Mustang Provides Update at Maskwa Nickel Project Feasibility Study
TORONTO, ONTARIO--(Marketwire - Dec. 1, 2008) - Mustang Minerals Corp., (TSX VENTURE:MUM)(FRANKFURT:NJF) today announced an update of corporate and project activities from the Maskwa Nickel Project located near Lac du Bonnet in southeast Manitoba. Mustang is progressing with key activities towards completion of a feasibility study for Maskwa. Micon International Limited ("Micon") has been retained to complete a National Instrument 43-101 compliant updated resource estimate as part of the feasibility study underway for the project. Priority project activities are completion of a new resource estimate (in progress) for the Maskwa Deposit and continuing metallurgical testwork to optimize metallurgical recoveries and concentrate grade. For the fiscal period ended September 30, 2008 Mustang had over $3 million in working capital which will be utilized to fund major project activities through 2009.

Resource Update

Micon will be completing a revised resource estimate for the project commencing this month. The new resource estimate will include results of new drilling completed since the last resource estimate of September 1, 2007 (Wardrop Engineering) and results from previously unsampled drill core. Four of the new resource drill holes (MM08-130 to 133) targeted near-surface intervals from sections in the resource base where spatially limited sampling from historic drill holes drilled in the 1970's resulted in a significant narrowing of the apparent mineralized zone. These holes were completed earlier in 2008 and results are tabulated below with comparative results from the historic holes. Holes were designed as duplicates of the historic holes, however some minor changes during drill set up were required due to ground surface conditions.

---------------------------------------------------------------------------
Drill hole             From     To   Interval     Ni     Cu      Co     PGM
---------------------------------------------------------------------------
 At 325655E              (m)    (m)        (m)    (%)    (%)     (%)    g/t
---------------------------------------------------------------------------
---------------------------------------------------------------------------
MM08-130               11.1   23.5       12.4   0.32   0.07    0.02   0.301
---------------------------------------------------------------------------
AND                   108.8  148.1       39.3   0.52   0.14    0.02   0.612
---------------------------------------------------------------------------
including             133.4  145.1       11.7   0.91   0.16    0.03   1.144
---------------------------------------------------------------------------
Historic Hole 74-46    96.9  134.3       37.4   0.46   0.14      NA      NA
---------------------------------------------------------------------------
 At 325763E
---------------------------------------------------------------------------
MM08-131               69.2  106.9       37.7   0.45   0.08    0.02   0.476
---------------------------------------------------------------------------
including              86.0   96.0       10.0   0.82   0.11    0.03   0.903
---------------------------------------------------------------------------
Historic Hole 74-68    38.9   56.4       17.5   0.63   0.14      NA      NA
---------------------------------------------------------------------------
 At 325800E
---------------------------------------------------------------------------
MM08-132               37.2   89.9       52.7   0.49   0.09    0.02   0.533
---------------------------------------------------------------------------
including              74.7   86.7       12.0   1.01   0.20   0.031   1.293
---------------------------------------------------------------------------
Historic Hole 74-49    69.0   93.8       24.8   0.48   0.15      NA      NA
---------------------------------------------------------------------------
 At 325933E
---------------------------------------------------------------------------
MM08-133               21.9   51.5       29.6   0.56   0.15    0.02   1.301
---------------------------------------------------------------------------
Above Includes         26.2   35.0        8.8   0.74   0.12    0.03   3.007
---------------------------------------------------------------------------
Historic Holes 74-45   70.3   81.7       11.4   0.43   0.11      NA      NA
---------------------------------------------------------------------------
Note: holes are apparent and not true width.
(m) equals meters Ni equals Nickel Cu equals Copper Co equals Cobalt PGM
equals Au+Pt+Pd
 
The four holes above were drilled over a strike length of 278 meters in the east-central part of the deposit. The historic holes were not assayed for platinum group metals. There were significant platinum group metals values found in the holes drilled by Mustang. The new holes showed that mineralization extended well beyond the limit indicated by past logging and assay work of the historic holes.

Reassay Program

Mustang has completed a reassay program on a total of 42 holes. Previously unsampled intervals of drill core from holes in the eastern portion of the resource pit shell were assayed. Mineralized zones were interpreted either as hangingwall mineralization or lower grade mineralization proximal to the main mineralized zone at Maskwa. Several of the best intercepts from the reassay program are presented in tabular form below.

---------------------------------------------------------------------------
Drill hole             From     To   Interval     Ni     Cu      Co     PGM
---------------------------------------------------------------------------
                         (m)    (m)        (m)    (%)    (%)     (%)    g/t
---------------------------------------------------------------------------
---------------------------------------------------------------------------

---------------------------------------------------------------------------
---------------------------------------------------------------------------
136                   189.9  203.6       14.6   0.48   0.11    0.02    0.56
---------------------------------------------------------------------------

---------------------------------------------------------------------------
MM04-02                47.9   61.6       13.7   0.40   0.17    0.02    0.38
---------------------------------------------------------------------------

---------------------------------------------------------------------------
MM04-21                64.6   75.3       10.7   0.39   0.08    0.02    0.53
---------------------------------------------------------------------------

---------------------------------------------------------------------------
MM04-09                43.0   55.5       12.5   0.33   0.10    0.02    0.38
---------------------------------------------------------------------------

---------------------------------------------------------------------------
MM04-04                31.1   38.7        7.6   0.55   0.14    0.03    0.43
---------------------------------------------------------------------------

---------------------------------------------------------------------------
MM05-51                25.0   44.8       19.8   0.34   0.11    0.02    0.41
---------------------------------------------------------------------------
All above intercepts are apparent not true width. Intervals are from
previously unassayed drill core and not included in previous resource
estimates.
 
Feasibility Study

Micon has been contracted as the lead consultant for a final feasibility study on the Maskwa Nickel Project. Other consultants will include Met-Chem Canada Inc., Wardrop Engineering and Golder Associates.

In addition to the update of the resource estimate, other activities underway currently include:

- Metallurgical testing on an average grade composite sample in order to finalize the process design has commenced with the laboratory of Xstrata Process Support;

- Metallurgical testing on a low grade material from the deposit hangingwall is also underway at a separate laboratory;

- Collection of samples from the recent drilling is commencing to allow metallurgical testing on material previously not examined, as a variability check;

- Preparing a site program to obtain detailed geotechnical design information for the open pit, processing area and the tailings containment system;

- Final details for the Environmental Impact Assessment report are being developed;

- Discussions have commenced with local utilities and services providers to establish final design parameters for the feasibility study.

Minesite Exploration

To further examine the immediate area of the proposed Maskwa pit, a 60 kilometer line grid is presently being cut. After completion a ground IP survey will be carried out to detect any potential near-pit mineralization.

Corporate

The Company is focused on enhancing project economics for the Maskwa Nickel Project. There is a strong anticipation that the currently depressed nickel prices and credit restrictions will improve and result in more favourable market conditions in the future. Maskwa combines simple mining and process techniques, modest capital cost, favourable infrastructure and jurisdiction and a project upside which Mustang believes makes the project unique in the Canadian junior nickel sector. Mustang remains sufficiently capitalized to complete important major project activities through 2009.

QA/QC

The drill core from the current drill program was processed and assayed at TSL Labs in Saskatoon, Saskatchewan. The core was split at the Maskwa site and a split of all the samples were retained as the other half was sent to the laboratory. Samples were analysed using a multi-acid digestion and assays presented are for total nickel. Mustang Minerals carries out a QA/QC program on all its drill holes including the insertion of standards and blanks.

Carey Galeschuk P. Geo and Ian Ward P. Eng., are the Qualified Persons for Mustang Minerals Corp. for purposes of National Instrument 43-101.

Disclaimer: The Company notes that assumptions and technical inputs used in the prefeasibility study may vary for the feasibility study. As such the results of a feasibility study will vary from those of the prefeasibility study.

To find out more about Mustang Minerals Corp. (TSX-V: MUM) visit our website at www.mustangminerals.com.

We seek safe harbour.

This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (Ontario) (together, "forward-looking statements"). Such forward-looking statements may include the Company's plans for its mineral projects in Manitoba, the overall economic potential of its properties, the availability of adequate financing and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements expressed or implied by such forward-looking statements to be materially different. Such factors include, among others, risks and uncertainties relating to potential political risk, uncertainty of production and capital costs estimates and the potential for unexpected costs and expenses, physical risks inherent in mining operations, currency fluctuations, fluctuations in the price of nickel and other metals, completion of economic evaluations, changes in project parameters as plans continue to be refined, the inability or failure to obtain adequate financing on a timely basis, and other risks and uncertainties, including those described in the Company's Management Discussion and Analysis for the period ended December 31, 2007 and thereafter and Material Change Reports filed with the Canadian Securities Administrators and available at www.sedar.com.

Shares Outstanding: 81,228,239


The TSX Venture Exchange has not reviewed and does not accept responsibility for the contents of this press release.

CONTACT INFORMATION:

Mustang Minerals Corp.
David Black
Investor Relations
(416) 955-4773
Email: info@mustangminerals.com
Website: www.mustangminerals.com

INDUSTRY: Manufacturing and Production - Mining and Metals

.
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Mustang Minerals Corp

DEVELOPMENT STAGE
CODE : MUM.V
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Mustang is a nickel and copper exploration company based in Canada.

Mustang develops nickel, copper, cobalt, palladium and platinum in Canada, and holds various exploration projects in Canada.

Its main asset in development is MAKWA in Canada and its main exploration properties are RIVER VALLEY PGM, EAST BULL LAKE, TILLICUM CLAIMS, RIVER VALLEY PGM and MAYVILLE in Canada.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Mustang Minerals Corp
1/24/2013Announces Completion of Additional Financing and 2013 Strate...
1/23/2012Completes Financing With Western Areas 7500m Drill Program U...
1/6/2012Completes Flow Through Financing
1/11/2010Completes Private Placement
12/8/2009Increases Private Placement Financing and Closes First Tranc...
11/6/2009Announces Non-Brokered Private Placement
Project news of Mustang Minerals Corp
2/20/2013(Mayville)Announces Increase to Mayville Resource
11/7/2012(Mayville)Provides Update on Mayville Drilling
9/12/2012(Mayville)Drilling at Mayville Property
6/14/2012(Mayville)Intersects Higher Grade Zone of Copper-Nickel-PGM Mineraliza...
5/17/2012(Mayville)Drilling Update-Mayville Project
6/2/2011(Mayville)Drill Program Resumes at Mayville Property
5/5/2011Drills 9=2E1 Meters of 3=2E9 g/t Platinum-Palladium Strike L...
4/6/2011(Mayville)Completes Additional Holes at New PGM Zone
3/23/2011MUSTANG MINERALS ANNOUNCES NEW PLATINUM AND PALLADIUM DISCOV...
3/22/2011Announces New Platinum and Palladium Discovery in Manitoba
12/1/2010(Mayville)s Exploration at Mayville/Tanco Properties
7/13/2010(Mayville)Exploration Deal With Tantalum Mining Corporation of Canada
3/22/2010(Makwa)Updates Project Economics at Makwa Nickel Project
2/17/2010(Makwa)Makwa Nickel Project Update
9/1/2009(Makwa)Advances its Maskwa Nickel Project
6/22/2009(East Bull Lake)Western Areas-Mustang JV Commences Drilling at East Bull Lak...
3/2/2009(Makwa)Completing Drilling at Manitoba Nickel Project
1/22/2009(Makwa)Provides Update on Maskwa Nickel Project Feasibility Study
12/1/2008(Makwa)Provides Update at Maskwa Nickel Project Feasibility Study
9/12/2008(East Bull Lake)and Western Areas Sign Agreement for Joint Venture at East B...
7/3/2008(East Bull Lake)New PGM+Ni+Cu Mineralization Drilled at East Bull Lake, Onta...
6/26/2008(Makwa)Mustang Tables Positive Prefeasibility for Maskwa Nickel Pro...
5/12/2008(East Bull Lake Pgm)Drilling at East Bull
5/9/2008(Makwa) Reports Positive Results From Prefeasibility Study at Maskw...
4/23/2008(Makwa)Tests Chromite Horizon at Maskwa Property
3/3/2008(Makwa)Drill Update at Maskwa North and Maskwa West
Corporate news of Mustang Minerals Corp
10/20/2015Board Resignation
12/10/2012(Mayville)Extends Mayville Cu-Ni Deposit Mineralization to the East
7/17/2012(Mayville)Drilling Extends Copper Nickel Mineralization to Depth at Ma...
3/5/2012Provides Exploration Update Continuesto Intersect PGM Minera...
12/1/2011(Mayville)Announces Mayville Exploration-Financing
9/9/2011: Corporate Update
3/3/2011(Mayville)Drills New Surface Zone of CopperNickel Mineralization at th...
4/15/2010Expands Resources in Project Area
11/19/2009and Sagkeeng First Nation Conclude Memorandum of Understandi...
9/18/2009AGM, September 22
10/1/2008Visit Our Booth This Weekend
8/5/2008Builds Project Development Team
7/17/2008 Closing of Oversubscribed, Increased Financing
7/16/2008Announces Increase to Brokered Financing
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (MUM.V)Other OTC (MSMGF)
0.175-2.78%0.048-4.00%
TSX-V
CA$ 0.175
06/07 13:54 -0.010
-2.78%
Prev close Open
0.180 0.180
Low High
0.175 0.195
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.175 -%
Volume 1 month var.
24,600 -%
24hGold TrendPower© : -31
Produces
Develops Cobalt - Copper - Nickel - Palladium - Platinum
Explores for Cobalt - Copper - Gold - Nickel - Palladium - Platinum - Rhodium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.66-0.71%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22+2.38%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :