Scorpio Gold Corp.

Published : October 01st, 2012

Reports on Mine Plan Study for the Drinkwater and Mary Pits, Mineral Ridge Gold Operation

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Gold | Gold Production | Recovery | Report | Water |

News - Monday, October 01, 2012
Scorpio Gold Reports on Mine Plan Study for the Drinkwater and Mary Pits, Mineral Ridge Gold Operation


Vancouver, October 1, 2012 - Scorpio Gold Corporation ("Scorpio Gold" or the "Company") (TSX-V: SGN) announces results of the Life of Mine Plan Study (LOM) completed by AMEC E&C Services Inc. (AMEC) of Sparks, Nevada dated July 15, 2012 for the Drinkwater and Mary pits at the 70% owned Mineral Ridge Gold Operation, Nevada. Scorpio Gold attained commercial production status at Mineral Ridge on January 1, 2012.

The mine plan projects a current 3 year mine life at 66,000 tons per month (t/m) based on estimated Measured and Indicated Mineral Resources of 3.2 million tons (MT) grading 0.059 ounces per ton (oz/ton) gold (190,800 oz contained gold) including Probable Mineral Reserves of 2.1 MT grading 0.062 oz/ton gold (131,000 oz contained gold).

This mine plan study is exclusive of ongoing studies by Telesto Nevada Inc. (Telesto), which includes deposit modelling and a NI 43-101 compliant Mineral Resource estimate for the satellite deposits, Brodie, Wedge B, Bluelite, Solberry and Oromonte (see July 24 2012 news release).

Peter Hawley, CEO comments, "This snapshot view of the LOM provides a strong base for the Company to grow at Mineral Ridge. Already the study's quoted throughputs, grades and produced ounces have been exceeded in operations to date at Mineral Ridge. The completed 2012 Mary LC drilling and the present drilling of the Drinkwater highwall zone will be incorporated into the 2013 mine reserve plan later this fall, which is expected to add additional years to the LOM. We are pleased to receive this economic study that solidly places over 68% of the total Measured and Indicated Resources into the Probable Reserve category, and provides good recommendations for improving the operation as we have already done and for advancing our satellite deposits to development and production stages. The estimated timing for Telesto's completion of the Mineral Resource estimate for the adjacent satellite deposits is the end of October."

Principal Outcomes - Life of Mine Plan Study
  • Estimated Probable Mineral Reserves: 2.1 Mt at 0.062 oz/ton gold (131,000 oz contained gold).
  • 3 year mine life at 66,000 t/m throughput.
  • Average annual gold production of 30,000 oz over the projected life of mine.
  • Total direct operating cash costs of $906/oz gold over the life of mine.
  • After tax net present value (NPV) of $25.8 million (8% discount rate) at an average gold price of $1,530/oz. Note that the average gold price used in the NPV calculation is based on a near-term spot gold price which regresses to a long-term price of $1,300 per ounce of gold, or the price at which the reserves and resources are reported.
  • Key risks to the Project include:
    • Current operations mining rate is lower than assumed in the LOM; extra equipment, operating shifts, or both will make up the difference.
    • Current operations heap leach solution application rates are lower than indicated in the LOM; this situation is likely to improve once the additional water well is operational, expected in the fourth quarter of 2012.
  • Key opportunities at the Project include:
    • Current mining results indicate that some of the material mined from voids left by historical underground mining contains gold mineralization, which has allowed a net increase in the ore recovered over what was predicted by the Mineral Reserve estimate.
    • There is potential to identify additional mineralization from drill-defined extensions to the Drinkwater and Mary deposits, which may support Mineral Resource estimation and potentially be converted into Mineral Reserves.
    • Exploration potential of identified prospects surrounding the Drinkwater and Mary deposits.

Mineral Reserves presented in Table 1 have demonstrated economic viability through the application of modifying factors in the LOM. All Mineral Reserves are classified as Probable Mineral Reserves with no Proven Mineral Reserves.

Table 1. Mineral Reserve Estimate - Drinkwater & Mary Pits
Pit Ore Tons
(x1000)
Gold Grade
(oz/ton)
Contained
Gold (oz)
Waste Tons
(x1000)
Strip Ratio
(waste:ore)
Drinkwater 1,269 0.061 77,000 4,537 3.6
Mary 832 0.065 54,000 5,488 6.6
Total 2,101 0.062 131,000 10,025 4.8

Notes:
  1. The effective date of the Mineral Reserve is April 30, 2012.
  2. The Mineral Reserve estimate was prepared by Jim Ashton, P.E., of Scorpio Gold and audited by independent qualified person, Don Tschabrun, SME-RM, of AMEC.
  3. Mineral Reserves are reported at a 0.020 oz/ton gold cut-off grade.
  4. Mineral Reserves are contained within a designed pit with access ramps based on the Lerchs-Grossmann (LG) algorithm utilizing a $1,300 oz gold price. The optimization mining cost was $5.40/t of ore mined at Drinkwater, $5.31/t of ore mined at Mary, $2.77/t of waste mined, and $1.46/t of fill mined. An average crushing cost of $2.57 and an average processing cost of $6.90 were applied per ton processed. G&A costs were applied at $3.98 per ton processed. Shipping and refining costs of $21/oz gold produced were applied. A 65% metallurgical recovery was applied. Overall pit slope angles ranged from 45 degrees to 49 degrees.

Table 2. Mineral Resource Estimate - Drinkwater & Mary Pits
Classification Tons
(x1000)
Gold Grade
(oz/ton)
Contained
Gold (oz)
Measured  - - -
Indicated 3,231 0.059 190,800
Measured + Indicated 3,231 0.059 190,800
Inferred 89 0.043 3,800

Notes:
  1. Mineral Resources are reported inclusive of Mineral Reserves.
  2. The effective date of the Mineral Resource is April 30, 2012.
  3. The Mineral Resource estimate was prepared by Jim Ashton, P.E., of Scorpio Gold and audited by independent qualified person, Michael Munroe, SME-RM, of AMEC.
  4. Mineral Resources are reported at or above a 0.020 oz/ton gold cut-off grade.
  5. Mineral Resources are reported using a long-term gold price of US$1,500/oz.
  6. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

The Mineral Resource estimate is based on a total of 1,510 drill holes and 52,682 assay results collected between 1939 and 2012 from the Drinkwater, Mary and Last Chance deposits. The cut-off date for information used in the geologic model and Mineral Resource model was February 29, 2012.

The key assumptions, parameters and methods used to estimate the Mineral Resource and Mineral Reserve are as follows:
  • Mineral Resources reported are constrained within a conceptual Lerchs-Grossmann (LG) pit shell and are inclusive of Mineral Reserves.
  • The economic parameters used to construct the Mineral Resource LG pit are the same as those used in the Mineral Reserve pit except that the price of gold was increased from $1,300 per ounce to $1,500 per ounce.
  • The block model consists of 15 ft x 15 ft x 10 ft blocks estimated using inverse-distance to the second power methodology. Mineralized envelopes were constructed on 50 ft spaced sections using a 0.010 oz/ton gold assay grade as a guide. The envelopes were combined into wire-frames that defined the extent of mineralization for both the Drinkwater and Mary deposits.
  • Extensive historical underground workings are present in the Drinkwater and Mary areas. Underground wire-frames were used to remove the percentage of the block contained within the mineralized envelope.
  • A single bulk density factor of 13 cubic ft per short ton was assigned to all blocks that represent in-situ rock and used in the Mineral Resource estimates.
  • In the Drinkwater area, assays were capped at a threshold of 1.6 oz/ton gold, and in the Mary area assays were capped at a threshold of 1.0 oz/ton gold.
  • Mineralization pinches and swells, and is not easily mapped, and correlation between sections is often difficult, therefore outlier restriction was also applied to restrict gold interpolation at a threshold of 0.5 oz/ton gold and a distance of 60 ft.

The Mineral Resource and Mineral Reserve estimates were prepared by Jim Ashton, P.E., of Scorpio Gold and audited by AMEC. An independent technical report supporting the disclosure of the Mineral Resource and Mineral Reserve estimate is being prepared by AMEC and will be filed on SEDAR within 45 days of this news release. The Mineral Reserve and Mineral Resource estimates have been prepared in accordance with the 2010 CIM Definition Standards for Mineral Resources and Mineral Reserves as incorporated by reference in National Instrument 43-101 of the Canadian Securities Administrators. The AMEC Qualified Persons for the estimates are Mr Don Tschabrun, RM-SME for Mineral Reserves, and Mr Michael Munroe, RM-SME for Mineral Resources. The Technical Report will be authored by Todd Wakefield, SME-RM, Michael Munroe, SME-RM, Don Tschabrun, SME-RM, and Michael Drozd, SME-RM, of AMEC. Readers are cautioned that the conclusions, projections and estimates set out in this press release are subject to important qualifications, assumptions and exclusions, all of which are detailed in the upcoming technical report. To fully understand the summary information set out above, the technical report that will be filed on SEDAR (www.sedar.com) should be read in its entirety.

Scorpio Gold's CEO, Peter J. Hawley, P.Geo., is a Qualified Person for the Mineral Ridge project and has reviewed and approved the content of this release. For additional information please see the Company's website at www.scorpiogold.com.

About Mineral Ridge

The Mineral Ridge gold mining operation is located in Esmeralda County, Nevada. Scorpio Gold holds a 70% interest with joint venture partner Waterton Global Value L.P. (30%), and is entitled to receive 80% of cash flow generated. Mineral Ridge is currently in production as a conventional open pit mining and heap leach operation. The property is host to multiple gold-bearing structures, veins and bodies at exploration, development and production stages.

ON BEHALF OF THE BOARD
SCORPIO GOLD CORPORATION


Peter J. Hawley,
CEO

For further information contact:
Steve Roebuck Tel: (819) 825-7618
Email:

Investor Relations:
Jim Macdonald, Torrey Hills Capital
Tel: (858) 456-7300
Email:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

The Company relies on litigation protection for "forward-looking" statements. This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur, and include, without limitation, statements regarding the Company's plans with respect to exploration, development and exploitation of its Mineral Ridge project. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements, including risks such as mining and operational risks affecting projected production and those risk factors outlined in the Company's Management Discussion and Analysis as filed on SEDAR. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty thereof.

Copyright � 2012 SCORPIO GOLD CORPORATION (TSX: SGN) All rights reserved. For more information visit our website at http://www.scorpiogold.com/ or send email to scorpio@scorpiogold.com
To Unsubscribe from this email list, please click on the link below:

Scorpio Gold Corp.

DEVELOPMENT STAGE
CODE : SGN.V
ISIN : CA80918M1041
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Scorpio Gold is a gold exploration company based in Canada.

Its main asset in development is MINERAL RIDGE MINE in USA and its main exploration properties are COCHRANE HILL, CARIBOU GOLD MINE, LAC ARSENAULT and MINERAL RIDGE in Canada.

Scorpio Gold is listed in Canada. Its market capitalisation is CA$ 25.0 millions as of today (US$ 18.2 millions, € 17.0 millions).

Its stock quote reached its highest recent level on March 12, 2010 at CA$ 1.12, and its lowest recent point on December 07, 2018 at CA$ 0.01.

Scorpio Gold has 124 950 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Scorpio Gold Corp.
5/27/2011Amends Debt Terms
3/8/2010Increases Size of Private Placement and Exercises Over-Allot...
2/24/2010Announces Terms of Private Placement
Option Grants of Scorpio Gold Corp.
1/27/2012Announces Stock Option Grants
6/13/2011Announces Results of AGM and Grants Options
4/6/2011Engages Torrey Hills Capital for Investor Relations
Nominations of Scorpio Gold Corp.
7/10/2013Appoints Peter A. Brieger to the Board of Directors
9/7/2012Appoints Steve Roebuck as President
Financials of Scorpio Gold Corp.
4/8/2016Reports Fourth Quarter and Provides Year-End Financial Resul...
7/14/2015(Mineral Ridge)Produces 8,738 Ounces of Gold in Second Quarter 2015 at the ...
11/26/2013Reports Financial Results for Third Quarter of 2013
8/23/2013Reports Financial Results for Second Quarter of 2013 and Pro...
7/16/2013(Mineral Ridge)Produces 10,769 Ounces Gold in Second Quarter 2013 at the Mi...
5/15/2013Reports Financial Results for First Quarter of 2013
4/15/2013Reports Record Fourth Quarter and Provides Year-End Financia...
8/28/2012Announces its Unaudited Financial and Operating Results for ...
5/16/2012Announces its Unaudited Financial and Operating Results for ...
Project news of Scorpio Gold Corp.
4/15/2015(Mineral Ridge)Reports Final Results from 2014 Drilling at the Mary LC Depo...
3/24/2015(Mineral Ridge)Commences 2015 Drilling Program at the Mineral Ridge Project...
1/19/2015(Mineral Ridge)Final Results from 2014 Expansion Drilling on the NW Brodie ...
2/25/2014(Mineral Ridge)Reports on Expansion Drilling at the Brodie Satellite Deposi...
2/13/2014(Mineral Ridge)Forecasts 40,000-45,000 oz. Gold Production in 2014 at the M...
1/14/2014(Mineral Ridge)Sets Quarterly Production Record at the Mineral Ridge Operat...
12/16/2013(Mineral Ridge)s Expansion Drilling at the Bluelite Satellite Deposit, Min...
11/13/2013(Mineral Ridge)s Expansion Drilling at the Brodie Satellite Deposit, Miner...
11/7/2013Intersects 4.43 g/t Gold over 10.67 meters at the Mary/LC Zo...
11/4/2013s Goldwedge Project
8/7/2013(Mineral Ridge)Reports on Expansion Drilling at the Brodie Satellite Deposi...
7/8/2013(Mineral Ridge)Intersects 1.76 g/t Gold over 10.67 meters and Continues to ...
6/5/2013(Mineral Ridge)Intersects 5.17 g/t gold over 21.34 meters and Extends Mary/...
4/24/2013(Mineral Ridge)Reports on 2013 Exploration Program at Mineral Ridge and Upd...
10/30/2012(Mineral Ridge)Intersects 16.77 metres grading 2.61 g/t Gold at the Drinkwa...
10/1/2012(Mineral Ridge)Reports on Mine Plan Study for the Drinkwater and Mary Pits...
7/11/2012Announces Settlement of Litigation Commenced by Former Joint...
5/2/2012(Mineral Ridge)Waterton Becomes Scorpio Gold's Joint Venture Partner at Min...
4/17/2012(Mineral Ridge)en Phoenix Announces Removal of Scorpio Gold as Manager of M...
4/5/2012Litigation Commenced by Scorpio Gold's Joint Venture Partner
1/18/2012en Phoenix JV Partner Scorpio Gold Intersects 12.20 Meters G...
9/13/2011(Mineral Ridge)Discovers Silver-Enriched Zone on Mineral Ridge Project
7/22/2011(Mineral Ridge)Provides Operations Update at the Mineral Ridge Project, Nev...
6/28/2011(Mineral Ridge)Announces First Gold and Silver Sales from the Mineral Ridge...
6/7/2011GP JV Partner Scorpio Gold Announces First Production Blast ...
6/7/2011(Mineral Ridge)Update on its Mineral Ridge Gold Project, Nevada
5/11/2011(Mineral Ridge)GP JV Partner Scorpio Gold Reports Sampling of Stockpile at ...
5/11/2011(Mineral Ridge)Sampling of Stockpile at the Mineral Ridge Gold Deposit, Nev...
5/9/2011(Mineral Ridge)GP JV Partner Scorpio Gold Awards Mining Contract For The Mi...
5/9/2011(Mineral Ridge)Awards Mining Contract for the Mineral Ridge Gold Deposit, N...
4/26/2011(Mineral Ridge)GP JV Partner Scorpio Gold Makes First Shipment of Loaded Go...
4/26/2011(Mineral Ridge)Makes First Shipment of Loaded Gold Carbon to Refinery from ...
4/20/2011(Cochrane Hill)Atlantic Gold Elects to Exercise Right to Purchase Cochrane ...
3/1/2011(Mineral Ridge)GP Joint Venture Partner Scorpio Gold Has Activated Leach Pa...
2/2/2011(Mineral Ridge)Commences 2011 Drilling at the Mineral Ridge Gold Project, N...
2/3/2011(Mineral Ridge Mine)GP JV Partner Scorpio Gold Begins 13,167m Drill Program
7/8/2010Rehab of the Mineral Ridge Pregnant/Barren Pond Facility Rev...
6/30/2010(Mineral Ridge)Surface RC Drilling on the Mineral Ridge Gold Deposit Contin...
Corporate news of Scorpio Gold Corp.
8/3/2016Scorpio Gold Reports Plans for Phase Two Exploration Program...
7/27/2016Scorpio Gold Reports Results of AGM
7/14/2016Scorpio Gold Produces 10,089 Ounces of Gold in Second Quarte...
6/27/2016Scorpio Gold Reports Final Results from 2016 Exploration Dri...
6/20/2016Scorpio Gold Reports Final Results from Exploration Drilling...
5/24/2016Scorpio Gold Reports Results from 2016 Exploration Drilling ...
5/13/2016Scorpio Gold Reports Financial Results for First Quarter of ...
5/10/2016Scorpio Gold Reports Results from 2016 Exploration Drilling ...
5/3/2016Scorpio Gold Reports Results from 2016 Definition Drilling o...
4/11/2016Scorpio Gold Produces 8,569 Ounces of Gold in First Quarter ...
4/8/2016Scorpio Gold Reports Fourth Quarter and Provides Year-End Fi...
3/23/2016Scorpio Gold Announces 2016 Production Forecast
12/21/2015Scorpio Gold Reports Results of Exploration Drilling at the ...
12/17/2015Scorpio Gold Reports Intersects 11.79 g/t Gold over 9.14 met...
11/27/2015Scorpio Gold Reports Financial Results for Third Quarter of ...
10/26/2015Scorpio Gold Reports Additional Results from 2015 Expansion ...
10/19/2015Scorpio Gold Reports Results from 2015 Exploration Drilling ...
10/14/2015Scorpio Gold Produces 9,497 Ounces of Gold in Third Quarter ...
9/28/2015Scorpio Gold Reports Results from 2015 Exploration Drilling ...
9/21/2015Scorpio Gold Reports Results from 2015 Expansion Drilling at...
9/14/2015Scorpio Gold Reports Results from 2015 Expansion Drilling at...
9/8/2015Scorpio Gold Reports Results from 2015 Underground Drilling ...
8/27/2015Scorpio Gold Reports Financial Results for Second Quarter of...
8/24/2015Scorpio Gold Reports Results from Exploration Drilling at th...
8/17/2015Scorpio Gold Closes Non-Dilutive Debt Financing with Waterto...
7/7/2015Scorpio Gold Reports Results from 2015 Exploration Drilling ...
4/27/2015Scorpio Gold Commences Underground Drill Program and Reports...
4/23/2015Scorpio Gold Sets Quarterly Production Record at the Mineral...
4/21/2015Scorpio Gold Reports Favourable Decision from BLM for Amende...
4/15/2015Scorpio Gold's Reports Final Results from 2014 Drilling at t...
4/8/2015Scorpio Gold Intersects 12.54 g/t gold over 15.91 meters at ...
4/8/2015(Mineral Ridge)Intersects 12.54 g/t Gold Over 15.91 Meters at the Solberry ...
3/24/2015Scorpio Gold Commences 2015 Drilling Program at the Mineral ...
3/11/2015Scorpio Gold Retires Debt Ahead of Schedule and Announces 20...
3/9/2015Scorpio Gold Announces Strategic Financing to Raise Gross Pr...
3/6/2015Scorpio Gold Announces Strategic Financing to Raise Gross Pr...
2/3/2015Scorpio Gold Reports Final Results from 2014 Expansion Drill...
1/15/2015Scorpio Gold Grants Incentive Stock Options
1/13/2015Scorpio Gold Reports Record Annual Gold Production at the Mi...
12/22/2014Scorpio Gold Reports Final Results from 2014 Expansion Drill...
12/16/2014Scorpio Gold's Intersects 7.79 g/t Gold Over 9.14 Meters at ...
12/1/2014Scorpio Gold Reports Results from 2014 Expansion Drilling at...
11/24/2014Scorpio Gold Intersects 1.12 g/t Gold Over 36.58 Meters on t...
11/20/2014Scorpio Gold Reports Financial Results for Third Quarter of ...
11/3/2014Scorpio Gold Announces Discovery - Intersects 31.79 g/t Gold...
10/22/2014Scorpio Gold Accelerates Exploration Program and Intersects ...
10/14/2014Scorpio Gold Provides News Release Correction
10/9/2014Scorpio Gold Produces 11,228 Ounces of Gold in Third Quarter...
10/7/2014Scorpio Gold's 2014 Drilling Continues to Upgrade the Mary L...
9/16/2014Scorpio Gold Reports Additional Results from 2014 Expansion ...
9/15/2014Scorpio Gold Reports Triggering of Bonus Share Consideration...
9/9/2014Scorpio Gold to Attend Precious Metals Summit and Denver Gol...
9/8/2014Scorpio Gold Reports Results from 2014 Expansion Drilling at...
2/11/2014(Mineral Ridge)Intersects 3.10 g/t over 9.14 meters at the Mary LC Zone, Mi...
2/3/2014(Mineral Ridge)Intersects 6.06 g/t Gold over 10.67 meters at the Solberry S...
1/29/2014Signs LOI to Sell Pinon Properties to Gold Standard Ventures
10/9/2013(Mineral Ridge)Produces 9,632 Ounces Gold in Third Quarter 2013 at the Mine...
9/23/2013Drilling at the Oromonte Deposit Intersects 10.67 meters Gra...
9/11/2013Expansion Drilling at the Bluelite Deposit Intersects Near-S...
8/16/2013(Mineral Ridge)Reports Mineral Resource Estimate on the Satellite Deposits ...
7/30/2013(Mineral Ridge)Mineral Ridge Operation to Receive Mine Operator Safety Awar...
6/25/2013Reports Results of Annual & Special Meeting
6/7/2013Grants Incentive Stock Options
5/9/2013Adopts Advance Notice Policy for Director Nominations
4/15/2013(Mineral Ridge)Announces First Quarter 2013 Operating Results for the Miner...
2/7/2013(Mineral Ridge)Releases Final Fourth Quarter 2012 Operating Results and Pro...
1/16/2013(Mineral Ridge)Announces Fourth Quarter 2012 Preliminary Operating Results ...
10/15/2012(Mineral Ridge)Announces Third Quarter 2012 Operating Results for the Miner...
10/11/2012Announces Signing of Definitive Asset Purchase Agreement to ...
9/26/2012to Commence Normal Course Issuer Bid
9/25/2012Provides Corporate Update
9/11/2012(Mineral Ridge)Mary LC Zone Drilling Intersects 7.62 metres Grading 3.15 g/...
8/30/2012Announces Non-Binding Letter of Intent to Acquire Nevada Min...
8/22/2012(Mineral Ridge)Mary LC Zone Drilling Intersects 7.62 metres grading 6.16 g/...
8/10/2012(Mineral Ridge)Announces its Operating Results for the Second Quarter of 20...
7/30/2012(Mineral Ridge)Drilling Intersects 7.62 metres grading 2.67 g/t Gold on the...
7/24/2012(Mineral Ridge)Provides Guidance for New NI 43-101 Compliant Mine Plan Stud...
7/9/2012(Mineral Ridge)Drilling Intersects 7.62 metres grading 2.92 g/t Gold on the...
6/25/2012(Mineral Ridge)Drilling Intersects 10.67 metres grading 8.25 g/t Gold on Or...
6/12/2012(Mineral Ridge)Drilling Intersects 10.67 metres grading 1.35 g/t Gold on th...
6/5/2012Announces Results of AGM
6/4/2012(Mineral Ridge)Drilling Intersects 21.34 metres grading 1.17 g/t Gold on Br...
5/24/2012(Mineral Ridge)Drilling Intersects 24.39 metres grading 0.90 g/t Gold on Br...
5/1/2012(Mineral Ridge)Provides 2012 Guidance for the Mineral Ridge Gold Operation,...
4/9/2012Provides Update on Golden Phoenix Litigation
3/21/2012(Mineral Ridge)Drilling Intersects 6.10 metres grading 5.82 g/t Gold on Mar...
2/28/2012(Mineral Ridge)Drilling Intersects 12.20 metres grading 4.22 g/t Gold on Ma...
2/8/2012(Mineral Ridge)Reports 2011 Operations Review and Achievements at the Miner...
1/17/2012(Mineral Ridge)Intersects 12.20 metres grading 3.99 g/t Gold Followed by 7....
1/5/2012(Mineral Ridge)en Phoenix JV Partner Scorpio Gold Intersects 10.67 Meters G...
1/5/2012(Mineral Ridge)Intersects 10.67 metres grading 3.65 g/t Gold on Mary Zone, ...
9/26/2011(Mineral Ridge)Intersects 3.05 metres grading 15.85 g/t Gold on Solberry Zo...
9/22/2011(Mineral Ridge)Provides Update at Mineral Ridge Operation
6/13/2011(Mineral Ridge)GP JV Partner Scorpio Gold Begins Exploration Drilling on Co...
6/13/2011(Mineral Ridge)Begins Exploration Drilling on Coyote Target, Mineral Ridge ...
4/19/2011(Mineral Ridge)GP JV Partner Scorpio Gold Appoints Mine Manager for the Min...
4/19/2011(Mineral Ridge)Appoints Mine Manager for the Mineral Ridge Gold Deposit, Ne...
4/12/2011(Mineral Ridge)=E2??s Exploration Drilling Expands Mineralization from Open...
4/11/2011(Cochrane Hill)Enters into Purchase Agreement to Sell Caribou and Cochrane...
3/1/2011(Mineral Ridge)Leach Pad Activated for Gold Recovery at Mineral Ridge
2/14/2011Commences Leach Pad Operations at Mineral Ridge
5/7/2010TSXV: SGN - Research Note
2/18/2010Surface Exploration on the Mineral Ridge Gold Project Prompt...
2/24/2010(TSXV: SGN) Press Release
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (SGN.V)
0.200+5.26%
TSX-V
CA$ 0.200
04/24 15:54 0.010
5.26%
Prev close Open
0.190 0.200
Low High
0.200 0.200
Year l/h YTD var.
0.190 -  0.265 -13.04%
52 week l/h 52 week var.
0.020 -  0.265 344.44%
Volume 1 month var.
3,650 900.00%
24hGold TrendPower© : 24
Produces
Develops Gold
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/18/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024300.00%
202325.00%0.080.03
2022-63.64%0.110.04
2021-26.67%0.170.09
202057.89%0.220.06
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.71%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :