Transeuro Energy Corp.: Ukraine Preparing for Production Test
Published : March 07, 2011

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

VANCOUVER, BRITISH COLUMBIA--(Marketwire - March 7, 2011) - Transeuro Energy Corp. ("Transeuro" or the "Company")(News - Market indicators)(OSLO:TSU) is pleased to issue the weekly update on its Ukraine operation as follows:

Logging operations have been completed successfully and the 7 inch casing has been run to Total Depth ("TD"), cemented and logged. At report time today drill pipe is being run into the hole to clean out cement and pressure test in preparation for production testing operations.

The open hole logs have identified the following:

  • Up to 117 metres of 'reservoir section' in the main targets: the Cretaceous Intervals C12; C13; C14; C15 and C16 from 3,110 to 3,510 metres (wire line depth). The reservoir sections are low porosity, fractured carbonate rocks with average porosity calculated in the range of 4 - 6.5%.
  • Gas saturations are calculated in 75 metres of 'reservoir section' with the remaining 42 metres showing ambiguous results, possibly due to the high mud weights of 1.69 sg (specific gravity) used at the end of drilling operations.
  • No obvious water intervals have been observed throughout the main targets from 3,110 to 3,510 metres.
  • In addition to the reservoir sections, there are numerous intervals where the rock is densely fractured, 'fracture zones' that correspond to gas shows while drilling.
  • These results are similar to the previous Karl 101 wellbore drilled in 2008 and are in line with expectations. The log results from the previous Karl-101 wellbore were incorporated into the third party reserves report, dated 31st December 2009.
  • The upper Turonian interval was affected by the sidetrack drilling operations and the high mud weights and no conclusive information was obtained from the open hole logs.

The proposed testing program is as follows:

  • The Company is planning 4 individual tests, with each test expected to take around 2 weeks, covering the following Cretaceous Intervals:

    • Test 1 - C16 and lower C15
    • Test 2 – C15
    • Test 3 – C13 and C14
    • Test 4 – C12

  • Each test will perforate around 40 to 50 metres covering both 'reservoir section' and 'fracture zones'.

  • The well will be flowed for around 12 hours to determine a 'pre-acidizing' rate, then stimulated with hydrochloric acid, then flowed for 48 hours for the main flow period, then shut in for 48 hours to obtain pressure information.

The testing program is subject to change depending on actual results. The Company will issue announcements as appropriate throughout the testing period.

The President & CEO, David Worrall commented; "Drilling operations have been completed successfully and the drilling risks are now behind us. The success of the cementing operation was particularly important so that we did not plug up the fractures in the rock that have flowed gas throughout the drilling operations. We are targeting these fractures during the testing and acidizing and we now look forward to the initial test results expected in around one week".

Transeuro is involved in the acquisition of petroleum and natural gas rights, the exploration for, and development and production of crude oil, condensate and natural gas. The Company's properties are located in Canada, Armenia, and Ukraine. In addition, the Company holds a back-in option to Eaglewood Energy Inc.'s exploration licenses in Papua New Guinea.

On behalf of the Board of Directors

Aage Thoen, Chairman 

The statements contained in this release that are not historical facts are forward-looking statements, which involve risks and uncertainties that could cause actual results to differ materially from the targeted results. The Company relies upon litigation protection for forward looking statements.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) nor the Oslo Bors accepts responsibility for the adequacy or accuracy of this release.

For more information, please contact

Transeuro Energy Corp.
Chris McGillivray
IR
+1 604 728 0040
or
Transeuro Energy Corp.
David Parry
SVP
+1 604 681 3939
or
Transeuro Energy Corp.
Karen Jenssen
IR
+47 91 729787
www.transeuroenergy.com
Data and Statistics for these countries : Armenia | Canada | Guinea | New Guinea | Papua New Guinea | Ukraine | All
Gold and Silver Prices for these countries : Armenia | Canada | Guinea | New Guinea | Papua New Guinea | Ukraine | All

Transeuro Energy Corp.

CODE : TSU.V
ISIN : 8936511093
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Transeuro Energy is a and oil exploration company based in Canada.

Transeuro Energy holds various exploration projects in Armenia, in Canada, in Papua New Guinea and in Ukraine.

Its main exploration properties are BEAVER-RIVER in Canada, CRIMEA in Ukraine and BLOCK 2 in Armenia.

Transeuro Energy is listed in Canada and in United States of America. Its market capitalisation is CA$ 6.9 millions as of today (US$ 6.2 millions, € 4.9 millions).

Its stock quote reached its highest recent level on August 05, 2005 at CA$ 3.20, and its lowest recent point on May 09, 2014 at CA$ 0.02.

Transeuro Energy has 345 230 016 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Transeuro Energy Corp.
5/10/2013(Povorotnoye)- POVOROTNOYE FINANCING UPDATE
4/2/2013(Povorotnoye)- POVOROTNOYE FINANCING
5/21/2012- FINANCING AGREEMENTS COMPLETED
4/30/2012- PROPOSED FINANCING
Nominations of Transeuro Energy Corp.
8/1/2008Appoints New Director
Financials of Transeuro Energy Corp.
3/1/2012- PRELIMINARY YEAR-END FINANCIAL RESULTS
Project news of Transeuro Energy Corp.
7/24/2012- KARL-101 TESTING UPDATE
6/19/2012TODAY - One2One Investor Forum | Orvana Minerals, Transeuro ...
6/11/2012Orvana Minerals, Transeuro Energy and PJX Resources Invest...
3/6/2012- FEBRUARY PRODUCTION
2/8/2012- JANUARY PRODUCTION
6/1/2011ACQUISITION OF BEAVER RIVER CLOSED
4/27/2011ACQUISITION OF BEAVER RIVER SIGNED
3/28/2011(Povorotnoye)UKRAINE FLOWING 1000 BOEPD FROM FIRST INTERVAL BEFORE ACIDIS...
2/28/2011(Karlavskoye)Logging Completed & Running Casing for Testing
2/16/2011- UBUNTU DISCOVERY UPDATE
2/14/2011UKRAINE DRILLING AHEAD IN C16
12/19/2008(Beaver-river)Beaver River Update
2/21/2008(Beaver-river)Beaver River Update
Corporate news of Transeuro Energy Corp.
4/30/2013- STRATEGY UPDATE
3/26/2013- SHARE PURCHASE AGREEMENT SIGNED AND IMPLEMENTATION SHARES ...
11/14/2012- UKRAINE UPDATE
10/15/2012- KARL-101 OPERATIONS RESUME
10/2/2012- KARL-101 OPERATIONS UPDATE
6/25/2012- KARL-101 FRACTURING COMPLETED
5/29/2012- UKRAINE OPERATIONS UPDATE
4/9/2012- UKRAINE RIG OPERATIONS COMPLETED
3/26/2012- UKRAINE OPERATIONS UPDATE
3/16/2012- UKRAINE OPERATIONS RESUME ON KARL-101
2/23/2012- UKRAINE RIG MOBILISATION & FRACTURING SCHEDULE
2/6/2012- BEAVER RIVER RESERVES REPORT
2/6/2012(Povorotnoye)- POVOROTNOYE FARM OUT COMPLETED
1/30/2012- EAGLEWOOD ENERGY ANNOUNCES PPL 259 FARM OUTS
12/6/2011- RIGHTS ISSUE COMPLETED & RESULT OF THE OFFERING
11/29/2011- LAST DAY OF TRADING IN SUBSCRIPTION RIGHTS COMMENCES
10/24/2011- RIGHTS ISSUE GUARANTEE INCREASE AND PRICE CHANGE
9/21/2011- RIGHTS ISSUE UPDATE
9/21/2011GENERAL OPERATIONS UPDATE
8/10/2011- UKRAINE FARM IN AGREEMENT
8/4/2011SHARE CONSOLIDATION
7/29/2011GENERAL UPDATE
6/16/2011UPDATE ON CONSOLIDATION AND RIGHTS ISSUE
6/8/2011(Karlavskoye)Investor Summary Sheet at Karlavskoye 101, Ukraine
6/7/2011CHANGE OF BOARD MEMBERS
5/16/2011- UKRAINE TEST '3&4' COMPLETED
5/16/2011(Karlavskoye)- KARLAVSKOYE DEVELOPMENT TO COMMENCE
5/5/2011UKRAINE TEST 3&4 COMMENCED
5/2/2011UKRAINE SECOND TEST COMPLETED
4/19/2011Ukraine Test 2 Commenced
3/29/2011UKRAINE FIRST TEST COMPLETED
3/14/2011Ukraine Testing Operations Continue
3/7/2011Ukraine Preparing for Production Test
2/22/2011Ukraine Logging Ongoing at TD
2/17/2011KARL-101 DRILLED SUCCESSFULLY AND LOGGING OPERATIONS UNDERWA...
1/24/2011UKRAINE DRILLING AHEAD WITH STRONG GAS SHOWS
2/26/2009Ukraine Arbitration Initiated
2/24/2009Warrant Re-pricing Completed
2/19/2009Debt Settlement
1/29/2009Debt Settlement
12/9/2008On Ukraine Joint Venture
12/8/2008Debt Settlement Negotiations
12/2/2008Change of President
12/1/2008Debenture Holders Grant Interest Payment Date Extension
11/27/2008Bond Holders Interest Payment Date Extension
11/25/2008Ukraine Operations Update
11/14/2008Suspends Interest Payments
9/11/2008Ukraine Well to be Sidetracked
8/27/2008 Commence Liard Shale Gas Test
8/12/2008Provides Ukraine Update
7/22/2008Trades Under One ISIN
5/26/2008Ukraine Drilling Update - Karlavskoye 101 well
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (TSU.V)OTHER OTC (TSUAF)
0.020+0.00%0.0000
TSX-V
CA$ 0.020
09/26 15:49 -
0%
Prev close Open
0.020 0.015
Low High
0.015 0.020
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.020 -%
Volume 1 month var.
84,030 -%
24hGold TrendPower© : -37
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :