Colossus Minerals Provides Development Update
Published : July 15, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

TORONTO, ONTARIO--(Marketwired - July 15, 2013) - Colossus Minerals Inc. (the "Company" or "Colossus") (News - Market indicators)(OTCQX:COLUF) provides a development update for its 75% owned Serra Pelada gold-platinum-palladium Mine. The Serra Pelada Mine is a joint venture between Colossus and Cooperativa de Mineração dos Garimpeiros de Serra Pelada ("COOMIGASP") located in the State of Pará, Brazil. 

HIGHLIGHTS

  • Mining has progressed through the CMZ with both water and ground conditions being managed. However, recently some dewatering wells and pumps have not performed to design specifications. As a result, the Company has determined that additional dewatering capacity, which is currently being brought on line, is required to mine the CMZ in a sustainable, effective and efficient manner.

  • As a result, mining activity through the Central Mineralized Zone ("CMZ") has been delayed and resources have been re-deployed to focus on infrastructure development and additional dewatering in order to keep the Company's plans of achieving 1,000 tonnes per day ("tpd") in the first quarter of 2014 intact. Infrastructure development in the red and gray siltstone is not impacted.

  • The Company now anticipates a delay in gold production from the mine until late in the fourth quarter of 2013.

  • Management is currently evaluating the amount and timing of additional funds required to address the impact of the delay in the ramp-up and otherwise continue development and construction of the Serra Pelada Mine.

  • Underground development continues in the red and gray siltstone at better than anticipated daily development rates with three headings (main decline, ventilation expansion and northern mineralization access) currently being developed. The Company will continue developing mine infrastructure and expects to end the year with five access drifts ready to enter the CMZ late in the fourth quarter to commence production at 500 tpd.

  • The ventilation expansion project remains on schedule.

  • The Company anticipates commissioning the mill commencing in the third quarter with surface stockpiles of approximately 3,000 tonnes collected during the bulk sample program.

  • Process plant construction is currently 87% complete. Structural steel erection is now 85% complete. Commissioning of the plant remains on schedule for later in the third quarter.

Claudio Mancuso, Chief Executive Officer commented, "Although the Company has managed ground conditions and water, the Company has determined additional dewatering capacity is required to mine the CMZ in a safe, sustainable, effective and efficient manner. Additional dewatering capacity has recently been brought on-line with additional capacity being mobilized continuously over the next 60 days. Although the Company has changed its mine plan and ramp-up schedule, management is confident that the additional dewatering capacity will enable the Company to achieve its plan of processing 1,000 tpd by the end of the first quarter of 2014."

CONSTRUCTION AND DEVELOPMENT ACTIVITIES

Underground Development

  • Mining has progressed through the CMZ with both water and ground conditions being managed. However, recently some dewatering wells and pumps have not performed to design specifications. As a result, the Company has determined that additional dewatering capacity, which is currently being brought on line, is required to mine the CMZ in a sustainable, effective and efficient manner.

  • As a result, mining activity through the CMZ has been delayed and resources have been re-deployed to focus on infrastructure development and additional dewatering in order to keep the Company's plans of achieving 1,000 tpd in the first quarter of 2014 intact. Infrastructure development in the red and gray siltstone is not impacted.

  • The Company now anticipates a delay in gold production from the mine until late in the fourth quarter of 2013.

  • The Company continues to make progress in its mine planning activities and has laid out (in the attached pictorial update) the month by month development which will take place between now and the end of 2013.

  • The Company plans to continue the decline development to have multiple horizons ready for mining in 2014, continue with the ventilation upgrade and prepare five access drives to commence production late in the fourth quarter of 2013.

  • The Company is currently fast-tracking its dewatering program expansion.

  • Technical services to support continued advancement of the mining program are in place and are currently being supported by Hatch engineering.

  • The ventilation expansion program is now in excess of 50% complete. Connection of underground drive to ventilation shaft expected in the third quarter.

Process Plant

The various phases of the process plant construction, along with respective percentages complete are presented in the table below.

  June 18 July 15
Total Project 85% 87%
Process Plant    
  Engineering 99% 99%
  Procurement 98% 99%
  Civil construction 99% 99%
  Structural steel fabrication 95% 100%
  Structural, mechanical, piping & electrical installation 55% 70%
Power house 97% 100%
Ventilation upgrade 50% 50%
Tailings impoundment facility 35% 40%

Process plant construction is progressing as planned. Significant milestones achieved since the last development update include:

  • The primary crusher area's structural steel, platework and associated equipment installation is approximately 95% complete. Electrical and instrumentation installations are approaching completion. Commissioning of the primary crusher is scheduled to occur in July.

  • The reagent handling area's structural steel, platework and associated equipment installation is approximately 95% complete. Electrical and instrumentation installations are progressing.

  • All of the structural steel and platework is currently on site with approximately 85% erected to date. 

  • Mechanical installations and structural steel erection in the grinding building are progressing well with this area now 75% complete.

  • Significant progress has been made in erecting the conveyor systems. Conveyor belts are on site and installation will proceed during July prior to the start of commissioning.

  • The primary screen, the scrubber, and a number of tanks have been installed in the Scrubbing & Screening building. Installation of pipe and electrical equipment has started.

  • Civil construction of the gold room is complete and this area has been turned over to the mechanical contractor. Erection of tanks and other mechanical installations in the gold room area are progressing. Commissioning of this area is scheduled for late August.

Infrastructure

Other infrastructure construction is progressing as planned. Significant milestones achieved since the last development update include:

  • The power house is now 100% complete and commissioned. Connection to the grid is expected by the end of July. The Company is currently running two of the four generators and electrical reticulation across the project site is substantially complete.

  • Construction of tailings dam has been advanced. The total construction is now 40% complete with the spillway wall formwork and rebar progressing as planned. The cut-off excavation is now finalized, the horizontal filter has been installed and the dam foundation is in place. The tailings dam is expected to be ready in conjunction with the start of mill commissioning.

  • Widening of the ventilation shaft is also progressing on schedule. A three-fold increase in air volume to the underground operations is expected by the end of the third quarter with an additional two-fold increase in air volume occurring in the fourth quarter.

To view the CSI Construction update, please visit the following link: http://media3.marketwire.com/docs/CSI_Construction_Update_July_Final.pdf.

About Colossus:

Colossus is a development-stage mining company focused on bringing its 75% owned Serra Pelada gold-platinum-palladium Mine into production. The Serra Pelada Mine is a joint venture between Colossus and COOMIGASP located in the State of Pará, Brazil. Serra Pelada, located in the mineral prolific Carajas region in the State of Pará, is host to one of the highest grade gold and platinum group metals deposits in the world. Between 1980 and 1986 Serra Pelada was host to the largest precious metals rush in Latin American history. Colossus Minerals Common Shares, warrants and notes trade on the Toronto Stock Exchange (TSX) under the symbols CSI, CSI.WT.A and CSI.NT respectively and in the United States its Common Shares trade on the OTCQX under the symbol COLUF. The Company is headquartered in Toronto, Canada.

Qualified Person:

David Anthony, P. Eng., President and Chief Operating Officer of Colossus, is a "qualified person" as such term is defined in National Instrument 43-101 and has reviewed and approved the technical information and data included in this press release.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Forward-looking statements in this press release include statements regarding the timing and nature of future exploration and development programs that are dependent on projections that may change as drilling continues, or if unexpected ground conditions are encountered. The Company does not currently have any mineral properties that are in production or that contain a reserve as defined by National Instrument 43-101. In addition, areas of exploration potential are identified which will require additional drilling to determine whether or not they contain similar mineralization to areas that have been explored in more detail. Significant additional drilling is required at Serra Pelada to fully understand system size.

Except for statements of historical fact relating to Colossus, certain statements in this press release constitute "forward-looking information" within the meaning of the Securities Act (Ontario) or "forward-looking statements" within the meaning of the United States Private Litigation Reform Act of 1995. Forward-looking statements include, but are not limited to, statements related to activities, events or developments that the Company expects or anticipates will or may occur in the future, including, without limitation, statements related to the Company's exploration and development plans, activities and intentions; additional funding requirements; the timing of commencing production; expected mining rates; and when such mining rates are expected to be achieved. These forward-looking statements represent management's best judgment based on current facts and assumptions that management considers reasonable. Forward-looking statements are frequently characterized by words such as "target", "plan", "expect", "project", "intend", believe", "anticipate" and other similar words, or statements that certain events or conditions "appear to", "may" or "will" occur. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. The factors include but are not limited to risks related to the joint venture operation, actual results of exploration activities, the inherent risks involved in the exploration and development of mineral properties, changes in project parameters (including the required dewatering capacity) as plans continue to be refined, delays in obtaining government approvals, the uncertainties of project cost overruns or unanticipated costs and expenses, uncertainties relating to the availability and costs of the additional funds currently required by the Company (there being no assurance that such additional funds will be available on terms acceptable to the Company, if at all) and funds that may be required in the future, the uncertainties inherent to conducting business in Brazil and the rest of Latin America, the availability of equipment and supplies, unexpected adverse climate conditions, the reliance on only a few key members of management, as well as those factors discussed in the section entitled "Risk Factors" in the Company's most recent Annual Information Form filed with Canadian provincial securities regulatory authorities and other regulatory filings which are posted on SEDAR at www.sedar.com. Unless required by law, Colossus undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change. The reader is cautioned not to place undue reliance on forward-looking statements.



Colossus Minerals Inc.
Claudio Mancuso
CEO
(416) 643-7655
cmancuso@colossusminerals.com
or
Colossus Minerals Inc.
Ann Wilkinson
VP, Investor Relations
(416) 643-7655
awilkinson@colossusminerals.com
www.colossusminerals.com
Data and Statistics for these countries : Brazil | Canada | All
Gold and Silver Prices for these countries : Brazil | Canada | All

Colossus Minerals Inc

EXPLORATION STAGE
CODE : CSI.TO
ISIN : CA19681L1094
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Colossus Minerals is a gold and palladium exploration company based in Canada.

Its main exploration properties are SERRA PELADA and NATIVIDADE in Brazil.

Colossus Minerals is listed in Canada. Its market capitalisation is CA$ 4.3 millions as of today (US$ 3.8 millions, € 2.8 millions).

Its stock quote reached its highest recent level on December 03, 2010 at CA$ 9.87, and its lowest recent point on January 17, 2014 at CA$ 0.03.

Colossus Minerals has 106 978 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Colossus Minerals Inc
11/30/2009Expiry of Warrants
11/25/2009’s Final Reminder to Holders of Unexercised $2.70 Common Sha...
10/26/2009Provides Notice of Early Expiry of Warrants
3/10/2009Announces Closing Of $24.7 Million Bought Deal Financing
2/12/2009Announces Cdn$21,500,000 Bought Deal Financing
Nominations of Colossus Minerals Inc
10/16/2013Names David Massola as New Chief Financial Officer
3/28/2013Provides Development Update and Announces the Addition of J....
12/11/2012Announces Management Appointments and Board Changes
11/8/2012Announces Search for Chief Operating Officer
10/12/2012Appoints John Frostiak as Chairman Following Planned Departu...
7/16/2012Appoints Lyle Pritchard as Vice President, Operations and Pr...
8/2/2011Appoints Antenor Silva and Mel Leiderman to its Board of Dir...
5/18/2011Appoints David Anthony to the Board of Directors
5/9/2011Appoints Paulo de Tarso Serpa Fagundes Chief Operating Offic...
3/3/2011Appoints Claudio Mancuso as Chief Financial Officer
9/28/2009Appoints Randy Reichert as President & COO
Project news of Colossus Minerals Inc
2/7/2013' Development Remains On Schedule for Initial Production In ...
12/15/2011(Serra Pelada)Extends High Grade Subzones in the CMZ and Expands the GT Zo...
3/24/2011(Serra Pelada)Drills 7.81 Metres at 136.43 g/t Gold, 249.20 g/t Platinum a...
12/17/2009(Serra Pelada)Approval of the Final Exploration Report for the Serra Pelad...
11/2/2009(Serra Pelada)Media Coverage: “Colossus Delivers More Monster Holes at Ser...
11/3/2009(Serra Pelada)Commences Metallurgical Testing on Gold-Platinum-Palladium M...
9/3/2009(Serra Pelada)Drills 4.15 Metres @ 8.04 g/t Gold, 154.5 g/t Platinum and 2...
6/1/2009(Serra Pelada)Sponsors First Essay Writing Contest in Serra Pelada
2/11/2009(Serra Pelada)7.88M @ 98.4 g/t Platinum, 115.7 g/t Palladium, 2.74 g/t Rho...
Corporate news of Colossus Minerals Inc
10/25/2013Announces Board Change
9/23/2013Provides Development Update
9/10/2013to Present at the Bank of America Merrill Lynch 19th Annual ...
8/26/2013(Serra Pelada). Clarifies Events at Serra Pelada
8/13/2013. Completes C$37,950,000 Million Bought Deal Financing
7/23/2013. Announces Overnight Marketed Offering
7/15/2013Provides Development Update
7/8/2013Intersects Gold and Copper in its Phase 1 Drilling Program o...
7/8/2013Intersects Gold and Copper in its Phase 1 Drilling Program o...
6/18/2013Provides Development Update
6/12/2013. Completes C$28.75 Million Bought Deal Financing
5/21/2013Announces Voting Results
5/15/2013Provides Development Update
4/16/2013to Present at the European Gold Forum 2013
2/25/2013to Present at the BMO Capital Markets 22nd Global Metals & M...
1/25/2013to Present at the 2013 TD Securities Mining Conference
1/10/2013Intersects High Grade Gold Values in Diamond Drilling at Ele...
9/19/2012and Sandstorm Agree to a US$75 Million Long-Term Precious Me...
9/10/2012to Present at the 2012 Denver Gold Forum
8/20/2012Provides Update on Exploration on Elefante Area
6/18/2012Drills 3.30 Metres at 54.48 g/t Gold, 0.69 g/t Platinum and ...
5/29/2012to Present at Euro Pacific Global Investment Conference
5/15/2012Provides Update and Reminder of Annual General Meeting
4/30/2012to Present at Macquarie's "Making the Grade" Mining Conferen...
4/25/2012Drills 109.89 g/t Gold, 0.75 g/t Platinum and 15.51 g/t Pall...
4/10/2012Announces Significant Achievement in Metallurgical Recoverie...
4/2/2012(Serra Pelada)Provides Operations and Development Update for Serra Pelada
3/12/2012Expands the Elefante Mineralization, Intersects Gold in Uppe...
3/1/2012. Joins OTCQX
2/23/2012to Present at BMO Capital Markets 2012 Global Metals & Minin...
1/24/2012to Present at TD Securities 2012 Mining Conference
1/16/2012Acquires Cutia Property
12/2/2011to Present at Clarus Securities Inc. "Top of the Rocks" Inve...
10/11/2011Continues Strategic Evolution Toward Producer Status
9/7/2011Drilling Extends the GT Zone and High-Grade Subzones in the ...
4/26/2011Drills 7.30 Metres at 1494.7 g/t Gold, 516.6 g/t Platinum an...
1/24/2011Announces Results of AGM and Expiry of Warrants
11/23/2009Earning a 75% Interest in Serra Pelada Project
11/12/2009Listed on Van Eck’s Junior Miners ETF Index
11/12/2009Announces an Amendment to the Partnership Agreement with Coo...
10/28/2009Media Coverage: Steve Palmer, President & CEO of Alpha North...
10/7/2009Announces Filing Of Preliminary Prospectus
10/1/2009Announces $57.5 Million Bought-Deal Financing and Adopts Sha...
9/30/2009Drills 70.70 metres @ 53.59 g/t gold, 20.77 g/t platinum and...
8/10/2009Announces Change of Auditors
8/4/2009’s Check Assays Yield Higher Precious Metal Grades
7/3/2009Media Coverage: Mining Journal’s Feature on Brazil Highlight...
7/2/2009Media Coverage: Sprott Asset Management's Charles Oliver and...
6/15/2009Media Coverage: John Embry, Chief Investment Strategist at S...
6/4/2009Drills 27.9 metres @ 35.49 g/t gold, 19.89 g/t platinum and ...
2/11/2009Media Coverage: Steve Palmer, President & CEO of Alpha North...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CSI.TO)
0.040+0.00%
TORONTO
CA$ 0.040
02/21 15:47 -
0%
Prev close Open
0.040 0.040
Low High
0.030 0.040
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.040 -%
Volume 1 month var.
1,866,075 -%
24hGold TrendPower© : -11
Produces
Develops
Explores for Gold - Palladium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 10/8/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :