UPDATE ON PROJECT FINANCING AND DFS FOR TULU KAPI

KEFI UPDATE 31 JAN 07

KEFI Minerals Plc

27-28 Eastcastle Street London W1W 8DH United Kingdom

Tel: +90 232 381 9431

Fax: +90 232 381 9071

Email: [email protected]

20 April 2015

KEFI Minerals plc

("KEFI" or the "Company")

UPDATE ON PROJECT FINANCING AND DFS FOR TULU KAPI

KEFI Minerals (AIM: KEFI), the gold exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, is pleased to announce the accomplishment of milestones towards the completion of an updated Definitive Feasibility Study ("2015
DFS") to the standards required by mining project financiers:

Independent review of Mine Plan and project costs

 Independent verification of the Mine Plan and associated costs by Snowden Mining Industry Consultants
Pty Limited ("Snowden") after taking into account:

o Updated Mineral Resources based on better delineation of individual ore lodes (see KEFI's

announcement of 4 February 2015)

o Detailed mine design which incorporated further geotechnical studies

o Semi-selective mining techniques and associated planning factors such as mine dilution and ore

losses

o An operating philosophy based on owner-mining and all-new plant

 The Mine Plan is now settled at:

o For initial 11 years, 12.0Mt ore mined at 1.2Mtpa at a head grade of 2.5 g/t and waste:ore ratio of c. 9.9:1, as compared with the most recently reported estimate of 13.0Mt ore mined at

1.2Mtpa at a head grade of 2.4 g/t and a waste:ore ratio of circa 10.1:1

o For an additional 2 years, to process low-grade stocks built up during the open-pit mining operation to increase total gold production

o Total ore mined of 15.4Mt at 1.2Mtpa at a head grade of 2.1 g/t and a reduced overall waste:ore ratio of c. 7.5:1

o Total gold recovery now planned at approximately 960,000 ounces over 13 years compared with the previously planned 925,000 over 11 years

 Project cost reviews (operating and capital) have been updated to reflect the updated Mine Plan and will be further refined as part of the 2015 DFS, after completing the final bidding by preferred mining contractors and the value-engineering on process plants.
 Estimated operating costs on an owner-operator basis are US$634/oz excluding royalty and US$721/oz including royalty. All-in Costs are US$906/oz including initial investment and US$768/oz excluding initial investment.
 The independent review of the Mine Plan and project costs was conducted by Snowden with input from the Company's other specialist advisers Cube Consulting (grade control), Geoff Davidson (detailed mine
planning), Senet (processing), Golders (environmental and social) and Epoch (tailings management).

Milestones for completion of 2015 DFS

The next scheduled milestones for completion of the 2015 DFS by mid-2015 include the following:
 Publication of updated Ore Reserves
 Arrangement of final bids by short-listed mining contractors
 Finalisation of value-engineering to reduce the cost of process plant, including due diligence on available existing processing plants
 Review of the 2015 DFS by the project financiers' independent technical expert
p.1 of 4 www.kefi-minerals.com

Project Development Finance

The planned development expenditure for Tulu Kapi has been reduced from the previous project owner's
estimate of c. US$289 million to KEFI's estimate of c. US$143 million, which is independently reviewed
and based on KEFI's semi-selective mining approach, assuming owner-mining and a new plant. The estimate has been further reduced by KEFI to c. US$120 million based on initial bids received from mining contractors and by assuming that savings in the order of 10% on an all-new plant are achieved through the value-engineering process. These savings are supported by the market prices for existing plants on offer for sale. The amount of US$120 million includes a contingency provision for plant construction costs and also for a working capital buffer for cost-overrun.
The development funding plan for Tulu Kapi is for KEFI to draw down, in H2 2015, on a combination of secured finance and equity finance. This is expected to comprise c. US$100 million of senior secured finance and c. US$20 million equity at parent or project level from project contractors and/or investment institutions.
KEFI's project finance adviser and arranger is Endeavour Financial, and the Independent Technical Experts for the project financiers have been selected and are being mobilised.
An Investor Update presentation has been uploaded to the Company's website: www.kefi-minerals.com

Harry Anagnostaras-Adams, Executive Chairman of KEFI, commented:

"Following the signing of the Mining Agreement last week, and the sign-off of the Mine Plan today, KEFI is now focusing on completing the DFS in this quarter as scheduled. We are also in the process of selecting our preferred mining contractors and value-engineering the process plant, which should allow us to finalise the full development funding in Q3 2015 for major works to commence, on schedule, in Q4 2015. KEFI would like to thank our experienced team for ensuring that we have progressed according to the plan that we set out at the time of the acquisition of Tulu Kapi in December 2013, which represents a great achievement."

Enquiries

KEFI Minerals plc

Harry Anagnostaras-Adams (Executive Chairman)

+357 99457843

Jeff Rayner (Exploration Director)

+905 339281913

SP Angel Corporate Finance LLP (Nominated Adviser)

Ewan Leggat, Katy Birkin

+44 20 3470 0470

Brandon Hill Capital Ltd (Broker)

Oliver Stansfield, Jonathan Evans

+44 20 3463 5000

Luther Pendragon Ltd (Financial PR)

Harry Chathli, Claire Norbury, Oli Hibberd

+44 207 618 9100

COMPETENT PERSONS' STATEMENTS

The information in this announcement that relates to input data used for the Mineral Resources is based on, and fairly represents, information and supporting documentation - the compilation of which was overseen by Simon Cleghorn, Resource Manager and a full-time employee of KEFI and a Member of The Australasian Institute of Mining and Metallurgy. Simon Cleghorn has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Simon Cleghorn consents to the inclusion in this announcement of the matters based on this information in the form and context in which it appears.
The information in this announcement that relates to the interpretation, estimation, classification and reporting of the Mineral Resources is based on, and fairly represents, information and supporting documentation - the compilation of which was reviewed by Lynn Olssen who is a Member of The

p.2 www.kefi-minerals.com

Australasian Institute of Mining and Metallurgy and a full-time employee of Snowden. Lynn Olssen has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which she is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Lynn Olssen consents to the inclusion in this announcement of the matters based on this information in the form and context in which it appears.
The Company confirms that it is not aware of any new information or data that materially affects the information included in the announcement dated 4 February 2015 (the "Announcement") and, in the case estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the Announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the Announcement.

NOTES TO EDITOR KEFI Minerals plc

KEFI is the operator of two advanced gold development projects within the highly prospective Arabian- Nubian Shield, with an attributable 2Moz (95% of Tulu Kapi's 1.9Moz and 40% of Jibal Qutman's 0.6Moz) Au Mineral Resources (JORC 2012) plus significant resource growth potential. KEFI is targeting for production at these projects to generate cash flows for further exploration and expansion as warranted, recoupment of development costs and, when appropriate, dividends to shareholders.
Expected milestones for the remainder of 2015 at Tulu Kapi include:
 Independently verified update to Ore Reserves
 Independently updated Definitive Feasibility Study for banking purposes
 Formalisation of bank syndicate, agreement of final terms for project finance
 Full development funding and commencement of construction
In addition, during 2015 KEFI anticipates submitting a Mining Licence Application for Jibal Qutman in
Saudi Arabia through its joint venture company, Gold & Minerals Ltd ("G&M").

KEFI in Ethiopia

KEFI has 95% ownership of the Tulu Kapi Mining Licence in western Ethiopia and is at an advanced stage in refining the development plan for the project, aimed at reducing the previously planned capital and operating expenditure. Detailed research has yielded encouraging results and has been summarised in recent Company announcements.
At the end of 2013, the Ethiopian Government improved the fiscal regime applying to the gold sector, and Tulu Kapi in particular. This included lowering the income tax rate for mining (to 25% from 35%); settling of repayment schedule for inherited VAT liability (over three years rather than up-front); the removal of VAT on future exploration drilling expenditure; lowering royalty on gold mining (to 7% from 8%); accelerating the depreciation of historical and future capital expenditure (over four years); and clarifying the workings of the Government's 5% free-carried interest so that it does not impede conventional project financing terms.

KEFI in the Kingdom of Saudi Arabia

In 2009, KEFI formed G&M in Saudi Arabia with local Saudi partner Abdul Rahman Saad Al-Rashid & Sons Company Limited ("ARTAR"), to explore for gold and associated metals in the Arabian Shield. KEFI has a 40% interest in the G&M and is the operating partner. To date, the G&M has conducted preliminary regional reconnaissance and has had five Exploration Licences ("EL") granted, including Jibal Qutman and the recently granted Hawiah Exploration Licence that contains over 5km2 of outcropping gossans developed on VMS altered and mineralised rocks.

p.3 www.kefi-minerals.com

G&M holds 24 Exploration Licence Applications that cover an area of approximately 1,484km2. ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) lease within the area.
The Kingdom of Saudi Arabia has instituted policies to encourage minerals exploration and development, and KEFI Minerals supports this priority by serving as the technical partner within G&M. ARTAR also serves this government policy as the major partner in G&M, which is one of the early movers in the modern resurgence of the Kingdom's minerals sector.

-Ends-


p.4 www.kefi-minerals.com

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Ethiopia | Saudi Arabia | United Kingdom | All
Gold and Silver Prices for these countries : Ethiopia | Saudi Arabia | United Kingdom | All

KEFI Minerals Plc.

EXPLORATION STAGE
CODE : KEFI.L
ISIN : GB00B1HNYB75
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

KEFI is a gold and copper exploration company based in United kingdom.

Its main exploration property is ARTVIN in Turkey.

KEFI is listed in United Kingdom. Its market capitalisation is GBX 175.0 millions as of today (US$ 204.3 millions, € 191.0 millions).

Its stock quote reached its highest recent level on January 21, 2011 at GBX 9.85, and its lowest recent point on September 06, 2019 at GBX 0.19.

KEFI has 332 702 973 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of KEFI Minerals Plc.
Annual Report 2007
Financings of KEFI Minerals Plc.
7/27/2016has raised Euro 3.8 million
Financials of KEFI Minerals Plc.
4/11/2016FIRST QUARTER 2016 OPERATIONAL UPDATE
12/31/2015Fourth Quarter 2015 Operational Update
10/19/2015Third Quarter 2015 Operational Update
9/28/2015Tulu Kapi Funding Update and Interim Results for the Half-Ye...
Project news of KEFI Minerals Plc.
6/3/2011exploration property sales and final results
Corporate news of KEFI Minerals Plc.
8/10/2017Reduced Funding Requirement
9/19/2016Investor Briefings
7/29/2016Total Voting Rights
7/13/2016Restructure For Develpment of Tulu Kapi
6/30/2016Result of AGM
6/7/2016Kefi Minerals 2015 Annual Report
6/7/2016Kefi Minerals Notice of AGM
6/7/2016KEFI Minerals Proxy
6/7/2016Appointment of Preferred EPC Contractor
6/2/2016Reduced Tulu Kapi Funding Requirements Replacement
4/25/2016KEFI at UK Investor Show
4/14/2016Electronic Communication
4/14/2016Letter to Shareholders re Electronic Communications
4/8/2016Holding(s) in Company
3/31/2016Total Voting Rights
12/31/2015Happy New Year 2016
12/30/2015Fourth Quarter 2015 Operational Update
12/14/2015Holding(s) in Company
10/19/2015Holding in Company
10/14/2015Appointment of Tulu Kapi Mine Contractor
10/5/2015Progress at Jibal Qutman, Saudi Arabia
9/28/2015Tulu Kapi Funding Update and Interim Results for the Half-Ye...
9/9/2015Update on Tulu Kapi Gold Project Financing
8/28/2015KEFI Presenting at Africa Down Under Conference
8/17/2015Contracting and Financing on Schedule, Tulu Kapi Gold Projec...
7/27/2015Director Dealing
7/17/2015Final Bidding Triggered for Project Contractors, Tulu Kapi G...
7/3/2015Director Share Purchase
7/1/2015Total Voting Rights
7/1/2015Second Quarter 2015 Operational Update
6/29/2015KEFI Presenting At Mining Capital Conference
6/24/2015Completion Of 2015 DFS & Development Funding Plan
6/19/2015New Investment – Kefi Minerals Plc
6/16/2015Conditional Placing to Raise £2.9 Million
6/16/2015Result of AGM
6/15/2015Chairman’s AGM Statement
4/22/2015Tulu Kapi Ore Reserve Statement
4/20/2015UPDATE ON PROJECT FINANCING AND DFS FOR TULU KAPI
4/13/2015KEFI Granted Mining Licence
4/9/2015KEFI - Webinar and UK Investor Show
4/7/2015Exploration Update at Hawiah - Saudi Arabia
4/1/2015First Quarter 2015 Operational Update
3/23/2015Grant of Share Options
3/18/2015Director Share Purchase
3/17/2015Financing Update
3/16/2015Tulu Kapi Update
3/4/2015EXPLORATION UPDATE - SAUDI ARABIA
2/26/2015Update on final tranche of placing
2/25/2015Appointment of Head of Operations
2/10/2015KEFI Presenting at Mining Indaba
2/10/2015Tulu Kapi Resource Update
2/10/2015Quarterly Update
10/15/2014QUARTERLY OPERATIONAL UPDATE
3/27/201427 March 2014 Share Option Scheme Approved
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (KEFI.L)
0.526-1.87%
LSE
GBX 0.526
04/26 18:22 -0.010
-1.87%
Prev close Open
0.536 0.534
Low High
0.504 0.550
Year l/h YTD var.
0.526 -  0.870 -22.65%
52 week l/h 52 week var.
0.526 -  0.976 -49.90%
Volume 1 month var.
51,995,903 -7.72%
24hGold TrendPower© : -17
Produces
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-21.49%
2023-9.46%1.230.51
2022-6.33%1.470.46
2021-58.85%2.470.75
202044.36%2.400.51
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :