BOISE, IDAHO--(Marketwired - Jan 26, 2015) - U.S. Geothermal Inc. (GTH.TO)(NYSE MKT:HTM), a leading renewable energy company focused on the development, production and sale of electricity from geothermal energy, provides this update on the results of its three operating projects for the fourth quarter of 2014, and the status of development activities.

OPERATIONS

Neal Hot Springs, Oregon

All three units have been, and are operating smoothly, with fourth quarter availability of 98.3%. Total generation for the fourth quarter was 54,472 megawatt-hours, which is a result of excellent availability and low seasonal temperatures. This compares to 32,246 megawatt-hours for the third quarter, 40,629 for the second quarter, and 56,047 for the first quarter, for a total generation at Neal Hot Springs for 2014 of 183,394 megawatt-hours. This compares to 155,428 megawatt-hours of generation for 2013, reflecting an 18% increase over the prior year.

Under the terms of our Power Purchase Agreement ("PPA"), November and December generation for 2014 was paid at a seasonally adjusted price of $123.34 per megawatt-hour, which is 120% of the 2014 average contract price, while October was paid at the average 2014 contract price of $102.78. For 2015, the average contract price will increase from $102.78 to $106.79 per megawatt-hour.

San Emidio, Nevada

The plant performance was exceptional, with fourth quarter availability of 99.2%. Total generation for the fourth quarter was 21,745 megawatt hours. This compares to 18,240 megawatt-hours for the third quarter, 15,686 for the second quarter, and 21,223 for the first quarter, for a total generation for 2014 of 76,894 megawatt-hours. This compares to 76,697 megawatt-hours of generation for 2013 reflecting continued, steady state operation of the facility.

Under the terms of our PPA, generation during the quarter was paid at the price of $91.17 per megawatt-hour. There is no seasonal adjustment under this power purchase agreement. For 2015, the contract price will increase from $91.17 to $92.08 per megawatt-hour.

Raft River, Idaho

The plant performance was exceptional, with fourth quarter availability of 97.3%. Total generation for the fourth quarter was 20,614 megawatt-hours, as a result of excellent availability and low seasonal temperatures. This compares to 18,501 megawatt-hours for the third quarter, 18,069 for the second quarter, and 21,614 for the first quarter, for a total generation for 2014 of 78,798 megawatt-hours. This compares to 77,560 megawatt-hours for the same period of 2013, reflecting continued steady state operation of the facility.

Under the terms of our PPA, November and December generation for 2014 was paid at a seasonally adjusted price of $72.86 per megawatt-hour, which is 120% of the 2014 average contract price, while October was paid at the 2014 average contract price of $60.72. For 2015, the average contract price will increase from $60.72 to $62.00 per megawatt-hour. In addition to the price paid for energy, Raft River currently receives $4.75 per megawatt-hour under a separate contract for the sale of Renewable Energy Credits.

"Our operations team has done an outstanding job during the year maximizing production from all of our facilities. Our units are all performing with exceptionally high availabilities, and with output that is at or above what we had expected. The total generation from all of our units for the full year of 2014 was 339,086 megawatt-hours, compared to 309,685 megawatt-hours for the full year of 2013, reflecting a fleet wide increase of 9.5% over the prior year period," said Dennis Gilles, Chief Executive Officer of U.S. Geothermal. "As a result of this strong performance, we anticipate our projected year-end results should be at the higher end of the guidance range previously provided, and we look forward to continued excellent results for the coming year."

DEVELOPMENT

WGP Geysers, California

A new transmission interconnection agreement has been applied for to the California Independent System Operator. Engineering optimization of the power plant design continues. The current well field reservoir model is being updated to reflect a new hybrid plant design that includes both water and air cooling, which will dramatically increase the volume of water available for injection back into the reservoir. Traditional water cooled steam plants re-inject approximately 20% of the water that is removed during power generation, while a hybrid design may re-inject up to 65% of the water. This higher injection rate will provide longer term, stable steam production, and will result in increased power generation over the life of the project.

A new conditional use permit application is being prepared for submittal to local regulatory agencies to replace the current conditional use permit that expires in July. A flow testing program for the production wells is being designed and will be scheduled during the first half of the year. During the quarter we responded to RFP's from WAPA-Navy and Stanford University for renewable energy PPA's, but unfortunately neither of the bids was selected.

San Emidio Phase II, Nevada

To further define the resource and confirm that it can support the Phase II plant, two additional wells (OW-14 and OW-15) were completed on the BLM administered land. While the wells extended the high temperature outline of the South Zone, neither well encountered the commercial permeability seen in Well 61-21 (OW-10). A cross tie pipeline was installed between the San Emidio Phase I and Phase II projects. Well 61-21 was connected and is producing 620 gpm of 297°F fluid to the San Emidio Phase 1 power plant as part of a long term flow test of the South Zone portion of the reservoir. San Emidio Phase I plant generation has increased approximately a half of MW.

Permitting for an expanded temperature gradient drilling program is underway for an area south west of the current resource. Results from the recent OW drilling program combined with 1970s era, shallow temperature gradient data, indicate a high temperature trend into this south-west zone. Geophysical surveys have also identified structural trends in this area. Several 1,000 foot deep temperature gradient wells are being permitted to follow up on this portion of the resource.

NV Energy issued a Request for Proposal ("RFP") from NV Energy for 100 megawatts of renewable energy on October 1st. We submitted a bid for an air cooled power plant to be developed on the Phase II project site. In early December, NV Energy submitted a request to the Nevada Public Utilities Commission ("NPUC") that the 2014 solicitation be combined with the 2015 solicitation for a total of 200 megawatts to be procured in 2014. The request also allows re-submittal of any projects that had been previously submitted for the original 2014 RFP. We plan to submit an alternative option into the new solicitation that uses a water cooled plant as the basis if the NPUC approves the request.

El Ceibillo, Guatemala

During the year we completed the drilling associated with our resource delineation program, and obtained surface leases for an additional 97 acres. A new drill pad, pond and cellar for EC-2, our planned new well, was completed. EC-2 is located on the new surface leasehold. Drilling of EC-2 is expected to begin as soon as the approval to extend the development schedule contained in the concession agreement has been obtained from the Guatemalan Ministry of Energy.

Our attempts to obtain approval of our modified development schedule from the Guatemala Ministry of Energy ("MEM") continue. Our request has been approved by the MEM legal department and is now being evaluated by the technical department. As a result of the delays in approval of the modified schedule, we requested an extension of our Memorandum of Understanding for a Power Purchase Agreement with the regional electricity broker. Our initial request was declined, but discussions are continuing regarding the terms of the memorandum and how it may be re-instated or renegotiated.

Crescent Valley, Nevada

In light of recently passed federal legislation that extended the qualification for the 30% Investment Tax Credit to projects that began construction prior to December 31, 2014, drilling of the first production well CVP-001 (67-3) was initiated in December of 2014 following completion of gravity surveys, and analysis of prior temperature gradient drilling data. The first string of production casing was set and cemented before year end, and drilling operations on Well 67-3 are continuing.

Neal Hot Springs, Oregon

A permit has been applied for to drill a water well at the Neal Hot Springs project. The water well will be tested for sustainable delivery, and if commercially successful, it would be used to support the installation of a water cooling system for the facility. The ability to use water cooling during the 5-6 months of summer and fall would increase power generation, when current air cooling results in a dramatic reduction in plant output.

Gerlach, Nevada

Drilling of well 18-10A was completed in late November. The well was drilled to a total depth of 2,889 feet, and encountered a maximum temperature of 275F.

MERGERS AND ACQUISITIONS

Our focus on M&A activities remains very active. As noted previously, the merger of Earth Power Resources ("EPR") into U.S. Geothermal was completed on December 12, 2014. The EPR acquisition adds high quality development projects to the company's pipeline, including the Crescent Valley prospect which is discussed above.

We are continuing due diligence on a number of other excellent opportunities that encompass operating projects, advanced development projects and green field opportunities.

REGULATORY UPDATE

Recent developments in the market are encouraging for the growth of renewable energy, and more specifically to geothermal energy in our opinion.

In Washington, D.C., legislation was passed by the house and senate that extended the tax credits available to new geothermal plants. Under the approved legislation, projects that began construction by December 31, 2014 would be eligible for a 30% Investment Tax Credit ("ITC"), or alternatively a 10 year Production Tax Credit ("PTC").

In California, the signing into law of AB-2363 earlier this year by the California Governor, will require the California Public Utilities Commission to establish the appropriate adders (integration cost) for each technology that must be used when evaluating bids for long term wholesale power contracts. We believe this change will add appropriate costs to wind and solar power generation due to their intermittent deliveries of power, which then should allow base load renewables like Geothermal and Biomass to compete for PPAs with Investor Owned Utilities based on a more accurate comparison of the full cost for power. That has not been the case in the past.

In the State of Nevada, in 2013 the legislature mandated that the utilities in the state must purchase 300 megawatts of renewable energy from independent power producers to replace retiring coal generation. NV Energy has issued their first of 3 Requests for Proposal for 100 MW of renewable energy. This creates a solid market of 100 MW per year for each of the next three years, which provides our company with a local option for selling power from both our existing and new projects.

"We are very pleased with our accomplishments to date, and are optimistic with the growth opportunities that lie ahead for our company and its shareholders," said Dennis Gilles, Chief Executive Officer of U.S. Geothermal Inc. "We are currently well capitalized, and with the addition of our positive cash flows from operations, are well positioned to fund internal development, and growth through strategic M&A activities, as was demonstrated this year with our Geysers and Earth Power acquisitions which we acquired without going to the market for capital."

About U.S. Geothermal Inc.:

U.S. Geothermal Inc. is a leading renewable energy company focused on the development, production and sale of electricity from geothermal energy and is operating geothermal power projects Neal Hot Springs, Oregon, San Emidio, Nevada and Raft River, Idaho. The company is currently developing a project at the Geysers, California, a second phase project at San Emidio, Nevada, a project at Crescent Valley, Nevada, and a project at El Ceibillo, in Guatemala.

The information provided in this news release may contain forward-looking statements within the definition of the Safe Harbor provisions of the US Private Securities Litigation Reform Act of 1995. Readers are cautioned to review the risk factors identified by the company in its filings with US and Canadian securities agencies. All statements, other than statements of historical fact, included herein, without limitation, statements relating to the future operating or financial performance of U.S. Geothermal, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible", and similar expressions, or statements that events, conditions, or results "will", "may", "could", or "should" occur or be achieved. These forward-looking statements may include statements regarding perceived merit of properties; interpretation of the results of well tests; project development; resource megawatt capacity; capital expenditures; timelines; strategic plans; or other statements that are not statements of fact. Forward-looking statements involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from U.S. Geothermal's expectations include the uncertainties involving the availability of financing in the debt and capital markets; uncertainties involved in the interpretation of results of well tests; the need for cooperation of government agencies in the development and operation of properties; the need to obtain permits and governmental approvals; risks of construction; unexpected cost increases, which could include significant increases in estimated capital and operating costs; and other risks and uncertainties disclosed in U.S. Geothermal's Annual Report on Form 10-K for the year ended December 31, 2013 filed with the United States Securities and Exchange Commission and Canadian securities regulatory authorities and in other U.S. Geothermal reports and documents filed with applicable securities regulatory authorities from time to time. Forward-looking statements are based on management's expectations, beliefs and opinions on the date the statements are made. U.S. Geothermal Inc. assumes no obligation to update forward-looking statements if management's expectations, beliefs, or opinions, or other factors, should change.

The NYSE MKT and the TSX do not accept responsibility for the adequacy of this release.

Read the rest of the article at finance.yahoo.com
Data and Statistics for these countries : Guatemala | All
Gold and Silver Prices for these countries : Guatemala | All

US Geothermal Inc.

CODE : GTH.TO
ISIN : US90338S1024
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

US Geothermal. is a exploration company based in United states of america.

US Geothermal. holds various exploration projects in USA.

Its main asset in development is NEAL HOT SPRINGS in USA and its main exploration property is RAFT RIVER in USA.

US Geothermal. is listed in Canada. Its market capitalisation is CA$ 97.0 millions as of today (€ 89.4 millions).

Its stock quote reached its highest recent level on November 02, 2007 at CA$ 4.17, and its lowest recent point on June 15, 2012 at CA$ 0.28.

US Geothermal. has 111 529 742 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of US Geothermal Inc.
9/30/2013U.S. Geothermal Closes Long Term Permanent Financing for San...
3/7/2011U.S. Geothermal Announces Closing of $5 Million Financing Wi...
2/24/2011U.S. Geothermal Secures $96.8 Million Project Loan for Hot S...
3/10/2010Announces $8,6 Million private placement financing
Option Grants of US Geothermal Inc.
8/24/2012U.S. Geothermal Announces Annual Stock Option Grant
Financials of US Geothermal Inc.
10/23/2013U.S. Geothermal Inc. to Discuss Third Quarter 2013 Earnings ...
5/14/2013U.S. Geothermal Inc. Reports First Quarter 2013 Results, Pro...
Project news of US Geothermal Inc.
4/3/2013(Neal Hot Springs)U.S. Geothermal Receives $33 Million Cash Grant at Neal Hot ...
6/21/2012U.S. Geothermal Inc. Announces San Emidio Achieves Commercia...
1/25/2012(Raft River)U.S. Geothermal Announces Completion Of Well RRG-2 Repair at...
8/31/2011(Neal Hot Springs)U.S. Geothermal Receives Funding From $96.8 Million Loan for...
7/6/2011(Raft River)U.S. Geothermal Announces Completion of Well RRG-7 Repair at...
4/11/2011(Neal Hot Springs)U.S. Geothermal Receives Key Reservoir Certificate for Neal ...
2/24/2011(Neal Hot Springs)U.S. Geothermal Secures $96.8 Million Project Loan for Neal ...
Corporate news of US Geothermal Inc.
5/10/2016Newsletter
12/15/2015The Zacks Analyst Blog Highlights: JA Solar Holdings, U.S. G...
12/15/2015U.S. Geothermal Inc. Acquires Majority of Goldman Sachs Inte...
12/14/20155 Stocks to Buy on Historic Climate Change Deal
11/23/2015U.S. Geothermal Inc. to Present at the LD Micro Main Event
11/2/2015U.S. Geothermal Inc. to Present at Upcoming Conferences on N...
10/28/2015U.S. Geothermal Updates El Ceibillo Project
10/22/2015U.S. Geothermal Inc. to Discuss 3rd Quarter 2015 Earnings Re...
9/21/2015U.S. Geothermal Confirms Reservoir at WPG Geysers Project
9/17/2015U.S. Geothermal (HTM) in Focus: Stock Moves 7.2% Higher
8/11/2015U.S. Geothermal posts 2Q loss
8/11/2015U.S. Geothermal Inc. Reports First Six Months 2015 Results, ...
8/11/2015U.S. Geothermal Inc. to Host Second Quarter 2015 Earnings Co...
8/10/2015U.S. Geothermal Inc. Announces Stock Repurchase Program and ...
7/29/2015U.S. Geothermal Inc. to Discuss 2nd Quarter 2015 Earnings Re...
7/23/2015U.S. Geothermal Inc.: El Ceibillo Project Receives Approval ...
7/14/2015U.S. Geothermal Inc. to Present at The Money Show, The Tripl...
4/6/2015U.S. Geothermal Inc. Appoints New Audit Firm
3/16/2015U.S. Geothermal Inc. Reports 2014 Year End Results, Reaffirm...
3/4/2015U.S. Geothermal Inc. to Discuss 2014 Year End Earnings Resul...
1/26/2015U.S. Geothermal Provides Company Update
12/16/2014U.S. Geothermal Completes Acquisition of Earth Power Resourc...
11/13/2014U.S. Geothermal Inc Reports Third Quarter 2014 Results and U...
11/13/2014U.S. Geothermal Inc. to Host Third Quarter 2014 Earnings Con...
10/29/2014U.S. Geothermal Inc. to Discuss 3rd Quarter 2014 Earnings Re...
10/23/2014U.S. Geothermal Provides Project Update
10/16/2014U.S. Geothermal Announces Acquisition of Earth Power Resourc...
8/14/2014U.S. Geothermal Inc. Reports First Six Months 2014 Results, ...
8/6/2014CORRECTION FROM SOURCE: U.S. Geothermal Inc. to Discuss Seco...
8/6/2014U.S. Geothermal Inc. to Discuss First Quarter 2014 Earnings ...
7/14/2014U.S. Geothermal Provides Mid-Year Update
6/25/2014U.S. Geothermal Inc. CEO, Dennis Gilles Interviewed by NBT E...
5/21/2014U.S. Geothermal Inc. to Present at the Marcum MicroCap Confe...
5/14/2014U.S. Geothermal Inc. Reports First Quarter 2014 Results, Con...
5/14/2014U.S. Geothermal Inc. to Host First Quarter 2014 Results Webc...
5/6/2014U.S. Geothermal Inc. Announces Annual General Meeting
4/29/2014U.S. Geothermal Inc. to Discuss 1st Quarter 2014 Earnings Re...
4/22/2014U.S. Geothermal Completes Acquisition of Ram Power's Geysers...
9/18/2013U.S. Geothermal Inc.: El Ceibillo Project Receives License t...
9/6/2013U.S. Geothermal Inc. and Enbridge Inc. Host FERC Chairman Jo...
9/4/2013U.S. Geothermal Inc.: Drilling Commences for San Emidio Phas...
8/13/2013U.S. Geothermal Inc. Announces Distribution of the $33 Milli...
8/1/2013(Neal Hot Springs)U.S. Geothermal Inc. Announces Final Completion of the Innov...
7/2/2013(Neal Hot Springs)U.S. Geothermal Inc. Announces Substantial Completion at Nea...
6/25/2013U.S. Geothermal Inc. Updates Drilling at El Ceibillo Project...
5/7/2013Earnings Call Tuesday May 14th, 2013 to Discuss U.S. Geother...
4/30/2013U.S. Geothermal Inc. Updates El Ceibillo Project; Drilling C...
4/22/2013U.S. Geothermal CEO Daniel Kunz to Retire; Dennis Gilles Nam...
3/20/2013Conference Call Thursday March 28th, 2013 to Discuss U.S. Ge...
1/24/2013U.S. Geothermal Inc. Ranked in ENR's Top 425 Owners
11/14/2012U.S. Geothermal's San Emidio Project Increases Plant Output ...
11/6/2012Conference Call Thursday November 15th, 2012 to Discuss U.S....
10/29/2012U.S. Geothermal Inc. Signs Power Purchase Agreement MOU For ...
9/4/2012U.S. Geothermal Inc.: Annual Letter to Shareholders
8/13/2012Conference Call Thursday August 16th, 2012 to Discuss U.S. G...
8/8/2012U.S. Geothermal Provides Development Update
7/9/2012Conference Call Monday, July 16th, 2012 to Discuss U.S. Geot...
6/28/2012(Neal Hot Springs)U.S. Geothermal Announces Mechanical Completion of Second Po...
5/29/2012(Neal Hot Springs)U.S. Geothermal Announces Mechanical Completion of First Pow...
5/22/2012U.S. Geothermal Inc. Announces Share Purchase Agreement With...
5/10/2012U.S. Geothermal Announces New San Emidio Power Plant Beginni...
4/20/2012U.S. Geothermal Provides Corporate Update
4/11/2012U.S. Geothermal Signs Commitment Letter for $15 Million Loan...
4/4/2012U.S. Geothermal Inc. Announces San Emidio Project Update: Un...
2/8/2012CORRECTION FROM SOURCE: Conference Call Friday, February 10,...
2/2/2012U.S. Geothermal Updates Status of New San Emidio Power Plant
1/3/2012U.S. Geothermal Announces Nevada PUC Approval of 19.9 Megawa...
12/20/2011U.S. Geothermal Announces Mechanical Completion of New San E...
9/12/2011U.S. Geothermal Announces New Board of Director and Manageme...
8/19/2011Senator Ron Wyden and Industry Experts Provide Briefing on U...
8/8/2011Conference Call Wednesday, August 10, 2011, to Discuss U. S....
6/1/2011U.S. Geothermal Signs 19.9 MW, 25 Year PPA With NV Energy fo...
5/17/2011(Raft River)U.S. Geothermal Commences Well Repairs at Raft River
12/14/2009(Neal Hot Springs)Signs neal hot springs PPA with Idaho Power
11/12/2009 Conference Call to Discuss 2nd Quarter Results
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (GTH.TO)
0.870+0.00%
TORONTO
CA$ 0.870
01/01 15:41 -
0%
Prev close Open
0.870 0.850
Low High
0.850 0.870
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.870 -%
Volume 1 month var.
9,000 -%
24hGold TrendPower© : 2
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :