Publié le 11 juillet 2008

Open BriefingR - MD on Feasibility Study & Future Plans

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter

BC Iron Limited (ASX: BCI)

 

ASX RELEASE                                                   11 JULY 2008

 

Open Briefing?. BC Iron. MD on Feasibility Study & Future Plans

 

 

corporatefile.com.au

BC Iron Limited (ASX code: BCI) has committed to a Feasibility Study on the Nullagine Iron Ore Project in the Pilbara in Western Australia following completion of a Scoping Study.  What did those results reveal about the potential economics of the project?  What impact does the recent iron ore price settlements have on your project?s economics?

 

MD Mike Young

The scoping study really confirmed what we?ve believed all long; these orebodies, because they are at surface and outcropping, will be relatively cheap to mine.  The projected A$42 a tonne operating cost and A$85 million capex cost are also pretty much in line with our expectations.  Most importantly, they highlight the economic attractiveness of the project.  That operating cost includes truck haulage to Christmas Creek, which is Fortescue?s planned operation to the south of Nullagine, and rail haulage and ship loading at Port Hedland.

 

Obviously the recent iron ore price negotiations has had a significantly positive impact on our project economics and provides us with a real buffer against any potential project cost increases that might occur.

 

corporatefile.com.au

How will the Feasibility Study outcomes differ from those outlined in the Scoping Study?  What will be the key milestones met under the Feasibility Study?  How long will it take to complete?

 

MD Mike Young

The Feasibility Study will stress test the Scoping Study results in much greater detail and the outcomes will really be a mining plan to move forward.  We?ve got people on the ground doing flora and fauna surveys and alongside the Feasibility Study we?re also initiating our EPA approvals and our mining agreements with our traditional surface owners.  This is a bit unusual, because normally what you do is your Scoping Study first, then your Feasibility Study and then you look at doing your permitting.  We?re doing as much as we can concurrently so that we can achieve the milestones that we?ve projected.

 

The key milestones for us under the Feasibility Study really are securing those permits.  They?ll be the key things that will determine when we can push the button on the project.  Of course, the feasibility study also all depends on the extensive resource drilling currently under way and should all be completed ahead of delivering our Feasibility Study during the first half of next calendar year.

 

corporatefile.com.au

You have forecast a cash operating cost (including transportation) of A$42/tonne.  Are you confident this can be achieved over the life of the project?  How will you manage costs going forward?  What about when possible future resource expansions mean trucking distances to the gate increase?

 

MD Mike Young

The forecast operating cost is like a mine cost.  It varies year on year, depending on which pit is being mined, but we?re pretty confident we can achieve that over the life of the project and we believe that we?ve built in enough of a buffer to absorb things like higher fuel prices.  As far as possible future expansions go, the furthest distance from the plant would only be around four or five kilometres, so really the incremental cost increase on the trucking distances would be minimal. 

 

corporatefile.com.au

The scoping study outlined a project capital cost estimate of A$85 million.  What are your funding options?  Does this include any contingency for additional ore processing capacity above the planned 3-5 Mtpa operation?

 

MD Mike Young

The current design assumes a starting throughput of 3 Mtpa moving up to 5 Mtpa reasonably quickly.  We?ve designed a plant that could comfortably do 6 Mtpa, and with minimal adjustment could possibly go as high as 8 Mtpa.  

 

Whilst the most likely finding scenario would be a combination of equity and debt, we are currently reviewing all our capital funding options. I?d like to emphasise that we have had no shortage of willing participants to assist us to that end.

 

corporatefile.com.au

The Company recently commenced a new drilling program at the Nullagine Project to in-fill and upgrade the current Inferred Resource 28Mt at 57.4% Fe at the Outcamp Well and Coongan Well deposits within the Bonnie Creek Channel Iron Deposit.  You are also targeting a further 15-25Mt of DSO grade ore (55-58% Fe) at the adjacent Warrigal Well, Bonnie Creek East, and Dandy Well prospects.  What progress have you made on this?  When will you be in a position to provide a revised resource statement?

 

MD Mike Young

The drilling is going very well and we?ve now got two track mounted rigs on site doing 200+ metres a day each.  Track-mounted rigs also allow us to move quickly around without excessive earth works, which is important from an environmental and heritage stand point.  We?ve finished the indicated drill out at Coongan Well and we?re waiting on those results.  We?re then going to move up to Warrigal Well and Bonnie Creek East, and finally drill Dandy Well off in the next few months.

 

As far as a revised resource statement goes, we?d be looking to do that at the second half of this year, most likely during the fourth quarter.  It?s not something we want to rush; we want to make sure we?ve got the geology right, as there?s going to be a lot of data to go through.  We?re also doing some test work just to give us an indication of what infill drilling we need to give us some portion of a Measured Resource.

 

corporatefile.com.au

Fortescue has provided BC Iron with a location for train loading at its proposed Christmas Creek operations.  What commitment has Fortescue made to the construction of the rail facilities for BC Iron?  Will the completion of this infrastructure link coincide with first expected DSO production from Bonnie Creek?  When do you expect to conclude a Commercial Agreement with Fortescue?

 

MD Mike Young

Before Fortescue can construct an extension of the The Pilbara Infrastructure (TPI) railway to Christmas Creek it needs to go through the procedures set out in the State Agreement.  While some requests and been made and approval has been given, a more detailed proposal has been submitted that includes provision for a loading spur that will be to accommodate not just BC Iron?s iron ore but any third party ore.  Fortescue has scheduled commencement of production from Christmas Creek for the end of calendar 2009, however the railway to Christmas Creek should be completed long before then.  The other critical item is the ability of the Port Hedland port to handle the additional material and again, we expect TPI to have these issues sorted by 2009.

 

Fortescue has not yet finalised the designs for it mining operation at Christmas Creek and a Commercial Agreement needs to be framed in the context of what is actually going to be constructed at the minesite as well as how ore could be efficiently handled through the port?s facilities.  Once the design for Fortescue?s expansion is finalised a Commercial Agreement can be negotiated, which is likely to be in the next few months.

 

corporatefile.com.au

Amidst record iron ore prices, the world?s major producers all have significant expansions planned.  If these proceed, is China equipped to process this increased material?  Is there a risk of oversupply and a possible downward pressure on future contract prices?  What are the options for BC Iron?s product?

 

MD Mike Young

I?ll answer the last question first.  We?ve had several meetings with trading houses who basically act between buyers and sellers.  As far as options for our product go, we would be targeting medium-sized steel mills in China and preferentially, the more modern ones.  We would look to set up commercial arrangements with those mills that are looking for guaranteed quality and quantity and then we would basically deliver into that niche market.  There exists a significant production opportunity in China for our size and type of material and those are the mill relationships we?ll be pursuing.  This will be critical for us to realise maximum value for our material.

 

All the signs are that China?s domestic consumption will continue to grow. While supply will also increase in an attempt to match this demand, we believe that establishing relationships and delivering our product into this niche market will assist to buffer us against any potential oversupply.

 

corporatefile.com.au

This announcement was seen as a significant milestone for BC Iron.  Can you explain the market?s reaction following the announcement?

 

MD Mike Young

Obviously, the broader volatility in the market has impacted the resources sector as a whole and we have been caught up in that. 

 

The completed Scoping Study has shown the fundamentals of the Nullagine project are excellent and we expect this to be reinforced through the Feasibility Study and supported by our ongoing drilling efforts. Also, we are working hard on our infrastructure solutions through negotiations with FMG but also through our continued involvement in the North West Iron Ore Alliance.  Based on our current projections, there is also significant opportunity to improve margins as the projects expands and matures. 

 

We recognise that there are a number of challenges for us ahead and we are ready to face them head on.

 

corporatefile.com.au

Thank you Mike.


 

For further information on BC Iron Limited please visit www.bciron.com.au or call Mike Young on (08) 9324 3200.

 

For previous Open Briefings by BC Iron Limited, or to receive future Open Briefings by email, please visit www.corporatefile.com.au.

 

DISCLAIMER: Corporate File Pty Ltd has taken reasonable care in publishing the information contained in this Open Briefing?.  It is information given in a summary form and does not purport to be complete.  The information contained is not intended to be used as the basis for making any investment decision and you are solely responsible for any use you choose to make of the information.  We strongly advise that you seek independent professional advice before making any investment decisions.  Corporate File Pty Ltd is not responsible for any consequences of the use you make of the information, including any loss or damage you or a third party might suffer as a result of that use.

 

For more information on the Mineral Resource Estimate, please refer to BC Iron?s release to the ASX dated 31 March, 2008.

 

The information relating to the terms ?exploration target?, ?iron ore?, ?economic pit shell? and ?direct shipping ore? should not be misunderstood or misconstrued as an estimate of Mineral Resources and Reserves as defined by the JORC Code (2004) and therefore the terms have not been used in this context.  It is uncertain if further exploration or feasibility study will result in the determination of a Mineral Resource or Mining Reserve.

 

This release may include forward-looking statements.  These forward-looking statements are based on management?s expectations and beliefs concerning future events.  Forward-looking statements are necessarily subject to risks, uncertainties and other factors, many of which are outside the control of BC Iron Limited that could cause actual results to differ materially from such statements.  BC Iron Limited makes no undertaking to subsequently update or revise the forward-looking statements made in this release to reflect events or circumstances after the date of this release.

 

 

READ CORPORATE
Public Relations Corporate Communications
T: (+61-8) 9388-1474 | F: (+61-8) 9388-1472 | E: info@readcorporate.com.au | Web: www.readcorporate.com.au 

PLEASE NOTE:

This e-mail and any attachments may contain confidential and/or privileged material and is for the intended addressee(s) only. If you are not an intended addressee, you must not use, copy, retain, disclose or distribute this information. Please notify the sender immediately by return e-mail and delete the message from your system. If you believe that this message constitutes a Commercial Electronic Message (CEM) under the Spam Act 2003 and you wish to unsubscribe please contact the originator of this message with the subject line of unsubscribe.

Note: Virus scanning is carried out on all incoming and outgoing email, but cannot be guaranteed to be timely, secure, error or virus-free. To protect against computer viruses, e-mail programs may prevent sending or receiving certain types of file attachments. If you are having problems please check your e-mail security settings to determine how attachments are handled.

 

BC Iron Limited

EN DÉVELOPPEMENT
CODE : BCI.AX
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

BC Iron est une société développant des projet miniers basée en Australie.

BC Iron est en développement de projets de fer en Australie.

Son principal projet en développement est NULLAGINE IRON en Australie.

BC Iron est cotée en Australie et en Allemagne. Sa capitalisation boursière aujourd'hui est 88,3 millions AU$ (58,1 millions US$, 54,3 millions €).

La valeur de son action a atteint son plus haut niveau récent le 07 mars 2014 à 4,87 AU$, et son plus bas niveau récent le 05 février 2016 à 0,08 AU$.

BC Iron possède 392 529 984 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Dans les médias de BC Iron Limited
01/03/2017BC Iron tries its luck in the potash industry
27/11/2014Heads roll as BC Iron forced to cut costs amid weakest price...
Rapports annuels de BC Iron Limited
I Annual Report To Shareholders 2012
Financements de BC Iron Limited
15/04/2011Regent Pacific Re-Instates Financing for Scheme of Arrangeme...
Nominations de BC Iron Limited
22/09/2016Appointment of Managing Director (2 pages)
15/03/2013Appoints New Managing Director
23/09/2011Director Appointment
Projets de BC Iron Limited
25/05/2012Achieves 5MTPA Production Milestone
02/04/2012Increases Mineral Resource at Nullagine JV - 30 March 2012
11/05/2011Presenting At The RIU Sydney Resources Round-up
09/04/2010Moves Closer To Production After Signing Key Native Title Mi...
17/12/2009(Nullagine Iron)Nullagine Iron Ore Jv - First Project Funding Installment Re...
14/12/2009(Nullagine Iron)BCI And FMG Confirm Move Into Development Of Nullagine Proje...
10/11/2009(Nullagine Iron)Nullagine JV Secures US$50 Million Project Finance
16/10/2009(Nullagine Iron)Trial Mining Supports Key Technical Aspects Of Nullagine Iro...
17/09/2009(Nullagine Iron)Commences Trial Mining at the Nullagine Iron Ore Project
24/08/2009(Nullagine Iron)Formally Enters into Nullagine JV with FMG
03/07/2009(Nullagine Iron)Board Approves Development of Nullagine Iron Ore Project
07/01/2009(Nullagine Iron)Increases DSO Resource by 64% to 46Mt, Total CID Resource 80...
30/09/2008(Nullagine Iron)Infill Drilling Completed at Nullagine Iron Ore Project
01/09/2008(Nullagine Iron)In-Fill Drilling Results Confirm Direct Shipping Resource Qu...
11/07/2008Open BriefingR - MD on Feasibility Study & Future Plans
01/07/2008(Nullagine Iron)Commits to Nullagine Feasibility Study Following Positive Sc...
31/03/2008(Nullagine Iron)Delivers Maiden 47 Million Tonne Iron Ore Resource at Nullag...
Communiqués de Presse de BC Iron Limited
14/09/2016Company Update
01/08/2016FY16 Full Year Results Release (6 pages)
01/08/2016Appendix 4E and FY16 Financial Report (61 pages)
29/07/2016Quarterly Activities Report (4 pages)
05/07/2016Response to ASX Price and Volume Query (4 pages)
27/06/2016Settlement of BC Iron Litigation
26/06/2016WTP: Settlement of BC Iron Litigation (1 pages)
24/06/2016Watpac Settlement (2 pages)
20/05/2016BCI: Iron Valley Update
20/05/2016Iron Valley Update (2 pages)
18/05/2016Management Changes (3 pages)
29/04/2016Update on litigation against Watpac (2 pages)
21/04/2016Quarterly Activities Report (7 pages)
28/01/2016Quarterly Activities Report (8 pages)
31/12/2015Appendix 3B - expiry of performance rights (12 pages)
24/12/2015Commencement of litigation against Watpac (2 pages)
22/12/2015NJV Contract Update (2 pages)
22/12/2015WTP:Update on Dispute with BC Iron - Nullagine Iron Ore Prjt...
27/11/2015Appendix 3B (13 pages)
27/11/2015Change of Director's Interest Notice - M Ball (2 pages)
26/10/2015Variation to NJV Rail and Port Tariff (3 pages)
23/10/2015NJV Awards Road Haulage Contract (2 pages)
21/10/2015Quarterly Activities Report (7 pages)
06/10/2015Managing Director Employment Terms (2 pages)
16/09/2015Change of Director's Interest Notice - M Ball (2 pages)
03/09/2015S&P DJ Indices Announces September Quarterly Rebalance (4 pa...
31/08/2015Correction to Underlying Net Loss After Tax (2 pages)
31/08/2015Updated FY15 Annual Report to shareholders (96 pages)
28/08/2015Company Secretary Resignation - A Bird (2 pages)
26/08/2015FY15 Full Year Results Presentation (24 pages)
26/08/2015FY15 Annual Report and Appendix 4E (97 pages)
26/08/2015Appendix 4G (14 pages)
25/08/2015NJV Ore Reserves and Mineral Resources (21 pages)
23/07/2015Quarterly Activities Report - June 2015 Quarter (8 pages)
11/06/2015Repayment of Term Loan Facility (2 pages)
23/04/2015NJV Warrigal Hub Contract Update 23.04.15
23/04/2015NJV Warrigal Hub Contract Update (2 pages)
22/04/2015BC Iron March 2015 Quarterly Activities Report (8 pages)
09/04/2015March 2015 Quarter Update (2 pages)
02/04/2015NJV Contracting Strategy Update (2 pages)
24/03/2015Warrigal Hub Contract Award (3 pages)
24/03/2015Mines & Money Presentation (20 pages)
09/03/2015Presentation (20 pages)
05/03/2015S&P DJ Indices Announces March Quarterly Review (9 pages)
06/09/2013Latest Headlines and New Issue Alert: Sibanye production rec...
22/10/2012September 2012 Quarterly Activities Report
21/08/2012I Forms Iron ore Stratigic Alliance in Brazil
16/08/2012I ASX Announcement - Mineral Resource and Ore Reserve 30 Jun...
05/07/2012I Achieves All Operational Guidance FY12
17/04/2012Quarterly Report for the period ending 31 March 2012
29/02/2012Half Year Results - December 2011 & Company Update
24/10/2011Quarterly Report for the period ending 30 September 2011
23/09/2011September Company Update
11/08/2011Operations Update
29/04/2010Quarterly Activities Report For The Period Ending March 31, ...
15/04/2010Welcomes New Institutional Investors
30/10/2009Quarterly Activities Report For The Period Ending 30 Septemb...
29/07/2009June 2009 Quarterly Report
19/06/2009Announces $22M Capital Raising
05/06/2009Seals Company-Making Deal with FMG
28/05/2009North West Iron Ore Alliance Congratulates BC Iron on Landma...
28/05/2009secures infrastructure deal with The Fortescue Metals Group ...
04/03/2009Open Briefing - MD on Off-take Agreement and Recent Progress
11/02/2009Secures Landmark Long-Term Off-Take Agreement for Nullagine ...
28/01/2009Quarterly Activities Report December 2008
08/01/2009Carmichael Quick Note
27/11/2008horses for courses
02/10/2008Practical Parenting Support for Families from Hedland's Juni...
08/09/2008Gearing Up For The New Iron Age
08/08/2008Plans in the Fire
06/08/2008New Access Rules for Infrastructure
06/08/2008Sunday Times Article - Hot Stock
31/07/2008June 2008 Quarterly Activities Report
29/07/2008Diggers and Dealers
24/07/2008Ocean Equities Ltd - Iron Ore Sector Update
14/07/2008Comment On Take Over Speculation
20/06/2008NCC Declaration
16/06/2008Shinier Than Gold in Stock Market
30/04/2008 Quarterly Activities Report
21/04/2008 Open BriefingR. MD Explains Nullagine Resource Upgrade.
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (BCI.AX)BERLIN (BC3.BE)
0,225-2.17%0,097+2.11%
AUSTRALIA
AU$ 0,225
29/04 15:42 -0,010
-2,17%
Cours préc. Ouverture
0,230 0,230
Bas haut
0,225 0,230
Année b/h Var. YTD
0,220 -  0,320 -19,64%
52 sem. b/h var. 52 sem.
0,205 -  0,320 -2,17%
Volume var. 1 mois
76 796 -4,26%
24hGold TrendPower© : 27
Produit
Développe Iron
Recherche
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
2024-18,18%
20231,85%0,300,20
2022-37,21%0,480,21
202143,33%0,620,29
202076,47%0,310,10
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,66 AU$-0,71%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,26 US$+0,00%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,52 GBX-0,76%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,63 CA$-0,38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,41 CA$+1,11%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 AU$+2,38%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,88 CA$+0,00%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
53,01 US$+0,57%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :