Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

LNG Ltd.

Publié le 18 mars 2015

Magnolia LNG Project Update ...

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   K Street | Report |

Magnolia LNG Project Update From FERC

Microsoft Word - Release ASX 2015-03-19 FERC Final.docx

ASX/MEDIA RELEASE

19 MARCH 2015

MAGNOLIA LNG PROJECT UPDATE FROM FERC

Liquefied Natural Gas Limited (ASX: LNG; OTC ADR: LNGLY) ("LNGL" or the "Company") wishes to provide an update on the status of Environmental Impact Statements ("EIS") due to be issued from the United States Federal Energy Regulatory Commission ("FERC") in relation to the Company's wholly owned subsidiary, Magnolia LNG LLC ("MLNG").

FERC has posted the attached report on its web site dated March 2015. The report provides the current status of the Magnolia LNG Project environmental review process, including the ongoing preparation of the draft EIS. The FERC information includes a summary of the steps involved in this overall process and the status of MLNG within this sequence of activities.

For further information contact:

Mr Maurice Brand

Managing Director/ CEO

+61 8 9366 3700

Mr David Gardner

Company Secretary

+61 8 9366 3700

Mr Michael Mott

Chief Financial Officer

+1 713 815 6909

Liquefied Natural Gas Limited

Level 1 10 Ord Street, West Perth WA 6005

Telephone: +61 8 9366 3700 Facsimile: +61 8 9366 3799

Email: [email protected]

Web site: www.LNGLimited.com.au

DisclaimerForward‐looking statements may be set out within this correspondence. Such statements are only predictions, and actual events or results may differ materially. Please refer to our forward‐looking statement disclosure contained on our website at www.LNGLimited.com.au and to the Company's Annual Report and Accounts for a discussion of important factors which could cause actual results to differ from these forward‐looking statements. The Company does not undertake any obligation to update publicly, or revise, forward‐looking statements, whether as a result of new information, future events or otherwise, except to the extent legally required.

NEXT STEPS

We are currently preparing the draft EIS for the projects based on the information we have received from the applicants and the comments we have received from stakeholders. After we have all the information to
complete our analysis, we will issue a Notice of Schedule for Environmental Review. This Notice will announce the target date for issuing the final EIS and disclose the 90- day federal authorization action/decision deadline.
When the draft EIS is completed, a Notice of Availability will appear in the Federal Register, and the draft EIS will be mailed to the environmental mailing list. There will be a 45-day comment period to review and comment on the document. In addition to accepting written comments, the date and location of a public comment meeting will be announced in the draft EIS and in the Notice of Availability.
At the close of the comment period, we will consider all comments received on the draft EIS, prepare written responses to those comments, and revise the draft EIS, as necessary, to create the final EIS. The final EIS will also be mailed to the environmental mailing list. The Commission will consider the findings in the final EIS when it makes its decision about whether or not to approve the projects.

HOW TO STAY INFORMED

Go to the FERC website at http://www.ferc.gov. Click on the eLibrary link, click on "General Search" and enter the docket number (i.e., CP14-347 or CP14-511). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at [email protected] or toll free at 1-866-208-
3676. For TTY, contact 202-502-8659.
In addition, the FERC offers a free service called eSubscription that allows you to keep track of all issuances and submittals in specific dockets. Using this service can reduce the amount of time you spend monitoring our website by automatically providing you with electronic notification when new items are posted and providing direct links to the documents. To register for this service, go to:

Magnolia also maintains a project website at:
http://www.magnolialng.com/IRM/content/default.aspx
While we believe that the Internet is the best way to stay informed of the projects, we realize that not everyone has Internet access. From this point forward on these projects, issuances by the environmental staff, including the EIS document, will be mailed to the environmental mailing list in either hard copy or compact disc format.

FEDERAL ENERGY REGULATORY COMMISSION

888 First Street, NE Washington, DC 20426

202-502-6088

1-866-208-3372 (toll free)

202-502-8659 (TTY)

http://www.ferc.gov

Federal Energy Regulatory Commission

Office of Energy

Projects

UPDATE FOR THE MAGNOLIA LNG AND LAKE CHARLES EXPANSION PROJECTS

March 2015

PURPOSE

The purpose of this mailing is to provide an update on the environmental review of the proposed Magnolia LNG Project and Lake Charles Expansion Project, explain the Federal Energy Regulatory Commission (FERC or Commission) environmental review process, describe the issues identified to date, and give you an idea of what's next in our review process.

DESCRIPTION OF THE PROJECTS

Magnolia LNG, LLC (Magnolia) plans to construct, own, and operate a facility in Calcasieu Parish, Louisiana to liquefy natural gas (LNG) and subsequently store and deliver LNG to: LNG carriers for export overseas; LNG carriers and barges for domestic marine distribution and the possibility of LNG bunkering; and LNG trucks for road distribution to LNG refueling stations in Louisiana and surrounding states. The proposed Magnolia LNG Project consists of two LNG storage tanks, four
LNG liquefaction trains, a 40-foot pipeline connecting to an existing interstate pipeline (described below), a LNG vessel loading terminal and berth, a LNG truck loading area, and other ancillary facilities.
We started our review of the Magnolia LNG Project on March 20, 2013, when we approved Magnolia's request to use the
FERC pre-filing process. The environmental issue identification process began during this phase of our review. The pre-filing

FERC's Environmental Review

Process

Approve Magnolia's pre-filing request and assign PF Docket No. PF13-9

Participate in Magnolia's open house to identify stakeholder concerns

Magnolia LNG Project -

Issue Notice of Intent to Prepare an EIS and open the scoping period to seek public comments

Public

process ended when Magnolia formally filed its application with the FERC on April 30, 2014.
Kinder Morgan Louisiana Pipeline (KMLP) is proposing additions and changes to its existing mainline system that would result in the creation of a new firm north-to-south service path that would supply natural gas to Magnolia's LNG Terminal. KMLP plans to construct and operate a 40-foot-long interconnect pipeline and a meter station within Magnolia's LNG Terminal, one compressor station, two header pipelines, and would also modify six existing meter stations in Acadia and Evangeline Parishes, Louisiana.
We started our review of the Lake Charles Expansion Project on June 30, 2014, when Kinder Morgan formally filed its application with the FERC.

WHERE WE ARE IN THE ENVIRONMENTAL REVIEW PROCESS

The FERC is the lead federal agency responsible for conducting the environmental review for these projects. In compliance with the National Environmental Policy Act, the FERC is preparing one environmental impact statement (EIS) for the Magnolia
LNG and Lake Charles Expansion Projects. The U.S. Army Corps of Engineers, U.S. Coast Guard, U.S. Department of Energy, U.S. Environmental Protection Agency, and U.S. Department of Transportation are cooperating agencies in the preparation of the EIS.

Input

Opportunities

Magnolia LNG Project -

Host public scoping meeting to obtain public comments

Magnolia LNG Project -

Issue Notice of Application and assign

CP Docket No. CP14-347

Lake Charles Expansion Project - Issue Notice of Application and assign CP Docket No. CP14-511

Lake Charles Expansion Project - Issue Notice of Intent to Prepare an EIS and open the scoping period to seek public comments

To date, we attended one open house sponsored by Magnolia to provide information about FERC and the EIS process. For each project, we issued a Notice of Intent to Prepare an Environmental Impact Statement, which opened a scoping period to seek public comments. We also conducted a public scoping meeting in Lake Charles, Louisiana; issued three environmental

We are here Analyze data and prepare draft EIS

data requests and four engineering and design data request to Magnolia; and issued three environmental data requests to KMLP.
Presently, we are conducting our environmental analysis of the proposed projects, the results of which will be presented in the draft EIS. The draft EIS will describe the potential environmental impacts of the projects, mitigation measures proposed for each project, alternatives considered, and will include an engineering design review of the proposed facilities. The draft EIS will also present our recommendations for additional mitigation and/or conservation measures to avoid or further reduce impacts on the affected environment.
In addition to the companies' applications and project data, we will analyze information that has been filed by other stakeholders and commenters in the proceeding. All substantive issues identified by commenters will be addressed in the draft EIS.

ISSUES IDENTIFIED

The following concerns that have been raised during scoping on the projects:

Public

Input

Opportunities

Public

Issue draft EIS and open public

comment period

Hold a public comment meeting on the draft EIS in Lake Charles

Respond to comments and revise the draft EIS

Commission issues Order approving or denying the applications

Purpose of and need for the projects

System alternatives

Storage of hazardous materials and fuel oil

Impacts on groundwater, existing hydrology, and drinking water supply

Noise and visual effects

Effects on public health and safety

Cumulative effects to health, safety, and the environment

Impacts on air quality

Effects on threatened and endangered species and habitat

Input

Opportunities

Commission reconsiders its decision

if requested by intervenors

Commission issues Notice to Proceed with construction if applications are approved and relevant conditions are met

Lire la suite de l'article sur www.noodls.com

LNG Ltd.

EN DÉVELOPPEMENT
CODE : LNG.AX
ISIN : AU000000LNG0
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

LNG est une société de production minière basée en Australie.

LNG est en développement de projets de gaz en Australie.

Son principal projet en développement est GLASSTONE LNG PROJECT en Australie.

LNG est cotée en Australie. Sa capitalisation boursière aujourd'hui est 22,1 millions AU$ (17,0 millions US$, 14,1 millions €).

La valeur de son action a atteint son plus haut niveau récent le 24 avril 2015 à 5,00 AU$, et son plus bas niveau récent le 24 avril 2020 à 0,04 AU$.

LNG possède 512 979 968 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Rapports annuels de LNG Ltd.
Annual Report 2011
Nominations de LNG Ltd.
02/08/2013Change to LNG Ltd's Board of Directors
Projets de LNG Ltd.
20/02/2014Magnolia LNG Project Update
08/01/2014Magnolia LNG Project Update
16/12/2013Key 2013 milestone achieved at Queensland Curtis LNG project
13/12/2013$10.85 Million Raised To Progress Magnolia LNG Project USA
09/12/2013Equity Placement to Further Progress Magnolia LNG Project
29/11/2013Magnolia LNG Submits Draft Resource Reports on Schedule
10/11/2013Magnolia LNG Project Update
15/10/2013Magnolia LNG Project Files for Additional Export Approvals
08/10/2013Magnolia LNG Project Update - Progress On Track
11/09/2013Magnolia LNG Project Update - On Track
14/08/2013Enterprise Shareholders Approve Acquisition By LNG Energy Lt...
06/08/2013Magnolia LNG Project Approval Process
31/07/2013$10M Capital Raising to Progress Magnolia LNG Project, USA
26/07/2013Stonepeak Strategic Alliance and Project Equity Magnolia LNG
15/05/2013Gladstone Fisherman's Landing LNG Project Gas Supply Update
08/05/2013Magnolia LNG Project Monthly Progress Report No.1
28/01/2013Magnolia LNG Project Site Option to Lease Term Sheet Signed
20/01/2013Magnolia LNG Project
13/09/2012Gladstone Fishermans Landing LNG Project Gas Supply Progress
04/06/2012Gladstone Fisherman's Landing LNG Project Update
12/12/2011Gladstone Fisherman's Landing LNG Project Update
02/06/2008(Glasstone Lng Project)Gladstone "Fisherman's Landing" LNG Project - Arrow/Shell Al...
01/04/2008(Glasstone Lng Project)Gladstone Fisherman's Landing LNG Project
05/02/2008(Glasstone Lng Project)Gladstone LNG Project - Fisherman's Landing
Communiqués de Presse de LNG Ltd.
18/01/2016Investor Presentation
21/12/2015Appendix 3Y
21/12/2015Appendix 3B
18/12/2015Gas Natural Rioja to start work this month on installation o...
19/11/2015Chief Development and Chief Technical Officers Appointment
19/11/2015Results of Annual General Meeting
19/11/2015AGM Presentation
27/10/2015Appendix 4C
26/10/2015Australia: Gladstone LNG ships first liquefied natural gas c...
19/10/2015Annual Report 2015 - Shareholders' Version
16/10/201515.09.2015 Contract for purchase of liquefied natural gas fo...
14/10/2015Iran Could Trigger A Resource War On Several Fronts Other Th...
05/10/2015Response to ASX Price Query
15/09/2015Contract for purchase of liquefied natural gas for the purpo...
28/08/2015Appendix 4E
18/08/2015Appointment of General Counsel and Joint Company Secretary
17/08/2015National Energy Board Grants Export Licence to Bear Head LNG
10/08/2015Change in substantial holding
07/08/2015Appendix 3Y
30/07/2015Global Alliance With Chart Industries, Inc.
29/07/2015Appendix 4C
28/07/201550 years of LNG – August 2013: the world’s first transhipmen...
21/07/2015PRESS DIGEST- Canada - July 21
20/07/2015Bear Head Receives DOE Approval of Exports to FTA Countries
15/07/2015Honeywell To Improve Operations For Liquefied Natural Gas Pi...
24/04/2015Appendix 4C
23/04/2015Magnolia LNG Project Tolling Agreement Update - Me
20/04/201550 years of LNG – 1962: the first experiments on transportin...
20/04/2015ExxonMobil President Calls for Urgent Action on U.S. Liquefi...
08/04/2015Shareholder Presentation
06/04/2015DF will carry out the extension to a Liquefied Natural Gas t...
02/04/2015Bear Head LNG Files Updated Registration with NSE
01/04/2015Shareholder Presentations
18/03/2015Magnolia LNG Project Update From FERC
15/03/2015Bear Head LNG Receives Permit to Construct
12/03/2015Investor Presentation
06/03/2015Qatargas to restart LNG production Train 4 in late March aft...
03/03/2015LNG Ltd Plans Dual Listing in USA
02/03/2015Magnolia EPC Contractor Joint Venture Finalized
28/02/2015Lithuania signs non-binding deal for U.S. LNG
27/02/2015Half Year Report and Appendix 4D
25/02/2015US Patent Update for OSMR Technology
19/02/2015GDF SUEZ wins an important liquefied natural gas supply cont...
15/02/2015Bear Head LNG Takes a Major Step Forward in Canadian Process
15/01/2015US Patents Update
13/01/2015GP Strategies Completes Liquefied Natural Gas Trailer Loadin...
13/01/2015Investor Presentation
12/01/2015Gas tanker runs aground off Nigeria -traders
06/02/2014Pivotal LNG and WesPac Midstream LLC Selected to Serve TOTE'...
05/02/2014Magnolia LNG Opens Lake Charles Office
04/02/2014Magnolia LNG Signs EPC MOU with SKEC Group
29/01/2014Magnolia LNG signs Definitive Pipeline Capacity Agreement
26/11/2013Tolling Term Sheet Signed with LNG Holdings Corp for 1.7mtpa
20/08/2013Energy Ltd. Completes Acquisition of Enterprise Energy Resou...
19/07/2013Magnolia LNG - Significant Community and Government Support
17/07/20132 MTPA Tolling Term Sheet Signed with Gunvor - Magnolia LNG
25/06/2013Energy Ltd. to Acquire All of the Shares of Enterprise in Fr...
22/03/2013Magnolia LNG Pre Filing Request Approved
13/03/2013Magnolia LNG Pre Files for Approvals
23/08/2012Market Briefing - LNG Ltd MD on strategic gas supply
02/12/2011Martin Place Securities Report 1 December 2011
25/11/2011Change of Share Register
24/11/2011Results of AGM
07/10/2011Form 604 Notice of change of interests of substantial holder
06/10/2011Form 603 - Notice of initial substantial holder
21/09/2011Queensland Gas Pipeline Interim Feed Agreement
05/09/2011Gas Pipeline Licence Granted
01/08/2011Appendix 3X
01/08/2011Quarterly Report June 2011
20/07/2011Carbon Tax Impact
14/07/2011OSMR Technology Patents Update
13/07/2011HQCEC Share Placement Completed and Appendix 3B
11/07/2011HQCEC Receives Foreign Exchange Approval For Share Placement
05/02/2008Notice of Shareholder Meeting
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
Australia (LNG.AX)
0,043+0.00%
Australia
AU$ 0,043
26/02 10:00 -
0%
Cours préc. Ouverture
0,043 0,043
Bas haut
0,043 0,043
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,043 -%
Volume var. 1 mois
0 -%
24hGold TrendPower© : 8
Produit
Développe Natural gas
Recherche
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
20210,00%0,040,04
2020-77,37%0,210,04
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,70 AU$-0,65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,26 US$+2,68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,53 GBX-1,87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,64 CA$-1,86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,23 CA$+4,04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+4,26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,20 AU$+2,63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,88 CA$+0,53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,71 US$+0,19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :