ASX RELEASE


QUARTERLY ACTIVITIES REPORT

MARCH 2016 QUARTER



ASX RELEASE - 21 APRIL 2016


MARCH 2016 QUARTERLY ACTIVITIES REPORT

  • Iron Valley EBITDA of A$1.1M from shipments of 1.66M wmt

  • Reduced capital and operating cost estimates for a standalone 8 Mtpa mine-to-port operation at the Buckland Project

    o In particular, C1 cash costs have reduced by A$10/wmt to A$31.6/wmt (US$22/wmt1)

  • Evaluation progressing on a proposed 20 Mtpa road and port infrastructure operation to service Buckland and other third parties in the West Pilbara, with preliminary cost estimates indicating low capital intensity and competitive operating costs

  • Temporary suspension of operations at the NJV implemented

  • Cash balance of A$23.3M, with debt of A$2.0M and royalty obligations of A$7.7M


BC Iron Limited (ASX: BCI) ('BC Iron' or the 'Company') presents its quarterly activities report for the period ended 31 March 2016.

Iron Valley, which is operated by Mineral Resources Limited ('MIN') under an iron ore sales agreement, shipped 1.66M wet metric tonnes ('wmt') during the quarter. This generated EBITDA for BC Iron of A$1.1M, inclusive of a negative pricing adjustment of A$0.2M relating to prior periods. MIN is also advancing a range of improvement initiatives that have the potential to improve Iron Valley's economics for both BC Iron and MIN.

BC Iron continues to assess and optimise its 100% owned Buckland mine-to-port development project. During the quarter, revised capital and operating costs were released for a standalone 8 Mtpa mine-to-port operation, with expected C1 cash costs reducing by more than A$10/wmt to A$31.6/wmt (US$22/wmt) and expected capital costs (upfront and deferred) reducing by A$55M to A$942M (US$660M). The significant decrease in C1 cash costs is due to the adoption of an innovative road haulage solution and updated diesel price assumptions. Further work is underway to assess the potential for further capital and operating cost reductions, with the current focus on mining, processing and support services.

BC Iron is also assessing opportunities to fully utilise its potential Cape Preston East port capacity allocation of 20 Mtpa. During the quarter, preliminary capital and operating cost estimates were released for a 20 Mtpa road and port infrastructure operation from a central location in the West Pilbara (160km from Cape Preston East). These estimates indicate low capital intensity and competitive operating costs, which BC Iron expects would underpin attractive access terms for third party users.

Given the progress with improving Buckland's economics, BC Iron has commenced preparations to re- initiate a strategic partner search and plans to begin engaging with potentially interested parties during the June 2016 quarter.

At the Nullagine Joint Venture ('NJV'), which is a joint venture between BC Iron (75%) and Fortescue Metals Group Limited ('Fortescue') (25%), the temporary suspension of operations was implemented


Head Office

Level 1, 15 Rheola Street West Perth WA 6005

1 All conversions between Australian dollars and US dollars in relation to Buckland are based on an exchange rate of 0.70.


BC IRON LIMITED

ABN 21 120 646 924

Registered Office

Level 1, 15 Rheola Street West Perth WA 6005 Tel: (08) 6311 3400

Fax: (08) 6311 3449

Web: www.bciron.com.au


ASX Code: BCI

GPO 2811

Listed: 15 December 2006 Perth WA 6001

Page 1 of 7

QUARTERLY ACTIVITIES REPORT

MARCH 2016 QUARTER


during the quarter. BC Iron is considering all of its strategic options in relation to the NJV, which include a potential sale of BC Iron's interest or a potential restart of operations. A restart decision is a Joint Venture decision that requires unanimous approval and will consider factors such as the iron ore price outlook, exchange rates and NJV operating costs. Based on current expectations, a sustainable CFR 62% Fe iron ore price in the mid-US$50's per dry metric tonne ('dmt') and an Australian dollar exchange rate in the low 0.70's (or similar combination) over the medium term supports a restart of the NJV.

Managing Director Morgan Ball said, "Iron Valley is generating earnings for BC Iron which are leveraged to an improving iron ore price. We continue to work with Mineral Resources to support the operation and its improvement initiatives.

"Optimisation work completed at the Buckland Project to date has substantially enhanced the global competitiveness of a standalone 8 Mtpa mine-to-port operation. However, this is only the first step and we believe further improvements will be achieved from work currently underway. A key attraction of the Buckland Project is the potential for BC Iron to also become an infrastructure provider to third parties and we are encouraged by the preliminary work completed on expanding the proposed infrastructure solution to 20 Mtpa.

"In relation to Nullagine, we are considering all the options available to BC Iron. This may include a potential sale of BC Iron's interest to an appropriate party if sufficient value can be realised or a restart of operations if supported by expected medium term market conditions."

  1. IRON VALLEY PROJECT

    MIN operates Iron Valley under an iron ore sale agreement with BC Iron and the mine is currently being operated as a direct shipping ore ('DSO'), truck haulage operation. During the quarter, MIN shipped 1.66M wmt of Iron Valley ore, generating an EBITDA for BC Iron of A$1.1M which includes a negative adjustment of A$0.2M relating to the finalisation of pricing for shipments that departed in prior periods.

    BC Iron continues to support MIN by preparing key approvals to facilitate the ongoing operation of Iron Valley and also supports MIN's progress of its Iron Valley improvement initiatives, including the bulk ore transport system ('BOTS'). These initiatives offer potential upside to BC Iron in the future through increased production rates and increased received prices.

  2. BUCKLAND PROJECT

    Buckland is an iron ore development project located in the West Pilbara region. The base case development concept for the project includes an 8 Mtpa mine at Bungaroo South and an independent infrastructure solution comprising a private haul road and transhipment port at Cape Preston East. BC Iron is also evaluating alternative development concepts that have the potential to fully utilise the Company's potential capacity allocation at Cape Preston East of 20 Mtpa.

    Optimisation of the 8 Mtpa Development Concept

    During the quarter, BC Iron provided an update on the capital and operating cost reductions that have been achieved to date for the standalone 8 Mtpa development concept.

    Expected C1 cash costs have reduced by more than A$10/wmt to A$31.6/wmt (US$22/wmt) as a result of road haulage optimisation studies and updated diesel price assumptions. BC Iron's revised road haulage concept for the Buckland Project envisages increased payloads of 260 tonnes per truck and the adoption of convoy road haulage, an innovative semi-autonomous haulage solution.



    Page 2 of 7

    QUARTERLY ACTIVITIES REPORT

    MARCH 2016 QUARTER


    Expected total capital costs (upfront and deferred) have reduced by A$55M to A$942M (US$660M). BC Iron sought updated costings from the contractors, vendors and suppliers that provided costings for certain capital works packages in the original feasibility study. The reduction in capital costs that resulted from this exercise was partially offset by allowing for higher specification road crossings that would be required for the convoy road haulage solution.

    BC Iron continues to assess opportunities to further reduce expected capital and operating costs and is currently undertaking a detailed assessment of the mining, processing and support services areas. Further updates will be provided to the market as this work is completed.

    Infrastructure Expansion Studies

    BC Iron's proposed road and port infrastructure has the potential to accommodate tonnages above 8 Mtpa. An expansion of capacity could see it become an attractive solution for other prospective West Pilbara iron ore producers, or facilitate a joint operation with the Australian Premium Iron Joint Venture's ('API') Buckland Hills deposit (which is contiguous with Bungaroo South) and/or development of BC Iron's western satellite deposits (i.e. Rabbit, Rooster and other potential deposits) in conjunction with Bungaroo South.

    During the quarter, BC Iron completed preliminary capital and operating cost estimates for a standalone

    20 Mtpa road and port infrastructure operation from a central location in the West Pilbara that is approximately 160 kilometres from Cape Preston East.

    Capital costs for the logistics related infrastructure are estimated at A$868M (US$608M), or a capital intensity of A$43/dmt of annual throughput. This compares favourably to the capital intensity for developing an infrastructure solution based on a rail and deep water port. BC Iron's proposed road and port infrastructure operating costs are expected to be competitive at A$13.5/wmt (US$9.5/wmt). BC Iron believes these capital and operating cost figures can together underpin an attractive access terms for potential third party users.

    Other

    Due to substantial progress with improving Buckland's economics, BC Iron plans to re-initiate a strategic partner search. Preparations are underway and the Company plans to begin engaging with potentially interested parties during the June 2016 quarter.

    Drafting of an agreement with API in relation to co-operatively mining the parties' contiguous Bungaroo South and Buckland Hills deposits continued. This would benefit both parties by providing additional mining inventory up to the tenement boundaries.

    The approvals process for Cape Preston East also continues to be progressed as planned.


  3. NULLAGINE JOINT VENTURE ('NJV')

    BC Iron Nullagine Pty Ltd, a wholly owned subsidiary of BC Iron, is the operator and manager of the NJV, a 75:25 unincorporated joint venture with Fortescue Metals Group Limited ('Fortescue'). The project is located approximately 140km north of Newman in the East Pilbara region of Western Australia.

    BC Iron announced in December 2015 that DSO operations at the NJV would be temporarily suspended due to low iron ore prices. The final DSO shipment departed during the quarter and the temporary suspension is now in effect. 0.38M wmt of Bonnie Fines was shipped, of which BC Iron's share was 0.26M wmt.


    Page 3 of 7

    QUARTERLY ACTIVITIES REPORT

    MARCH 2016 QUARTER


    The NJV also investigated the potential to sell ore from existing low grade stockpiles to Fortescue. However, the parties have agreed not to proceed at this time. Approximately 10.9M wmt of low grade stockpiles remain at the NJV site for potential future sale, blending or beneficiation.

    BC Iron is considering all of its strategic options in relation to the NJV, which include a potential sale of BC Iron's interest or a potential restart of operations. Any sale would need to be executed with an appropriate party and realise sufficient value for BC Iron's shareholders. A restart of operations would need to be supported by market conditions and BC Iron continues to monitor these as well as evaluate opportunities to further lower the NJV's operating cost base. Whilst iron ore prices have improved recently, significant volatility persists. In addition, there have been unfavourable movements in the Australian dollar exchange rate and sea freight rates. Any decision to restart the NJV is a Joint Venture decision that requires unanimous approval and will consider factors such as iron ore price outlook, NJV operating costs and the Australia dollar exchange rate. Based on current expectations, a sustainable iron ore price in the mid-US$50's per dmt (CFR 62% Fe basis) and an Australian dollar exchange rate in the low 0.70's (or similar combination) over the medium term supports a restart of NJV operations.

    No lost time injuries were recorded during the quarter and as at 31 March 2016, the rolling 12 month lost time injury frequency rate was 1.6 (31 December 2015: 3.9).

  4. EXPLORATION PROJECTS

    BC Iron owns a number of non-iron ore exploration projects located in Western Australia that are prospective for gold, base metals and salt. During the quarter, work was undertaken at the Mt Fraser (base metals and gold) and Peak Hill (gold) projects.

    The Mt Fraser project contains several historical copper and gold workings. During the quarter, soil sampling and rock chip sampling was undertaken at a number of identified targets, including at the historical workings. Results received to date are encouraging and BC Iron plans to complete further exploration work.

    At Peak Hill, BC Iron completed a heritage survey and initial reconnaissance of identified geophysical targets. Reconnaissance drilling is currently being planned.

  5. CORPORATE

Cash and Debt Position

BC Iron's cash balance was A$23.3M as at 31 March 2016.


During the Quarter, a net cash outflow of A$13.8M was associated with BC Iron's interest in the NJV. This included revenue and operating costs from the NJV's final shipments, costs associated with implementing the temporary suspension and a net working capital outflow relating to the previous quarter. All material one-off costs associated with the temporary suspension had been paid by the end of the quarter, but certain operational costs were still to be paid in accordance with normal working capital cycles, such as State Government and Native Title royalties for March 2016 quarter shipments.


Page 4 of 7

Read the rest of the article at www.publicnow.com
Data and Statistics for these countries : Australia | Georgia | All
Gold and Silver Prices for these countries : Australia | Georgia | All

BC Iron Limited

DEVELOPMENT STAGE
CODE : BCI.AX
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

BC Iron is a development stage company based in Australia.

BC Iron develops iron in Australia.

Its main asset in development is NULLAGINE IRON in Australia.

BC Iron is listed in Australia and in Germany. Its market capitalisation is AU$ 90.3 millions as of today (US$ 58.7 millions, € 54.8 millions).

Its stock quote reached its highest recent level on March 07, 2014 at AU$ 4.87, and its lowest recent point on February 05, 2016 at AU$ 0.08.

BC Iron has 392 529 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of BC Iron Limited
3/1/2017BC Iron tries its luck in the potash industry
11/27/2014Heads roll as BC Iron forced to cut costs amid weakest price...
Annual reports of BC Iron Limited
I Annual Report To Shareholders 2012
Financings of BC Iron Limited
4/15/2011Regent Pacific Re-Instates Financing for Scheme of Arrangeme...
Nominations of BC Iron Limited
9/22/2016Appointment of Managing Director (2 pages)
3/15/2013Appoints New Managing Director
9/23/2011Director Appointment
Project news of BC Iron Limited
5/25/2012Achieves 5MTPA Production Milestone
4/2/2012Increases Mineral Resource at Nullagine JV - 30 March 2012
5/11/2011Presenting At The RIU Sydney Resources Round-up
4/9/2010Moves Closer To Production After Signing Key Native Title Mi...
12/17/2009(Nullagine Iron)Nullagine Iron Ore Jv - First Project Funding Installment Re...
12/14/2009(Nullagine Iron)BCI And FMG Confirm Move Into Development Of Nullagine Proje...
11/10/2009(Nullagine Iron)Nullagine JV Secures US$50 Million Project Finance
10/16/2009(Nullagine Iron)Trial Mining Supports Key Technical Aspects Of Nullagine Iro...
9/17/2009(Nullagine Iron)Commences Trial Mining at the Nullagine Iron Ore Project
8/24/2009(Nullagine Iron)Formally Enters into Nullagine JV with FMG
7/3/2009(Nullagine Iron)Board Approves Development of Nullagine Iron Ore Project
1/7/2009(Nullagine Iron)Increases DSO Resource by 64% to 46Mt, Total CID Resource 80...
9/30/2008(Nullagine Iron)Infill Drilling Completed at Nullagine Iron Ore Project
9/1/2008(Nullagine Iron)In-Fill Drilling Results Confirm Direct Shipping Resource Qu...
7/11/2008Open BriefingR - MD on Feasibility Study & Future Plans
7/1/2008(Nullagine Iron)Commits to Nullagine Feasibility Study Following Positive Sc...
3/31/2008(Nullagine Iron)Delivers Maiden 47 Million Tonne Iron Ore Resource at Nullag...
Corporate news of BC Iron Limited
9/14/2016Company Update
8/1/2016FY16 Full Year Results Release (6 pages)
8/1/2016Appendix 4E and FY16 Financial Report (61 pages)
7/29/2016Quarterly Activities Report (4 pages)
7/5/2016Response to ASX Price and Volume Query (4 pages)
6/27/2016Settlement of BC Iron Litigation
6/26/2016WTP: Settlement of BC Iron Litigation (1 pages)
6/24/2016Watpac Settlement (2 pages)
5/20/2016BCI: Iron Valley Update
5/20/2016Iron Valley Update (2 pages)
5/18/2016Management Changes (3 pages)
4/29/2016Update on litigation against Watpac (2 pages)
4/21/2016Quarterly Activities Report (7 pages)
1/28/2016Quarterly Activities Report (8 pages)
12/31/2015Appendix 3B - expiry of performance rights (12 pages)
12/24/2015Commencement of litigation against Watpac (2 pages)
12/22/2015NJV Contract Update (2 pages)
12/22/2015WTP:Update on Dispute with BC Iron - Nullagine Iron Ore Prjt...
11/27/2015Appendix 3B (13 pages)
11/27/2015Change of Director's Interest Notice - M Ball (2 pages)
10/26/2015Variation to NJV Rail and Port Tariff (3 pages)
10/23/2015NJV Awards Road Haulage Contract (2 pages)
10/21/2015Quarterly Activities Report (7 pages)
10/6/2015Managing Director Employment Terms (2 pages)
9/16/2015Change of Director's Interest Notice - M Ball (2 pages)
9/3/2015S&P DJ Indices Announces September Quarterly Rebalance (4 pa...
8/31/2015Correction to Underlying Net Loss After Tax (2 pages)
8/31/2015Updated FY15 Annual Report to shareholders (96 pages)
8/28/2015Company Secretary Resignation - A Bird (2 pages)
8/26/2015FY15 Full Year Results Presentation (24 pages)
8/26/2015FY15 Annual Report and Appendix 4E (97 pages)
8/26/2015Appendix 4G (14 pages)
8/25/2015NJV Ore Reserves and Mineral Resources (21 pages)
7/23/2015Quarterly Activities Report - June 2015 Quarter (8 pages)
6/11/2015Repayment of Term Loan Facility (2 pages)
4/23/2015NJV Warrigal Hub Contract Update 23.04.15
4/23/2015NJV Warrigal Hub Contract Update (2 pages)
4/22/2015BC Iron March 2015 Quarterly Activities Report (8 pages)
4/9/2015March 2015 Quarter Update (2 pages)
4/2/2015NJV Contracting Strategy Update (2 pages)
3/24/2015Warrigal Hub Contract Award (3 pages)
3/24/2015Mines & Money Presentation (20 pages)
3/9/2015Presentation (20 pages)
3/5/2015S&P DJ Indices Announces March Quarterly Review (9 pages)
9/6/2013Latest Headlines and New Issue Alert: Sibanye production rec...
10/22/2012September 2012 Quarterly Activities Report
8/21/2012I Forms Iron ore Stratigic Alliance in Brazil
8/16/2012I ASX Announcement - Mineral Resource and Ore Reserve 30 Jun...
7/5/2012I Achieves All Operational Guidance FY12
4/17/2012Quarterly Report for the period ending 31 March 2012
2/29/2012Half Year Results - December 2011 & Company Update
10/24/2011Quarterly Report for the period ending 30 September 2011
9/23/2011September Company Update
8/11/2011Operations Update
4/29/2010Quarterly Activities Report For The Period Ending March 31, ...
4/15/2010Welcomes New Institutional Investors
10/30/2009Quarterly Activities Report For The Period Ending 30 Septemb...
7/29/2009June 2009 Quarterly Report
6/19/2009Announces $22M Capital Raising
6/5/2009Seals Company-Making Deal with FMG
5/28/2009North West Iron Ore Alliance Congratulates BC Iron on Landma...
5/28/2009secures infrastructure deal with The Fortescue Metals Group ...
3/4/2009Open Briefing - MD on Off-take Agreement and Recent Progress
2/11/2009Secures Landmark Long-Term Off-Take Agreement for Nullagine ...
1/28/2009Quarterly Activities Report December 2008
1/8/2009Carmichael Quick Note
11/27/2008horses for courses
10/2/2008Practical Parenting Support for Families from Hedland's Juni...
9/8/2008Gearing Up For The New Iron Age
8/8/2008Plans in the Fire
8/6/2008New Access Rules for Infrastructure
8/6/2008Sunday Times Article - Hot Stock
7/31/2008June 2008 Quarterly Activities Report
7/29/2008Diggers and Dealers
7/24/2008Ocean Equities Ltd - Iron Ore Sector Update
7/14/2008Comment On Take Over Speculation
6/20/2008NCC Declaration
6/16/2008Shinier Than Gold in Stock Market
4/30/2008 Quarterly Activities Report
4/21/2008 Open BriefingR. MD Explains Nullagine Resource Upgrade.
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (BCI.AX)BERLIN (BC3.BE)
0.230+2.22%0.097+2.11%
AUSTRALIA
AU$ 0.230
04/24 11:00 0.010
2.22%
Prev close Open
0.225 0.225
Low High
0.220 0.230
Year l/h YTD var.
0.220 -  0.320 -17.86%
52 week l/h 52 week var.
0.205 -  0.320 2.22%
Volume 1 month var.
803,220 -%
24hGold TrendPower© : 27
Produces
Develops Iron
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-16.36%
20231.85%0.300.20
2022-37.21%0.480.21
202143.33%0.620.29
202076.47%0.310.10
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.79+7.97%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64+10.92%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.67+2.28%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.38+0.54%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :