Fire River Gold

Published : May 16th, 2012

Update on the Progress of the Nixon Fork Gold Mine

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
 


FIRE RIVER GOLD CORP. UPDATE ON THE PROGRESS OF THE NIXON FORK GOLD MINE


May 16, 2012 Vancouver, Canada - Fire River Gold Corp. and Mystery Creek Resources Inc. (collectively, the "Company") [TSXV: FAU| OTCQX: FVGCF| FSE: FWR] is pleased to provide this update on the progress of the mining and milling activities at the Nixon Fork Mine.

The Company has been developing the Nixon Fork Mine since June 2011. Mill processing started ramping up on July 4, 2011, using gravity and flotation circuits to produce the two products: dor� and gold-rich copper concentrate. In addition, mechanical completion of the carbon-in-leach ("CIL") circuit was accomplished on March 20, 2012. The CIL circuit was designed with a capacity of 250 tonnes per day, which is 100 tonnes per day higher than the gravity/flotation mill. The purpose of the CIL circuit is to increase gold recovery from ongoing mined ore and to recover residual gold from the existing gold-rich historic tailings, which run between 7 and 8 grams per tonne of gold.

Accomplishments:

The operation has achieved several milestones over the past few months, including:

  • Mill start-up with gravity and flotation processes began July 4, 2011; a total of 34,400 tonnes of ore has been processed to-date.
  • Started commissioning the CIL circuit in the mill
  • Converted tailings disposal from wet tailings impoundment to dry stack placement
  • Successfully implemented longhole open stoping in the mine in two locations (208 to 220 mASL and 240 to 270 mASL of the 3300 zone)
  • Developed access to six new mining zones
  • Re-established all operating permits and updated the bonding
  • Established a broken ore inventory of approximately 14,000 tonnes at an estimated grade of 22 grams of gold per tonne (as of May 9, 2012)

Production:

The ramp up to full production targets continues, albeit at a slower pace than we originally had anticipated. From July 4, 2011 to the end of March 2012 the mine produced 25,875 tonnes of ore grading approximately 15.5 grams of gold per tonne; so a total of 12,875 ounces of gold were mined. From this feed, 175 tonnes of copper concentrate has been sold to Glencore Ltd. containing 5,994 ounces of gold. The dor� production over the same period totalled 1,180 ounces of gold.

Processing:

The mill started up on July 4, 2011 using gravitational separation and flotation as its two recovery methods. The construction of the CIL circuit was completed in March 2012, adding leaching as a third gold recovery process, which will allow us to produce dor� on-site. The construction project's longer timeline became necessary due to several reasons: retrofits to the existing plant were required in order to incorporate the new process and several modifications to the original CIL design were necessary for process optimization. The addition of the CIL circuit should not only increase overall gold recovery for mined ore, but also provide us a process by which we may recover residual gold from the high-grade historic tailings pond, which runs between 7 and 8 grams per tonne of gold. Going forward, approximately 20% of the gold production will be in the form of dor� and 80% will be added to the copper concentrate.

From start-up until mid-January 2012, the mill ran at an average process rate of 130 metric tonnes per day (mtpd), depositing the final tailings into a dammed subaqueous tailings pond. The tailings disposal system was changed in January 2012 from wet tailings impoundment in a lined dam to placement of filtered tailings on a dry stack. The addition of leaching as the third recovery process in April 2012 also imposed a conversion of the mill to a zero-discharge facility. These process changes resulted in numerous commissioning issues and downtime from various sources, including the mechanical reliability of the final tailings filter, maintaining clear water overflow from the tailings thickener, and upgrading key transfer pumps resulting in an average process rate of 92 mtpd so far in 2012. Each issue is being dealt with so that we may achieve steady incremental improvement at the mill, increasing operating times and throughput. It is projected that the mill will achieve its full target of 150 mtpd over the next four weeks.

Mining Operations:

The mine was muck-bound for much of the first quarter due to the commissioning delays in the mill. This allowed the mine operators to focus on developing six new mining zones for future extraction and to create a large inventory of broken and drilled-off ore stored in the longhole stopes. At present, the broken inventory is estimated to be 14,000 tonnes of ore grading 22 grams of gold per tonne. One of the most recent stopes, near the 160 mASL level of the 3300 zone, has just returned a muck pile sample grade of 81 grams of gold per tonne.

Longhole open stoping has been successfully employed in two stopes located in the 3300 zone, one between 208 mASL and 220 mASL and one between 240 mASL and 270 mASL. This mining method will continue to be used to provide most of the mill feed, with supplemental feed coming from selectively mined cut and fill stopes.

The mine has been very successful at mining outside of the known resources. To-date approximately half of the mill feed and half of the current broken inventory was extracted from sources not identified in the current resources. As experience was gained over the past six months, mine management changed its approach to ore definition and thereby improved the selectivity of mining methods used. In general terms, Diamond drilling is effective at identifying mineralized zones and the contact location, but it is not useful for defining stopes prior to mine design. After Diamond drilling, which defines the zone location, an ore drift is developed through the zone and a smaller bazooka-type of drill is used to drill 15 to 25 m holes that help to define the higher grade pods of mineralization. The Company owns and operates both the bazooka and Hagby drills.

Financing:

On April 4, 2012, the outstanding $7.5 million Sprott Resource Lending Partnership loan was paid in full using the proceeds from a loan of US$12.75 million provided by Waterton Global Value LP ("Waterton"). The purpose of the Waterton loan was to provide the property with additional working capital and to defer the first loan repayments while the property overcomes its start-up issues.

Outlook:

Commissioning the mill and ramping up the operation to full production expectations is ongoing. The 2012 production target is 29,000 ounces of gold mined, with targets of 40,000 ounces in 2013 and 50,000 ounces in 2014. It is anticipated that a declaration of full commercial production, defined by 30 days of consecutive operations at 100 metric tonnes per day throughput (two-thirds of our budgeted throughput) with +90% gold recovery is projected to be made within the next three months.

Despite the few delays, our operating costs have conformed fairly closely to our 2012 Budget of $29.6 M for the calendar year. Accordingly, meeting our production target should result in a near-term operating cost of approximately $950 per ounce and a projected improvement to $750 per ounce in 2013 and $600 per ounce in 2014. Our ability to discover additional resources outside of our current estimate supports our assertion that once the project has realized its full economic potential, it will be possible to sustain operations well beyond the limits of the current mineral inventory.

Fire River Gold Corp. would like to thank our shareholders for their continued support through the project development period.

On behalf of the Board of Directors,


"Richard Goodwin"

Richard Goodwin
President

 

 

Cautionary Note Regarding Forward-Looking Statements:

Certain information regarding the Company including management's assessment of future plans and operations, may constitute forward-looking statements under applicable securities laws and necessarily involve risks associated with mining exploration and development, volatility of prices, currency fluctuations, imprecision of resource estimates, environmental and permitting risks, access to labour and services, competition from other companies and ability to access sufficient capital. As a consequence, actual results may differ materially from those anticipated in the forward-looking statements. A feasibility study has not been completed and there is no certainty the disclosed targets will be reached nor that the proposed operations will be economically viable. Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. We seek safe harbour.


LATEST NEWS

 
  14 May.
Fire River Gold Corp. Appoints New Director

 
  4 Apr.
Fire River Gold Corp. enters into Gold Stream Credit Agreement with Waterton Global Value, L.P.

 
  20 Mar.
Fire River Gold Corp. Announces the Completion and Commissioning of the CIL Circuit

 
  6 Feb.
Fire River Gold Corp. Announces Promotion of Timothy G. Smith to Vice President, C.O.O.

 
  21 Dec.
Fire River Gold Corp. Receives Further Revenue from Concentrate and Dor� Production

 
  15 Dec.
Fire River Gold Corp. Appoints Vice President of Finance and CFO

 
  14 Dec.
Fire River Gold Corp. Resumes Full Operations At Nixon Fork Mine

 
  12 Dec.
Fire River Gold Corp. receives 2nd and final drawdown from Sprott Resource Lending Partnership

 
  21 Nov.
Fire River Gold Corp. Report on Nixon Fork Mine Project

 
  18 Nov.
Fire River Gold Corp. Announces Additional Revenue from the Nixon Fork Mine Project

 

 

RECENT ARTICLES


Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Fire River Gold

DEVELOPMENT STAGE
CODE : FAU.V
ISIN : CA31811Q1063
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Fire River is a gold exploration company based in Canada.

Fire River develops gold and silver in USA.

Its main asset in development is GOLDEN ZONE PROPERTY in USA and its main exploration properties are NIXON FORK, GOLDEN ZONE, KANSAS CREEK and DRAKEN in USA.

Fire River is listed in Canada. Its market capitalisation is CA$ 3.2 millions as of today (US$ 2.8 millions, € 2.2 millions).

Its stock quote reached its highest recent level on November 27, 2009 at CA$ 0.75, and its lowest recent point on October 09, 2014 at CA$ 0.01.

Fire River has 316 160 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Fire River Gold
9/20/2012Announces Additional Brokered Private Placement with Sunel S...
9/7/2012Announces Closing of Second Tranche of Brokered Financing Fo...
8/10/2012Announces Closing of First Tranche $5.7 Million Brokered Fin...
6/11/2012Annouces $4M Private Placement
5/18/2011Announces Extension of Warrant Expiry Date
5/26/2010Previously Announced Non-Brokered Private Placement Oversubs...
5/5/2010Increases Non Brokered Private Placement to $4 million
11/19/2009Announces $10 Million Brokered Private Placement
Nominations of Fire River Gold
1/10/2014Appoints New Director
1/10/2014Appoints New Director
1/10/2014Appoints New Director
3/27/2013Director Resignation
11/8/2012Appoints New Director
10/3/2012Announces New Directors And Officers
10/3/2012appoints new directors and officers
6/28/2012Appoints Interim President & CEO
5/16/2012Appoints New Director
12/19/2011Appoints Vice President of Finance and CFO
6/23/2011Appoints Fred Sveinson to the Board of Directors
Project news of Fire River Gold
1/8/2013(Nixon Fork)Drills 3.34 Metres Grading 219.1 g/t Gold at Nixon Fork
12/10/2012(Nixon Fork)Drills 7.6 Metres Grading 50.26 g/t Gold at Nixon Fork
5/16/2012(Nixon Fork)Update on the Progress of the Nixon Fork Gold Mine
12/22/2011Provides Updated Resource Estimate
12/21/2011Receives Further Revenue from Concentrate and Dor=E9 Product...
12/14/2011(Nixon Fork)Resumes Full Operations At Nixon Fork Mine
12/12/2011receives 2nd and final drawdown from Sprott Resource Lending...
10/3/2011(Nixon Fork)Announces New Ore Zone Discovered at the Nixon Fork Mine
8/25/2011(Nixon Fork)on Progress of the Nixon Fork Mine Start Up
8/23/2011Announces Further Drill Results
7/5/2011(Nixon Fork)Starts Up the Nixon Fork Mill
5/19/2011Releases Additional High Grade Results and Explains the Sign...
4/8/2011(Nixon Fork)Announces 108.0 g/t (3.15 opt) Gold Over 2.4 m (7.9 ft) At N...
4/1/2011(Nixon Fork)Announces 65.3g/t (1.90 opt) Gold Over 5.5 m (18.0 ft) At Ni...
3/25/2011(Nixon Fork)Announces 125.5g/t (3.66 opt) Gold Over 6.0 m (19.7 ft) At N...
3/14/2011(Nixon Fork)Reports Additional Underground Drill Holes Results: 202.7 g/...
3/7/2011(Nixon Fork)Reports New Underground Drill Holes Results: 92.2 g/t (2.69 ...
2/17/2011(Nixon Fork)Announces Results of Snowden's PEA for the Resumption of Und...
8/19/2010(Nixon Fork)Announces 215 g/t (6.27 opt) Gold Over 0.2 m (0.7 ft) At the...
8/3/2010(Nixon Fork)Announces 20 g/t (0.58 opt) Gold Over 2.5 m (8.2 ft) At the ...
7/27/2010(Nixon Fork)Commences 28,000 Metre Drill Program
7/6/2010(Nixon Fork)Announces 144 g/t (4.2 opt) Gold over 2.5 m (8.2 ft) Nixon F...
6/30/2010(Nixon Fork)Generates Over $1 Million Revenue From Ball Mill Clean Up At...
6/21/2010(Nixon Fork)Announces 498 g/t (14.52 opt) Gold over 3.0 m (9.8 ft) Nixon...
6/18/2010(Nixon Fork)Announces 67 g/t (1.95 opt) Gold over 6.3 m (20.7 ft), Nixon...
3/23/2010(Nixon Fork)produces excellent gold results from geological re-assessmen...
2/1/2010(Nixon Fork)Project Update -- Nixon Fork Gold Mine, Alaska Winter 2010
1/29/2010(Nixon Fork)Lays A Lot Of Geological Love Onto Its Nixon Fork Gold Proje...
Corporate news of Fire River Gold
3/25/2014Announces Reclassification to Tier 2
3/11/2014Announces New Mailing Address and Phone Number
12/18/2013Announces New Mailing Address and Phone Number
12/5/2013Announces OTCQX Delisting
10/8/2013Receives Default Notice
8/13/2013Misses Payment to Lender
6/28/2013Suspends Operations
3/28/2013Provides Operations Update
6/29/2012Amends Waterton Debt Facility
6/25/2012Accepts Resignations of Senior Management and Board Members
4/24/2012Provides Additional Information Regarding Credit Facility
4/5/2012enters into Gold Stream Credit Agreement with Waterton Globa...
3/20/2012Announces the Completion and Commissioning of the CIL Circui...
2/6/2012Announces Promotion of Timothy G. Smith to Vice President, C...
2/3/2012New Office Address & Phone Number
12/12/2011Announces Temporary Suspension of Operations Due To Inclemen...
9/14/2011Receives First Concentrate Payment
8/10/2011Announces Concentrate Sales Agreement
7/11/2011Announces Refining Contract
7/7/2011(Nixon Fork)Announces Additional Drill Results At Nixon Fork Gold Mine, ...
6/6/2011(Nixon Fork)Announces 107.13 g/t (3.12 opt) Gold and 36.26 g/t (1.06 opt...
5/16/2011(Nixon Fork)Announces 71.4 g/t (2.08 opt) Gold and 40.1 g/t (1.17 opt) S...
5/12/2011Timothy G. Smith Joins Fire River Gold as Vice President, Op...
4/28/2011(Nixon Fork)Announces 41.0 g/t (1.20 opt) Gold and 33.8 g/t (0.99 opt) S...
4/19/2011(Nixon Fork)Announces 16.7 g/t (0.49 opt) Gold and 51.2 g/t (1.49 opt) S...
4/5/2011Announces President's Message
3/4/2011(Nixon Fork)Corporate Update for the Nixon Fork Gold Mine - $7,000,000 N...
3/2/2011Appoints R. David Russell as Chairman and Richard Goodwin a...
6/9/2010Announces 12,000 Metre Drilling Program
6/7/2010closes final tranche of financing for proceeds of a cumulati...
5/17/2010Closes First Tranche of Financing For Proceeds of $3,625,500
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (FAU.V)
0.010+0.00%
TSX-V
CA$ 0.010
10/09 15:51 -
0%
Prev close Open
0.010 0.005
Low High
0.005 0.010
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.010 -%
Volume 1 month var.
849,310 -%
24hGold TrendPower© : -37
Produces
Develops Gold - Silver
Explores for Copper - Gold - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/18/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.84+1.95%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :