Dragon Mining NL

Published : November 02nd, 2015

Quarterly Activities Report

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Quarterly Activities Report

23b3cdd7-b689-4013-b0eb-df127281574f.pdf


Dragon Mining Limited Quarterly Activities Report

For the Quarter ended 30 September 2015


Quarter Overview


  • Improved safety performance continued with a Lost Time Injury ('LTI') free quarter reducing the Group's 12 month rolling LTI frequency rate per million work hours to 3.08, an 85% reduction compared to Q2 2014. Management remains focused on continuing to improve safety and to this end have ordered new seismic monitoring equipment at Orivesi and are seeking to obtain approval from Mine Inspectors to replace underground safety ladders with emergency evacuation cages.


  • Gold production of 14,270 ounces included 4,124 ounces produced from external concentrate sources at the Svartliden Production Centre in Sweden.


  • Concentrate processing at the Svartliden Production Centre included 100% of the concentrate from Jokisivu. Metallurgical issues prevented the processing of Orivesi concentrate at Svartliden, instead this was delivered to the Boliden refinery. The processing of external concentrates continued to ramp up during the quarter, generating a further benefit to the Group revenue stream.


  • A Group C1 Cash Cost of US$942/oz was achieved during the quarter. This achievement was in line with the C1 Cash Cost from the previous quarter and was again driven by the improved recovery from the Vammala Plant and the reduction in refining costs associated with the processing of Jokisivu concentrate at the Svartliden Production Centre.

    Company receiving the remaining A$750,000 of the A$1.0 million cash consideration payable (plus penalty interest of A$128,773) pursuant to the Share Sale Agreement. Ausinox plc also reimbursed the Company an additional A$33,742 which represented costs incurred, over and above the purchase price, by the Company as a result of the delays in completion.


    Quarter at a Glance


    Gold Production

    14,270

    ounces

    C1 Cash Cost US/oz(1)


    US$942

    Safety Performance

    0 LTI


    Available Cash(2) (Quarter end)


    A$18.6m

  • For the Vammala Production Centre, the Group uses the C1 Cash Cost definition as set out by Mackenzie Wood. For the Svartliden Production Centre, the Group calculates C1 Cash Costs by including total production costs (which includes concentrate purchases) divided by total ounces sold from all sources.

  • Available Cash = Cash at bank plus Receivables less Accounts Payable.


  • Statutory Tailings Storage Facility ('TSF') inspections were conducted by the environmental authorities in Finland and Sweden. The inspections confirmed both TSF's are approved for continued use.


  • Sale and Purchase Agreement to acquire the Fäboliden Gold Project completed, with the Company and the Bankruptcy Estate agreeing to amend the condition relating to the extension of the existing Environmental Permit in consideration for a lower total purchase price of 38 million SEK. 6 million SEK had already been paid, the remaining 32 million SEK was paid on 30 July 2015.


    20,000

    Ounces

    15,000

    10,000

    5,000

    0

    Dragon Mining Quarterly Gold Production

    and C1 Cash Cost

    USD/Oz

    3,000

    2,000

    1,000

    2Q13

    3Q13

    4Q13

    1Q14

    2Q14

    3Q14

    4Q14

    1Q15

    2Q15

    3Q15

    0


    Ounces Produced (Oz, LHS) C1 Cash Cost (USD/Oz, RHS)

  • Results from the Fäboliden infill program were received during the quarter. The results from the drilling program have shown that the high grade zone displays good continuity both down dip and along strike; the grades received from drilling are commensurate with the results from historic drilling.


  • Available cash was depleted by A$3.5 million during the quarter. Available cash (bank accounts plus trade receivables less accounts payable) totalled AU$18.6m at the end of the quarter (details of cash movement are given on page 10).


  • The Sale of the Weld Range Metals investment to Ausinox plc was completed during the quarter, with the


Ore Mined vs Ore Milled

300,000

200,000

100,000

2Q13

3Q13

4Q13

1Q14

2Q14

3Q14

4Q14

1Q15

2Q15

3Q15

0


Ore Mined (t) Ore Milled (t)


Page | 1


Operations Review


The Group's gold production for the quarter was 14,270 ounces at a C1 Cash Cost of US$942/oz.


To compensate for lower production from Orivesi, ore production from Jokisivu was increased. Production at Orivesi will be limited to existing sill pillars until the new stopes are available in December. Drilling and blasting has commenced with some cracking in the rock making progress difficult.


The ramp up in concentrate throughput at Svartliden continued during the quarter with

4,124 additional ounces sourced from external concentrate (Q2: 2,370 ounces). This was the first quarter that Svartliden processed concentrate only. Metallurgical issues associated with the processing plant caused precautionary production stoppages in September to ensure discharge limits were maintained. External technical assistance was sought and the resulting metallurgical recommendations are in the process of being implemented, yielding early positive results.


Vammala Production Centre, Southern Finland



Quarter

Ore Mined (t)


Ore Milled (t)

Head Grade (g/t)


Recovery (%)

Plant Utilisation (%)

Total Gold Production (Ounces)

C1

Cash Cost1 USD/oz

Dec 2014

86,224

73,499

5.5

80.6

98.2

11,022

793

Mar 2015

72,771

71,113

4.6

86.3

92.3

28,722

793

Jun 2015

59,778

66,993

4.7

85.6

85.7

29,820

800

Sep 2015

55,540

75,304

4.9

85.9

94.9

10,146

1701

1For the Vammala Production Centre, the Group uses the C1 Cash Cost definition as set out by Mackenzie Wood. For the September 2015

quarter, the calculation denominator has been changed to gold sold (rather than gold produced). The change was implemented at Vammala to ensure consistency across the Group.

2The total gold production includes a positive quarterly true up to reconcile the provisional ounces sold to Boliden against the final gold

outturn from Boliden.


Safety


September represented the ninth consecutive month of zero LTI's. The rolling 12 month accident frequency rate per 1 million working hours reduced from 20.3 at the end of Q4 2014 to 3.9 in Q3 2015.


During the quarter:


  • A two week maintenance shutdown at the Vammala Mill was completed without any accidents or incidents;

  • New blasting procedures were implemented for the Orivesi Mine;

  • A design for emergency evacuation cages has been presented to the Mine Inspectors for approval;

  • Prior to the maintenance shutdown, a safety focus has continued on those issues related to heightened risks surrounding the performance of non-routine tasks; and

  • A total of 11 reportable incidents were reported during the quarter; 3 at Orivesi, 6 at Vammala and 2 at Jokisivu.


    Production


    Gold production at the Vammala Production Centre for the quarter was 10,146 ounces, which was 368 ounces below forecast. Mill feed at Vammala comprised 26,783 tonnes from

    Orivesi at 6.0 g/t gold and 48,521 tonnes from the Jokisivu at 4.2 g/t gold.


    Orivesi is presently attempting to mine out the remaining sill pillars while the decline is progressing to the new stope are. Overall ore


    production volumes have been maintained but with lower grade ore from Jokisivu.


    Orivesi Gold Mine


    Production from Orivesi was 16,646 tonnes of ore (57% below forecast). Mining capacity was affected by the difficult condition of the stopes that were in production.


    The Kutema decline advanced 91 metres by the end of the quarter to the 1,120m level.


    Development works advanced a total of 456 metres during the quarter, this being 56 metres above forecast.


    Jokisivu Gold Mine


    Ore mined totalled 38,894 tonnes (16% above forecast) and development advanced 480 metres (60 metres above forecast) during the quarter. Production from Jokisivu has been ramped up to help compensate for the reduced ore production from the higher grade Orivesi mine.


    The deepening of the main decline has advanced as planned to the 340m level.


    Vammala Plant

    Ore milled totalled 75,304 tonnes and mill recovery averaged 85.9%.


    The following occurred during the quarter:


    • Follow up work has shown the new cyclones have resulted in a flotation recovery increase of 1% - 3% for Orivesi ore, better size classification and less ultra-fines;

    • The maintenance shutdown began as planned on 27 September 2015. Primary tasks involved replacing the conveyor from the cone crusher to the silo, replacing the rotators and stators for the rougher flotations cells, replacement of the transformer for the crusher and repair work for the Larox filter;

    • TSF embankment raising work was completed as planned by the beginning of August 2015;

    • A statutory TSF safety inspection was completed by the relevant authorities. The TSF is being operated and maintained as intended. The inspection confirmed the dams can be raised with minor modifications; and

    • Dust from the TSF resulted in the Company receiving one complaint from neighbours during the quarter. Two sprinkler systems were installed during the quarter. The area has been watered continuously with lime milk and dust binding chemicals (Refer to Environment - Vammala Plant Section).


Environment


Vammala Plant


The new Environmental Permit for the Vammala Plant was granted in June 2014 and - as detailed in the Company's quarterly announcement on 31 July 2014 - was later appealed by the Company (and a few other parties).


In September, the Vaasa Administrative Court requested the Company's response with regard to statements and opinions it had received concerning the appeal. The Company provided its response on 5 October, after which the Vaasa Administrative Court should have enough information to determine a ruling.


During spring and early summer, strong winds combined with work to raise the TSF embankment resulted in the Company receiving dust complaints. As a result, a statement

outlining any potential health impacts was requested by the ELY centre and the health inspector for the Sastamala Municipality ('Relevant Authorities'). The statement was completed by the Finnish Institute of Occupational Health and delivered to the Relevant Authorities on 31 August 2015. The Company's preventative actions produced positive results and have been continued throughout the quarter. The Relevant Authorities have confirmed that the preventative actions taken by the Company were adequate.


The inspection of the TSF embankments, carried out every fifth year, was organised for September. The inspection confirmed the TSF embankments are being operated and maintained as planned and can be raised higher after minor repair work.


According to monthly water analyses, the discharge amount of nickel and sulphate continued to decrease by comparison to previous years. This is mainly the result of seepage waters being pumped successfully back to the TSF.


Orivesi Gold Mine


In August, as part of the review process associated with renewing the Orivesi Environmental Permit the permit setting authority, The Regional State Administrative Agency ('AVI'), asked the Company's opinion on the statements provided by the ELY Centre and Metsähallitus, the state land owner, regarding the Natura assessment that was completed in late 2014. The statements are not binding on AVI and, as expected, both questioned the granting of a new Environmental Permit. The Company responded accordingly to both statements on 16 October.


Noise mitigation work continued during the quarter. The noise silencers were inspected and found that some lamellas in the fan were damaged. New lamellas have been ordered and are to be installed as soon as possible. Noise measurements will be carried out after the installation has been completed.


Orivesi operated according to its permit conditions in August and September. In July, monthly water analyses showed that aluminium concentration (6,900µg/l) exceeded the Environmental Permit's limit (3,000µg/l). The ELY Centre requested a report of the reasons for the breach and planned future preventative actions. The report was submitted in August and was approved by the ELY Centre by late September, no remedial actions were required.

As a result of test fishing, carried out in the lakes downstream every third year, a number of fish were caught in the lake Ala-Jalkajärvi (within the immediate vicinity of the site). In 2009 and 2012, previous test fishing occasions, no fish were caught in the lake.


Jokisivu Gold Mine


The Environmental Permit application for crushing waste rock at the Jokisivu mine site was submitted to AVI in July. The permit will allow the crushing of a maximum 100,000 TPA. The waste rock is considered inert and therefore is suitable for using as an aggregate.


Discharge water limit monthly analyses confirmed the mine continues to operate according to its permit conditions. The analyses sampled in August showed anomalous concentrations of e.g. sulphate and nitrogen in the ditch downstream when compared to previous water analyses. Concentrations are related to seasonally low water flows.


Kaapelinkulma Gold Project


In April 2015, the Supreme Administrative Court handed down its decision to dismiss the appeal of the Nature Conservation Organization of Pirkanmaa, which was concerned with the possible threat to a local protected butterfly's habitat, by the Company's mining activities. The decision by the mining authority Tukes, to issue a Mining Concession for Kaapelinkulma is now final and the process for ordering the Mining Concession is proceeding. Consequently, a meeting with local land owners providing information regarding the land purchase was organised by the Company in September with follow up negotiations planned for the coming quarter.

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Finland | Sweden | All
Gold and Silver Prices for these countries : Finland | Sweden | All

Dragon Mining NL

PRODUCER
CODE : DRA.AX
ISIN : AU000000DRA1
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Dragon Mining is a nickel and gold producing company based in Australia.

Dragon Mining develops nickel, gold and copper in Australia, in Eritrea and in Finland, and holds various exploration projects in Australia, in Finland and in Spain.

Its main assets in production are SVARTLIDEN in Sweden and ORIVESI in Finland, its main assets in development are VAMMALA, PAMPALO and KUUSAMO in Finland, WELD in Australia and ZARA in Eritrea and its main exploration properties are ASHBURTON and WELD RANGE in Australia, KAAPELINKULMA, RITAKALLIO, TAMMIJÄRVI, SUKSETON, HANHIMAA, KUHMO and KYLYLAHTI in Finland and LUGO in Spain.

Dragon Mining is listed in Australia and in Germany. Its market capitalisation is AU$ 197.2 millions as of today (US$ 128.6 millions, € 120.1 millions).

Its stock quote reached its lowest recent point on December 12, 2014 at AU$ 0.08, and its highest recent level on July 23, 2021 at AU$ 4.69.

Dragon Mining has 88 840 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Dragon Mining NL
Annual Report 2007
2007 Annual Report
2007 Annual Report
Nominations of Dragon Mining NL
11/14/2008Appointment of Director
Project news of Dragon Mining NL
1/22/2016Maiden Mineral resource for Faboliden gold deposit
1/22/2016Update on acquisition of Faboliden Gold Project
9/15/2015Update on sale of interests in Weld Range Metals
9/15/2015Completion of sale of interest in Weld Range Metals
7/28/2015Update on acquisition of Faboliden gold project
7/2/2015Update on sale of interests in Weld Range Metals Limited
3/17/2015Robust drill intercepts received from Orivesi gold mine
3/17/2015Update on sale of interests in Weld Range Metals Limited
1/24/2013(Kuusamo)Kuusamo Mine Project Continues To Advance
2/6/2012(Kuusamo)Renounceable Rights Issue to Advance the Kuusamo Gold Projec...
1/30/2012Maiden Cobalt Resource Highlights Size of Juomasuo Mineralis...
1/18/2012(Kuusamo)Exceptional Intercept Confirmed - Kuusamo North, Finland [Dr...
10/12/2011(Kuusamo)Kuusamo North Yields Another High Grade Intercept [Dragon Mi...
8/31/2011(Kuusamo)Spectacular Intercept from Kuusamo North, Finland [Dragon Mi...
8/12/2011(Kuusamo)First Intercepts Received From Hangaslampi, Kuusamo Gold Pro...
7/18/2011(Kuusamo)Further Gold Intercepts From The Kuusamo Gold Project, Finla...
6/2/2011(Kuusamo)Further Encouraging Intercepts From The Kuusamo Gold Project...
5/27/2011(Svartliden)Secures 100% of the Svartliden Gold Mine, Sweden [Dragon Min...
5/13/2011Early Encouragement From The Harpsund Joint Venture, Sweden ...
3/28/2011Increase in Scandinavian Gold Ore Reserves [Dragon Mining]
3/9/2011Scandinavian Gold Resource Inventory Exceeds 1 Million Ounce...
3/3/2011(Svartliden)Awards Contract for Underground Mining at the Svartliden Gol...
2/27/2011(Kuusamo)2011-02-23 First Drilling & Re-Assay Results Received for th...
10/27/2009(Vammala)High Grade Gold Intercepts From Jokisivu, Finland [Dragon Mi...
10/19/2009(Vammala)First Production From The Jokisivu Gold Mine, Finland [Drago...
5/16/2008(Svartliden)Further Drill Success at Svartliden Gold Mine, Sweden [Drago...
2/22/2008(Svartliden)Encouraging Intercepts from Deeper Drilling at Svartliden, S...
Corporate news of Dragon Mining NL
7/27/2016Quarterly Activities Report
5/26/2016Dragon Mining terminates the agreement with Endomines
4/8/2016Corporate Governance Statement
12/15/2015Update on Environmental Permit for the Orivesi Gold Mine
9/15/2015Robust results highlight potential at Faboliden
8/28/2015Half Yearly Report and Accounts
7/28/2015High grade gold intercepts received from Faboliden
7/28/2015Drilling activities continue to advance in Southern Finland
4/16/2015Ore Reserves for the Finland and Sweden Production Centres
4/16/2015Notice of Annual General Meeting/Proxy Form
3/17/2015Purchase Agreement with Aurion Amended
3/17/2015Lapse of Options
3/17/2015Preliminary Final Report and Annual Financial Statements
3/17/2015Mineral Resources Updated
10/21/2014DRA_Weld Range Extension
2/8/2012Boardroom Radio Broadcast
12/6/2011(Kuusamo)Encouraging Results Continue From Kuusamo North [Dragon Mini...
10/24/2011Boardroom Radio Broadcast [Dragon Mining]
10/20/2011(Kuusamo)Kuusamo North Yields Further Encouraging Gold Intercepts [Dr...
10/13/2011Patersons Gold Book - October 2011 [Dragon Mining]
10/11/2011Boardroom Radio Webcast [Dragon Mining]
9/16/2011Patersons Materials Research Note [Dragon Mining]
9/15/2011(Kuusamo)Further Exceptional Results from Kuusamo North, Finland [Dra...
9/14/2011(Svartliden)Resource and Exploration Update - Svartliden Gold Mine, Swed...
9/1/2011Green Leader Research Report - Dragon Mining Limited [Dragon...
8/31/2011Half Year Report for the 6 months ending 30 June 2011 [Drag...
8/18/2011(Kuusamo)Highlight Intercept Confirmed - Kuusamo Gold Project, Finlan...
8/1/2011June 2011 Quarterly Report [Dragon Mining]
6/30/2011(Orivesi)Further High Grade Gold Results Received From Orivesi Gold M...
6/14/2011(Orivesi)Bonanza Drill Results From Orivesi Gold Mine, Finland [Drago...
5/11/2011(Kuusamo)Depth Extensions Yield High Grade Intercepts - Kuusamo Gold ...
4/6/2011(Kuusamo)High Grade Intercepts Received From The Kuusamo Gold Project...
3/30/2011(Kuusamo)Significant Intercept From The Kuusamo Gold Project, Finland...
3/11/2011Further Promising Drill Results at Jokisivu Gold Mine, Finla...
2/25/20112010 Full Year Results [Dragon Mining]
2/11/2011(Svartliden)2011-02-11 Increase in Ore Reserves at Svartliden Gold Mine,...
1/5/2009On Market Purchase of Convertible Notes [Dragon Mining]
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (DRA.AX)FRANKFURT (DRM.F)
2.22-3.48%0.092+1.10%
AUSTRALIA
AU$ 2.22
04/24 15:41 -0.080
-3.48%
Prev close Open
2.30 2.30
Low High
2.21 2.30
Year l/h YTD var.
1.60 -  2.30 38.75%
52 week l/h 52 week var.
1.30 -  2.30 5.71%
Volume 1 month var.
11,688 5.21%
24hGold TrendPower© : 30
Produces Gold
Develops Copper - Gold - Nickel
Explores for Copper - Gold - Iron - Nickel - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/24/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202430.59%
2023-15.00%2.101.30
2022-40.30%3.401.88
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.00-0.99%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.58+5.09%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.45-0.81%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.49+1.57%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.76-1.68%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.07-0.95%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :