In the same category

Roca Mines Inc.

Published : December 24th, 2008

Reports Annual Results

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
=======================================================================
Re:   News Release - Wednesday, December 24, 2008
      ROCA Reports Annual Results
=======================================================================

Vancouver, British Columbia: Roca Mines Inc. (ROK: TSX-V) ("Roca" or
"the Company") has released its financial results for the annual period
ended August 31, 2008, including production and sales from the MAX
molybdenum mine located in British Columbia, Canada.  All dollar
amounts are stated in Canadian dollars unless otherwise indicated.

Overview and highlights:

- Revenues of $18.8 million since reaching commercial production as of
  April 12, 2008;
- The Company reported a net loss of $2.5 million or 3 cents per share;
- The Company reported cash flows from operations of $7.8 million or 10
  cents per share;
- Molybdenum production during the year was 1,027,907 pounds (including
  pre-commercial production).
- Phase II progress at MAX including the 1,400 meter #2 adit,
  installation of a third primary ball mill, and significant
  underground ventilation upgrades are complete or nearing completion.
- Exploration results from Diamond drill programs conducted below the
  MAX molybdenum deposit confirm resource expansion potential and have
  extended high grade zones within the known resource.
- Metal prices declined sharply post year-end and the Company has taken
  action to minimize costs at the MAX mine and throughout the
  organization.

MAX Molybdenum Mine - Production Results and Concentrate Sales

The Company announced that it had achieved its commercial production
targets on April 12, 2008 at its MAX molybdenum mine located in British
Columbia, Canada.  The mine became British Columbia's first new metal
mine in a decade and the newest primary molybdenum mine in Canada.
 
Production during the Phase I commissioning prior to April 12, 2008 was
facilitated utilizing stockpiled development material to run mill tests
and optimize circuits, in addition to variably graded ore from stope
development. As a result, head grades and concentrate production during
this period were generally lower than current levels. After April 12,
2008 delivery and processing of ore directly from mine stopes to the
mill commenced. Head grades from the initial stopes were lower than
anticipated due to mine dilution.  Mine dilution occurs as a result of
diluting higher grade material with lower grade rock and can occur for
a number of reasons. Lack of previous exposure in the high-grade zone
and inexperience with geological controls on mineralization in general
are believed to have caused the lower overall head grades to the mill.

Opportunities to run continuous milling operations were also hampered
due to availability and unscheduled maintenance requirements of on-site
generator sets.  These primary power sources impacted production
capacity and therefore concentrate produced during the year. 
 
During the pre-production period, the Company produced approximately
412,000 lbs of molybdenum contained in concentrates processing a blend
of ore grade material and variably mineralized development and waste
rock. Pre-commercial concentrate proceeds of approximately $10.1
million were used for mill completion costs and underground
development.  For accounting purposes, these pre-commercial revenues
are recorded as an offset to mine development costs. Revenues of $18.8
million for the year ended August 31, 2008 result from sales that
occurred after the commencement of commercial production on April 12,
2008. Concentrate inventory at August 31, 2008 was 11,394 lbs of
molybdenum contained.
 
The table below is a summary of the operating statistics from
commercial production start to August 31, 2008:

----------------------------------------------------------------
    MAX Mine
----------------------------------------------------------------
                   APR
                      13-30      MAY      JUN      JUL      AUG
                        '08      '08      '08      '08      '08
----------------------------------------------------------------
Molybdenum Produced   77,056  150,502  112,255  138,125  137,330
(lbs)(1)
Average Head Grade     0.755    0.732    0.473    0.584    0.757
(% Mo)
Molybdenum Recovery     93.8     94.3     94.1     93.6     94.1
(%)
Mill Availability         82       82       81       94      100
(%)
Average Daily
Throughput (tpd)         280      335      399      388      292
----------------------------------------------------------------
Note 1 - molybdenum (Mo) in concentrate



Cash costs of production during the fourth quarter were significantly
higher than in the third quarter ended May 31, 2008 largely because of
lower average grades received at the mill during June and July. Cash
costs averaged approximately Cdn$13 per lb of molybdenum during the
post commercial production period from April 13, 2008 through August
31, 2008. Management believes that its grade control programs and
underground infrastructure improvements will dramatically reduce the
average production costs going forward into 2009. Post year-end 2008,
in September through November, molybdenum in concentrate production
averaged 226,566 lbs per month which will lead directly to lower
average cash costs/lb due to economies of scale.

On December 4, 2008, a rockfall occurred underground at the mine which
has impacted the availability of production ore. The rockfall was
localized to the stope development area of the 875 m level. No workers
were present on the level at the time and no one was harmed. The
rockfall poses no threat to other working areas of the mine, but does
impact the immediate production schedule.  A maintenance break
originally scheduled between December 12 and December 29, 2008, will
now be extended until January 19, 2009.

MAX Mine/Mill Expansion

Initial production at MAX is focusing on the "HG" Zone, including an
estimated 280,000 tonnes of ("measured + indicated") ore grading 1.95%
MoS2.  Expansion of the mine and mill is being guided by prevailing
molybdenum prices and an assessment of ongoing operating costs
throughout 2009.

During the year ended August 31, 2008, the Company completed
significant development work on the #2 Adit and subsequent to year-end,
completed the installation of an upgraded ventilation system including
bulkheads and underground fans. The Company has also completed the
foundations on a mill base for a third ball mill acquired in 2007. The
installation of this mill will allow for greater production flexibility
and will provide for a nominal capacity of more than 1,000 tonnes per
day.
 
The Company plans to seek graduated permitting to increase the
production of the mine over time including the Phase II mine.  Under
current requirements, a permit to operate at the as-built capacity will
be required in late 2009.  The application for this increase in
production rate will be submitted after environmental and water quality
data is collected and compiled.  The information will demonstrate that
the mine is working well within its compliance requirements and with
minimal impact to the environment. 

As a result of recent global economic uncertainty and declining
commodity prices, management of the Company has undertaken several
initiatives to cut costs at the MAX molybdenum mine while continuing to
operate under its Phase I mine plan.  Grade control through detailed
geological mapping and modifications to material handling will
contribute to lower cash costs going forward. Phase II expansion plans,
including completing capital spending for that expansion, are being
minimized.

MAX Molybdenum Exploration

The Company has previously reported the results from underground and
surface Diamond drill programs focused on the exploration for new
molybdenite mineralization both at depth below the known MAX resource
and in areas previously unexplored areas within the MAX property
boundary.

The Company's underground exploration drilling has thus far intersected
strong hydrothermal alteration, indications of several intrusive
phases, and significant multiple episodes of mineralization below the
MAX deposit. Detailed petrographic studies by previous workers also
concluded that there are at least four intrusive pulses, and a highly
repetitive mineralizing event at MAX.  The size of the inferred system
is also significant.  It is estimated that a pluton at depth could have
a diameter of roughly 1,000 m, based on the width of the contact
metamorphic aureole on surface, whereas the intrusion at the centre of
the deposit is roughly 200 m in diameter.  This suggests that the known
deposit may have other zones and/or other deposits that are not yet
discovered.  Additional exploration drilling will be collared from new
locations within the mine workings in the future.

The North molybdenum biogeochemical anomaly has a surface footprint of
150 metres (m) X 350 m and is centered approximately 200 m north of
Adit #2.  Two initial holes intersected a wide zone (over 100 m) of
intense silicification, hornfelsing, locally strong quartz veining and
pervasive sericite alteration with trace molybdenite throughout.
Further Diamond drilling is planned from the Adit #2 area to test for a
separate molybdenum deposit on the east side of the Z Fault, or a
faulted extension of the MAX deposit itself.

While economically significant molybdenum values were not intersected
the geologic and near-surface expression of this new zone is
reminiscent of the MAX resource itself where the extent of a relatively
minor molybdenite mineralized zone on surface lies atop a large-scale
mineralized deposit currently being mined.

MAX Tungsten Exploration

The Company's initial drill program tested the size and potential of
the Ridge and Upper Ridge tungsten zones located approximately 1.2
kilometres southwest of the MAX mine portal area.  Surface
Diamond-drilling conducted on the southern portion of the Ridge
Tungsten Zone intersected significant intervals and grades of tungsten
mineralization.  Combined with past work, the recent results suggest
great potential for a new tungsten resource to be defined at MAX based
on the exceptional continuity observed. The mineralization was
intersected above and in close proximity to the producing MAX Mine.  At
their lowest point, the tungsten intervals are located approximately
650 metres (m) above the Main Haulage Adit 960 level of the MAX Mine.
Existing infrastructure at the MAX Mine is well suited to the potential
development of a tungsten resource.

Foremore VMS-Gold Project

The Company holds a 100% interest in the Foremore VMS-Gold project
situated in the "Golden Triangle" one of the most active mining and
exploration areas in north-western British Columbia. The property
comprises 65 contiguous mineral claims totaling 23,609 hectares in the
Liard Mining Division. Significant operations in the area include
Barrick Gold's legendary Eskay Creek Mine, Cominco's historic Snip Mine
and NovaGold and Teck Cominco's Galore Creek Project.  Foremore has
been the focus of the Company's exploration efforts dating back to the
summer of 2002 and was the focus of exploration by Cominco Limited
between 1989 and 1996.
 
While relatively inactive at Foremore during the two prior fiscal
years, the Company has recently completed an extensive program at
Foremore including gridding in four areas totaling 78.0 line km.  A
total of 52.6 line km of Induced Polarization (IP) surveys and 57.7
line km of Total Field Ground Magnetometer surveys were completed.  In
addition, 3,299.4 m of core drilling was completed in 13 holes from
which 890 samples were submitted for analytical work.  During the
course of geological mapping a total of 301 rock and 197 soil samples
were submitted for chemical analysis.  One of the primary objectives of
the 2008 work program was to explore for a potential bedrock source for
the sulphide-rich boulders and blocks of the South Boulder Field (SBF).


The drilling program was significantly smaller in scope than that
originally planned, due to a shortage of drill equipment and to the
short season remaining once the drill arrived on the property.
Consequently there remain a number of excellent untested drill targets
on the property, including the Ryder NW, Westmore, H.Valley/SBF, SG VMS
Horizon, Antler and Zig Zag Areas.

In the Antler area the Company completed 20.6 line km of grid (17
lines). The grid was mapped, a Ground Magnetometer survey and 3.0 km of
Induced Polarization completed.  Exploration targeted a north trending,
locally pyrite-rich felsic intrusion 2.5 km long and 200 m thick where
historical rock sampling by the Company yielded extremely anomalous
arsenic values.  No drilling was completed in the Antler Area during
2008. Massive sulphide boulders have been discovered in adjacent Rumble
Cr, as well as west of the Antler Grid.

In the SBF/Hanging Valley area 43.2 line km of grid (29 lines) were
completed.  The grid was mapped, Ground Magnetometer surveys and 35.7
km of Induced Polarization were completed.  Exploration targeted an
area where historical soil sampling by the Company defined a
multi-element soil anomaly, a potential source of, and proximal to the
South Boulder Field, comprised of more than 900 polymetallic massive
sulphide boulders.  Five drill holes, totaling 822.5 m, tested several
high chargeability anomalies but intersected mainly pyrite. A number of
intermediate anomalies remain to be tested and these may be indicative
of less conductive sphalerite/galena mineralization. Further work is
planned.

In the Westmore area 8.5 line km of grid (13 lines) were completed.
The grid was mapped and 8.3 km of Induced Polarization completed.
Exploration in this area targeted the prospective, altered rhyolite
unit host to the Ryder VMS mineralization located some 3 km to the
northeast.  Two drill holes, totaling 396.0 m, tested a high
chargeability anomaly associated with the altered rhyolite but failed
to intersect significant base or precious metal values.

Subsequent geophysical interpretations suggest that the drill holes may
have been collared updip from the anomaly & further work is planned
here.  In addition, a total of 21 samples were taken on one contoured
soil line to follow up on several historical soil samples which yielded
high Au values. The line was about 600 m long and sample stations
varied between 25 and 50 m apart.  Only one sample yielded an anomalous
value of 216.6 ppb Au.

In the Ryder/BRT area 5.7 line km of grid (5 lines) and 5.6 km of
Induced Polarization were completed.  Exploration in this area targeted
the prospective, altered rhyolite unit host to the Ryder and BRT VMS
mineralization.  Six drill holes, totaling 2,081.9 m, tested several
chargeability anomalies associated with the altered rhyolite.  Four of
these drill holes intersected VMS mineralization for which selected
intercepts are tabulated below:

---------------------------------------------------------------------
                        From       To   Width      Cu      Pb      Zn
Hole ID        Area      (m)      (m)     (m)       %       %       %
---------------------------------------------------------------------
FM08-43       Ryder   229.82   234.00    4.18   0.036   0.039   0.797
                      240.65   242.15    1.50   0.091   0.190    2.47
FM08-46         BRT   128.05   130.10    2.05   0.006   0.013    0.04
---------------------------------------------------------------------
FM08-53       Ryder    30.00    43.50   13.50   0.346   0.021   0.305

          Including    41.90    42.50    0.60   1.497   0.104   3.660
FM08-54       Ryder    24.00    27.00    3.00   0.131   0.117   0.575
                       42.43    43.35    0.92   0.045   0.011   0.404
 
                       48.73    51.00    2.27   0.180   0.038   0.509
                       55.50    64.50    9.00   0.214   0.030   0.428

          Including    60.88    62.37    1.49   0.923   0.120   1.100
                       73.50    81.00    7.50   0.380   0.053   0.600
          Including    75.00    77.30    2.30   0.954   0.093   1.420
                       89.20    99.15    9.95   0.163   0.059   0.328
                      106.50   108.00    1.50   0.092   0.021   0.235
                      115.50   124.50    9.00   0.088   0.023   0.184
                      154.50   177.00   22.50   0.132   0.009   0.198

          Including   159.00   160.80    1.80   0.194   0.010   1.270
                      181.50   202.50   21.00   0.066   0.038   0.440
          Including   186.00   187.50    1.50   0.034   0.070   1.200
                      212.15   217.50    5.35   0.152   0.026   0.107
                      223.50   228.00    4.50   0.065   0.025   0.160
                      237.00   243.00    6.00   0.128   0.009   0.094
                      249.00   252.00    3.00   0.073   0.016   0.176
                      259.50   265.50    6.00   0.166   0.016   0.451
                       24.00   265.50  241.50   0.076   0.017   0.170
---------------------------------------------------------------------

-----------------------------------------------------
                                 Ag               Au
    Hole ID           Area    (g/t)            (g/t)
    -------------------------------------------------
    FM08-43          Ryder      1.6    less than 0.1
                                6.1    less than 0.1
    FM08-46            BRT      9.7             0.34
    -------------------------------------------------
    FM08-53          Ryder     13.0              0.5

                 Including    195.2              1.1
    FM08-54          Ryder      3.4    less than 0.1
                                4.6              0.3

                                3.0    less than 0.1
                                6.3              0.1

                 Including     22.2              0.6
                                6.1              0.1
                 Including     13.7              0.2
                                4.5    less than 0.1
                                5.8              0.1
                                2.2    less than 0.1
                                2.9    less than 0.1

                 Including      3.8    less than 0.1
                                3.1    less than 0.1
                 Including      3.9    less than 0.1
                                3.3    less than 0.1
                                3.0    less than 0.1
                                3.4    less than 0.1
                                1.6    less than 0.1
                                2.3    less than 0.1
                                2.3    less than 0.1
    -------------------------------------------------


The last hole, FM08-54, intersected a thick (>250m) altered, dominantly
felsic sequence, highly anomalous in base & precious metals, indicating
that the VMS mineralizing system remains open to the northwest.
Drilling was curtailed due to the onset of winter conditions, and
additional work is planned to test the extension of the Ryder in this
direction.  Additional Chargeability anomalies remain to be tested.

In addition, three contoured soil lines (197 samples) were completed In
the Ryder area along the northwest facing mountain slope where the
prospective rhyolite stratigraphy is covered with overburden and
vegetation.  The 2008 soil sampling survey defined a multi-element
anomaly overlying altered rhyolite associated with the Ryder
mineralized system.  The anomaly is elongate towards the NNE, up to 500
m long and 200 m wide and defined by elevated concentrations of Zn, Cu,
Pb, As, Au, and Ag. This anomaly remains to be tested by drilling.
 
Expenditures on the Foremore Project during the fiscal year ended
August 31, 2008 were $1,374,824 and at August 31, 2008 totaled
$5,548,509 including $452,113 in acquisition, staking costs and advance
royalties.

SeaGold Property

The Company holds a 50% interest in the SeaGold Project, comprising 8
claim blocks of 4,000 hectares, centered on a number of gold and copper
occurrences approximately 35 km north of Barrick Gold's Eskay Creek
gold/silver mine in British Columbia.  The balance of the property
interest is now held by Romios Gold Resources Inc., which serves as the
operator of a 50:50 joint venture on the SeaGold project. Results are
pending from this fieldwork.

Lardeau Properties

A 2006 exploration program by the Company reviewed potential targets
within a 100 km radius of the MAX Molybdenum Mine. This work resulted
in the optioning of a 100% interest in four projects in the historic
Lardeau Mining Camp covering an area of approximately 5,600 hectares.
The Company has recently conducted exploratory prospecting and limited
Diamond drill programs on these four properties.

In 2007, the Company acquired by staking a 100% interest in the Butters
Peak Molybdenum Property, located approximately 25 km northeast of the
MAX Mine. Covering approximately 1,650 hectares, the property was
originally discovered by tracing highly anomalous regional silt
geochemical results to molybdenite float. The Company conducted limited
prospecting and reconnaissance on the property in 2008.

In light of current economic conditions, management considers it
unlikely that it will continue exploration on these early-stage
prospects in order to focus on its more advanced mining and exploration
projects in 2009. Therefore the Company has taken an impairment charge
of the total $1,244,873 in expenditures incurred on these projects
through August 31, 2008

Share Capital

In May of 2008, the Company received approval to repurchase up to a
maximum of 4,078,500 outstanding common shares in the Company through
the facilities of the TSX Venture Exchange (the "Exchange") until June
1, 2009. Pursuant to the policies of the Exchange, the Company is
permitted to repurchase through open market purchases, up to 2 per cent
of its outstanding common shares in any given 30-day period. The
Company did not repurchase any shares during the year ended August 31,
2008. Subsequent to August 31, 2008 the Company purchased through the
facilities of the TSX Venture Exchange, and subsequently cancelled a
total of 1,460,700 common shares under its normal course issuer bid.
Also subsequent to August 31, 2008 a total of 8,354,978 warrants and
121,000 options expired unexercised and 246,000 options were exercised
for proceeds of $49,200.  The Company had 80,755,628 common shares
outstanding, 90,172,378 on a full-diluted basis as at the date of this
report.

Outlook

As a result of recent global economic uncertainty and rapidly declining
commodity prices, management has decisively cut costs at the MAX
Molybdenum mine while continuing to operate under its Phase I mine
plan.  Phase II expansion plans, including completion capital spending
for that expansion, are being minimized.  Similarly, exploration work
at the Company's projects, including the MAX property, will be limited
to definition drilling where required. Management will continue to
operate the mine while it generates positive cash flow, recognizing
that the MAX Molybdenum Mine was originally designed to operate at
historic prices.  Significant gains have also been realized from the
recent Canada-USA exchange rate and fuel cost reductions.

It remains management's belief that molybdenum prices should remain
significantly greater than historic values for the foreseeable future
due to i) production problems globally, ii) the reduction of by-product
production related to copper mines and iii) the inability of new mines
to achieve financing.  In real terms, recent events have seriously
eroded the global supply of molybdenum and management believes that a
realization of supply and demand fundamentals in the medium-term will
result in positive changes to pricing.  It is therefore Management's
goal to remain in operation and preserve the value of the resource and
the opportunity to produce molybdenite concentrate in a rapidly
appreciating environment. 

In the interim, production at the MAX Molybdenum Mine will be limited
to current target levels in an effort to preserve the molybdenum
resource, and the mine will be readied, with minimal additional cost,
for a rapid response to periods when greater margins on sales can be
realized. Few other producers will have similar ability to ramp-up
production.

Management has observed that experience with the geological controls on
mineralization, its grade control program, and underground
infrastructure improvements have dramatically reduced the average
production costs and anticipate lower cash costs going forward.
 
Financial Results

The information in this news release and the selected financial
information should be read in conjunction with the audited consolidated
financial statements, and management discussion and analysis, for the
year ended August 31, 2008, which will be available at Roca's website
at www.rocamines.com.

For the year ended August 31, 2008, the Company reported a loss of
$2,493,151 and an accumulated deficit of $4,909,947 at that date.
Total assets were $60,462,014 and cash and cash equivalents were
$2,497,077 at August 31, 2008.  While the Company had cash flow from
operations of $7,795,318 for the year ended August 31, 2008, a recent
decline in the price for molybdenite concentrates has significantly
reduced cash operating margins. The ability of the Company to continue
as a going concern is dependent upon its ability to reduce costs and
improve operating margins or to continue to raise adequate financing.
Management has implemented a series of cost cutting measures and
contingency plans for future financing should economic conditions
deteriorate. There is no assurance that these initiatives will be
successful in the future.

Summary Consolidated Statements of Operations and Loss

Summary Consolidated Statements of Operations and Loss

--------------------------------------------------------------------
                                                          Year ended
                                                     August 31, 2008
                                                                Cdn$
--------------------------------------------------------------------
Total Revenues                                            18,785,083
--------------------------------------------------------------------
Cost of sales                                            (7,872,063)
--------------------------------------------------------------------
Depletion, amortization, accretion                      (12,472,155)
--------------------------------------------------------------------
Mining Loss                                              (1,559,135)
--------------------------------------------------------------------
G&A, Stock-based comp., write-offs                       (3,800,186)
--------------------------------------------------------------------
Loss from Operations                                     (5,359,321)
--------------------------------------------------------------------
Other income (expenses)                                       74,161
--------------------------------------------------------------------
Income and mining tax provision (recovery)               (2,792,009)
--------------------------------------------------------------------
Net Loss for the Year                                    (2,493,151)
--------------------------------------------------------------------
Loss per Share - Basic and Diluted                            (0.03)
--------------------------------------------------------------------


Scott E. Broughton, P.Eng, is the qualified person responsible for the
preparation of this news release under National Instrument 43-101.

ROCA MINES INC.
"Scott Broughton"
     
Scott E. Broughton, P.Eng. - President & CEO


For further information contact:
Investor Relations
Tel:   604-684-2900
Fax: 604-684-2902
Email: info@rocamines.com
Web:  www.rocamines.com

The TSX Venture Exchange does not accept responsibility for the
adequacy or accuracy of this release.

=======================================================================
Copyright (c) 2008 ROCA MINES INC. (ROK)  All rights reserved.  For
more information visit our website at http://www.rocamines.com/ or send
mailto:info@rocamines.com
=======================================================================
.
<
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Roca Mines Inc.

DEVELOPMENT STAGE
CODE : ROK.V
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Roca Mines is a gold and molybdenum exploration company based in Canada.

Roca Mines holds various exploration projects in Canada.

Its main asset in development is MAX in Canada and its main exploration properties are FOREMORE and SEAGOLD in Canada.

Roca Mines is listed in Canada and in United States of America. Its market capitalisation is CA$ 38.2 millions as of today (US$ 27.8 millions, € 26.1 millions).

Its stock quote reached its highest recent level on December 31, 2007 at CA$ 3.98, and its lowest recent point on August 24, 2012 at CA$ 0.02.

Roca Mines has 123 250 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Roca Mines Inc.
Reports Annual Results
2008 Annual report
Reports Annual Results
Financings of Roca Mines Inc.
5/10/2011Closes $2.5 million Financing
8/8/2007Closes Bought Deal Financing
Option Grants of Roca Mines Inc.
1/28/2010Amends Incentive Stock Options
8/21/2008Incentive Stock Options Granted
11/16/2007Incentive Stock Options Granted
Nominations of Roca Mines Inc.
9/7/2012Director and Officer Resignations
Financials of Roca Mines Inc.
7/29/2011Reports Third Quarter Results
5/2/2011Reports Second Quarter Results
7/30/2010Reports Third Quarter Results
4/30/2010Reports Second Quarter Results
1/29/2010Reports First Quarter Results
7/30/2009Reports Third Quarter Results
Project news of Roca Mines Inc.
10/3/2011(Max)MAX Molybdenum Production to be Suspended
7/28/2011(Max)MAX Molybdenum Mill Restarts
7/11/2011(Max)- MAX Molybdenum Mine Schedule Update
4/29/2010(Max)MAX Molybdenum Mine Receives 1,000 tonnes/day Permit
4/14/2010Drilling Results At Nuevo / Once Bocas Target
4/2/2010(Max)Max Wins 2009 Bc Mining And Sustainability Award
11/27/2009(Max)Targets Increased Production and New Exploration at MAX
1/9/2009(Max)MAX Mine Restarts Ahead of Schedule
12/11/2008(Max)MAX Mine Rockfall Extends Maintenance Break
12/4/2008(Max)MAX Mill & Concentrator Christmas Shutdown
11/19/2008(Max)MAX Molybdenum Mine Production Review and Outlook
8/13/2008(Max)Drilling Intersects New Molybdenum Zone at MAX and Drilling ...
7/30/2008(Max)Drilling Intersects Significant Tungsten Mineralization Abov...
6/13/2008(Max)MAX Property Exploration Update
6/12/2008(Max)MAX Molybdenum Mine Production Update
4/17/2008(Max)MAX Molybdenum Mine Achieves Commercial Production
2/8/2008 MAX Molybdenum Drilling - Initial Results Confirm Deep Pote...
11/14/2007(Max)MAX Exploration Drilling Update
10/30/2007(Max) Production Commences at MAX Molybdenum Mine
9/11/2007(Max)MAX Molybdenum Mine Update
9/4/2007(Max)MAX Molybdenum Mine Construction Update
7/19/2007(Max)Molybdenum Exploration Drill Program Commences
7/11/2007(Max)MAX Molybdenum Mine Development Update
4/26/2007(Max)Molybdenum Mine Development Update
Corporate news of Roca Mines Inc.
11/6/2013Announces Delisting from TSX Venture Exchange
11/6/2013(Max)Discovery Ventures And Roca Mines Announce Entry Into Agreem...
10/10/2012Announces Trading Suspension
7/13/2012Announces Strategic Review
12/29/2011Reports Year End Results
8/3/2011(Max)MAX Molybdenum Mine Production Resumes
6/29/2011(Max)MAX Molybdenum Mine Production Schedule
4/28/2011(Max)MAX Molybdenum Mine Production Financing
7/23/2010 Termination of Nuevo Milenio Option
3/23/2010 Director Resignation
3/1/2010Positive initial drill results at Nuevo Milenio
9/11/2009Plans New Drilling Program at Nuevo Milenio Gold/Silver Proj...
7/27/2009Options Precious Metals Project in Mexico
2/16/2009Closes $2.435 Million Financing
1/27/2009Closes First Tranche of Financing
1/31/2009Team Presented with E.A. Scholz Award
1/17/2009Increases Financing
1/16/2009to Complete Working Capital Financing
7/8/2008Exploration Drilling Update
5/28/2008Notice of Intention to Make Normal Course Issuer Bid
12/11/2007Molybdenite Concentrate Shipments Commence
8/20/2007CLOSES OVER-ALLOTMENT OPTION
3/7/2007Closes $10 million Financing
2/28/2007Arranges MAX Molybdenum Project Expansion Financing
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (ROK.V)Other OTC (ROCAF)
0.310+0.00%0.002+0.00%
TSX-V
CA$ 0.310
04/19 16:05 -
0%
Prev close Open
0.310 0.310
Low High
0.295 0.315
Year l/h YTD var.
0.260 -  0.340 -3.12%
52 week l/h 52 week var.
0.260 -  0.440 -19.48%
Volume 1 month var.
641,027 14.81%
24hGold TrendPower© : -37
Produces
Develops Molybdenum
Explores for Copper - Gold - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/11/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-19.48%
2023-19.79%0.480.28
2022166.67%0.550.18
20210.00%0.300.18
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.22+1.63%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.59%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.48-1.59%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.84-1.31%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.85-2.63%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.83+0.78%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :