September 2016 Quarterly Activities Report

September 2016 Quarterly Report 19 October 2016

Highlights

  • A$24M generated from operations after interest and contractor profit share

  • 4.1M WMT shipped (June 2016 Quarter 3.7M WMT)

  • Average realised price of A$56/WMT CFR (June 2016 Quarter A$57/WMT CFR)

  • Full cash costs* of A$50/WMT CFR (June 2016 Quarter: A$49/WMT CFR)

  • Net Debt reduced to A$89M at 30 September 2016 (A$109M at 30 June 2016) following increase in cash and favourable foreign exchange movements

  • Cash on hand at 30 September 2016 A$95M (30 June 2016: A$81M)

  • A$15M of debt will be repaid in October 2016 via term loan cash sweep mechanism

Atlas Iron Limited (ASX: AGO) is pleased to report on the September 2016 Quarter.

Atlas Managing Director, Daniel Harris said the September 2016 Quarter results provided further evidence of the Company's turnaround on both the operational and financial fronts.

"These results continue to demonstrate that Atlas is maintaining its tight control on costs while generating strong production volumes," Mr Harris said. "This combination is enabling Atlas to take advantage of solid iron ore prices, as shown by our margins and our overall free cash flow generation."

"This in turn means we will repay A$15 million in debt in October 2016 which will further strengthen our balance sheet," Mr Harris added. "Net debt at 30 September 2016 was under A$90M, a significant improvement from the levels prior to the restructure, which stood at A$257M at 31 March 2016.'

"We are increasingly confident that Atlas has a bright future marked by strong cash flows and reducing debt levels," Mr Harris said.

Quarterly - Key Metrics

September16 Quarter

June 16 Quarter

Variance Quarter

Ore tonnes shipped (WMT)

4.1M

3.7M

8%

C1 cash costs (A$/WMT FOB)

$34

$33

(3%)

Full cash cost* (A$/WMT CFR China)

$50

$49

(2%)

Depreciation & Amortisation (A$/WMT)

$5

$4

(20%)

Net Atlas CFR Sale Price (A$/WMT)

$56

$57

(2%)

Development Capital (A$M)

$1.3

-

-

* Please refer to Glossary in this announcement

Note: All costs in this table are unaudited and are quoted in Australian dollars unless otherwise stated.

Operations

Table 1 - Production

September 16 Quarter (WMT)

June 16 Quarter (WMT)

Variance Quarter (WMT)

Variance Quarter (%)

Ore Mined*

3,792,573

3,636,530

156,043

4%

Ore Processed

3,934,872

3,898,937

35,935

1%

Haulage to Port

3,994,798

3,817,371

177,427

5%

*- Includes intra-mine tonnes

Table 2 - Inventory and Shipping

September 16 Quarter (WMT)

June 16 Quarter (WMT)

Variance Quarter (WMT)

Variance Quarter (%)

Final Product Stock at site

299,330

327,862

(28,532)

(9%)

Final Product Stocks - Port

91,727

148,678

(56,951)

(38%)

Shipping

Ore Shipped (Wet)

4,051,749

3,741,281

310,468

8%

Ore Shipped (Dry)

3,822,956

3,510,354

312,602

9%

Note 1: Please see Appendix 1 for further details of production outputs by mine and inventory.

Atlas shipped 4.1M WMT for the September 2016 Quarter; 2.3M WMT of Standard Fines, 0.4M WMT of Value Fines and 1.4M WMT of Atlas Lump.

Shipped tonnes were higher than the June 2016 Quarter due to a significantly higher contribution from Mt Webber (371kt), which lead to a slight increase in C1 costs due to the additional distance of that mine from the port. Freight costs have increased on the back of higher fuel prices and strong demand for seaborne coal, which combined with the increase in C1 costs resulted in a minor increase in Full Cash Costs.

Marketing

The benchmark Platts 62% Fe IODEX averaged US$58.55/DMT in the September 2016 Quarter compared with US$55.71/DMT in the June 2016 Quarter. Atlas achieved an average price of US$45/DMT (June 16 Quarter US$45/DMT), which was inclusive of 3.5 cargos of lower grade Value Fines product and increased discounts for products of Atlas' grade over the September 2016 Quarter.

Increased discounts resulted from a significant increase in coal price over recent months, with steel mills preferring higher grade ores, which require less coal in the steelmaking process, when coal prices are elevated.

The average AUD:USD exchange rate strengthened over the Quarter (September 2016: 0.758, June 2016: 0.746) which negatively impacted on the received AUD sale prices in the September 2016 Quarter.

At the date of this report, Atlas had approximately 1.7M WMT of December 2016 Quarter sales subject to some form of forward price fixing via the use of forward sales, swaps and collars. This includes some 0.2M WMT of fixed price sales or swaps at an approximate average 62% Fe DMT equivalent price of US$50/t and collars comprising 1.5Mt of puts with an average 62% Fe DMT equivalent of US$49/t and 1.1Mt of calls with an average 62% Fe DMT equivalent price of US$57/t. 0.9Mt of puts have price protection limited to US$40/t at 62% Fe DMT equivalent levels.

Financial Position Summary

Cash as at 30 September 2016 was A$95M (30 June 2016: A$81M) with the increase attributable to positive cashflow generated from the Company's operations, partially offset by repayment of a further A$3M in State Government royalty relief and A$4M of interest and principle repayments.

Corporate

On 5 August 2016, the Company advised the market that Tony Walsh had been appointed as a director of the Company. Mr David Flanagan, who had resigned as Managing Director on 28 June 2016, left the Company on 5 August 2016.

Atlas Non-Executive Director, Mr Daniel C Harris, continues as Managing Director (MD) and Chief Executive Officer (CEO) until a permanent replacement MD and CEO is appointed and commences employment with the Company.

On 22 September 2016 the Company released its Mineral Resources and Ore Reserves at 30 June 2016 to ASX.

Investor Enquiries: Atlas Iron Limited Tony Walsh,

Company Secretary +61 8 6228 8000

Media Enquiries:

Read Corporate +61 8 9388 1474

Paul Armstrong +61 421 619 084

Notes:

  1. All costs in this announcement are quoted in Australian dollars unless otherwise stated.

  2. All costs in this announcement are unaudited

  3. Net Debt in this announcement is Debt less cash & cash equivalents, listed shares and derivatives

Important Notice

This ASX Announcement does not constitute an offer to acquire or sell or a solicitation of an offer to sell or purchase any securities in any jurisdiction. In particular, this ASX Announcement does not constitute an offer, solicitation or sale to any U.S. person or in the United States or any state or jurisdiction in which such an offer, tender offer, solicitation or sale would be unlawful. The securities referred to herein have not been and will not be registered under the United States Securities Act of 1933, as amended (the "Securities Act"), and neither such securities nor any interest or participation therein may not be offered, or sold, pledged or otherwise transferred, directly or indirectly, in the United States or to any U.S. person absent registration or an available exemption from, or a transaction not subject to, registration under the United States Securities Act of 1933.

Glossary

Full cash costs includes C1 Cash Costs, royalties, freight, corporate and administration, exploration and evaluation, interest expense, contractor profit share and sustaining capital expenditure, but excludes depreciation and amortisation, one-off restructuring costs, suspension and ramp up costs of operating mine sites, and other non-cash expenses. C1 Cash Costs are inclusive of contractors and Atlas' costs including Contractor Rate Uplift. Full cash costs are derived from unaudited management accounts.

WMT means Wet Metric Tonnes. All tonnes referred to in this document are Wet Metric Tonnes unless otherwise stated.

Read the rest of the article at www.publicnow.com
Data and Statistics for these countries : China | Georgia | All
Gold and Silver Prices for these countries : China | Georgia | All

Atlas Iron Limited

PRODUCER
CODE : AGO.AX
ISIN : AU000000AGO1
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Atlas Iron is a iron exploration company based in .

Atlas Iron holds various exploration projects in Australia.

Its main asset in production is PARDOO in Australia, its main assets in development are WODGINA and RIDLEY MAGNETITE PROJECT in Australia and its main exploration properties are ABYDOS, MT WEBBER and MID WEST IRON in Australia.

Atlas Iron is listed in Australia and in Germany. Its market capitalisation is AU$ 416.8 millions as of today (US$ 302.7 millions, € 265.6 millions).

Its stock quote reached its highest recent level on July 29, 2011 at AU$ 3.96, and its lowest recent point on June 24, 2016 at AU$ 0.01.

Atlas Iron has 9 261 129 728 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Atlas Iron Limited
10/16/2018Australia's Atlas Iron names ex-Hancock executive CEO in boa...
6/8/2018Australia's Fortescue takes stake in Atlas Iron, may block b...
2/28/2018Atlas Iron reveals strategy to weather storm of discounts
12/24/2014Atlas Iron to take a $900 million write-down
Nominations of Atlas Iron Limited
5/25/2011Retirement of Chairman and Appointment of Interim Chairman
12/2/2008Appoints Geoff Clifford as Chairman
Financials of Atlas Iron Limited
10/19/2016September 2016 Quarterly Activities Report
Project news of Atlas Iron Limited
9/22/2016Mineral Resources and Ore Reserves at 30 June 2016
5/9/2011(Wodgina)Increases production capacity at Wodgina by 75% to 7Mtpa
6/21/2010(Wodgina)Mining Commences at Wodgina
6/16/2010(Wodgina)New DSO Discovery at Wodgina
4/7/2010(Wodgina)Key DSO Growth Projects on Track
10/13/2009(Pardoo)Progress Update - North Pilbara DSO Projects
8/4/2009(Mt Webber)Maiden Resource for Mt Webber DSO Project
7/31/2009(Wodgina)Wodgina DSO Project Feasibility Study Compete
6/19/2009(Mt Webber)Continued North Pilbara Exploration Success
5/26/2009(Wodgina)Wodgina DSO Project - Interim Feasibility Study Outcomes
5/21/2009(Mt Webber)New DSO Discovery at Mt Webber
5/19/2009(Wodgina)500% Increase in Wodgina DSO Resource
3/9/2009Drilling Results Add to Wodgina Infrastructure Potential
1/29/2009(Pardoo)Atlas Increases Pilbara DSO Resources By 45 per cent to 56.7...
1/7/2009(Pardoo)Intersects High Grade at Pardoo DSO Project
12/31/2008(Abydos)New Hematite Discoveries at the Abydos DSO Project
12/11/2008(Abydos)New DSO Discovery at Wodgina
12/8/2008(Abydos)Signs Native Title Mining Agreement for Abydos
11/26/2008(Pardoo)Ridley Magnetite Resource Upgrade to 2 Billion Tonnes
11/24/2008(Pardoo)Pilbara DSO Projects - Operations Update
11/10/2008(Pardoo)Delivers First Iron Ore to Port
10/2/2008(Pardoo)Ridley Magnetite Resource Upgrade
8/6/2008(Abydos)Abydos Magnetite Joint Venture with FMG
7/30/2008(Abydos)Abydos Direct Shipping Ore Project - Pre Feasibility Study U...
6/17/2008Ridley Magnetite Pre Feasibility Study Technical Update
4/7/2008(Abydos)Abydos Drilling Continues To Impress
Corporate news of Atlas Iron Limited
11/16/2016Change in substantial holding for Centaurus
11/16/2016Change in substantial holding (Marathon)
7/27/2016June 2016 Quarterly Report
6/28/2016Atlas welcomes WA Government announcement
6/28/2016David Flanagan resigns as Managing Director
6/23/2016Change in substantial holding for CTM
6/6/2016Appointment of Chairman
5/23/2016May 2016 Investor Presentation
5/10/2016Ceasing to be a substantial holder
5/6/2016Implementation of Creditors' Scheme
4/29/2016Creditors' Scheme
4/27/2016Chairman's Address to Shareholders at General Meeting
4/27/2016Presentation at General Meeting
4/21/2016Atlas March 2016 Quarterly Activities Report
4/18/2016Letter to Shareholders
4/4/2016Update on Debt Restructure
3/24/2016Notice of General Meeting/Proxy Form
12/23/2015Atlas signs debt restructure agreement
12/22/2015Trading Halt
12/15/2015Change in substantial holding for CTM
12/2/2015Change in substantial holding for CTM
10/28/2015Managing Director's AGM Presentation
10/28/2015Chairman's Address to Shareholders
10/22/2015Atlas Iron September 2015 Quarterly Report
10/22/2015Pre-feasibility Study Underway for Corunna Downs
10/6/2015Company Secretary Appointment/Resignation
9/29/2015Notice of Annual General Meeting/Proxy Form
9/29/2015Annual Report
9/24/2015New Iron Ore Sales Agreement and Marketing Update
9/9/2015Atlas Production Figures
9/1/2015Executive Changes as Part of Cost Reduction Programme
8/28/2015Production Update
8/17/201513 August 2015 Sale of Pilbara Iron Tenements
8/14/20152015 Annual Results
8/14/20152015 Annual Financial Report
8/14/2015Appendix 4E - 30 June 2015
8/13/2015Full Year Results Presentation FY2015
8/13/20152015 Annual Financial Report and Appendix 4E
8/13/2015SFX: Sale of Pilbara Iron Tenements
7/31/2015Quarterly Report
7/30/2015Ceasing to be a substantial holder
7/29/2015Becoming a substantial holder
7/29/2015MCS: Business Update and FY15 Result
7/27/2015Shares in Australia's Atlas Iron sink 70%
7/24/2015Reinstatement to Official Quotation
7/24/2015Request to Lift Suspension
7/22/2015Australia shares fall on profit taking, NZ stocks up
7/20/2015Atlas set for stronger future after raising $86m
7/15/2015Extension of the Closing Date - SPO and General Placement
7/8/2015Update on Forward Price Strategies
7/6/2015Supplementary Prospectus
7/2/2015Letter to Shareholders
6/17/2015Prospectus
6/11/2015Capital Raising to Strengthen Balance Sheet
6/11/2015Change of Date for General Meeting
6/11/2015David Flanagan Appointed as Managing Director
4/21/2015Voluntary Suspension Extension Request
4/14/2015Update Regarding Operational and Financial Review
4/13/2015Atlas Iron Suspends Production
4/12/2015Abydos Contract Update (1 pages)
4/10/2015Atlas Suspends Production in Response to Low Iron
4/6/2015Voluntary Suspension
3/9/2015Resignation of Director
3/6/2015S&P DJ Indices Announces March Quarterly Review
2/13/2015AGO: Investment Update - Mt Webber Project and Shaw River
2/13/2015Investment Update - Mt Webber Project and Shaw River
4/21/2011Quarterly Report for the Period Ending 31 March 2011
4/7/2011Media Alert - Atlas Iron MD to shed his locks this Friday......
4/4/2011Atlas posts shipping record in March
2/24/2011Reports $30M maiden half year profit
2/14/2011Declares Giralia takeover offer unconditional and accelerate...
7/6/2010More DSO Success at Hercules
5/28/2010Broker Report from Credit Suisse
5/5/2010to Ship Additional Tonnes Through Port Hedland Port Ahead of...
4/29/2010To Raise $63.5 Million To Capitalise On Strong Iron Ore Pric...
2/22/2010Atlas And Aurox Enter Into Utah Point Port Cooperation Agree...
11/6/2009Dr David Smith Joins The Atlas Board
10/20/2009Merger Moves Ahead
9/8/2009and Warwick Resources Agree to Merge
7/31/2009June 2009 Quarterly Report
6/15/2009to raise $116.7 Million to fund development of Pilbara Iron ...
2/17/2009and Talison Complete Infrastructure Sharing Agreement
1/19/2009 Ships Second Commercial Iron Ore to China
1/15/2009Maiden Inferred Resource At Wodgina
12/19/2008Completes Sale of Second Shipment of Connie Deposit Ore
12/15/2008Additional Excellent Results Enhance Wodgina DSO Project
12/5/2008Ships First Commercial Iron Ore to China
11/21/2008Managing Director's Address
9/25/2008Pardoo DSO Project - Mining Team Mobilised to Site
8/6/2008Signs Port Access Agreement with FMG
8/4/2008North West Iron Ore Alliance Maintains Pressure for Fair and...
8/1/2008June 2008 Quarterly Activities Report
7/28/20081.3 Billion Tonne Ridley Magnetite Resource
7/25/2008 DSO Resource and Reserve Update Summary
7/22/2008Pardoo Project Development Update
7/17/2008New Hematite Mineralisation Discovered at Pardoo
6/23/2008Welcomes NCC Recommendation to Declare Goldsworthy Railway
6/16/2008EPA Recommends Pardoo DSO Project for Ministerial Approval
5/19/2008Pardoo Mining Contract Awarded to CDE Capital
5/1/2008Supports Goldsworthy Railway Declaration
4/23/2008to Raise $100 Million to Accelerate Growth of Pilbara Iron O...
3/25/2008 Targets 120-180Mt of Pilbara Iron Ore
2/25/2008Open BriefingR. Production and Export of DSO
1/31/2008December 2007 Quarterly Activities Report
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (AGO.AX)Berlin (ATU.BE)
0.045+0.00%0.0000
AUSTRALIA
AU$ 0.045
11/21 10:00 -
0%
Prev close Open
0.045 0.045
Low High
0.045 0.045
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.045 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : 19
Produces Iron
Develops Iron
Explores for Iron
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :