarded in Q2 2014.

About Golden Queen Mining Co. Ltd.

The Company is developing its wholly-owned, gold-silver, open pit, heap leach operation on its fully-permitted Soledad Mountain property, located just outside the town of Mojave in Kern County in southern California. The Project will use conventional open pit mining methods and the cyanide heap leach and Merrill-Crowe processes to recover gold and silver from crushed, agglomerated ore.

H. Lutz Klingmann, P.Eng., the President of the Company, is a qualified person for the purposes of National Instrument 43-101 and has reviewed and approved the technical content of this press release.

Caution With Respect To Forward-looking Statements

The information in this news release includes certain "forward-looking statements".  All statements in this news release, other than statements of historical fact, including, without limitation, plans for and intentions with respect to construction and other development activities on the Soledad Mountain Project, capital cost estimates, and future mining operations on the Project, are forward-looking statements. There can be no assurance that such statements will prove to be accurate, and actual capital costs, results of our development plans, and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from statements in this news release regarding our intentions include the uncertainties involving the availability of project financing in the debt and capital markets; changes in capital cost estimates or actual costs due to delays in construction or for other reasons, risks of construction and mining such as accidents, equipment breakdowns, non-compliance with environmental and permit requirements, and other risks and uncertainties disclosed in the section entitled "Risk Factors" contained in our Annual Report on Form 10-K for the year ended December 31, 2013.  Investors are cautioned that forward-looking statements are not guarantees of future performance and, accordingly, should not to put undue reliance on forward-looking statements.  Any forward-looking statement made by us in this release is based only on information currently available to us and speaks only as of the date on which it is made. 

SOURCE Golden Queen Mining Co. Ltd.

Image with caption: "Photograph 1 - Concrete pouring near completion at warehouse area (CNW Group/Golden Queen Mining Co. Ltd.)". Image available at: http://photos.newswire.ca/images/download/20140327_C7543_PHOTO_EN_38442.jpg

For further information:


regarding this news release please contact:

Lutz Klingmann, President
Telephone: (604) 921-7570
Email: lklingmann@goldenqueen.com

Golden Queen Mining

DEVELOPMENT STAGE
CODE : GQM.TO
ISIN : CA38115J1003
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Golden Queen is a gold development stage company based in Canada.

Golden Queen develops gold and silver in USA.

Its main asset in development is SOLEDAD in USA.

Golden Queen is listed in Canada and in United States of America. Its market capitalisation is CA$ 2.8 millions as of today (US$ 2.1 millions, € 1.8 millions).

Its stock quote reached its highest recent level on September 23, 2011 at CA$ 3.95, and its lowest recent point on July 25, 2019 at CA$ 0.02.

Golden Queen has 111 050 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Golden Queen Mining
12/31/2014secures loan financing
Nominations of Golden Queen Mining
5/31/2013Appoints New Board Members
Financials of Golden Queen Mining
8/10/2016Golden Queen Announces Financial Results for the Second Quar...
11/10/2014reports financial results for the third quarter of 2014
8/11/2014Announces Financial Results and Review of Operations for the...
3/17/2014reports year end results and provides a construction update
11/13/2013Files Financial Statements
2/18/2011 Quarterly Report
Project news of Golden Queen Mining
4/13/2015Golden Queen comments on a US Fish and Wildlife Service noti...
11/25/2014(Soledad)Company Ltd. provides update on the Soledad Mountain Project
9/15/2014(Soledad)announces closing of joint venture to develop and operate th...
6/9/2014(Soledad)announces joint venture to develop and operate the Soledad M...
10/25/2012(Soledad)Files Updated Feasibility Study Report for Soledad Mountain ...
4/8/2011(Soledad)ANNOUNCES UPDATED FEASIBILITY STUDY FOR SOLEDAD MOUNTAIN PRO...
Corporate news of Golden Queen Mining
7/25/2016Golden Queen Completes C$16.1 Million Bought Deal Financing
7/14/2016Golden Queen Announces C$13 Million Bought Deal Financing
7/13/2016Golden Queen Annouces Proposed C$13 Million Unit Financing
6/9/2016Golden Queen Provides A Project Update
6/6/2016Golden Queen Provides A Project Update
6/3/2016Golden Queen Announces Voting Results of Annual General Meet...
5/10/2016Golden Queen Announces Financial Results for the First Quart...
2/1/2016A Look Inside the Chart, Technical Insights - Analyst Notes ...
1/21/2016Direction of Market Influences -- Featured Research on Salee...
1/14/2016Today's Market Driven by Key Factors - New Research on Trans...
1/5/2016Golden Queen Begins Commissioning of Processing Facility and...
1/4/2016Golden Queen Begins Commissioning of Processing Facility and...
1/4/2016Golden Queen Begins Commissioning of Processing Facility and...
8/13/201510-Q for Golden Queen Mining Co. Ltd.
8/13/201510-Q for Golden Queen Mining Co. Ltd.
8/10/2015Golden Queen Announces Senior Management Changes And Reports...
8/10/2015Golden Queen Announces Senior Management Changes and Reports...
5/14/201510-Q for Golden Queen Mining Co. Ltd.
5/14/201510-Q for Golden Queen Mining Co. Ltd.
5/5/201510-K for Golden Queen Mining Co. Ltd.
5/5/201510-K for Golden Queen Mining Co. Ltd.
4/13/2015Golden Queen Comments on a US Fish and Wildlife Service Noti...
3/16/2015Golden Queen Reports Financial Results for the Year Ending D...
3/16/2015Golden Queen reports financial results for the year ending D...
2/27/2015Golden Queen Mining Company Ltd. Announces Filing of NI 43-1...
2/27/2015Golden Queen Mining Company Ltd. Announces Filing of NI 43-1...
2/10/2015Company Ltd. provides update on resource estimates, reserve ...
1/1/2015Golden Queen Secures Loan Financing
12/3/2014CANADA STOCKS-TSX set to open lower ahead of Bank of Canada ...
11/26/2014Golden Queen Mining Company Ltd. Provides Update on The Sole...
11/11/2014Golden Queen Reports Financial Results for the Third Quarter...
9/9/2014Company Ltd. shareholders approve the joint venture with Gau...
7/31/2014announces date for Extraordinary Shareholder Meeting to appr...
7/31/2014announces date for Extraordinary Shareholder Meeting to appr...
7/2/2014(Soledad)secures an advance with Leucadia and Auvergne for the ongoin...
4/22/2014on the Center for Biological Diversity Emergency Petition
3/27/2014provides a construction update and updates its capital cost ...
2/3/2014Petition Filed with the United States Fish and Wildlife Serv...
1/6/2014(Soledad)secures interim financing for the ongoing development of its...
12/9/2013provides a construction update
10/8/2013Proposed Extraordinary General Meeting to Increase Authorize...
7/25/2013Announces $10 Million Private Placement
4/30/2013Appointment of Project and Construction Manager
9/11/2012Begins Trading on OTCQX International
5/17/2011(Soledad)ANNOUNCES FILING OF FEASIBILITY STUDY FOR SOLEDAD MOUNTAIN ...
1/21/2011 Financials
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (GQM.TO)Other OTC (GQMNF)
0.025+0.00%0.163-9.44%
TORONTO
CA$ 0.025
07/25 16:45 -
0%
Prev close Open
0.025 0.025
Low High
0.025 0.030
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.025 -%
Volume 1 month var.
557,744 -%
24hGold TrendPower© : -24
Produces
Develops Gold - Silver
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.06+0.96%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.24%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.56-4.83%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.88+1.79%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.93+3.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.48-0.25%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :