Asian Mineral Resources Limited

Publié le 04 septembre 2008

Ban Phuc Project Development Progress Update

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Copper | Nickel | Vietnam |

Marketwire

 
 
Asian Mineral Resources Limited
TSX VENTURE: ASN
Other Recent News

September 4, 2008
Asian Mineral Resources: Ban Phuc Project Development Progress Update
TORONTO, ONTARIO--(Marketwire - Sept. 4, 2008) - Asian Mineral Resources Limited ("AMR" or the "Company") (TSX VENTURE:ASN) is pleased to provide an update on its construction and development activities at its 90% owned Ban Phuc Nickel-Copper Project in north Vietnam.

Ban Phuc Development Project:

Construction of the project is on target for commissioning early in the 2nd quarter of 2009. All key operating staff are on board and drill results of the resource inside the Mining License add further confidence to the reserve model. Relations with the community and local authorities remain excellent.

Process Plant and Infrastructure Construction

- Construction of the internal Process Plant access roads and related drainage completed

- Plant and infrastructure earthworks completed

- Engineering, Procurement, Construction and Management ('EPCM') contractor has mobilized to the site

- Concrete contract has been awarded and the contractor has commenced work on site

- Ball mill refurbishment in progress and on schedule for dispatch from Australia in the third quarter 2008

- Construction of the 300 bed camp is progressing well and is expected to be complete in the 3rd quarter

- Site preparation of the Tailing Storage Facility is underway and mobilisation of the contractor is on target to commence in late September when the end of the rainy season is expected to allow unrestricted access of earthmoving equipment

Underground Mine Development

- The upper and lower portals are completed

- Development of the lower portal (main haulage ramp) is on schedule - 422 meters advanced and is 40 meters from the orebody

- The cross cut to the western ore pass has advanced 22 meters from the ramp and is 20 meters from the target position of the first raisebore hole

- Progress of the upper access drive has been impacted by its proximity to surface and the weathered ground has required more support than expected. It is now in competent rock and has just 120 meters to complete before intersecting the orebody

- A contract for the excavation of the vertical raises for ore passes and ventilation has been awarded - the contractor has mobilized to site and piloting of the first hole is due to commence in mid September

Mine Definition Drilling

A diamond drilling program within the Mining License has been developed with two primary objectives:

- In-fill drilling of the massive reserves to facilitate mine planning and stope design. This is being carried out by underground drilling from the existing adits supplemented by surface drilling in deeper areas

- Development of the disseminated nickel resource - testing of the zone adjacent to the massive reserves is designed to determine whether a higher grade section(s) exists in minable dimensions

Massive Sulphide Reserve Confirmation

- 53 'in-fill' holes drilled from the adits have been completed for a total of 1,889 meters

- A detailed analysis of the in-fill drilling over a 100m x 25m section of strike adjacent to adit 301 (which contains close to 10% of the resource) has been completed and compared with the original geological model. The results indicate that:

1) small changes in the geometry of the mineralised areas can be expected, these have the potential to result in a modest loss in tonnage,

2) previous estimates for total metal content may be understated as a number of higher grade drill intersections have been recognized. While it is not possible to quantify this until the drill program is completed and a revised resource calculated, it is considered to be encouraging.

Long Section looking north showing widths of massive sulphide reserves is available at the following web link: http://media3.marketwire.com/docs/asndiagram1.jpg

- Key results from the drilling along adit 301 include the following:

----------------------------------------------------------------------------
Hole         From       To     Intercept        True      Ni     Cu      Co
ID             (m)      (m)     Width (m)   Width (m)      %      %       %
----------------------------------------------------------------------------
BP301-4     16.60    23.20           6.6         4.2     3.5    1.4     0.1
----------------------------------------------------------------------------
BP301-5     22.00    24.50           2.5         2.0     6.8    1.9     0.2
----------------------------------------------------------------------------
BP301-6     46.90    52.50           5.6         3.0     6.6    1.7     0.2
----------------------------------------------------------------------------
BP301-18    48.30    54.70           6.4         2.2     5.8    1.7     0.2
----------------------------------------------------------------------------
BP301-18A   34.35    36.95           2.6         2.6     6.7    2.3     0.2
----------------------------------------------------------------------------
BP301-19    16.00    17.90           1.9         1.3     6.9    0.6     0.2
----------------------------------------------------------------------------
            21.40    26.00           4.6         3.1     5.2    1.8     0.1
----------------------------------------------------------------------------
            33.90    35.10           1.2         0.8     4.2    1.0     0.1
----------------------------------------------------------------------------
BP301-23    32.30    44.40          12.1         7.1     4.4    1.6     0.1
----------------------------------------------------------------------------
BP301-24    12.00    26.50          14.5        13.9     1.9    0.5     0.1
----------------------------------------------------------------------------
BP301-25    25.65    31.00           4.8         3.8     3.6    1.5     0.1
----------------------------------------------------------------------------
            34.60    48.40          13.8        10.9     4.2    1.9     0.1
----------------------------------------------------------------------------
BP301-28     8.30    12.00           3.7         3.3     1.8    0.9     0.0
----------------------------------------------------------------------------
            18.76    23.00           4.2         3.9     5.8    1.5     0.2
----------------------------------------------------------------------------
BP301-30    24.00    31.50           7.5         7.4     3.9    1.7     0.1
----------------------------------------------------------------------------
 
Disseminated Sulphide Resource Evaluation

- Drilling of the disseminated resource lying within the Mining License ('ML') and below the base of oxidation is well underway with receipt of the results from 10 holes drilled from surface. The target area extends over a strike of 150 meters and drilling to date has confirmed the presence of a zone with elevated grades as reported in the table below:

----------------------------------------------------------------------------
Hole ID      From (m)    To (m)   Intercept (m)  True Width (m)  Ni %  Cu %
----------------------------------------------------------------------------
BP07-01        70.00     78.00            8.00            4.59   0.95  0.22
----------------------------------------------------------------------------
BP07-02        58.10     66.45            8.35            4.79   0.76  0.67
----------------------------------------------------------------------------
               74.00     82.00            8.00            4.59   0.84  0.34
----------------------------------------------------------------------------
BP07-03        89.90    101.00           11.10            6.37   0.93  0.08
----------------------------------------------------------------------------
BP07-04        52.96     55.90            2.94            1.69   2.50  0.76
----------------------------------------------------------------------------
BP08-01       163.75    164.90            1.15            0.74   6.68  2.31
----------------------------------------------------------------------------
BP08-02       187.85    195.90            8.05            4.62   1.79  0.57
----------------------------------------------------------------------------
BP08-03       154.40    160.00            5.55            5.00   0.68  0.54
----------------------------------------------------------------------------
BP08-05       165.30    180.00            14.7            8.10   0.57  0.06
----------------------------------------------------------------------------
BP08-09        82.00    107.20            25.2            20.0   1.33  0.20
----------------------------------------------------------------------------
BP08-12        61.40     82.00            20.6            16.9   1.01  0.46
----------------------------------------------------------------------------
 
- These results indicate the presence of a zone of greater than 0.7% Ni, drilling is continuing and it is anticipated that the program will be completed and a resource calculated in the 4th quarter.

- Preliminary metallurgical testwork carried out on a bulk sample taken from the adits indicates that a saleable concentrate can be produced with minimal changes to the existing flowsheet. Confirmatory testwork is planned on a composite sample to be collected from select core taken from the current drilling program.

Exploration:

- Exploration activities in the areas around the mine continued with the primary focus in the 2nd quarter being the completion of a series of Fixed Loop Electro Magnetic surveys. Overall, 1097 stations were acquired for a total of 52 line km of data (7 fixed loops and 49 survey lines) over 4 prospect areas. Preliminary assessment of the data has identified five anomalies and, subject to final review, drilling of these targets will commence in the 3rd quarter, weather permitting. These five targets have been identified as follows:

-- Adit 7 (approx 1km east of Ban Phuc ML) - 1x deep, moderate-weak conductor

-- Suoi Tao (approx 6km east of Ban Phuc ML) - 2x conductors, one strong and one moderate

-- BanTran (approx 3km SE of Ban Phuc ML) - 1x strong conductor

-- Co Muong (approx 4km SE of Ban Phuc ML) - 1x weak conductor

A map of the five targets is available at the following web link: http://media3.marketwire.com/docs/asndiagram2.jpg

- Drilling of these anomalies has commenced, with:

-- Two holes completed in Ban Trang which intersected an unmineralised graphitic horizon

-- At Suoi Tao drilling of the moderate conductor has commenced. A previous hole to the south of the anomaly intersected low grade disseminated sulphides within what is likely a continuation of the same ultramafic dyke.

- An agreement to supply three drill rigs has been concluded with an Indonesian contractor, which will increase the current drill fleet and allow a more detailed program of follow up drilling. The first rig is expected on site in September.

Grade calculations are based on a 0.4% Ni lower cut off to define the mineralised structure, with no upper cut. Analytical work is being carried out at the independent ALS Laboratory Group., Perth, Australia. Analysis is by ICP from a four acid digest. Blanks and standards are being used to monitor laboratory performance during the analysis. This press release has been reviewed by in-house qualified person Simon Mottram, Member of the Australian Institute of Mining and Metallurgy (AusIMM).

Liquidity

At June 30, the Company had on hand cash and cash equivalents of $28.5 million. This amount was reduced to a current level of $14 million, with most of the expenditures having been incurred for the project development described above. As previously disclosed, the Company requires a further $45 million for project completion and other budgeted expenditures. Negotiations are ongoing for the financing of this amount.

Company Profile:

AMR is developing the Ban Phuc Nickel-Copper Project in which it has a 90% interest. The Project based on current reserves is designed to produce some 5,500 tonnes pa of nickel and associated copper credits in concentrate in the first two years and average 4,500 tonnes pa of nickel over the mine life. Commercial sulphide concentrate production is scheduled in the second quarter of 2009. The Company has also reinstituted a regional exploration program around its Ban Phuc Nickel Project.

For further details on the Company and the Ban Phuc Nickel Project please refer to the website at www.asianminres.com.

Forward-Looking Statements

This press release includes certain "Forward-Looking Statements." All statements, other than statements of historical fact, included herein, including without limitation, statements regarding potential mineralization and reserves, exploration results and future plans and objectives of Asian Mineral Resources Limited are forward-looking statements that involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from Asian Mineral Resources Limited's expectations are disclosed under the heading "Risk Factors" and elsewhere in Asian Mineral Resources Limited documents filed from time-to-time with the TSX Venture Exchange and other regulatory authorities.


The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this news release.

CONTACT INFORMATION:

Asian Mineral Resources Limited
Collin Ellison
President and CEO
(416) 360-3412
Fax: (416) 367-1954
Email: info@asianminres.com
Website: www.asianminres.com

INDUSTRY: Manufacturing and Production - Mining and Metals

Footer

.

Asian Mineral Resources Limited

EXPLORATEUR
CODE : ASN.V
ISIN : CA0451731016
CUSIP : 045173101
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Asian Mineral Res. est une société développant des projet miniers de nickel et de cuivre basée au Canada.

Son principal projet en exploration est BANPHUC au Viet Nam.

Asian Mineral Res. est cotée au Canada. Sa capitalisation boursière aujourd'hui est 236,7 millions CA$ (178,9 millions US$, 151,9 millions €).

La valeur de son action a atteint son plus haut niveau récent le 22 juin 2007 à 3,00 CA$, et son plus bas niveau récent le 06 septembre 2018 à 0,01 CA$.

Asian Mineral Res. possède 788 920 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Rapports annuels de Asian Mineral Resources Limited
2007 Annual Report
Financements de Asian Mineral Resources Limited
28/03/2013Successful Closing of $12,500,000 Rights Offering
15/02/2013Files Final Rights Offering Prospectus
11/10/2012Announces Private Placement With Pala Investments and Lion
07/01/2010Completion of Private Placement
01/12/2009Private Placement & Board Appointment
02/07/2009Completes Private Placement
15/06/2009Confirms Private Placement
29/05/2009Announces Proposed Private Placement
28/04/2008-Malaysia Smelting Corporation Exercises Warrants
Nominations de Asian Mineral Resources Limited
24/10/2013Share Compensation Agreements and Payment of Directors' Fees...
24/06/2013Announces Appointment of Chief Financial Officer
02/10/2012Announces Appointment of Chief Executive Officer
Projets de Asian Mineral Resources Limited
16/10/2009(Banphuc)Identifies Elevated PGE's Within the Ban Phuc Deposit and at
22/07/2008(Banphuc)Outlines Export Tariff Increase Impact on Ban Phuc Nickel Pr...
Communiqués de Presse de Asian Mineral Resources Limited
02/10/2015Asian Mineral Resources Issuance of Shares and Grant of Opti...
30/09/2015Asian Mineral Resources Repays US$14.7m in Debt; Enters Brid...
18/08/2015Asian Mineral Resources' Operational Excellence Delivers Low...
20/07/2015Asian Mineral Resources Surpasses Production and Sales Targe...
26/01/2015Asian Mineral Resources Issuance of Shares
26/01/2015Asian Mineral Resources Provides Q4 2014 Operational Update
19/12/2014Asian Mineral Resources Announces New Chairman
02/12/2014Asian Mineral Resources Appoints Non-Executive Director
20/11/2014Asian Mineral Resources Appoints New General Manager Operati...
05/11/2014Asian Mineral Resources Issuance of Shares and Grant of Opti...
08/10/2014Asian Mineral Resources Results of Annual & Special Meeting
15/07/2014Asian Mineral Resources Awarded Exploration License and Comm...
10/07/2014Asian Mineral Resources Issuance of Shares
30/06/2014Asian Mineral Resources Announces Board Changes
19/06/2014Asian Mineral Resources Announces New Website
22/05/2014Asian Mineral Resources Announces New Corporate Presentation
23/04/2014Asian Mineral Resources Announces Appointment of Chief Finan...
10/04/2014Asian Mineral Resources Issuance of Shares
07/10/2013Issuance of Shares
23/08/2013Grants of Stock Options
24/07/2013Announces Closing of its Project Debt with LienViet Post Ban...
11/07/2013Announces Results of Annual & Special Meeting
02/07/2013Share Compensation Agreements
06/06/2013Announces Project Financing Proposal With Lien Viet Post Ban...
05/02/2013Announces $12,500,000 Rights Offering, Re-Filing of Interim ...
10/01/2013Welcomes Favourable Export Tariff for Nickel Matte
04/01/2013Receives Extension of Permission to Export Nickel Concentrat...
11/09/2009Payment of Directors Fees in Shares
19/05/2009Adjustment to Export Restrictions for Ban Phuc
03/11/2008Revised Corporate Strategy
01/10/2008Typhoon 'Hagupit' Impact on the Ban Phuc Project
26/09/2008Ban Phuc Project Suspension
04/09/2008Ban Phuc Project Development Progress Update
14/07/2008Closes Financing
12/06/2008Comments on Increase in Tariff on Nickel Exports
15/05/2008New Chief Executive Officer
05/05/2008-Jinchuan Offtake and Subscription Agreements
08/04/2008 Grants Share Options
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TSX-V (ASN.V)
0,300+7.14%
TSX-V
CA$ 0,300
08/09 16:35 0,020
7,14%
Cours préc. Ouverture
0,280 0,300
Bas haut
0,300 0,320
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,300 -%
Volume var. 1 mois
131 643 -%
24hGold TrendPower© : 5
Produit
Développe
Recherche Cobalt - Copper - Nickel
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 22/02/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
2020-50,00%0,600,15
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,66 AU$-0,71%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,39 US$+1,06%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,52 GBX-0,76%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,64 CA$+0,00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,30 CA$+0,40%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 AU$+2,38%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,89 CA$+0,53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
53,16 US$+0,84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :