Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Northgate Minerals Corporation

Publié le 25 juin 2008

Files Preliminary Assessment Report for the Young-Davidson Project

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Canada | Copper |

Attention Business Editors:

Northgate Files Preliminary Assessment Report for the Young-Davidson Project

     TSX: NGX
     AMEX: NXG

     VANCOUVER, June 24 /CNW/ - (All figures in US dollars except where noted)
Northgate Minerals Corporation (TSX: NGX, AMEX: NXG) is pleased to report the
completion of a NI 43-101 Preliminary Assessment Report (the "Preliminary
Assessment") on the Young-Davidson Project in Matachewan, Ontario. The
Preliminary Assessment indicates that the gold resources are sufficient to
produce a positive cumulative undiscounted cash flow. AMEC Americas Limited
has been commissioned to complete the Feasibility Study.

                Highlights of the Preliminary Assessment Report

     The Preliminary Assessment lays out the basis for the development of a
combined underground and open pit mining operation and highlights areas that
may be optimized in order to improve the project economics. Highlights of the
Preliminary Assessment, which was based on a gold price of $635 per ounce and
an exchange rate of US$/Cdn$0.90 (all figures in Q2-2008 US$) are:

     -   Average annual production of 158,000 ounces of gold at a net cash
         cost of $405 per ounce

     -   A total of 1.75 million recovered ounces of gold over a 12 year mine
         life

     -   Initial capital cost of $306 million (including 17.5% contingency)

     -   Sustaining capital costs of $52.9 million during the life of the mine

     The after-tax net present value and after-tax internal rate of return of
the Young-Davidson Project at a variety of gold prices is shown in Table 1.

     Table 1: Project Economics (after-tax, unlevered)

     -------------------------------------------------------------------------
     Gold Price US$/oz                   NPV (US$M)
                           --------------------------------------        IRR
                           (Undiscounted)     5%            8%
     -------------------------------------------------------------------------
            635                 18.3         -74.0        -104.5         0.8%
            735                134.0           6.5         -38.7         5.4%
            835                249.1          84.3          24.0         9.6%
            935                364.6         161.4          85.8        13.5%
     -------------------------------------------------------------------------
     (Base case in bold)

     Ken Stowe, President and CEO, stated: "In just two and a half years, we
have advanced the Young-Davidson project to the point where we now have a
solid conceptual understanding of the technical and operating parameters of
the mine and expect to be in a position to make a production decision in first
quarter 2009 after the feasibility study is complete. We are confident that
the economics of the project will continue to improve as exploration drilling
increases the known resource and the geotechnical drilling program provides
more information about ground conditions in the area. We will be placing
orders for certain long lead-time equipment in the coming months in order to
keep the project schedule for an early 2011 startup. With the completion of
the Preliminary Assessment, our original goal of defining a three million
ounce resource at Young-Davidson and constructing a Canadian gold mine with a
15+ year mine life has moved significantly closer to reality. I wish to
express my gratitude to our geologists and engineers at Young-Davidson who
have worked many long hours in pursuit of our goal."

     -------------------------------------------------------------------------

     REPORT OVERVIEW

     The Preliminary Assessment was prepared by AMEC Americas Limited of
Oakville, Ontario and will be filed on the SEDAR website at www.sedar.com
within the next 45 days. The economic analysis of the Young-Davidson deposit
contained in the Preliminary Assessment is based on a resource estimate
released by Northgate on February 6, 2008, which included 18.75 million tonnes
(Mt) of indicated mineral resources and 4.55 Mt of inferred mineral resources.
It should be noted that mineral resources are not mineral reserves and do not
have demonstrated economic viability. In addition, while NI 43-101 allows for
the inclusion of inferred resources in a Preliminary Assessment, unlike
measured and indicated resources, inferred resources are considered too
speculative geologically to have the economic considerations applied to them
and as such they cannot be upgraded to mineral reserves. Furthermore, owing to
the preliminary nature of the work done to date, there is no certainty that
the results projected in the Preliminary Assessment will be realized and
actual results may vary substantially.

     Resource Base

     The Preliminary Assessment is based on underground mineral resources with
an effective date of December 20, 2007 (Press Release February 6, 2008(1))
using a 1.90 gram per metric tonne (g/t) gold cut-off grade that consists of
11.49 Mt grading 3.79 g/t gold in the indicated category and 3.99 Mt grading
3.35 g/t gold in the inferred category. Open pit mineral resources estimated
in May 2007 uses a 0.80 g/t gold cut-off grade that consists of 4.28 Mt
grading 2.00 g/t gold in the indicated category and 0.04 Mt grading 2.11 g/t
gold in the inferred category. Mining recovery and dilution were added to the
mineral resources to calculate the mill feed.

     ----------------------------
     (1) Technical Report filed on www.sedar.com on March 26, 2008.


     Table 1: Open Pit and Underground Mineral Resources
     -------------------------------------------------------------------------
            Open Pit & Underground Zones - 2008 Mineral Resources -
                            Young-Davidson Property
     Using Base Case Cut-off Grades of 0.80 g/t Gold - Open Pit & 1.90 g/t
                              Gold - Underground
     -------------------------------------------------------------------------
                    Gold Cut-off   Resource     Tonnes    Gold Id2   Gold (oz)
         Zone           (g/t)       Class        (000)      (g/t)      (000)
     -------------------------------------------------------------------------
     Open Pit(1)        0.80      Indicated      4,280       2.00         275
     Underground(2)     1.90      Indicated     11,494       3.79       1,401
     -------------------------------------------------------------------------
     -------------------------------------------------------------------------
     Total                        Indicated     15,774       3.31       1,676
     -------------------------------------------------------------------------


     -------------------------------------------------------------------------
                    Gold Cut-off   Resource     Tonnes    Gold Id2   Gold (oz)
         Zone           (g/t)       Class        (000)      (g/t)      (000)
     -------------------------------------------------------------------------
     Open Pit(1)        0.80       Inferred         42       2.11           3
     Underground(2)     1.90       Inferred      3,988       3.35         430
     -------------------------------------------------------------------------
     -------------------------------------------------------------------------
     Total                         Inferred      4,030       3.34         433
     -------------------------------------------------------------------------

     (1) Gold cut-off has applied total operating costs of US$15.70/t (mining,
         processing, G&A), metal price of US$600/oz gold and
         US$0.90 equals CND$1.00 and metal recovery of 89% gold
     (2) Gold cut-off has applied total operating costs of US$39.22/t, metal
         price of US$700/oz gold and USD$0.90 equals CND$1.00 and metal
         recovery of 91.7% gold (the difference in gold price reflects the
         different assumed long term gold price between the date of the open
         pit and underground studies)


     Total resources in the open pit decreased relative to Northgate's 2007
year end resource and reserve statement as a consequence of pit optimization
calculations performed at a gold price of $635/ounce, which reduced the size
of the pit in order to reduce initial capital costs. At higher prices of gold,
it is possible that more of the gold mineralization in the pit resource may
increase.

     Mining Method

     During the initial three years of the mine life, feed for the mill will
be sourced from a small open pit and the upper region of the underground mine.
The open pit design incorporates 10 metre high benches with 15 metre wide haul
roads, which will accommodate 50 metric tonne (mt) haul trucks. The stripping
ratio for the open pit is 2.9:1. Production from underground will be ramped up
as the open pit production declines. For the last nine years of the projected
mine life, mill feed will be provided exclusively from the underground mine.
     The underground deposit is currently located approximately between
210 metres to 1,300 metres below surface. A new 6 metre diameter shaft will be
sunk in the footwall, central to the deposit to a depth of 1,390 metres with
three main levels (9730, 9415 and 9100). The underground mine will be
developed on 50 metre sub-level spacing using sublevel open stoping mining
methods (SLOS). The mine will operate 17 mt scooptrams to load, haul and
transfer stope production to the ore pass system from where it will be hoisted
to the surface via 18 mt skips. Initial mining capital costs are estimated to
be $103.2 million for the completion of the new production shaft, completion
of the ramp with initial lateral development, ventilation raises, a paste
backfill plant and the purchase of underground mobile equipment to complete
these activities.

     Please see Figure 1: Open Pit and Underground Mine Design Schematic:
     http://files.newswire.ca/593/Figure1_OpenPitSchematic.doc

     Production Facility and Infrastructure

     Based on pilot plant test results derived from processing an underground
bulk sample, a 5,000 mt/day autogenous grinding mill was selected for the
operation. This mill will produce an average of 158,000 ounces of gold per
year over a 12 year mine life. Gold will be recovered by gravity, flotation
and standard Carbon in Leach (CIL) circuits. Preliminary metallurgical
evaluations have indicated gold recoveries should average 91.5% over the mine
life. The initial capital cost of the process plant is $69.3 million.
     Electric power for the mine site will be supplied by upgrading
approximately 50 kilometres (km) of a an existing 115 kV power line,
installing 7 km of new 115 kV line and the site distribution for an estimated
cost of $18.1 million. A preferred on-land location for the tailings
impoundment facility has been identified that incorporates and remediates an
historic tailings site. The cost for this facility is estimated at
$7.7 million. Surface facilities to support the Young-Davidson mine will
include an administration/engineering building, a warehouse and a maintenance
shop. Indirect costs such as engineering, procurement and construction
management (EPCM), freight, start-up/commissioning, vendor support, first
fills/capital spares, and owners' costs are estimated at $50.9 million. An
additional $45.6 million are estimated as contingency.

     Economic Analysis

     Table 2 contains a summary of the economic parameters used in the
Preliminary Assessment.

     Table 2: Summary of Economic Parameters
     -------------------------------------------------------------------------
     Item                                         Unit                  Value
     -------------------------------------------------------------------------
     Gold price                                   US$ per ounce           635
     Silver price                                                          10
     -------------------------------------------------------------------------
     Foreign exchange rates - US$/CDN$                                   0.90
     -------------------------------------------------------------------------
     Income tax rate        - Federal             %                        15
                            - Provincial                                   12
     -------------------------------------------------------------------------
     Initial Capital        - Infrastructure      US$ millions           36.8
                            - Process plant                              69.3
                            - Mining                                    103.3
                            - Indirect Costs                             51.0
                            - Contingency                                45.6
                            - Mine closure                                9.6
                                                                      --------
     Total Initial Capital                                            $ 368.4
     -------------------------------------------------------------------------
     Sustaining Capital                           US$ millions          $52.9
     -------------------------------------------------------------------------
     Average mining cost                          US$ per tonne milled  21.88
     Processing cost                                                     9.99
     General and
      Administration                                                     3.47
                                                                      --------
     Total                                                            $ 35.34
     -------------------------------------------------------------------------
     Mining                 - Recovery (average)  %                        92
                            - Dilution (average)                           15
     -------------------------------------------------------------------------
     Processing Recovery    - Gold                %                      91.5
                            - Silver                                     78.0
     -------------------------------------------------------------------------

     A number of initiatives are underway to refine and enhance the rate of
return of the Young-Davidson project, including:

     1.  Exploration - Surface based diamond drilling to fill in the region
         between the Boundary zone and the Young-Davidson zone will continue
         with the goal of increasing the total mineral resources and
         increasing the mine life of the proposed operation.

     2.  Resource Update at Higher Metal Prices - During the second half of
         2008, the resource model will be updated to reflect more current
         estimates of long term gold price. This process may reduce the
         economic cutoff grade for existing resources and capture more
         resource tonnes and contained gold.

     3.  Reduction in Backfilling Requirement - A geotechnical drilling
         program is underway to determine the maximum stable excavation size
         for the mine design. This will directly impact backfill requirements
         and has the potential to reduce the cash cost of the operation. The
         current Preliminary Assessment assumes a worst case scenario where
         100% of the stopes will be paste backfilled at an average cost of
         US$3.45 per mt of mill feed whereas historic mining on the property
         did not utilize any backfill due to the competent and stable host
         rock. In addition to a potential reduction in cash cost, it may also
         be possible to increase the sublevel spacing from the 50 m spacing
         used in the Preliminary Assessment which would reduce total mine
         development capital.

     4.  Open Pit Wall Slopes - Inter-ramp wall angles in the Preliminary
         Assessment were set at 55 degrees. Historic mining on the property
         suggests that these angles can be increased which would reduce the
         waste/ore strip ratio and reduce operating costs. The geotechnical
         drilling program will confirm the appropriate inter-ramp wall angle.

     Environment and Permitting

     Based on numerous community meetings held throughout the district, there
is strong community support for the Young-Davidson project. Development of the
mine would bring substantial economic development to the town of Matachewan
and the surrounding district. A construction workforce of 600 people will be
created at the peak of a two year construction period and the mine will
provide direct employment for 250 people over its 12 year operating life.
     Environmental baseline studies in support of permitting have been ongoing
for the past 18 months and will be completed by the end of 2008. Testing to
date on the Young-Davidson mineralization has confirmed that the mill tailings
will be non-acid generating, which will allow them to be impounded in the same
area as historic tailings from the two mines that previously operated on the
property. The current development plan envisions the remediation and expansion
of an historic on-land tailings impoundment site in order to support future
mining at Young-Davidson.
     Northgate has been working cooperatively with the Matachewan First Nation
since it began exploring Young-Davidson property in 2006 and on March 26, 2008
the two parties signed a Memorandum of Understanding (MOU) which provides the
foundation for a cooperative and mutually beneficial relationship between the
Matachewan First Nation and Northgate and outlines the basic framework for the
negotiation of a long-term Impact and Benefit Agreement (IBA). Negotiation of
the IBA began in April 2008 and Traditional Use Studies in cooperation with
First Nations elders are progressing well.

     Project Timeline

     1.  An updated Resource estimate at revised long term gold prices which
         will include 2008 drilling up to September 30 will be completed in
         Q4-2008 and will be used as a basis for the feasibility study.

     2.  The Feasibility Study is scheduled for completion by first quarter
         2009.

     3.  Negotiations on an Impact Benefit Agreement (IBA) are ongoing.

     4.  Permitting activities are being advanced to support a late 2009
         construction start.

     5.  Orders will be placed in the second half of 2008 for long lead
         equipment in order to meet the project timeline.

     QUALIFIED PERSONS

     Carl Edmunds, PGeo, Northgate's Exploration Manager, Northgate Minerals
Corporation, is the Qualified Person responsible for reviewing and approving
the press release.
     Pierre Rocque, P. Eng., Consulting Manager Mining and Geology, AMEC
Americas Limited, is the Qualified Person responsible for supervising the
preparation of the Preliminary Assessment including the cost estimates and
financial analysis.
     Armando Simon, R.P.Geo, Principal Geologist, AMEC Americas Limited, is
the Qualified Person responsible for supervising the preparation of the
mineral resource estimates.

     NORTHGATE MINERALS CORPORATION is a mid-tier gold and copper producer
with mining operations, development projects and exploration properties in
Canada and Australia. The company is forecasting over 400,000 ounces of
unhedged gold production in 2008 and is targeting growth through further
acquisitions in stable mining jurisdictions around the world. Northgate is
listed on the Toronto Stock Exchange under the symbol NGX and on the American
Stock Exchange under the symbol NXG.

     FORWARD-LOOKING STATEMENTS:

     This news release contains certain "forward-looking statements" and
"forward-looking information" as defined under applicable Canadian and U.S.
securities laws. Forward-looking statements generally can be identified by the
use of forward-looking terminology such as "may," "will," "expect," "intend,"
"estimate," "anticipate," "believe," or "continue" or the negative thereof or
variations thereon or similar terminology. Forward-looking statements are
necessarily based on a number of estimates and assumptions that are inherently
subject to significant business, economic and competitive uncertainties and
contingencies. Certain of the statements made herein by Northgate Minerals
Corporation ("Northgate") including those related to future financial and
operating performance and those related to Northgate's future exploration and
development activities, are forward-looking and subject to important risk
factors and uncertainties, many of which are beyond the Corporation's ability
to control or predict. Known and unknown factors could cause actual results to
differ materially from those projected in the forward-looking statements. Such
factors include, among others: gold price volatility; fluctuations in foreign
exchange rates and interest rates; impact of any hedging activities;
discrepancies between actual and estimated production, between actual and
estimated resources and between actual and estimated metallurgical recoveries;
costs of production, capital expenditures, costs and timing of construction
and the development of new deposits; and, success of exploration activities
and permitting time lines. In addition, the factors described or referred to
in the section entitled "Risk Factors" of Northgate's Annual Information Form
(AIF) for the year ended December 31, 2007 or under the heading "Risks and
Uncertainties" of Northgate's 2007 Annual Report, both of which are available
on SEDAR at www.sedar.com, should be reviewed in conjunction with this
document. Accordingly, readers should not place undue reliance on
forward-looking statements. The Corporation does not undertake any obligation
to update publicly or release any revisions to forward-looking statements to
reflect events or circumstances after the date of this document or to reflect
the occurrence of unanticipated events, except in each case as required by
law.

     NOTE TO US INVESTORS:

     The terms "Mineral Reserve", "Proven Mineral Reserve" and "Probable
Mineral Reserve" are Canadian mining terms as defined in accordance with
NI 43-101 Standards of Disclosure for Mineral Projects under the guidelines
set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the
"CIM") Standards on Mineral Resources and Mineral Reserves Definitions and
Guidelines adopted by the CIM Council on August 20, 2000. The terms "Mineral
Resource", "Measured Mineral Resource", "Indicated Mineral Resource", and
"Inferred Mineral Resource" used in this news release are Canadian mining
terms as defined in accordance with NI 43-101-Standards of Disclosure for
Mineral Projects under the guidelines set out in the CIM Standards.

     ----------------------------------
     (1) Technical Report filed on www.sedar.com on March 26, 2008.

     %CIK: 0000072931
For further information: Ms. Keren R. Yun, Director, Investor Relations, Tel:
(416) 216-2781, Email: ngx@northgateminerals.com, Website:
www.northgateminerals.com

.
Données et statistiques pour les pays mentionnés : Canada | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous

Northgate Minerals Corporation

PRODUCTEUR
CODE : NGX.TO
ISIN : CA6664161024.
CUSIP : 666416102
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Northgate Minerals est une société de production minière d'or et de cuivre basée au Canada.

Northgate Minerals est en développement de projets d'or, de cuivre et d'argent au Canada, et détient divers projets d'exploration au Canada.

Ses principaux projets en production sont STAWELL MINE et FOSTERVILLE MINE en Australie et KEMESS SOUTH au Canada, son principal projet en développement est YOUNG - DAVIDSON au Canada et ses principaux projets en exploration sont BOULEVARD, KEMESS UNDERGROUND, MATACHEWAN MINE et AWAKENING GOLD au Canada.

Northgate Minerals est cotée au Canada. Sa capitalisation boursière aujourd'hui est 943,3 millions CA$ (928,4 millions US$, 655,4 millions €).

La valeur de son action a atteint son plus bas niveau récent le 28 janvier 2000 à 0,60 CA$, et son plus haut niveau récent le 12 mai 2006 à 5,29 CA$.

Northgate Minerals possède 254 245 479 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Dans les médias de Northgate Minerals Corporation
26/10/2011AuRico Gold Completes Acquisition Of Northgate Minerals Corp...
14/08/2006Follow up N° 8
29/04/2006Follow up N° 7
Financements de Northgate Minerals Corporation
28/02/2011Sells Auction Rate Securities
23/09/2009Announces C$100 Million Bought Deal Financing
Nominations de Northgate Minerals Corporation
12/07/2011Northgate Minerals Corporation Announces the Appointment of ...
11/07/2011Announces the Appointment of Richard Hall as President and
10/05/2011Announces Retirement of President and CEO Ken Stowe
Rapports Financiers de Northgate Minerals Corporation
14/10/2011Reports Strong Third Quarter Production
10/08/2011Primero Reports Second Quarter 2011 Results; Earnings Increa...
10/05/2011Reports First Quarter Results
07/04/2011Northgate Minerals Provides Details for its 2011 First Quart...
07/04/2011Provides Details for its 2011 First Quarter Results and ...
10/08/2010Reports Second Quarter Results
11/05/2010Solid First Quarter Results
08/04/2010Details for Annual General and Special Meeting and 2010 Firs...
10/08/2009Strong Second Quarter Operating Cash Flow of $50 Million
04/03/2009Posts Fourth Quarter Net Earnings of $0.07 per Share
14/01/2009Reports Record Gold Production in the Fourth Quarter 2008
01/08/2008Generates Cash Flow from Operations of $41 million in the Se...
02/05/2008 Reports First Quarter Financial Results; Adjusted Net Earni...
08/04/2008 announces details for annual general meeting and 2008 first...
29/02/2008 posts fourth quarter net income of $32 million
28/01/2008Reports fourth quarter operating results and production fore...
30/11/2007Revises fourth quarter metal production forecast
04/05/2007first quarter gold production on plan; Kemess South mine-lif...
Projets de Northgate Minerals Corporation
24/10/2011AuRico Gold's Acquisition of Northgate Minerals Receives Ove...
16/09/2011(Young - Davidson)Announces a 500,000+ Ounce Indicated Resource at YD West
25/08/2011(Young - Davidson)Intersects Two Major Intervals in the YD West Zone at Young-...
02/08/2011(Kemess Underground)Announces Positive Preliminary Assessment for its Kemess Und...
24/06/2011(Young - Davidson)Provides Update on Construction and Exploration Activities a...
23/06/2011(Awakening Gold)Initiates Drill Program at =?ISO-8859-1?Q?=20the=20Awakening...
08/06/2011(Young - Davidson)Intersects 4=2E31 Grams per Tonne Gold Over 79=2E6 Metres at...
27/05/2011(Young - Davidson)Underground Delineation Drilling at NorthgateMinerals' Young...
20/05/2011(Matachewan Mine)Matachewan Consolidated Mines, Limited Announces Sale of Min...
13/04/2011Northgate Minerals Provides Update on Construction and Explo...
13/04/2011(Young - Davidson)' Young-Davidson Project Remains On Schedule and On Budget
16/02/2011(Kemess Underground)Northgate Minerals Announces Updated Resource Estimate for K...
12/01/2011(Young - Davidson)Drilling at Northgate Minerals' Young-Davidson Project Confi...
30/11/2010(Kemess South)Northgate Minerals Successfully Completes 2010 Diamond Drill...
02/07/2010(Young - Davidson)Receives Key Permit for the Development
09/02/2010(Young - Davidson)Receives Board Approval for Development of the Young-Davidso...
25/01/2010(Young - Davidson)Releases Final Feasibility Study for the Young-Davidson Proj...
15/09/2009(Fosterville Mine)Significant Extension of Mineralization Discovered at Northg...
10/09/2009(Young - Davidson)New Gold Zone Discovery at Northgate Minerals' Young-Davidso...
06/08/2009(Stawell Mine)Extends Mine Life at the Stawell Gold Mine
15/07/2009Announces Positive Young-Davidson Pre-Feasibility Study
30/06/2009(Fosterville Mine)Three-Year Collective Agreement Ratified at Northgate's Fost...
10/12/2008(Young - Davidson)Announces Dramatic Increase in Resources at its Young-Davids...
18/07/2008(Young - Davidson) Additional Drill Results for the Young-Davidson Project
23/04/2008reports first quarter production results and updated 2008 pr...
16/04/2008Exploration drilling at Northgate's Stawell mine intersects ...
09/04/2008(Kemess South)New three-year collective agreement ratified at Northgate's ...
17/03/2008(Kemess South)Tentative labour agreement reached at Northgate's Kemess min...
08/03/2008(Kemess South)Federal and Provincial Environmental Ministers announce fina...
05/03/2008(Kemess South)Unionized employees at Northgate's Kemess mine turn down ten...
21/12/2007(Young - Davidson) Announces Additional Young-Davidson Drill Results - Drill H...
31/05/2007(Kemess South)2007 Technical report
02/05/2005(Kemess South)2005 Technical report
Communiqués de Presse de Northgate Minerals Corporation
10/10/2011Miners Boost Hedging Even as Gold Demand Strengthens
14/09/2011Miners Continue to Underperform in Gold Market
13/09/2011AuRico Gold and Northgate Minerals Provide Update on Special...
29/08/2011Primero Announces Termination of Arrangement Agreement With ...
29/08/2011AuRico Gold to Acquire Northgate Minerals and Create A Leadi...
13/07/2011and Primero to Combine and Create
31/05/2011..lling at Northgate Minerals\342\200\231 Young-Davids...
17/05/2011Recognized for Its Commitment to Sustainability
13/04/2011Northgate Minerals Provides Update on
08/03/2011Northgate Minerals Reports Excellent Cash
16/02/2011Northgate Minerals Announces Updated
14/01/2011Reports 2010 Gold
14/01/2011Reports 2010 Gold
02/07/2010Renews Base Shelf Prospectus
11/06/2010To Renew Universal Base
07/06/2010& Nevada Exploration Sign Formal Option Agreement
22/03/2010Added to S&P/TSX Composite Index
09/03/2010Reports Record Cash Flow from Operations in 2009
19/01/2010Reports Record Gold Production of 362,743 Ounces in 2009
14/10/2009Announces Diamond Drill Results Adjacent to Established Rese...
30/09/2009 Closing of C$100 Million Common Share Offering
20/07/2009Confirms Discussions with Dioro Exploration NL
03/07/2009Matachewan First Nation Signs Impact and Benefits Agreement ...
22/12/2008Comments on Recent Market Activity
20/09/2008Issues Statement on its American Stock Exchange Closing Pric...
09/09/2008 Announces Increase in Gold Reserves at its Stawell Gold Min...
25/06/2008Files Preliminary Assessment Report for the Young-Davidson P...
17/05/2008files preliminary base shelf prospectus
26/03/2008Matachewan First Nation signs Memorandum of Understanding wi...
18/03/2008 reports final audited revenue and net earnings for 2007
25/02/2008's Fosterville Gold Mine to Transition to Owner Mining
18/02/2008Completes Acquisition of Perseverance
14/02/2008Tentative labour agreement reached at Northgate's Kemess min...
07/02/2008Major increase of indicated resources at Northgate's Young-D...
01/02/2008Final court approval received for Northgate's acquisition of...
21/01/2008Perseverance shareholders and warrant holders approve Northg...
18/12/2007Updates progress on Perseverance acquisition
05/11/2007reports strong quarterly production and record low cash cost...
28/10/2007Announces Friendly Proposal to Acquire Perseverance Corporat...
20/09/2007to speak at Denver Gold Forum - Update on Kemess North Proje...
18/09/2007announces further drill results at Young-Davidson analysts' ...
18/09/2007Review Panel submits recommendation report for Northgate's K...
10/09/2007Review panel announces date for the release of recommendatio...
02/08/2007Review panel announces recommendation report for Northgate's...
27/07/2007reports strong quarterly cash flow of $43.7 million - A thir...
02/12/2005Follow Up N° 6
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TORONTO (NGX.TO)
3,71-0.27%
TORONTO
CA$ 3,71
27/10 15:00 -0,010
-0,27%
Cours préc. Ouverture
3,72 3,76
Bas haut
3,65 3,84
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  3,71 -%
Volume var. 1 mois
1 270 800 -%
24hGold TrendPower© : 11
Produit Copper - Gold
Développe Gold
Recherche Copper - Gold - Silver
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 22/01/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,82 AU$+1,69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,04 US$+1,38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,54 GBX-2,53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,52 CA$+6,78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,05 CA$+2,62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+2,13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,19 AU$-7,32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,90 CA$+1,60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
51,43 US$-0,46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,03 AU$+0,00%Trend Power :