Stornoway Provides Renard Project Update
Published : June 03, 2013

Progress on Project Financing, Access Road Construction, and Final Permitting

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

MONTREAL, QUEBEC--(Marketwired - June 3, 2013) - Stornoway Diamond Corporation (News - Market indicators) is pleased to provide an update on progress at the Renard Diamond Project, Stornoway's 100% owned Diamond development project located in north-central Québec. Stornoway's principal focus at this time is the timely completion of project financing on a schedule defined by the development of the Renard Mine Road, which is currently in construction under Stornoway's management. Stornoway's development team is also engaged in detailed mine engineering work, the completion of all outstanding permitting, and an update to the project's NI 43-101 Mineral Resource estimate following the completion of the recent bulk sample at the Renard 65 kimberlite.

Matt Manson, Stornoway's President and CEO, stated: "We are pleased to report continued good progress on the construction of the Renard Mine Road, where we are forecasting completion on schedule and within budget. We are also encouraged by the progress made to date on project financing. Stornoway is pursuing a financing strategy based on a combination of debt, equity and the forward sale of diamonds. Despite challenging market conditions, the project has been well received by potential financing partners based on, among other things, its scale of resource, accessibility, strong social acceptability, and long potential mine life. Our aim is the completion of this financing on a schedule that allows us to utilize the Renard Mine Road for mine construction as soon as it becomes available for all-season traffic later in the year. This schedule offers Stornoway the opportunity to develop the Renard Project over a period when the Diamond market is expected to strengthen markedly, and when the global mining sector has entered a period of cost stabilization and contractor availability."

The Renard Mine Road

On March 27th Stornoway announced that construction on the 97km long Renard Mine Road had commenced ahead of schedule due to favourable winter weather conditions. Good progress has continued to be made through April and May, and overall completion currently stands at 22% with 7 of 16 permanent bridges in place. First all-season vehicle access to Renard is currently scheduled for October 2013, well within the previously announced schedule.

The cost of the Renard Mine Road has been budgeted at $77 million, including a 15% contingency. This cost is being funded through a credit facility provided to Stornoway by the Québec Ministère des Finances et de l'Économie bearing interest at the rate of 3.35% and amortized over a period of 15 years. Stornoway is also entitled to draw an additional $7.7 million bearing interest at the rate of 6.3%, for a total facility of up to $84.7 million, should extra contingencies be required. The schedule of repayment of these loans will be based on the financing and construction schedule of the Renard Diamond Project. To-date, Stornoway has drawn $26.3 million from the credit facility and anticipates completing construction work within the base budget.

Project Financing

On September 6th, 2012 Stornoway announced that it had entered into a Mandate Letter and draft term sheet with seven financial institutions (the "Mandated Lead Arrangers") in connection with a potential senior debt financing of up to US$475 million. Since that time, the Mandated Lead Arrangers have undertaken their due diligence and are well advanced in this process. When all due diligence has been completed, the parties will establish a final view on the quantum of debt, equity, forward sale proceeds and contingent overrun facilities required to be in place at closing. The Mandate Letter does not itself constitute a commitment to underwrite, provide or secure financing, which remains subject to, among other things, the terms and conditions of the term sheet attached to the Mandate Letter, credit and other approvals, and the completion of definitive loan documentation. However, based on the progress made to date, Stornoway has engaged in discussions with potential equity investors and off-takers with a view to completing the balance of project funding forthwith. These discussions are ongoing.

Project Permitting and Social Acceptance

The Renard Diamond Project Mining Lease was issued by the Québec Ministère des Ressources naturelles in October 2012 and the Québec Certificate of Authorization was issued by the Ministère du Développement Durable, de l'Environnement,de la Faune et des Parcs ("MDDEFP") in December 2012. The accompanying Government of Canada review of the project under the Canadian Environmental Assessment Act remains ongoing. Federal authorizations are required from Fisheries and Oceans Canada and Natural Resources Canada with respect to the Fisheries Act and the Explosive Act. Successful local hearings on the project were held by the federal regulators in June 2012, and on May 10th, 2013 the Canadian Environmental Assessment Agency ("CEEA") released its Comprehensive Study Report ("CSR"), which concluded that the Renard Project is "not likely to cause significant adverse environmental effects". The CEEA have invited public comments on the CSR before June 10th, 2013. Following completion of this process the Renard Project will become eligible to receive its federal approval, termed an "Environmental Assessment Decision", at which time all major permitting milestones will have been achieved.

Stornoway received the transfer of the Certificate of Authorization for the construction of the Renard Mine Road from the MDDEFP in December 2012. Consistent with this transfer, and the reduced scope of the Renard Mine Road compared to the two-lane public highway that was previously contemplated, Stornoway filed an amendment to the road project's Environmental and Social Impact Assessment on February 15th, 2013 with the Evaluation Committee ("COMEX") of the James Bay and Northern Québec Agreement, the environmental protection regime for the James Bay Region of Québec. On May 30th Stornoway received the addendum to the road's Certificate of Authorisation relating to this amendment.

Renard Resource Update

Stornoway expects to complete an update to the project's National Instrument "NI" 43-101 Mineral Resource Estimate prior to the end of the second quarter. This new estimate is expected to incorporate the conversion of a portion of existing Inferred Mineral Resources at Renard 65 to Indicated Mineral Resources following the completion of the 2012 5000 tonne bulk sampling program and March 2013 Diamond valuation exercise. In addition, Stornoway will update the existing Mineral Resource estimates for certain other kimberlite pipes, including Renard 2, based on new drill data received following normal-course geotechnical and hydrogeological studies over the past 12 months.

About the Renard Diamond Project

The Renard Diamond Project is located approximately 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau in the James Bay region of north-central Québec. In November 2011, Stornoway released the results of a Feasibility Study at Renard, followed by an Optimization Study in January 2013, which highlighted the potential of the project to become a significant producer of high value rough diamonds over a long mine life. Probable Mineral Reserves as defined under National Instrument ("NI") 43-101 stand at 17.9 million carats, with a further 17.5 million carats classified as Inferred Mineral Resources, and 23.5 to 48.5 million carats classified as non-resource exploration upside. All kimberlites remain open at depth. Pre-production capital cost stands at an estimated C$752 million, with a life of mine operating cost of C$57.63/tonne giving a 67% operating margin over an initial 11 year mine life. Readers are referred to the technical report dated December 29th, 2011 in respect of the November 2011 Feasibility Study for the Renard Diamond Project, and the technical report dated February 28th, 2013 in respect of the January 2013 Optimization Study, for further details and assumptions relating to the project.

About Stornoway Diamond Corporation

Stornoway is a leading Canadian Diamond exploration and development company listed on the Toronto Stock Exchange under the symbol SWY and headquartered in Montreal. Our flagship asset is the 100% owned Renard Diamond Project, on track to becoming Québec's first Diamond mine. Stornoway is a growth oriented company with a world class asset, in one of the world's best mining jurisdictions, in one of the world's great mining businesses.

On behalf of the Board

STORNOWAY Diamond CORPORATION

Matt Manson, President and Chief Executive Officer

This press release contains "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as "forward-looking statements", are made as of the date of this press release and the Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by law.

Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: (i) the amount of mineral resources and exploration targets; (ii) the amount of future production over any period; (iii) net present value and internal rates of return of the mining operation; (iv) assumptions relating to recovered grade, average ore recovery, internal dilution, mining dilution and other mining parameters set out in the Feasibility Study or the Optimization Study; (v) assumptions relating to gross revenues, operating cash flow and other revenue metrics set out in the Feasibility Study or the Optimization Study; (vi) mine expansion potential and expected mine life; (vii) expected time frames for completion of permitting and regulatory approvals and making a production decision; (viii) the expected time frames for the construction of a mining grade road by Stornoway and completion generally of the Route 167 extension and the financial obligations or costs incurred by Stornoway in connection with such road extension; (ix) future exploration plans; (x) future market prices for rough diamonds; and (xi) sources of and anticipated financing requirements. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "assumes", "intends", "strategy", "goals", "objectives" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements are made based upon certain assumptions by Stornoway or its consultants and other important factors that, if untrue, could cause the actual results, performances or achievements of Stornoway to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which Stornoway will operate in the future, including the price of diamonds, anticipated costs and Stornoway's ability to achieve its goals. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking statements include, but are not limited to: (i) estimated approval date of the Environmental and Social Impact Assessment; (ii) required capital investment and estimated workforce requirements; (iii) estimates of net present value and internal rates of return; (iv) receipt of regulatory approvals on acceptable terms within commonly experienced time frames; (v) the assumption that a production decision will be made, and that decision will be positive; (vi) anticipated timelines for the commencement of mine production; (vii) anticipated timelines related to the construction of a mining grade road by Stornoway and completion generally of the Route 167 extension and the impact on the development schedule at Renard; (viii) anticipated timelines for community consultations and the impact of those consultations on the regulatory approval process; (ix) market prices for rough diamonds and the potential impact on the Renard Project's value; and (x) future exploration plans and objectives.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important risk factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, including the assumption in many forward-looking statements that other forward-looking statements will be correct, but specifically include, without limitation, (i) risks relating to variations in the grade, kimberlite lithologies and country rock content within the material identified as mineral resources from that predicted; (ii) variations in rates of recovery and breakage; (iii) the greater uncertainty of exploration targets; (iv) developments in world Diamond markets; (v) slower increases in Diamond valuations than assumed; (vi) risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar; (vii) increases in the costs of proposed capital and operating expenditures; (viii) increases in financing costs or adverse changes to the terms of available financing if any; (ix) tax rates or royalties being greater than assumed; (x) results of exploration in areas of potential expansion of resources; (xi) changes in development or mining plans due to changes in other factors or exploration results of Stornoway; (xii) changes in project parameters as plans continue to be refined; (xiii) risks relating to receipt of regulatory approvals or the implementation of the existing Impact and Benefits Agreement with aboriginal communities; (xiv) the effects of competition in the markets in which Stornoway operates; (xv) operational and infrastructure risks; (xvi) technical, environmental, permitting and execution risk relating to the construction by Stornoway of a mining grade road forming part of the Route 167 extension, (xvii) the additional risks described in Stornoway's most recently filed Annual Information Form, annual and interim MD&A, and Stornoway's anticipation of and success in managing the foregoing risks. Stornoway cautions that the foregoing list of factors that may affect future results is not exhaustive.

When relying on our forward-looking statements to make decisions with respect to Stornoway, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. Stornoway does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by Stornoway or on our behalf, except as required by law.



Stornoway Diamond Corporation
Matt Manson
President and CEO
416-304-1026 or Toll Free: 1-877-331-2232
or
Stornoway Diamond Corporation
M. Ghislain Poirier
Vice-president, Affaires publiques
418 254-6550
gpoirier@stornowaydiamonds.com / info@stornowaydiamonds.com
www.stornowaydiamonds.com
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Stornoway Diamond Corporation

DEVELOPMENT STAGE
CODE : SWY.TO
ISIN : CA86222Q8065
CUSIP : 86222Q806
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Stornoway Diamond is a gold and copper exploration company based in Canada.

Stornoway Diamond develops gold, copper, diamonds and nickel in Canada, and holds various exploration projects in Botswana and in Canada.

Its main asset in development is RENARD (FOXTROT) in Canada and its main exploration properties are CHURCHILL, KINGORA, LDG, DARING LAKE, JEWEL, STARFISH, WALES ISLAND, HAMMER, RAVEN, SCEPTRE AND TIARA, QILALUGAQ, PORTAGE MINE, MELVILLE PENIN. and MELVILLE PENINSULA (AVIAT PROJECT) in Canada.

Stornoway Diamond is listed in Canada. Its market capitalisation is CA$ 16.6 millions as of today (US$ 12.6 millions, € 11.4 millions).

Its stock quote reached its highest recent level on May 14, 2004 at CA$ 9.80, and its lowest recent point on September 06, 2019 at CA$ 0.01.

Stornoway Diamond has 828 659 968 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Stornoway Diamond Corporation
4/10/2019Stornoway Diamond halts open pit operations at Quebec mine
11/15/2018Stornoway Diamond shares down on $37 million loss, departure...
Annual reports of Stornoway Diamond Corporation
LAUNCHES 2008 ONLINE ANNUAL REPORT: Posts Presentation from ...
Financings of Stornoway Diamond Corporation
7/11/2016Stornoway Receives C$82.72 Million from Warrant Exercise
3/31/2016Stornoway Announces Funding Of Third Tranche Of Stream Finan...
10/1/2015Stornoway Announces Funding of Second Tranche of Stream Fina...
11/13/2013Announces Increase To Bought Flow-Through Financing
4/19/2012Closes Private Placement of Units
3/8/2012Announces Bought Deal Equity Financing
8/1/2011Announces Financing Agreements With Québec For the Route 167...
5/29/2009Announces Closing of Flow-Through Financing
11/14/2008Announces Closing of Financings
11/5/2008Increases Previously Announced Private Placement
11/4/2008Announces Flow-Through Financing
8/1/2008Closes $22 Million Private Placement and Redeems Convertible...
7/28/2008Announces $22 Million Private Placement To Close Within 21 D...
7/16/2008ARRANGES $22 MILLION PRIVATE PLACEMENT Proceeds To Redeem Co...
Nominations of Stornoway Diamond Corporation
8/15/2013Announces Appointment to Board of Directors
6/25/2013Announcement of Appointment
8/3/2011Announces Changes To The Board Of Directors
7/20/2011Announces New Appointments to the Board of Directors
5/3/2010Announces Appointment Of Chief Operating Officer
3/1/2010Announces Management Appointments
Financials of Stornoway Diamond Corporation
8/10/2017Second Quarter Results
7/27/2017Stornoway Announces Second Quarter Release Date
5/17/2016Stornoway Announces Results From Annual General Meeting
5/10/2016Stornoway Announces FY2016 First Quarter Results
5/5/2016Annual General Meeting
9/15/2009First Quarter Financial Results Posted, Matt Manson’s AGM Pr...
Project news of Stornoway Diamond Corporation
7/15/2016(Renard (foxtrot))Stornoway Commences Ore Processing At Renard Diamond Project
1/28/2014Provides Update On Exploration Joint Ventures
10/10/2013To Commence Early Construction Of Renard Mine Airport
9/3/2013First Vehicle Arrives At Renard Project Site Via New Permane...
8/7/2013Provides Update On Exploration Joint Ventures
7/23/2013Announces Updated Renard Mineral Resource Estimate
7/16/2013Receives Federal Government Authorisation For Renard Project
6/3/2013Provides Renard Project Update
3/14/2013Options Non-Core Exploration Projects
2/14/2013Reports Arrival Of Winter Road At Renard Project Site
1/28/2013Reports Optimized Renard Mine Design And Cost Estimates
6/1/2012Exhibiting at the World Resource Investment Conference: Vanc...
3/27/2012Signs Impacts And Benefits Agreement For The Renard Diamond ...
2/17/2012Renard Diamond Project Digital Fly-Through Video
1/4/2012Files NI 43-101 Technical Report For The Renard Feasibility ...
12/10/2011Renard Diamond Project Community Relations Video
10/3/2011Provides Update On Pipeline Projects
5/25/2011(Hammer)Announces Exploration Drill Program at Hammer Property, Nuna...
4/28/2011(Renard (foxtrot))Provides Renard Project Update Feasibility Study on Track fo...
4/1/2011(Renard (foxtrot))Announces Closing Of Agreement To Acquire Remaining 50% Of R...
3/7/2011(Aviat)Announces New Microdiamond Results From the Aviat Project, N...
2/23/2011(Renard (foxtrot))Announces Positive Microdiamond Results from Renard 1
2/10/2011(Renard (foxtrot))Shareholders Overwhelmingly Approve Acquisition Of Remaining...
2/7/2011(Renard (foxtrot))Files NI 43-101 Technical Report On The Recently Revised Res...
1/24/2011(Renard (foxtrot))Announces Increased Ni 43-101 Mineral Resource Estimate For ...
12/14/2010(Renard (foxtrot))Stornoway Announces Acquisition Of Remaining 50% Of Renard P...
3/22/2010(Renard (foxtrot))Renard Updated Economic Assessment Teleconference Archive No...
12/8/2009Announces Revised Ni 43-101 Mineral Resource Estimate For Re...
3/9/2009(Renard (foxtrot))Provides Renard Drilling Update: Renard 2 Kimberlite Greatly...
2/19/2009(Aviat)Reports Initial Diamond Results From Aviat 200 Tonne Bulk Sa...
12/15/2008Reports Filing of NI 43-101 Technical Report for Renard Prel...
11/28/2008(Churchill)Reports Diamond Counts From Two Kimberlites At Churchill
9/24/2008(Churchill)And Shear Announce 9 New Kimberlites At Churchill Diamond Pr...
9/15/2008(Churchill)and Shear Announce New Killiq Kimberlite at Churchill Diamon...
9/8/2008(Aviat)Doubles Size of Aviat’s Highly Diamondiferous AV267 Sheet
9/4/2008(Qilalugaq)Discovers New Kimberlite at Qilalugaq
7/2/2008(Churchill)and Shear Announce 2008 Program Underway at the Churchill Di...
6/27/2008(Churchill)And Shear Report Additional High Interest Mineral Dispersion...
5/15/2008(Aviat) Provides Aviat Project Spring Update Increases Project Inte...
4/28/2008(Renard (foxtrot))New Renard Diamond Valuation Results and Pre-Feasibility Upd...
3/13/2008(Aviat)Improves On Diamond Content of Aviat Kimberlites AV1 and AV2...
2/20/2008(Churchill)and Shear Report Additional Diamonds from Kahuna Drilling
1/31/2008(Churchill) and Shear Report High Diamond Counts from Four Kimberlites ...
1/29/2008(Aviat)Reports Diamond Content of 162 Cpht from 20.6 Tonne Aviat Sa...
1/28/2008(Renard (foxtrot))HIGH DIAMOND CONTENT CONFIRMED AT HIBOU DYKE 126 Cpht from 3...
12/12/2007(Melville Peninsula Aviat 1)Third Kimberlite Pipe At Aviat Proves Diamondiferous
11/14/2007(Churchill Project) and Shear Recover a 5.43 Carat Diamond fromChurchill?sKahun...
9/25/2007(Sua Pan (stornoway/motapa Jv))and Motapa Commence Drilling at Sua Pan Project, Botswana
7/25/2007 Commences Pre-Feasibility Study on Renard Diamond Deposit
Corporate news of Stornoway Diamond Corporation
6/29/2016Stornoway Reminds Warrantholders Of Upcoming Exercise Deadli...
6/22/2016Stornoway commences plant commissioning at Renard Diamond Pr...
6/6/2016Stornoway Provides Renard Operational Readiness Update
5/5/2016Stornoway Intersects Kimberlite At Adamantin Project
3/30/2016Stornoway Announces Updated Renard Mine Plan and Mineral Res...
10/14/2015Stornoway Files Renard NI 43-101 Technical Report
9/8/2015North Arrow Confirms High Diamond Counts From Pk150 Kimberli...
3/30/2015North Arrow Discovers Three New Kimberlites at the Pikoo Dia...
3/24/2015Stornoway Announces Third Quarter 2015 Results
3/24/2015Stornoway Commences Pre-Stripping at Renard 2-Renard 3 Open ...
3/11/2015Stornoway Announces Third Quarter 2015 Results
2/26/2015North Arrow Reports Initial Diamond Recoveries From First 60...
2/12/2015Stornoway to Attend Upcoming Investor Conferences
2/11/2015North Arrow Drilling Program Underway at Pikoo, Saskatchewan
1/21/2015North Arrow Updates Qilalugaq Project Bulk Sample Processing
12/16/2014Stornoway Announces Second Quarter 2015 Results
12/15/2014Stornoway Announces Second Quarter 2015 Results
11/17/2014Stornoway Completes Field Portion Of 2014 Renard Drill Progr...
11/17/2014Stornoway Completes Field Portion of 2014 Renard Drill Progr...
11/10/2014Stornoway Lists Convertible Debentures
11/10/2014Stornoway Lists Convertible Debentures
10/22/2014Stornoway Announces Results From Annual General Meeting
10/22/2014Stornoway Announces Results From Annual General Meeting
10/20/2014Stornoway Adds Large Diamond Recovery Capacity To Renard Dia...
10/20/2014Stornoway Adds Large Diamond Recovery Capacity to Renard Dia...
9/23/2014North Arrow Identifies New Targets at the Pikoo Diamond Proj...
9/22/2014Stornoway Announces Notice of 2014 Annual Meeting of Shareho...
9/15/2014Stornoway Announces First Quarter 2015 Results
8/25/2014Stornoway Provides Renard Project Update
7/21/2014Stornoway Awards EPCM Contract to SNC-Lavalin Inc.
7/16/2014Stornoway Announces Appointment of Douglas Silver to Board o...
7/10/2014Stornoway Announces Formal Production Decision at Renard
7/8/2014Announces Closing Of Comprehensive Financing Package To Fund...
7/8/2014Stornoway Announces Closing of Comprehensive Financing Packa...
6/27/2014Shareholders Overwhelmingly Approve Resolutions Relating To ...
6/26/2014Stornoway Shareholders Overwhelmingly Approve Resolutions Re...
3/27/2014Stornoway Confirms Negotiations For Project Financing
11/13/2013Announces Flow-Through Financing For Renard Resource Expansi...
11/5/2013Hosts Québec Minister of Natural Resources at Montreal Press...
10/24/2013Announces Results From Annual General Meeting
10/21/2013to Proceed With Liquefied Natural Gas (LNG) Power Plant for ...
10/2/2013Arranges $20M Bridge Facility for Renard Diamond Project
6/25/2013Reports Quebec Strike Action Settled
6/19/2013Provides Renard Mine Road Update
5/7/2013Welcomes Clarity On Future Quebec Mining Taxation
4/11/2013Reports Positive Renard 65 Diamond Valuation Result
3/27/2013Provides Construction Update on the Renard Mine Road
3/12/2013Reports Fatality In Accident On The Winter Road
2/25/2013Completes Renard 65 Diamond Recovery
12/11/2012Recovers High Value 9.78 Carat Stone From Renard 65 Bulk Sam...
10/29/2012Provides Update on the Route 167 Extension
10/18/2012Receives Renard Mining Lease
9/25/2012Annual Summary
9/11/2012Announces Results From Annual General Meeting
9/6/2012Executes Mandate Letter With Lead Arrangers For Renard Proje...
8/30/2012Announces The Successful Completion Of The Final Public Hear...
7/23/2012to Commence Bulk Sampling of Renard 65 Kimberlite
7/5/2012Signs Partnership Accord With Chibougamau And Chapais
7/4/2012Provides Update On Renard Powerline Study
7/4/2012Presentation from the RBC Diamond Conference in London, June...
6/12/2012(Qilalugaq)Reports Initial 26.1 Million Carat Mineral Resource Estimate...
6/8/2012Announces the Successful Completion of Federal Public Consul...
5/31/2012Announces Establishment Of Head Office In Montreal
5/24/2012Video of the Mecheshoo Agreement Signing Ceremony
5/23/2012Announces $28.4m Renard Pre-Development Capital Program
5/4/2012Arranges a $20 Million Unsecured Debt Facility for Renard Di...
3/22/2012Conducts Successful Open Houses in Chibougamau and Mistissin...
2/3/2012Announces Commencement Of Construction Of Route 167 Extensio...
1/12/2012Corporate Video, Social Media, and Upcoming Events
12/28/2011Announces Filing of the Renard Environmental and Social Impa...
12/7/2011Québec Releases Certificate Of Authorization For The Constr
12/5/2011Video Presentation from the 2011 Scotia Capital Mining Confe...
10/26/2011Annual Summary
9/20/2011Provides Renard Project Update
9/12/2011Announces Addition to S&P/TSX SmallCap Index
8/6/2011English Language Media Attention Regarding Route 167 Road Ag...
8/1/2011Announces FinancingAgreements With Québec For Th
7/11/2011Announces Acquisition of "Aeon" Claims in Northern Quebec
6/13/2011Announces 56% Increase in Renard Diamond Price Estimate
4/27/2011Announces 2011 Exploration Program And Budget
3/20/2011Welcomes Quebec Budget Announcement of Financing for the Rou...
2/18/2011to Commence Trading on Consolidated Basis at Market Opening ...
4/7/2010Matt Manson on CBC's the Lang and O'Leary Exchange
3/22/2010Reports Updated Renard Preliminary Assessment Pre-Tax NPV In...
3/8/2010Reports Overall Diamond Recovery Of 86.2 CPHT From Notch Sam...
2/12/2010Files Renard “Notice Of Intent”
1/15/2010Upcoming Conferences in Vancouver
11/28/2009Presentation from the Quebec Exploration Conference: the 200...
10/6/2009s Announces Fourfold Tonnage Increase In Renard 2 Following ...
8/10/2009And Shear Option Chesterfield Inlet Claims, Nunavut
7/30/2009(Hammer)Reports Discovery Of Hammer Kimberlite
7/8/2009is now on Twitter
6/8/2009Renard Summer Drill Program Commences
1/24/2009Upcoming Events
1/15/2009Reports 144 Cpht In Large Tonnage Hibou Dyke Sampling
1/7/2009Provides 2009 Exploration Outlook
12/17/2008Provides Corporate Update
7/14/2008Related News
5/1/2008 is Attending the CIM Conference in Edmonton, May 4-6
3/4/2008Additional Diamond Results From Renard 65 and North Anomaly ...
1/21/20083.64 Carat Diamond Recovered from AV2 Kimberlite at Aviat
12/14/2007 Announces Additional Renard Diamond Recovery Results
12/3/2007 And Shear Recover 337 Carats From 356 Tonne Kahuna Bulk Sam...
10/22/2007 Announces Positive Valuation Results From Renard Bulk Sampl...
9/19/2007Yves Harvey Appointed Member of Stornoway Board of Directors
9/18/2007And Shear Confirm High Commercial Diamond Content AtChurchil...
9/11/2007Qilalugaq Diamond Exploration Program Update
9/6/2007Aviat's Eastern Sheet Complex Points To Significant Tonnage
8/23/2007New Kimberlite Pipe Discovered At Aviat
8/14/2007 Reports 2,213 Carats Recovered From Renard 4
8/1/2007Reports an Additional 31 Diamonds Weighing 1.74 Carats from ...
7/31/2007Reports 1,642 Carats Recovered from Renard 2 Including a 15....
7/17/2007and Shear Announce Closing of BHP Billiton Diamond Inc's Int...
7/10/2007Enters Into Agreement with Bayswater to Explore Diamond Targ...
6/20/2007Reports 2,681 Carats Recovered From Renard 3 Including A 10....
5/17/2007Reports an Initial Diamond Content of 150 cpht from Renard 3...
5/14/2007Provides Exploration Update - On Schedule For First Renard D...
5/14/2007Provides Exploration Update
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (SWY.TO)
0.020+100.00%
TORONTO
CA$ 0.020
09/06 17:15 0.010
100%
Prev close Open
0.010 0.010
Low High
0.010 0.020
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.020 -%
Volume 1 month var.
15,947,741 -%
24hGold TrendPower© : -33
Produces
Develops Diamonds
Explores for Diamonds - Gold - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.79+1.04%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55-0.90%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+5.26%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.88%Trend Power :