NOVEMBER/DECEMBER 2012


PROJECT UPDATE

Reverse Osmosis (RO) pilot plant: a milestone in proving the water treatment process for clean water will meet standards.
 

 

At PolyMet, we�re committed to mining in an environmentally responsible way.

To demonstrate that our project will effectively treat water with elevated sulfate levels, we recently completed comprehensive testing in partnership with Barr Engineering and GE Water & Process Technologies. Working with these global leaders in environmental engineering and wastewater treatment, we designed a pilot plant that uses RO membrane technology and confirmed that this modern technology will effectively treat our water to meet Minnesota�s stringent water quality standards.

RO is used in applications all over the world; it is even used to purify ocean water to make clean drinking water. The technology forces water under pressure through specially designed membranes that allow only clean water to pass through.

Since the launch of the pilot plant in May 2012, we have effectively treated more than 1,500,000 gallons of water. The success of this pilot project demonstrates that we can meet Minnesota's sulfate standard of 10-mg/liter to protect wild rice, which is much more stringent than the state�s drinking water standard of 250mg/l.

After PolyMet obtains the necessary permits for the mining project, this test system will be expanded to a full-scale wastewater treatment plant at the NorthMet tailings basin. In the meantime, we continue testing the pilot plant to increase efficiencies.

Sincerely,

Jon Cherry, President/CEO
 




WDIO
 
Minneapolis/St Paul Business Journal
 
Bloomberg
 
 
 


FAST FACT
 
Construction of the NorthMet project will require approximately two million hours of labor. That�s about the same amount of labor hours that went into building Target Field, the new Twins stadium.
 



EMPLOYEE SPOTLIGHT
Paul Brunfelt, Plant Division Manager

 
Paul has been with PolyMet for four years and has more than 20 years of engineering and management experience in operations and maintenance in the mining, power, and material-handling industries. Paul has his bachelor�s degree in mechanical engineering from the University of Minnesota and is a registered professional engineer.
He serves on the Industrial Advisory Committee for the Chemical Engineering Department at the University of Minnesota Duluth and on the Industrial Advisory Board for Iron Range Engineering. He lives on Lake Vermilion in Cook, Minn., with his wife, Lainie Plotnik, who works for Minnesota Power. They have two children, Kellen (17) and Hannah (14), and a yellow lab named Millie.
Paul Brunfelt
What does your job entail?
As plant division manager, I oversee the engineering design and construction of the processing facilities for the NorthMet project. Currently, I am acting as an engineer, providing input into the design of the wastewater treatment facilities. Once the process facilities are fully constructed, I will also be responsible for the commissioning and operation of the facilities.
Where did you grow up?
Mt. Iron, Minnesota.
What is your favorite thing about where you work?
Fishing and hunting deer and grouse are some of my favorite things to do. Since I live on Lake Vermilion, I�m able to fish and enjoy the outdoors often.
In fact, all of us who work at PolyMet live in Minnesota to enjoy the outdoors. Since nature is something I personally value, I would only be part of a project that preserves the natural resources that northern Minnesota has to offer.
What is your favorite thing about where you live?

I like the variety. Although I�ve grown accustomed to working in a leadership role while operating facilities, it has been rewarding to get into the engineering side of the plants and have so much input into the design and construction of the project.
 

I�m also looking forward to helping form a world-class workforce to operate our processing plants. Our team will place safety and minimizing environmental impacts as top priorities while producing metals we use every day.



 
DID YOU KNOW?
The truth about acid rock drainage

 
What is acid rock drainage?
Acid rock drainage is caused by a natural oxidation process when rock containing metallic sulfides is exposed to water and air. This combination can form a chemical reaction that can change the characteristics of the water that contacts the rock, making the water acidic. (An acidic solution is one that has a pH of less than 7. pH is the measurement of the acidity or alkalinity of a solution.) If not properly collected and treated, contact water could enter into the environment, where it could have a negative impact.

A question we get a lot is: Will the NorthMet project produce acid rock drainage (ARD)?

We are committed to minimizing and treating acid rock drainage if and when it occurs. That�s why, even though PolyMet�s ore contains less than 1 percent sulfur, we worked with the Minnesota Department of Natural Resources to complete comprehensive waste characterization testing. The analysis, which measured the pH of water that comes in contact with waste rock, showed that even without treatment, 96 percent of the contact water would have a pH of 6.5 to 7, which is within the normal range of stream water (pH of 5 to 8) and less acidic than rain water (pH of 5.5 to 5.8). The remaining 4 percent of the waste rock could produce contact water with a pH of approximately 4, which is slightly less acidic than orange juice (pH 3.3). The testing, which started in 2005, is ongoing and currently includes more than 1.5 million analyses.

With this information, PolyMet has developed a systematic plan to ensure water discharged from the project meets applicable water quality standards. This includes using stringent protocol to sort waste rock into stockpiles based on its potential to generate acid and a robustly engineered system to capture and treat any water that comes in contact with the waste rock.

Each stockpile will have an engineered foundation with an engineered system to collect and treat water that contacts exposed mining rock. Any contact water will then be treated using RO technology at wastewater treatment facilities (with the RO process described above) at both the mine and plant sites prior to being discharged offsite. Mining at the site will begin on the east side in an area designated as the East Pit. Once the East Pit is mined out, the rock that could potentially generate acid will placed into the pit and permanently stored under water as the pit is reflooded. This will eliminate the rock�s exposure to oxygen and prevent oxidation which could lead to the potential formation of acid rock drainage.

 
PolyMet (NYSE MKT: PLM; TSX: POM) is a publicly traded mine development company with operational headquarters located near the mine in Hoyt Lakes, Minnesota, and executive offices in St. Paul, Minnesota.

This newsletter contains forward-looking statements concerning anticipated developments in PolyMet's operations in the future, which are based on the beliefs, expectations and opinions of management on the date the statements are made. For more information, click here.

PolyMet Mining  |  PO Box 475, County Road 666  |  Hoyt Lakes, MN 55750
Subscribe

 



This message was sent to .com from:

PolyMet Mining | 6500 County Road 666 | Hoyt Lakes, MN 55750

 |  Forward This Message

Polymet Mining Corp

CODE : POM.TO
ISIN : CA7319161021
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Polymet est une société développant des projet miniers de cuivre et de nickel basée au Canada.

Polymet détient divers projets d'exploration en USA.

Son principal projet en exploration est NORTHMET en USA.

Polymet est cotée au Canada, aux Etats-Unis D'Amerique et en Allemagne. Sa capitalisation boursière aujourd'hui est 909,5 millions CA$ (727,2 millions US$, 690,1 millions €).

La valeur de son action a atteint son plus bas niveau récent le 27 mars 2020 à 0,26 CA$, et son plus haut niveau récent le 04 septembre 2020 à 8,30 CA$.

Polymet possède 318 549 984 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Dans les médias de Polymet Mining Corp
05/07/2008Duluth Complex: A World-Class Value Play
07/09/2006Follow up
Financements de Polymet Mining Corp
27/06/2013Reminder to Shareholders Rights Offering Closes at 5:00 pm E...
24/05/2013Announces Terms of US$60=2E5 Million Rights Offering and Fil...
06/12/2011Closes $20 Million Private Placement With Glencore
30/11/2011and Glencore Agree to Extend Debentures
18/01/2011Polymet Closes First $10 Million Tranche of Glencore Financi...
17/11/2009Modifies Terms of Existing Glencore Warrants
Nominations de Polymet Mining Corp
25/01/2011Names Brad Moore Executive VP-Environmental and Governmental...
19/02/2008 Appoints Frank Sims and Joe Scipioni to the Board
13/03/2007Appoints Chief Operating Officer and NorthMet Senior Constru...
Rapports Financiers de Polymet Mining Corp
15/06/2016Reports First Quarter Fiscal 2017 Results
22/04/2016Reports Fiscal 2016 Results
16/12/2015Reports Third Quarter Fiscal 2016 Results
04/09/2015Reports Second Quarter Fiscal 2016 R =?ISO-8859-1?Q?esults,=...
05/12/2013Reports Third Quarter Fiscal 2014 Results
11/09/2013Reports Second Quarter Fiscal 2014 Results
11/06/2013Reports First Quarter Fiscal 2014 Results-Rights Offering Ma...
07/09/2012Reports Second Quarter Fiscal 2013 Results
18/06/2012Reports First Quarter Fiscal 2013 Results
08/09/2011Reports Second Quarter Fiscal 2012 Results
06/07/2011Reports First Quarter Fiscal 2012 Results: Update on State o...
07/05/2011Announces Fiscal 2011 Full-Year Results
30/04/2008Reports Fiscal 2008 Fourth Quarter and Full Year Results
Projets de Polymet Mining Corp
14/07/2016Project Update at Shareholders' Meeting
16/12/2013Federal Wetlands Permit Application Published for PolyMet Pr...
28/08/2013and E&D: Polymetal swings to a loss and Ncondezi gets permit...
29/07/2013and Finance: Polymetal to take writedown of up to US$340m an...
30/05/2013(Northmet)Reports Further Progress at NorthMet Copper-Nickel Project R...
14/02/2013(Northmet)Improves NorthMet Project
07/11/2012Drilling Commences at the Croydon Polymetallic Project
03/02/2011(Northmet)Simplifies Metallurgical Process at NorthMet Project
26/09/2007(Northmet)Reports a 51% Interim Increase in Reserves at NorthMet
09/08/2007(Northmet) Reports a 51% Increase in Mineral Resources at NorthMet
10/07/2007(Northmet) Drill Program Confirms Expansion of "Magenta" Zone and Demo...
Communiqués de Presse de Polymet Mining Corp
14/07/2016PolyMet Project Update at Shareholders’ Meeting
11/07/2016PolyMet Submits Water-Related Permit Applications to the Sta...
15/06/2016PolyMet Reports First Quarter Fiscal 2017 Results
22/04/2016PolyMet Reports Fiscal 2016 Results
27/01/2016PolyMet Secures Additional US$11 Million Loan From Glencore
16/12/2015PolyMet Reports Third Quarter Fiscal 2016 Results
06/11/2015IIROC Trade Resumption - POM
06/11/2015PolyMet Final EIS Completed - Demonstrates Project Meets Env...
06/11/2015IIROC Trading Halt - POM
04/09/2015PolyMet Reports Second Quarter Fiscal 2016 Results, Progress...
17/07/2015PolyMet Reports Accomplishments at Annual Shareholders’ meet...
16/07/2015PolyMet Reports Accomplishments at Annual Shareholders' Meet...
15/12/2014PolyMet Reports Third Quarter Fiscal 2015 Results - Project ...
15/12/2014PolyMet Reports Third Quarter Fiscal 2015 Results Project Up...
08/10/2014PolyMet Final EIS "Early Spring" 2015
09/09/2014PolyMet Reports Second Quarter Fiscal 2015 Results
11/06/2014PolyMet Reports First Quarter Fiscal 2015 Results
25/04/2014PolyMet Reports Fiscal 2014 Results
25/04/2014PolyMet and Glencore Agree to Extend Term of US$32.2 Million...
13/03/2014IIROC Trade Resumption - POM
13/03/2014IIROC Trading Halt - POM (all issues)
24/02/2014DNI Metals - Operating in a Polymetallic Paradise
06/12/2013Achieves Key Milestone in Environmental Review Process
05/12/2013DNI REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR ITS...
06/11/2013Three-Week Federal Government Shutdown Results in Two-Week P...
11/09/2013DNI'S RESOURCE STUDY REPORT UPDATING AND EXPANDING THE MINER...
27/08/2013DNI EXPANDS BUCKTON ZONE INFERRED RESOURCE TO 4.9 BILLION TO...
26/08/2013Significant Progress for PolyMet Environmental Review
23/08/2013Minnesota DNR Announces Publication Date for PolyMet Supplem...
25/07/2013s Investors With Exclusive Interview With The Wall Street An...
10/07/2013Reports Strong Positioning at Shareholders' Meeting
05/07/2013Closes Successful Rights Offering; Financed to Complete Perm...
19/06/2013on PolyMet Rights Offering-Informationfor Those Who Have Not...
13/05/2013Reports Completion of Drafting of Preliminary EIS
23/04/2013Reports Fiscal 2013 Results
19/04/2013(Northmet)NorthMet News - PolyMet Mining, Inc.
10/04/2013US$60 Million Common Share Rights Offering to All Shareholde...
11/01/2013DNI CONSOLIDATES AND EXPANDS BUCKTON RESOURCE TO 3.49 BILLIO...
11/12/2012(Northmet)NorthMet News - PolyMet Mining, Inc.
01/11/2012s Technical Disclosure
15/10/2012Closes $10 Million Third Tranche of Glencore Financing
10/10/2012Reports Successful Water Treatment Pilot Plant
13/09/2012(Northmet)NorthMet News - PolyMet Mining, Inc.
11/09/2012Strengthens Permitting Expertise
17/07/2012Focuses Corporate Leadership Team in Minnesota
11/07/2012Announces Results of Shareholders' Meeting
28/06/2012Form 20-F Availability
21/06/2012Strengthens Leadership Team
15/06/2012for IMMEDIATE Dissemination - Verbatim - Kootenay and Pinecr...
14/06/2012Reports Technical Disclosure Review
23/05/2012Reports Progress on Environmental Review
01/05/2012Reports Fiscal 2012 Results
19/03/2012DNI EXTRACTS METALS FROM ITS ALBERTA POLYMETALLIC SHALES USI...
29/02/2012Acquires Control of Wetlands
13/02/2012Clarifies Status of Environmental Review Following Misleadin...
01/02/2012s Status of Environmental Review
16/01/2012DNI ANNOUNCES 250 MILLION TON INFERRED RESOURCE FOR REE-Y-Sc...
14/12/2011orate and Project Update; Third Quarter Fiscal 2012 Results
30/11/2011Agrees to Sell US$20 Million of Common Shares to Glencore
12/10/2011Everett Resources Commences Second Phase 2,500 Meter Drill P...
19/09/2011(Northmet)s Progress on NorthMet Environmental Review
15/07/2011Closes Second $10 Million Tranche of Glencore Financing
30/06/2011Closes IRRRB Loan
17/06/2011Reports Mailing of Information Circular
05/05/2011to File Financial Statements on or Before May 9, 2011
03/05/2011Announces Delay in Filing Year-End Financial Statements
15/04/2011s Status of Environmental Review
25/06/2010EIS-Path Forward to Completion Announced
15/03/2010Statement on Environmental Review Timeline
04/03/2010Environmental Review Process Clarified
23/02/2010s NorthMet Environmental Review Progress
26/01/2010Receives Second Installment From Glencore
24/11/2009Closes Financing-Project Update
17/11/2009Sells US$25 Million of Common Shares to Glencore
28/10/2009Environmental Impact Statement Published
05/10/2009Draft EIS Available the Week of October 19, 2009
01/10/2009s EIS Publication Schedule
02/09/2009Draws Fourth Tranche of Loan From Glencore
27/08/2009Files US$500 Million Universal Shelf Registration
19/06/2009Draws Third Tranche of Loan From Glencore
24/12/2008Draws Second Tranche of Loan From Glencore
22/12/2008Receives Draft EIS From Department of Natural Resources
24/09/2008EIS and Glencore Update
04/09/2008and Glencore Sign Strategic Marketing Agreement
12/08/2008Minnesota DNR Updates PolyMet EIS Progress
12/06/2008s EIS Progress
02/06/2008Present at the New York Society of Security Analysts' 8th An...
20/05/2008Capital and Operating Costs
15/02/2008Updates EIS Schedule for Its Copper-Nickel-Precious Metals P...
05/02/2008Strengthens Minnesota Focus
05/11/2007Present at Third Annual Sanders Morris Harris Investor Growt...
04/10/2007Hosts Analyst and Investor Tour
14/09/2007Quarterly Financials
04/09/2007Signs Northmet Construction Labor Agreement
21/08/2007Expands NorthMet Management Team
16/05/2007Updates NorthMet Environmental Review
07/05/2007Research Capital Report
07/05/2007Announces Retirement of Warren Hudelson Receives Approval fo...
21/03/2007Financial Adviser Engages NorthMet Independent Engineer
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TORONTO (POM.TO)AMEX (PLM)
2,86+0.53%2,09-0.48%
TORONTO
CA$ 2,86
12/10 16:15 0,020
0,53%
Cours préc. Ouverture
2,84 2,82
Bas haut
2,82 2,86
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
1,03 -  2,87 14,40%
Volume var. 1 mois
4 178 0,175%
24hGold TrendPower© : 30
Produit
Développe
Recherche
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
20241,96%
2023-22,65%3,761,01
20220,56%6,153,05
2021-15,49%6,713,28
20201252,38%8,300,26
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,70 AU$-0,65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,26 US$+2,68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,53 GBX-1,87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,64 CA$-1,86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,23 CA$+4,04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+4,26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,20 AU$+2,63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,88 CA$+0,53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,71 US$+0,19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :