Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Troy Resources NL

Publié le 13 juillet 2016

Operational Update

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   9/11 |

Operational Update

9fb58de9-3bf5-4b54-bcbd-f25b15b6b16b.pdf

13 July 2016

TROY OPERATIONAL UPDATE

Troy Resources Limited (ASX: TRY) provides the following update on activities at its Karouni Gold Operation in Guyana ahead of the release of its next Quarterly Report for the period ending 30 June 2016 later this month.

Operational

Progress advancing the Smarts pit into fresh rock has been slower than anticipated. This is due to the prolonged severity of the wet season and the requirement to cordon off sections of the pit to allow for the commencement of an RC grade control drilling program. This program was commenced to test the continuity of North-South vein structures within the deposit, improve grade control information and formulate ongoing mining sequences.

Disruptions to the mill lubrication system during May and June, as well as ongoing difficulties with the processing characteristics of the Saprolite clay material that will not be fully resolved until the Smarts pit is in fresh rock, reduced the plant throughput rate during the June quarter. New "made to order" pumps and parts for the worn components in the lubrication unit, are currently on track to be delivered in July and preparations have been made by the on-site maintenance team to ensure that the work to refurbish the lubrication system will not result in any significant downtime for the mill.

The impact of these factors on the Karouni operation during the June quarter is reflected in the following performance figures:

Karouni Preliminary Production Data for June 2016 Quarter

June 2016 Quarter

YTD FY 2016

Tonnes processed (t)

161,764

356,772

Grade (g/t)

3.04

3.37

Recovery (%)

92.0

90.0

Gold produced (oz.)

14,553

34,748

Whilst every effort will be made to make up for this situation in the second half of the year, the increase in production that had been expected over the course of the June Quarter, prior to these disruptions, will now only take effect in the September Quarter. This is expected to have an impact on guidance for CY2016, the extent of which is currently being established through the preparation of revised schedules to incorporate the current status of mining and processing activities.

Exploration

Further geological understanding of the orebody from grade control drilling and progressive mining, has identified the presence of additional quantities of lower grade ore that was largely uncaptured in the original drilling programme. These lower grade ore zones occur as disseminated mineralisation up to several metres away from the North-South veins. The inclusion of these new ore zones in the block model will increase the overall ore tonnes mined and therefore ounces per vertical metre, albeit resulting in a reduced overall grade for the tonnes recovered and processed.

During June, a Reverse Circulation (RC) drilling program commenced from the floor of the Smarts Stage 2 Pit. A total of 23 holes (2,081m) of RC drilling were completed to test this area on drill grid of about 30m x 10m spacing.

This drilling targeted the area between the hanging-wall and footwall Shears, where the gold bearing veins are preferentially developed within the mafic units. This program targeted North-South striking vein orientations but also intersected a number of NW-SE striking veins.

The drilling highlighted the fact that one of the key controls is the host lithology. In the andesite unit there is a limited alteration halo whereas in the basalt unit there is a more diffuse pyritic alteration adjacent to the veins which is readily apparent in the drill chips.

The holes pushed beyond the bounding shear have confirmed the fact that the gold mineralisation is entirely confined to the area bounded by the main NW-SE striking Smarts Shear.

The drilling has also confirmed that the N-S Veins are often "cm" scale widths and are widely spaced over the strike length of the pit. Although narrow widths, the N-S veins intercepted have visible gold and high gold grades. To date, partial assay results have been received for 10 of the 23 holes drilled. Significant results include (see Table 1, JORC Section 1 & Section 2 Tables and Figure 1: Geology & Drill Collar Plan):

1m @ 132.5g/t from 21m

  • 2m @ 53.0g/t from 3m

    2m @ 23.1g/t from 30m

    7m @ 18.2g/t from 33m

    3m @ 18.9g/t from 24m

  • 1m @ 17.4g/t from 1m

    4m @ 13.9g/t from 20m

    2m @ 11.7g/t from 20m

  • 5m @ 7.8g/t from 35m

  • 9m @ 6.5g/t from 3m

  • 8m @ 4.9 g/t from 28m

  • 8m @ 4.8 g/t from 62m

  • 3m @ 3.8g/t from 6m

    10m @ 3.5g/t from 69m

  • 5m @ 3.2g/t from 16m

The program has confirmed the N-S Veins are continuous at shallow depths below the current planned pit floor. Fourteen of 29 total downhole intercepts were reported below the current design pit. Intersections are reported as downhole widths with true widths about 60% to 70% of the reported width. Once all assays are received, this infill drilling data will allow for a more robust Grade Control model to be constructed to aid in the mine planning for the remaining benches in the pit. An investigation of the potential of the N-S Veins at depth is likely to be warranted which will require a Diamond Core follow-up program.

Figure 1: Smarts Stage #2 Pit Geology & Drill Collar Plan

Following completion of the Smarts Stage 2 drilling program in late June, the rig is currently completing a 40 hole, 1,880m program in the Smarts Stage 4 pit area which is targeted at delineating gold mineralisation associated with the bounding NW-SE striking Smarts Shears as well as three N-S striking veins highlighted in earlier drilling.

An additional RC rig has arrived in Guyana from Brazil to enable dedicated grade control drilling to be scheduled into the mining sequence. The rig will also assist with extensional drilling around the pits.

Investec

Following a scheduled repayment of US$3.75 million to Investec at the end of June, the amount owing under the Investec Facility is now US$39.2 million, with the Company having repaid US$32.4 million (1) in the last 12 months.

(1) The amount outstanding under the Investec Facility at 30 June 2015 was A$100 million or US$71.57 million if converted at the A$/US$ rate of 0.7157 (being the rate used to convert the Facility from A$ to US$ on 20 May 2016).

Personnel

Following the staged divestment of the Company's interest in Casposo in Argentina and the closure of Andorinhas in Brazil, Troy's Chief Operating Officer in South America, Andrew Storrie, has decided to leave the Company. Andrew joined Troy in 2009 and played a key role in achieving reliable and consistent performance at both of these challenging operations and the Board wishes him well in his future endeavours.

ENDS

For further information please contact:

Martin Purvis Stacey Apostolou

CEO Company Secretary

Troy Resources Limited Troy Resources Limited

T: (61 8) 9481 1277 T: (61 8) 9481 1277‌

E: [email protected] E: [email protected]

Competent Person's Statement

The information in this presentation that relates to Exploration Results, Mineral Resources or Ore Reserves for the Karouni project is based on, and fairly represents, information and supporting documentation prepared by Mr Peter J Doyle, Vice President Exploration and Business Development of Troy, a Competent Person who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Doyle has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Mr Doyle consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. Mr Doyle is a full time employee of Troy.

The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements relating to drill results, mineral resource estimates or studies and that all material assumptions and technical parameters underpinning the drill results and estimates in the relevant market announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented here have not been materially modified from the original market announcements.

Lire la suite de l'article sur www.publicnow.com

Troy Resources NL

PRODUCTEUR
CODE : TRY.AX
ISIN : AU000000TRY7
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Troy Res. est une société de production minière d'or basée en Australie.

Troy Res. est productrice d'or, d'argent au Bresil, en Australie et en Argentine, en développement de projets d'or en Australie, et détient divers projets d'exploration au Bresil, en Australie, en Argentine et en Finlande.

Ses principaux projets en production sont GOIAS VELHO / SERTAO MINE et ANDORINHAS au Bresil, BULCHINA MINE, CORNISHMAN & DOUBLE O, CORNISHMAN MINE, LORD NELSON et LORD HENRY en Australie et CASPOSO en Argentine, ses principaux projets en développement sont SANDSTONE - LORD NELSON et SERTAO en Australie et ses principaux projets en exploration sont DALY RIVER, THREE RIVERS, TWO MILE, THREE RIVERS et TROJAN JV en Australie et OIJARVI en Finlande.

Troy Res. est cotée au Canada, en Australie et en Allemagne. Sa capitalisation boursière aujourd'hui est 13,7 millions AU$ (9,9 millions US$, 8,7 millions €).

La valeur de son action a atteint son plus haut niveau récent le 05 octobre 2012 à 5,02 AU$, et son plus bas niveau récent le 01 septembre 2023 à 0,03 AU$.

Troy Res. possède 456 600 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Présentations des Compagnies de Troy Resources NL
23/08/2016Investor Presentation
09/05/2016Gold Tour Presentation
27/07/2011Company Presentation-Investor Update
Rapports annuels de Troy Resources NL
: 2012 Annual Report to Shareholders
Annual Report 2011
Financements de Troy Resources NL
09/04/2013Provides Funding to Azimuth Pursuant to Convertible Note Fac...
Attributions d'options de Troy Resources NL
10/01/2012Payment of Dividend and Issuance of Shares Under the Troy Di...
Nominations de Troy Resources NL
29/07/2016Appointment of Independent Non-Executive Director
29/08/2013: Change to Directors
05/02/2013: Appointment of Company Secretary
14/03/2011Resignation of Company Director
01/02/2010Appointment of Mr David Dix
Rapports Financiers de Troy Resources NL
29/07/2016Quarterly Activities Report - June 2016
28/04/2016Quarterly Activities Report - March 2016
27/09/2012: Full Year Statutory Financial Statements-30 June 2012
Projets de Troy Resources NL
21/05/2014Australian company to open gold mine in Guyana
29/08/2011Strong Production Growth Returns Troy to Profit
27/04/2011(Kamila)Follow-up Drilling at Kamila SE Extension Zone Produces Furt...
20/03/2011(Casposo)- High Grade Drill Intercept
17/05/2010(Casposo) NI-43101 Technical Report Casposo Project San Juan, Argenti...
11/05/2010(Casposo)Casposo financing complete
06/05/2010(Casposo)Casposo updated mining reserve and production schedule
08/03/2010(Sandstone - Lord Nelson)New Nickel Sulphide Discovery at Sandstone JV
23/02/2010(Andorinhas)Andorinhas Robbery
27/01/2010(Casposo)Casposo Update
09/10/2009(Casposo)Casposo Project Update
14/09/2009(Casposo)NI43-101 Updated Technical Reports for Casposo & Sandstone
18/08/2009(Casposo)Updated Mineral Reserves and Resources
31/07/2009(Two Mile)New Inferred Resource Two Mile Hill Prospect Sandstone WA
29/07/2009(Casposo)Significant (32%) Increase in Casposo
16/07/2009(Two Mile)High Grade Results at Two Mile Hill Prospect
12/06/2009(Casposo)Files technical report for the Casposo deposit
09/09/2008(Andorinhas)Andorinhas Iron Ore Resource
04/08/2008(Andorinhas)Troy Resources NL - Andorinhas Iron Drill Results
25/07/2008(Andorinhas)Colluvial Iron Ore Study Update - Andorinhas Project Brazil
Communiqués de Presse de Troy Resources NL
23/09/2016Becoming a substantial holder from CBA
13/07/2016Operational Update
27/06/2016Director Appointment/Resignation
27/05/2016Karouni Operational Update
13/05/2016Ceasing to be a substantial holder
04/05/2016 Troy Restructures Investec Facility
03/05/2016Troy Restructures Investec Facility
01/02/2016Change of Director's Interest Notices
01/02/2016Change of Director's Interest Notices
28/01/2016Appendix 3B and Cleansing Notice
28/01/2016Results of Meeting
28/01/2016Quarterly Activities Report - December 2015
28/12/2015Change in substantial holding
28/12/2015Change in substantial holding
24/12/2015Ceasing to be a substantial holder
23/12/2015Appendix 3B and Cleansing Notice
23/12/2015Notice of General Meeting/Proxy Form
17/12/2015Troy Announces Completion of $10 million Placement
17/12/2015Capital Raising Investor Presentation
17/12/2015Capital Raising Investor Presentation
15/12/2015Trading Halt
15/12/2015Trading Halt
30/10/2015Quarterly Activities Report - September 2015 (Relodge)
30/10/2015Quarterly Activities Report - September 2015
29/10/2015Change in substantial holding
26/10/2015Commissioning Complete at Karouni Gold Project
26/10/2015Commissioning Complete at Karouni Gold Project
23/10/2015Corporate Governance and Appendix 4G
23/10/2015Annual Report to shareholders
23/10/2015Notice of Annual General Meeting/Proxy Form
23/10/2015Annual Report to shareholders
23/10/2015Notice of Annual General Meeting/Proxy Form
25/09/2015Full Year Statutory Accounts - 30 June 2015
25/09/2015Full Year Statutory Accounts - 30 June 2015
14/09/2015TRY to Convert Currency of Loan Facility and Resets Hedging
10/09/2015Change to Securities
10/09/2015Change to Securities
31/08/2015Mineral Resources and Ore Reserves Update
31/08/2015Mineral Resources and Ore Reserves Update
31/08/2015Appendix 4E - Preliminary Final Report - 30 June 2015
31/08/2015Appendix 4E - Preliminary Final Report - 30 June 2015
31/08/20152015 Financial Year Results Announcement
13/08/2015Appendix 3Y - Change of Director's Interest Notice - Jones
13/08/2015Appendix 3Y - Change of Director's Interest Notice - Jones
04/08/2015Diggers and Dealers 2015 Presentation
04/08/2015Diggers and Dealers 2015 Presentation
31/07/2015Quarterly Activities Report - June 2015
31/07/2015Quarterly Activities Report - June 2015
22/07/2015Change in substantial holding
14/07/2015Troy Chairman Leave of Absence
10/07/2015Karouni Gold Project - Operational Update
09/07/2015Becoming a substantial holder
15/06/2015Appendix 3Y - Change of Director's Interest Notice - Jones
09/06/2015Successful Completion of Placement and Share Purchase Plan
09/06/2015Appendix 3B and Cleansing Notice
04/06/2015Results of General Meeting
27/04/2015Trading Halt
24/04/2015Quarterly Activities Report - March 2015
20/04/2015Appendix 3Z - Final Director's Interest Notice - Harvey
20/04/2015Resignation of Director
20/04/2015Resignation of Director
14/04/2015UK Investor Update Presentation - April 2015
14/04/2015UK Investor Update Presentation - April 2015
14/04/2015Voluntary Delisting from Toronto Stock Exchange
14/04/2015: Voluntary Delisting From Toronto Stock Exchange
25/03/2015Notice of Initial Substantial Holder for ALY
25/03/2015Half - Year Ended 31 December 2014 Financial Results
25/03/2015Half - Year Report for the Period Ended 31 December 2014
25/03/2015ALY: Purchase of Reserve Payment from Troy
25/03/2015S&P DJ Indices Announces March Quarterly Review
25/03/2015Appendix 3Y - Change of Director's Interest Notice - Parish
25/03/2015Change in substantial holding
25/03/2015Ceasing to be a Substantial Holder for ALY
25/03/2015Half - Year Report for the Period Ended 31 December 2014
25/03/2015ALY: Purchase of Reserve Payment from Troy
25/03/2015S&P DJ Indices Announces March Quarterly Review
25/03/2015Change in substantial holding
25/03/2015Ceasing to be a Substantial Holder for ALY
20/02/2015: Investor Update Presentation, February 2015
18/12/2014Appendix 3B - Issue of Share Appreciation Rights
18/12/2014Appendix 3Y - Change of Director's Interest Notice - Purvis
20/10/2014Troy Signs Minerals Agreement for the Karouni Gold Project
14/10/2014The Dollar Rally: Where Will The Buck Stop?
25/02/2014Troy Resources to Raise Up to A$28 Million by Way of Placeme...
25/02/2014Troy to Raise Up to A$28 Million by Way of Placement and Up ...
23/02/2014Troy Resources Limited: Half Year Ended 31 December 2013 Fin...
20/02/2014Troy Resources Limited: RIU Explorers Conference Presentatio...
17/02/2014Troy Reaches Agreement to Sell Its 70% Interest in the Serta...
02/02/2014Troy Resources Limited: Investor Update, February 2014
02/02/2014Troy Resources Limited: Exceptional Channel Sample Results a...
31/01/2014Troy Resources Limited: Quarterly Activities Report December...
29/10/2013Presentation-ASX Small to Mid Caps
25/10/2013-Notice of 2013 Annual General Meeting and Explanatory Memor...
26/09/2013Full Year Statutory Accounts-30 June 2013
16/09/2013Investor Presentations-September 2013
28/08/2013: Completion of Compulsory Acquisition of Ordinary Shares in...
06/08/2013Presentation-Diggers & Dealers 2013
29/07/2013: Quarterly Activities Report June 2013
29/07/2013: Quarterly Activities Report June 2013
09/07/2013Corporate and Operational Update-BRR Webcast
27/06/2013Cuts Costs in Decisive Response to Price Volatility
24/06/2013Takeover Bid by Troy Resources Limited for Azimuth Resources...
17/06/2013Takeover Bid By Troy Resources Limited for Azimuth Resources...
07/06/2013Takeover Bid by Troy Resources Limited for Azimuth Resources...
24/05/2013: Institutional Acceptance Facility and First Supplementary ...
08/05/2013: Change to Securities
30/04/2013on Progress of Troy Takeover Offer for Azimuth
22/04/2013Secures A$40 Million Funding from Investec
03/04/2013and Azimith Resources CEOs Discuss Proposed Takeover-BRR Web...
28/03/2013: Media Conference Call Recording
25/03/2013(Kamila)Casposo Exploration Drilling Update Kamila Southeast Trend I...
30/01/2013: Quarterly Report on Activities December 2012
25/10/2012: Notice of 2012 Annual General Meeting & Proxy Form
16/10/2012Presentation: ASX Small to Mid Caps Asia
14/08/2012Announces Agreement to Sell the Sandstone Property to Southe...
08/08/2012Presentation: Diggers & Dealers
27/07/2012: Quarterly Report on Activities June 2012
12/07/2012(Casposo): Dr. J.W. Hedenquist Casposo Site Visit and Report
25/06/2012: Presentation & Webcast-The Gold Coast Resources Showcase
20/06/2012(Casposo): Reserve and Mine Plan Updated Technical Report (NI 43-101)...
30/05/2012(Casposo): Casposo Mineral Reserve Update Gold Equivalent Production ...
13/04/2012to Be Included in the S&P ASX 200 Index
04/04/2012: Company Presentation
24/02/2012(Casposo)Doubles Production & Revenue as Low Cost Casposo Hits its St...
08/02/2012: Revised December 2011 Quarterly Report
30/01/2012: Quarterly Report on Activities December 2011
09/01/2012ASX Announcement - ASIC Approves Change of Company Type and ...
15/12/2011New Corporate Office and Registered Address
12/10/2011(Casposo)Resource Update Report Released for Casposo Project San Juan...
04/10/2011(Casposo)Casposo Achieves Nameplate Throughput
29/08/2011(Kamila): Initial Resource Estimate Kamila Southeast Discovery at Ca...
24/08/2011Introduces A Shareholder Dividend Re-Investment Plan
03/08/2011Public Announcement Media Speculation
02/08/2011(Kamila)Kamila Southeast Target Drilling Update-More High Grade Resu...
20/07/2011(Casposo)ASX Announcement - High Grade Intercepts Drilling at Casposo...
21/06/2011(Kamila)Kamila Southeast Zone Drilling Continues to Deliver High Gra...
07/06/2011(Casposo)Declares Dividend as Low Cost Casposo Mine Officially Opened
19/05/2011(Kamila)Kamila Southeast Zone Step-Out Drilling Delivers High Grade ...
28/02/2011Half Year Ended December 31, 2010 Financial Results
24/01/2011 Quarterly Report on Activities December 2010
02/08/2010Diggers & Dealers 2010 Company Presentation
29/07/2010Sales of Andorinhas Iron Ore
16/07/2010Initial Inferred Resource Julieta Prospect Casposo Project
30/04/2010Quarterly Report on Activities March 2010
17/03/2010Corporate Update Presentation
10/02/2010Financing Update
04/02/2010Moving to Where the Gold Is
29/01/2010Quarterly Report on Activities December 2009
29/01/2010Aztec Vein Initial Grade Control Drilling - Casposo Project
21/01/2010 Notice of Forfeited Shares Auction
20/01/2010 Sale of Mongolian Assets
14/12/2009Form 604 -Notice of change of interests of substantial holde...
07/12/2009Share Placement and Appendix 3B
04/12/2009Entitlements Issue - Under Subscription
02/12/2009Amended Constitution
09/11/2009Troy Resources NL - Chairman's Letter to Shareholders - EGM ...
05/11/2009Shareholder Letters Re Entitlements Issue
04/11/2009Entitlements Issue 708AA Notice & Appendix 3
04/11/2009Withdrawal of Request for EGM
28/10/2009Quarterly Report on Activities September 2009
02/10/2009Notice of Shareholder Meeting
30/09/2009Full Year Statutory Accounts
25/09/2009CALL ON PARTLY PAID SHARES
27/08/2009Profit of A$16.7 Million and Builds the Foundation for Futur...
10/08/2009Declares 10th Consecutive Fully Franked Dividend
30/07/2009Quarterly Report on Activities June 2009
09/02/2009Quarterly Report and Operations Update - Audio Broadcast
23/02/2009Half Year Report
03/02/2009ASX Release - Voluntary Annual Information Form
28/01/2009Quarterly Report
20/01/2009ASX Announcement
27/11/2008AGM Results November 2008
26/11/2008Resignation of Non-Executive Director T D McKeith
13/11/2008ASX Announcement
30/09/2008ASX Announcement
29/08/2008ASX Announcement
31/07/2008Quarterly Report
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (TRY.AX)TORONTO (TRY.TO)
0,030+0.00%0,430+1.18%
AUSTRALIA
AU$ 0,030
01/09 11:00 -
0%
Cours préc. Ouverture
0,030 0,030
Bas haut
0,030 0,030
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
0,030 -  0,030 -%
Volume var. 1 mois
0 -%
24hGold TrendPower© : -26
Produit Gold - Silver
Développe Gold
Recherche Copper - Gold - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 24/11/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
20240,00%
20230,00%0,030,03
2022-18,92%0,040,03
2021-62,63%0,100,03
20208,79%0,200,06
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,82 AU$+1,69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,04 US$+1,38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,56 GBX+3,70%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,52 CA$+0,00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
15,92 CA$-0,81%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+2,13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,19 AU$-7,32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,90 CA$+1,60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,12 US$+1,34%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,03 AU$+0,00%Trend Power :