TORONTO--(Marketwired - April 30, 2013) - Golden Star Resources Ltd. (NYSE MKT: GSS) (TSX: GSC) (GHANA: GSR)

Highlights of drill program:

  • BSDD 226 - 32.6 m (meters) grading 7.5 g/t (grams per tonne) gold
  • BSDD 233 - 11.2 m grading 20.0 g/t
  • BSDD 220 - 29.0 m grading 7.5 g/t including 7.3 m grading 27.5 g/t
  • BSDD 246 - 19.0 m grading 10.2 g/t
  • 242DD 068 - 31.7 m grading 7.3 g/t

Golden Star Resources Ltd. (NYSE MKT: GSS) (TSX: GSC) (GHANA: GSR) ("Golden Star" or the "Company") today provided an update on exploration activities at its Wassa gold mine in Ghana. Full drill results, plans, and sections will be available on the Company's website at www.gsr.com or by clicking the following link: http://www.gsr.com/Operations/Wassa.asp.

Drilling at Wassa Main continues to show encouraging results. As announced in the Golden Star press release dated March 21, 2013, the Company's year-end Mineral Reserve update for Wassa/HBB increased 85%, from 18 million tonnes grading 1.38 g/t for 799,000 ounces of contained gold in December 31, 2011 to 31.9 million tonnes grading 1.44 g/t for 1.5 million ounces of contained gold as of December 31, 2012. This updated Mineral Reserve and Resource estimate utilized drilling results up to the end of August 2012. From September 1, 2012 to March 31, 2013, the Company drilled an additional 194 holes for 70,332 m drilled. Drilling in the first quarter of 2013 alone amounted to 89 holes covering 32,863 m.

Sam Coetzer, President and CEO, commented, "We continue to create additional value at our Wassa mine through this drilling program. Assessment of these and previous drilling results from Wassa Main is ongoing, and we expect the gold grades at depth to support the potential for an expansion of Wassa operations. The Wassa mine remains a major focus for Company growth as it can potentially add incremental, non-refractory ounces to our future production stream, and lower operating costs."

During the quarter and for this drill campaign, the Company utilized six multi-purpose drill rigs, testing mineralized zones both down the plunge of the gold bearing fold hinge in addition to infill drilling to increase confidence in the current Mineral Resource estimate. The aim of this drilling is to convert current Inferred Mineral Resources into Indicated Mineral Resources, and ultimately into Probable Mineral Reserves, subject to favorable economics and the completion of an updated Mineral Resource model, which is expected in the third quarter of 2013.

Highlights of the drill campaign include hole BSDD226, an infill hole, which intersected 32.6 m (true width) grading 7.5 g/t from 421 m drilled depth and was drilled approximately 50 m up dip from BSDD186 which intersected 26.6 m grading 6.4 g/t. The intersections in these two holes represent two distinct zones of mineralization which have been interpreted to be limbs of an earlier fold closure and do not correlate directly with one another on this drill section.

Drill holes BSDD246 and BSDD233 were both infill holes drilled to further test mineralization previously intersected in drill hole BSDD181 (see Golden Star Jan 16, 2013 press release). BSDD233 was drilled on the same section as BSDD181 approximately 80 m down dip and intersected 15.7 m grading 2.5 g/t, and 11.2 m grading 20 g/t, respectively. BSDD246 was drilled on section 19775 N located 25 m south of BSDD226 and 50 m up dip and intersected 12.9 m at a grade of 10.7 g/t.

Drill hole BSDD220 was collared in the B-shoot area and intersected several zones of mineralization in the upper 100 m of the hole including, 7.9 m grading 3.3 g/t and 7.1 m grading 3.1 g/t. The main target of this hole was the South East Zone at depth where we intersected 29 m grading 7.5 g/t including 7.3 m grading 27.5 g/t from 355 m drilled depth. These grades and widths intersected in the South East Zone are higher and wider than previously intersected and are expected to have a positive effect on average grade estimates when the Mineral Resource model is updated.

Drill hole 242DD068 tested an Inferred portion of the Mineral Resource model and intersected an upper and a lower zone. The lower zone intersected wider and higher grade mineralization than previously modeled with 31.7 m grading 7.3 g/t.

Significant drill hole intersections for the first quarter of 2013 are tabulated below and in bold font. Also included in this table are other intersections encountered in the same hole. The inclusion of all of the intersections above and below the main significant intersection (in bold) demonstrates the robustness of the Wassa gold mineralization. These zones, although lower grade than the significant intersections, are above economic cut-off and would report to the stockpiles rather than waste dumps in an open pit mining scenario.

 
Wassa Main Q1 2013 significant drill intersections with additional in hole zones
 
Hole ID   E
(m)
  N
(m)
  Elev (m)   Azim (°)   Dip (°)   From (m)   To (m)   Drilled Width (m)   ~ True Width (m)   Gold Grade (g/t)
242DD068   39722   20072   1030   325   -65   87.0   94.0   7.0   6.6   5.4
242DD068   39722   20072   1030   325   -65   169.5   203.0   33.5   31.7   7.3
BSDD209   39753   19950   1025   90   -49   60.0   65.0   5.0   4.1   1.7
BSDD209   39753   19950   1025   90   -49   70.0   83.0   13.0   10.8   1.4
BSDD209   39753   19950   1025   90   -49   91.0   95.0   4.0   3.3   1.2
BSDD209   39753   19950   1025   90   -49   340.0   347.3   7.3   7.3   1.4
BSDD209   39753   19950   1025   90   -49   361.8   367.0   5.2   5.2   0.6
BSDD209   39753   19950   1025   90   -49   382.4   387.6   5.2   5.2   2.7
BSDD209   39753   19950   1025   90   -49   421.0   431.2   10.2   10.2   12.1
BSDD210   39882   20175   985   90   -50   62.0   68.0   6.0   4.9   3.7
BSDD210   39882   20175   985   90   -50   181.0   201.0   20.0   16.4   1.0
BSDD210   39882   20175   985   90   -50   220.0   241.0   21.0   17.2   5.2
BSDD210   39882   20175   985   90   -50   385.0   393.0   8.0   8.0   0.8
BSDD210   39882   20175   985   90   -50   397.0   405.0   8.0   8.0   1.3
BSDD212   39896   19900   1021   90   -62   114.0   121.5   7.5   5.1   2.6
BSDD212   39896   19900   1021   90   -62   124.5   129.5   5.0   3.4   0.9
BSDD212   39896   19900   1021   90   -62   138.7   155.7   17.0   11.6   0.7
BSDD212   39896   19900   1021   90   -62   228.1   306.0   77.3   75.6   1.7
BSDD212   39896   19900   1021   90   -62   355.8   361.0   5.2   5.1   2.2
BSDD212   39896   19900   1021   90   -62   368.2   374.4   6.2   6.1   2.0
BSDD218   39814   20026   995   90   -61   34.0   59.0   25.0   17.4   1.7
BSDD218   39814   20026   995   90   -61   258.7   270.0   11.3   11.1   4.7
BSDD218   39814   20026   995   90   -61   301.0   334.0   33.0   32.4   3.5
BSDD219   39757   20050   1015   90   -60   154.0   158.0   4.0   2.8   1.1
BSDD219   39757   20050   1015   90   -60   333.5   338.5   5.0   4.9   2.5
BSDD219   39757   20050   1015   90   -60   361.0   367.0   6.0   5.9   7.0
BSDD219   39757   20050   1015   90   -60   378.5   383.4   4.9   4.8   27.4
BSDD220   40022   19875   982   90   -53   17.0   27.0   10.0   7.9   3.3
BSDD220   40022   19875   982   90   -53   92.0   101.0   9.0   7.1   3.1
BSDD220   40022   19875   982   90   -53   352.0   381.0   29.0   29.0   7.5
BSDD224   40032   20200   971   90   -58   62.0   72.0   10.0   7.3   0.7
BSDD224   40032   20200   971   90   -58   139.1   143.1   4.0   2.9   1.0
BSDD224   40032   20200   971   90   -58   218.7   242.7   24.0   17.6   3.9
BSDD226   39792   19800   1032   90   -62   192.5   198.5   6.0   4.1   1.2
BSDD226   39792   19800   1032   90   -62   221.0   245.4   24.4   16.6   3.7
BSDD226   39792   19800   1032   90   -62   248.8   272.0   23.2   22.7   1.2
BSDD226   39792   19800   1032   90   -62   328.0   339.6   11.6   11.3   1.6
BSDD226   39792   19800   1032   90   -62   421.0   454.3   33.3   32.6   7.5
BSDD226   39792   19800   1032   90   -62   489.8   502.0   12.2   11.9   1.1
BSDD227   39748   19700   1039   90   -63   194.0   206.0   12.0   8.0   1.0
BSDD227   39748   19700   1039   90   -63   228.0   239.0   11.0   7.4   0.7
BSDD227   39748   19700   1039   90   -63   266.0   277.0   11.0   10.7   1.3
BSDD227   39748   19700   1039   90   -63   301.0   307.0   6.0   5.8   2.7
BSDD227   39748   19700   1039   90   -63   349.0   354.0   5.0   4.9   3.1
BSDD227   39748   19700   1039   90   -63   399.0   443.0   44.0   42.9   3.8
BSDD230   39910   19875   1018   90   -59   113.0   140.0   27.0   19.4   4.1
BSDD230   39910   19875   1018   90   -59   145.0   152.0   7.0   5.0   1.4
BSDD230   39910   19875   1018   90   -59   223.0   229.0   6.0   4.3   1.0
BSDD230   39910   19875   1018   90   -59   314.5   323.4   8.9   8.8   11.2
BSDD231   39915   19825   1018   90   -57   101.0   119.0   18.0   13.4   1.1
BSDD231   39915   19825   1018   90   -57   223.0   243.2   20.2   15.0   3.7
BSDD231   39915   19825   1018   90   -57   276.2   281.2   5.0   5.0   1.9
BSDD231   39915   19825   1018   90   -57   285.2   296.2   11.0   10.9   2.1
BSDD231   39915   19825   1018   90   -57   322.2   333.0   10.8   10.7   7.9
BSDD231   39915   19825   1018   90   -57   413.0   416.0   3.0   3.0   21.5
BSDD233   39793   19825   1031   90   -62   235.0   245.5   10.5   7.2   0.7
BSDD233   39793   19825   1031   90   -62   248.0   253.0   5.0   4.9   1.3
BSDD233   39793   19825   1031   90   -62   275.0   289.0   14.0   13.7   0.5
BSDD233   39793   19825   1031   90   -62   322.0   338.0   16.0   15.7   2.5
BSDD233   39793   19825   1031   90   -62   429.2   434.0   4.8   4.7   2.8
BSDD233   39793   19825   1031   90   -62   446.5   458.0   11.5   11.2   20.0
BSDD233   39793   19825   1031   90   -62   512.0   524.0   12.0   11.7   1.2
BSDD235   39871   19800   1023   90   -64   147.0   161.2   14.2   9.3   1.5
BSDD235   39871   19800   1023   90   -64   309.0   323.8   14.8   14.4   4.3
BSDD237   39691   19900   1043   90   -67   125.2   129.2   4.0   2.5   2.2
BSDD237   39691   19900   1043   90   -67   170.5   215.9   45.4   28.0   1.5
BSDD237   39691   19900   1043   90   -67   226.7   231.9   5.2   3.2   3.2
BSDD237   39691   19900   1043   90   -67   335.6   353.4   17.8   17.0   0.8
BSDD237   39691   19900   1043   90   -67   407.4   411.0   3.6   3.4   2.2
BSDD237   39691   19900   1043   90   -67   436.4   455.4   19.0   18.2   4.7
BSDD241   39924   20000   1007   90   -57   43.0   79.0   36.0   26.8   0.8
BSDD241   39924   20000   1007   90   -57   164.5   175.0   10.5   7.8   1.1
BSDD241   39924   20000   1007   90   -57   186.5   190.5   4.0   3.0   5.6
BSDD241   39924   20000   1007   90   -57   230.0   238.0   8.0   5.9   12.1
BSDD241   39924   20000   1007   90   -57   254.0   263.0   9.0   8.9   7.1
BSDD241   39924   20000   1007   90   -57   330.5   333.5   3.0   3.0   3.7
BSDD241   39924   20000   1007   90   -57   354.5   360.5   6.0   6.0   7.1
BSDD246   39806   19775   1033   90   -58   173.0   199.0   26.0   19.0   10.2
BSDD246   39806   19775   1033   90   -58   228.2   237.2   9.0   6.6   1.0
BSDD246   39806   19775   1033   90   -58   314.7   320.7   6.0   5.9   1.2
BSDD246   39806   19775   1033   90   -58   425.9   438.9   13.0   12.9   10.7
BSDD246   39806   19775   1033   90   -58   444.9   448.9   4.0   4.0   5.0
BSDD251   39936   19850   1018   90   -60   80.0   137.0   57.0   49.4   2.0
BSDD251   39936   19850   1018   90   -60   216.5   231.0   14.5   12.6   0.6
BSDD251   39936   19850   1018   90   -60   264.0   278.0   14.0   12.1   0.7
BSDD251   39936   19850   1018   90   -60   295.0   306.8   11.8   10.2   4.4
SEDD073   40061   19801   1007   90   -60   71.0   78.0   7.0   5.0   0.8
SEDD073   40061   19801   1007   90   -60   213.0   219.3   6.3   4.5   1.7
SEDD073   40061   19801   1007   90   -60   222.3   233.3   11.0   7.9   0.9
SEDD073   40061   19801   1007   90   -60   243.3   273.5   30.2   21.7   2.8
SEDD073   40061   19801   1007   90   -60   277.5   290.9   13.4   9.6   1.7
SEDD073   40061   19801   1007   90   -60   359.2   375.0   15.8   11.4   1.6
                                         

The Company plans to downsize the drilling fleet over the next quarter and close the assay results off at the end of June 2013 so that an updated Mineral Resource model can be completed. The updated Mineral Resource model will be used to run economic pit shells to help guide further drilling, as well as the direction of the Wassa expansion feasibility study.

Company Profile

Golden Star holds a 90% equity interest in Golden Star (Bogoso/Prestea) Limited and Golden Star (Wassa) Limited, which respectively own the Bogoso/Prestea and Wassa/HBB open-pit gold mines in Ghana. In addition, Golden Star has an 81% interest in the currently inactive Prestea Underground mine in Ghana, as well as gold exploration interests elsewhere in Ghana, in other parts of West Africa and in Brazil in South America. Golden Star has approximately 259 million shares outstanding.

Statements Regarding Forward-Looking Information:

Some statements contained in this news release are forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995 and other applicable securities laws. Such statements include: the Company's expectations regarding its exploration and drilling activities during 2013 and the timing thereof; expectations regarding the interpretation of drilling results; the potential to expand Wassa operations and add production, lower operating costs and generate cash flow; expected increases in Mineral Resources and Reserves at Wassa Main including grade increases and contained gold growth and the timing thereof; and the timing for completing a National Instrument 43-101 report. Investors are cautioned that forward-looking statements are inherently uncertain and involve risks and uncertainties. Factors that could cause actual results to differ materially include timing of and unexpected events during exploration; variations in ore grade; variations in relative amounts of refractory, non-refractory and transition ores; technical or permitting issues; fluctuations in gold price and costs; availability of capital and/or external financing on acceptable terms; changes in U.S. and Canadian securities markets; and general economic conditions. There can be no assurance that future developments affecting the Company will be those anticipated by management. Please refer to the discussion of these risks and other factors in the Company's Form 10-K for 2012 and other filings of the Company with the United States Securities and Exchange Commission and the applicable Canadian securities regulatory authorities. The forecasts contained in this press release constitute management's current estimates, as of the date of this press release, with respect to the matters covered thereby. We expect that these estimates will change as new information is received. While we may elect to update these estimates at any time, we do not undertake to update any estimate at any particular time or in response to any particular event.

QA/QC:
The technical contents of this press release have been reviewed and approved by S. Mitchel Wasel, BSc Geology, a Qualified Person pursuant to National Instrument 43-101. Mr. Wasel is Vice President of Exploration for Golden Star and an active member and Registered Chartered Professional of the Australasian Institute of Mining and Metallurgy.

The results for Wassa quoted herein are based on the analysis of saw-split HQ/NQ Diamond half core or a three kilogram single stage riffle split of a nominal 25 to 30 kg Reverse Circulation chip sample which has been sampled over nominal one meter intervals (adjusted where necessary for mineralized structures). Sample preparation and analyses have been carried out at SGS Laboratories in Tarkwa using a 1,000 gram slurry of sample and tap water which is prepared and subjected to an accelerated cyanide leach (LEACHWELL). The sample is then rolled for twelve hours before being allowed to settle. An aliquot of solution is then taken, gold extracted into Di-iso Butyl Keytone (DiBK), and determined by flame Atomic Absorption Spectrophotometry (AAS). Detection Limit is 0.01ppm.

All analytical work is subject to a systematic and rigorous Quality Assurance-Quality Control (QA-QC). At least 5% of samples are certified standards and the accuracy of the analysis is confirmed to be acceptable from comparison of the recommended and actual "standards" results. The remaining half core is stored on site for future inspection and detailed logging, to provide valuable information on mineralogy, structure, alteration patterns and the controls on gold mineralization.

Additional information on earlier drilling results and Mineral Reserve and Mineral Resource estimates at Wassa are available in the Company's National Instrument 43-101 compliant Technical Report titled "NI 43-101 Technical Report on Mineral Resources and Mineral Reserves Golden Star Resources Ltd, Wassa Gold Mine, Ghana, Effective Date 31st December 2012".



For further information, please contact:

GOLDEN STAR RESOURCES LTD.
Jeff Swinoga
Executive Vice President and Chief Financial Officer
416-583-3803

INVESTOR RELATIONS
Belinda Labatte
The Capital Lab, Inc.
647-427-0208

Greg DiTomaso
The Capital Lab, Inc.
647-427-0208

Data and Statistics for these countries : Brazil | Ghana | All
Gold and Silver Prices for these countries : Brazil | Ghana | All

Golden Star Resources

PRODUCER
CODE : GSC.TO
ISIN : CA38119T1049
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Golden Star is a gold producing company based in United states of america.

Golden Star holds various exploration projects in Burkina Faso.

Its main assets in production are BOGOSO / PRESTEA, WASSA, HWINI-BUTRE (FATHER BROWN) and BENSO in Ghana and its main exploration properties are MANO RIVER in Sierra Leone, SARAMACCA and AMÉLIKIA in Suriname, AKROPONG TREND and DUNKWA in Ghana and GOULAGOU - ROUNGA in Burkina Faso.

Golden Star is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 2.9 billions as of today (US$ 2.3 billions, € 2.1 billions).

Its stock quote reached its highest recent level on November 28, 2003 at CA$ 9.94, and its lowest recent point on December 24, 2014 at CA$ 0.20.

Golden Star has 584 169 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Golden Star Resources
10/14/2006Insiders Go for Ghanese Gold Play Called Golden Star
Financings of Golden Star Resources
7/26/2016GSR - Golden Star Announces Pricing of US$30 Million Offerin...
7/25/2016GSR - Golden Star Announces US$65 Million Private Offering o...
4/28/2016 Announces US$15 Million Bought Deal Financing
5/17/2012Contemplates Exchanging Its Existing Convertible Debentures ...
Nominations of Golden Star Resources
7/18/2016GSR - Golden Star Announces Appointment of Gil Clausen to Bo...
5/6/2016GSR - Golden Star Announces Election of Directors
2/25/2014Announces Changes to Board of Directors and Adopts Advance N...
9/17/2013Announces Appointment of Investor Relations Director
6/13/2012Enhances Board of Directors With Addition of Mining Executiv...
1/31/2012Names Roger Palmer Chief Financial Officer, Replacing John L...
10/5/2011Strengthens Board of Directors With Addition of Veteran Audi...
3/13/2011Appoints Sam Coetzer as Chief Operating Officer
3/9/2011Golden Star Appoints Sam Coetzer as Chief Operating Officer
4/2/2008 Appoints Scott Barr as Chief Operating Officer
3/7/2008Appoints President and CEO
12/20/2007Appoints Interim CEO
Financials of Golden Star Resources
7/18/2016GSR - Golden Star Announces Second Quarter 2016 Operational ...
5/9/2016GSR - Golden Star Resources Completes US$15 Million Bought D...
5/4/2016GSR - Golden Star Reports First Quarter 2016 Results
4/13/2016GSR - Golden Star First Quarter Operational Results Exceed E...
2/23/2016GSR - Golden Star Reports Fourth Quarter and Full Year 2015 ...
10/29/2015GSR - Golden Star Reports Third Quarter 2015 Results
7/30/2015GSR - Golden Star Second Quarter 2015 Financial Results
2/20/2014Reports Fourth Quarter and Full Year 2013 Financial Results
11/4/2013Reports Financial Results for the Third Quarter of 2013
8/12/2013Reports Financial Results for the Second Quarter of 2013
5/9/2013Reports Financial Results for the First Quarter of 2013
1/8/2013Reports Preliminary Fourth Quarter Operational Results and 2...
11/7/2012Reports Third Quarter and Nine Month Financial Results
5/9/2012Reports First Quarter Financial Results
2/23/2012Reports 2011 Fourth Quarter and Full Year Results
1/5/2012Reports Preliminary Fourth Quarter Operational Results
8/8/2011Reports Second Quarter 2011 Financial Results
7/19/2011Reports Preliminary Operational Results and Guidance and Sch...
5/11/2011Reports First Quarter 2011 Financial Results
2/24/2011Reports Fourth Quarter and Year-End 2010 Financial Results
1/18/2008REPORTS RECORD OPERATING RESULTS FOR 2007 AND GUIDANCE FOR 2...
Project news of Golden Star Resources
2/10/2014Announces Mineral Reserves and Resources Estimates as at Dec...
11/7/2013(Wassa)Announces a 45% Increase in Gold Ounces of Wassa Main Indica...
7/8/2013Reports Preliminary Second Quarter 2013 Production Results
1/16/2013(Wassa)Drilling at Wassa Mine Yields Further Encouraging Results Th...
7/25/2012(Wassa)Announces Continued Drilling Success at Wassa Main and Adds ...
9/1/2011(Bogoso / Prestea)Announces Pampe Pit Re-Opening and Commencement of Mining Op...
4/28/2011(Wassa)Excellent Grades and Widths From Buesichem South Drilling: G...
2/24/2011(Wassa)Increases Mineral Reserves by 24%; Increases Measured and In...
2/24/2011(Bogoso / Prestea)Reports Fourth Quarter and Year-End 2010 Financial Results
2/24/2011(Wassa)Reports Fourth Quarter and Year-End 2010 Financial Results
1/25/2011(Bogoso / Prestea)Golden Star Achieves Full Certification by ICMI at Bogoso/Pr...
1/14/2008(Bogoso / Prestea) Increases Resources at Prestea South
7/11/2007(Bogoso / Prestea)Declares Commercial Production at Bogoso Sulfide Processing ...
6/3/2003(Wassa)2003 Technical report
Corporate news of Golden Star Resources
8/3/2016Golden Star Announces Closing of Public Offering of Common S...
8/3/2016Golden Star Announces Closing of Public Offering of Common S...
8/3/2016Golden Star Announces Closing of Public Offering of Common S...
7/26/2016Golden Star Announces Pricing of Private Offering of US$65 M...
7/26/2016Golden Star Announces Pricing of US$30 Million Offering of C...
7/25/2016Golden Star Announces US$65 Million Private Offering of Conv...
7/25/2016Golden Star Announces US$30 Million Offering of Common Share...
7/25/2016Golden Star Reports Second Quarter 2016 Results
7/25/2016Golden Star reports 2Q loss
1/26/2016Golden Star Resources (GSS) Looks Good: Stock Jumps 7%
1/15/2016Golden Star Announces Filing of Feasibility Study for Preste...
1/11/2016Golden Star Exceeds 2015 Production Guidance, Provides Opera...
1/4/2016Edited Transcript of GSC.TO earnings conference call or pres...
12/31/2015Golden Star Announces Amendment to the May 2015 Stream Agree...
12/9/2015Should You Stay Away From FX Energy, Inc. (FXEN)?
12/1/2015Golden Star Announces Positive Feasibility Study Results for...
11/30/2015Hedge Funds Are Dumping A M Castle and Co (CAS)
11/24/2015Is Golden Star Resources Ltd. (USA) (GSS) A Good Stock To Bu...
10/28/2015Should You Buy Golden Star Resources (GSS) Ahead of Earnings...
10/22/2015Golden Star Third Quarter 2015 Results Conference Call
9/4/2015Edited Transcript of GSC.TO earnings conference call or pres...
8/26/2015Edited Transcript of GSC.TO earnings conference call or pres...
7/29/2015Golden Star Second Quarter 2015 Financial Results
7/29/2015Golden Star successfully closes Royal Gold Financing
7/22/2015Golden Star Second Quarter 2015 Results Conference Call
7/21/2015Blues for the Yellow Metal: 3 Dull Gold Stocks - Analyst Blo...
7/7/2015Golden Star Gives Update on Bogoso Refractory Operations - A...
7/3/2015Update on Bogoso Refractory Business
4/27/2015Golden Star Announces First Quarter Results Conference Call ...
3/26/2015Golden Star Announces Mineral Reserves and Resources Estimat...
3/26/2015Golden Star Announces Wassa Mine Feasibility Study Results
1/30/2014(Wassa)Wassa Drilling Program Extends High Grade Mineralized Zone 2...
1/9/2014Achieves 2013 Production Guidance, Provides 2014 Guidance an...
11/19/2013Chairman to Become Non-Executive
10/23/2013Third Quarter 2013 Conference Call Details
10/3/2013Announces Preliminary Third Quarter 2013 Production Results
7/30/2013Announces the Closing of a US$50 Million Secured Medium Term...
7/26/2013Announces Filing of Feasibility Study for Prestea Undergroun...
7/18/2013(Wassa)Wassa Gold Mine Q2 2013 Step Out and Infill Drilling Results...
6/17/2013Provides Operational Update on Cost Reduction Measures, Mine...
6/11/2013Publishes Positive Feasibility Study for Prestea Underground...
4/30/2013(Wassa)Wassa Gold Mine Drilling Campaign Completes an Additional 32...
4/4/2013Reports Preliminary First Quarter 2013 Production Results an...
3/21/2013(Wassa)Files Updated NI 43-101 Technical Report for its Mineral Res...
2/20/2013Announces Extension of Scheduled Maintenance at Bogoso Mine ...
2/11/2013Announces Fourth Quarter and Full-Year 2012 Earnings Release...
2/5/2013Announces Mineral Reserves and Resources Estimates as at Dec...
10/15/2012(Wassa)Continues to Generate Encouraging Intercepts at Wassa Mine S...
10/5/2012Reports Preliminary Third Quarter 2012 Production Results
7/17/2012Reports Preliminary Second Quarter 2012 Production Results
5/31/2012Completes Sale of $77.5 Million Convertible Senior Unsecured...
5/2/2012(Wassa)Announces Drilling Results From Wassa Mine in Ghana
4/19/2012Reports Preliminary First Quarter 2012 Production Results
3/21/2012Announces Positive Preliminary Economic Assessment for Prest...
12/28/2011Announces Exercise of Goulagou-Rounga Option by Riverstone R...
9/14/2011Announces Third Quarter Production Update
4/13/2011Schedules First Quarter 2011 Results Conference Call
11/28/2008Files New Shelf Registration Statement to Replace Expiring R...
6/27/2008Reports Increased Power Costs
2/1/2008ANNOUNCES COMPLETION OF GHANAIAN OFFERING
12/5/2007 Completes EURO Ressources Transactions
11/7/2007 Reports Q3 2007 Results.pdf
10/26/2007 Announces Start of HBB Project
10/22/2007Schedules 3Q2007 Results
10/16/2007Options its Goulagou-Rounga Properties to Riverstone
8/8/2007Reports Q2 2007 Results
8/7/2007Reports CEO to Step Down at end 2007
2/24/2006(Mano River)Announces new date for filing form 10-K for 2005
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (GSC.TO)FRANKFURT (GS5.F)
4.96-0.80%0.616-1.12%
TORONTO
CA$ 4.96
01/31 16:00 -0.040
-0.8%
Prev close Open
5.00 4.99
Low High
4.96 4.99
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  4.96 -%
Volume 1 month var.
124,627 -%
24hGold TrendPower© : 4
Produces Gold
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/26/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20225.76%5.004.68
2021-0.42%5.122.58
2020-0.63%6.892.56
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.92-1.71%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+0.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.38-3.64%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.32+0.46%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.77-1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.10-0.89%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :