| | Publié le 12 février 2013 | Production Report for the 12 months ended 31 December 2012 |
|
Article
|
Commentaires
|
Commenter
|
Notation
|
♥
Suivre la société
|
|
Zug, 12 February 2013
Production Report for the 12 months ended 31 December 2012
Highlights:
- Record annual thermal coal production resulting from the successful commissioning of the Ravensworth North, Ulan West and Ulan open cut projects in Australia, productivity improvements at Cerrej�n and the continued transition of our South African thermal coal operations into large-scale, low-cost operations;
- Record refined nickel volumes which benefited from the commissioning of Raglan mine�s Kikialik expansion and above capacity ferronickel production from Falcondo;
- A second consecutive year of record Australian zinc production volumes as a result of improved productivity levels;
- On-going de-risking of our capital programme as nine growth projects were successfully commissioned across our commodity portfolio, transforming volumes, costs and asset quality:
- We completed, on schedule, the first stage of the 8 million tonne per annum Ravensworth North thermal coal operation in New South Wales. The second stage, the expansion of the existing coal preparation plant, is on schedule for completion in 2013;
- Operations began at the 1.5 million tonne per annum Ulan open cut thermal coal mine in New South Wales and are on schedule to reach full production in 2013;
- Ernest Henry Mining commenced processing ore in September from Xstrata Copper�s nearby Mount Margaret mine in north-west Queensland, Australia, which will add around 30,000 tonnes of annual copper production to Ernest Henry�s production profile;
- Expansion of the concentrator and associated mine at our Antamina copper/zinc joint venture mine in Peru was successfully commissioned in the first quarter of 2012 and throughput rates are now consistently exceeding the planned 38% capacity increase;
- In September, ore production commenced, over one year ahead of schedule and on budget, at Xstrata Zinc�s high grade Lady Loretta mine in Queensland, Australia. Full-scale commercial mining will begin in mid-2013, delivering at full production an estimated 1.6 million tonnes of ore per annum;
- In early October, Xstrata Alloys commissioned the Tswelopele pelletizing and sintering plant, on time and on budget. The plant will reach full capacity of around 600,000 tonnes per annum of sintered pellets early in 2013;
- In November, Xstrata Copper commenced commercial grade production from our new Antapaccay mine, ahead of its progressive ramp up to nameplate processing capacity of 70,000 tonnes per day in the first half of 2013 and in line with budget. The mine is expected to produce an average of 160,000 tonnes of copper in concentrate per annum, plus gold and silver by-products, in the initial years of its more than 20 year projected life;
- In December, Xstrata Copper commissioned on schedule Lomas Bayas� Lomas II project which will extend the mine life by 16 years at existing production levels of 75,000 tonnes of copper cathodes per annum; and
- First ore was delivered six months ahead of schedule at our 1 million tonnes per annum mine expansion at George Fisher zinc mine.
- Construction was completed on Line 1 at the Koniambo ferronickel operation in New Caledonia. Following the Line 1 furnace heat up during February 2013, we expect to be generating commercial-grade ferronickel by the end of March, in line with our commissioning and ramp up plans. With metal production commencing in 2013, the site is well positioned to deliver the two-year production ramp-up to achieve its nameplate 60,000 tonnes of nickel in ferronickel per annum run rate by the end of 2014.
- We confirmed a definitive estimate of $5.2 billion for Xstrata Copper�s Las Bambas project in southern Peru, reconfirming the project�s status as a world class, Tier 1 copper asset that will deliver substantial value. Las Bambas is now in full construction phase and set to produce 400,000 tonnes of copper per annum from 2015 for at least the first five years of its more than 20 year projected life;
- We approved the $360 million (AUD360 million) Phase 3 expansion of Xstrata Zinc�s McArthur River Mine that will increase annual production to an average of 380,000 tonnes of zinc in conventional concentrate from 2014;
- We achieved further substantial increases in our copper Mineral Resources, mainly due to a significant 19% increase in total Mineral Resources at our Collahuasi joint venture in Chile to 9 billion tonnes; a 20% increase in total Mineral Resources at our El Pach�n project in Argentina to 3.3 billion tonnes; and a 27% increase in total Mineral Resources at our new Antapaccay mine in Peru to over 1 billion tonnes; and
- Xstrata�s shareholders approved the proposed merger between Glencore and Xstrata, subject to the necessary regulatory approvals being received.
Neither the content of the company's website nor the content of any other website accessible from hyperlinks on the company's website is incorporated into, or forms part of, this announcement
Xstrata contacts:
Alison Flynn |
|
Martin Fewings |
Pamela Bell |
|
Caroline Yates |
Notes to editors
About Xstrata plc
We are a major producer of a range of vital commodities used in everything from constructing buildings and delivering electricity, to developing jet engines and mobile phones. We are one of the top five global producers of copper, thermal and metallurgical coal, ferrochrome, zinc and nickel and we also produce silver, lead, platinum, gold, cobalt and vanadium.
Founded in 2002 and headquartered in Switzerland, we operate in over 20 countries and employ over 70,000 people at more than 100 operations and projects around the world. We work in a responsible and sustainable way, with an entrepreneurial spirit and dynamic approach. For more information, visit www.xstrata.com
Copper
Total mined copper production of 747,000 tonnes was 16% lower compared to 2011 as Xstrata Copper transitioned from older, end of life mines to new mines and expansions and addressed production challenges at the Collahuasi joint venture. Our production steadily increased during 2012 as we commissioned and/or ramped up five organic growth projects reaching an annualised production rate of approximately 900,000 tonnes in December 2012 compared to 700,000 tonnes in January 2012.
Copper in concentrate production at Antamina rose by 34%, increasing attributable volumes to 150,800 tonnes compared to 2011 due to increased mill throughput following the successful completion in March of a major capital investment project to expand processing capacity to 130,000 tonnes per day, along with improved grades and recoveries.
At Alumbrera mine, we increased copper in concentrate production by 16% to 135,700 tonnes compared to the previous year, primarily due to higher throughput, head grades and recoveries after a geotechnical event in 2011 restricted access to the pit.
At Lomas Bayas mine, we completed construction and successfully commissioned our Lomas II mine life extension project allowing us to maintain copper production in line with the previous year as ore from the new Fortuna de Cobre pit supplemented declining volumes from the original pit. Lomas II extends the life of Lomas Bayas by a further 16 years to at least 2028 at existing production levels of around 75,000 tonnes per annum of copper cathode.
Planned lower production at the Ernest Henry mine contributed 34,100 tonnes of copper in concentrate in 2012, a reduction of 66% compared to 2011, as the operation transitioned to underground mining following the completion of the open pit in December 2011. During the year, the new underground decline mine continued to ramp up to mining rates of 3 million tonnes per year and the satellite Mount Margaret open pit commenced production in September. Ernest Henry will produce an average of approximately 70,000 tonnes of copper in concentrate per annum from the combined underground mining and Mount Margaret open pit operations.
Production commenced in line with budget and schedule at the new Antapaccay mine in November, with the concentrator plant continuing to rapidly ramp up to its nameplate capacity of 70,000 tonnes per day. The long life Antapaccay mine is scheduled to produce an average of 160,000 tonnes of copper in concentrate per annum for at least its first five years of production and during the year we announced a further 27% increase in total Antapaccay Mineral Resources to over 1 billion tonnes. Antapaccay is replacing production from the adjacent Tintaya mine, where copper production decreased by 51% to 46,800 tonnes in 2012 due to lower grades and pit depletion as it reached the end of its life. Ore mining was completed in the Tintaya open pit by the end of January 2013.
Copper production at Collahuasi decreased by 38% compared to the previous year, due to planned lower grades and recoveries, adverse weather conditions, safety stoppages and an extended ball mill outage. A comprehensive business improvement plan initiated in July 2012 by shareholders was successfully completed by the end of 2012, resulting in more reliable operating performances and a strengthened organisational structure. Annualised production levels are expected to be restored to around 400,000 tonnes of copper per annum (on a 100% basis) in 2013. In February 2013, Collahuasi announced a further increase to Mineral Resources of 19% to 9 billion tonnes at an average grade of 0.81% copper confirming the world-class status of this deposit. Ore Reserves increased by 10% to 3.2 billion tonnes.
Gold production decreased by 19% to 421,600 ounces due to lower grades and the closure of the Ernest Henry open pit mine at the end of 2011 and the final phase of operations at Tintaya.
Total mined, integrated and third party copper cathode production decreased by 3% in 2012 as a result of reduced concentrate production at Ernest Henry for the Townsville refinery and the planned lower processing of oxide ores as Tintaya reached the end of its mine life.
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
Argentina � Alumbrera*
Material mined (t)
Ore mined (t)
Copper head grade (%)
Gold head grade (g/t)
Ore treated (t)
Concentrate produced (t)
Copper in concentrate (t)
Gold in concentrate (oz)
Gold in dor� (oz)
Total gold (oz)
Silver in concentrate (oz)
Silver in dor� (oz)
Total silver (oz) |
97,009,506
31,390,580
0.41
0.40
39,698,984
521,124
135,743
337,826
26,471
364,297
1,483,140
3,633
1,486,773 |
74,428,957
22,226,785
0.40
0.42
38,201,036
446,718
116,698
327,887
28,129
356,016
1,011,298
3,979
1,015,278 |
Australia - Ernest Henry
Material mined (t)
Ore mined (t)
Copper head grade (%)
Gold head grade (g/t)
Ore treated (t)
Concentrate produced (t)
Copper in concentrate (t)
Gold in concentrate (oz)
Silver in concentrate (oz)
Magnetite in concentrate (t) |
17,687,262
3,721,574
0.95
0.34
7,053,595
127,769
34,106
39,898
194,213
496,250 |
11,350,039
9,098,260
1.05
0.51
10,360,819
352,537
100,303
128,701
449,464
498,975 |
Australia - Mount Isa copper mine and smelter
Ore mined (t)
Copper head grade (%)
Ore treated (t)
Concentrate produced from ore (t)
Copper in concentrate from ore (t)
Silver in concentrate (oz)
Concentrate treated � third party (t)
Concentrate treated - integrated� (t)
Total concentrate treated
Anode copper (t) |
6,321,294
2.49
6,305,368
580,025
142,705
723,795
58,979
661,143
720,122
172,664 |
5,873,705
2.73
5,882,967
609,865
148,759
726,100
23,192
917,119
940,311
237,667 |
Australia � Townsville refinery
Anode copper feed� integrated� (t)
Refined copper (t) |
276,287
266,798 |
288,149
276,535 |
Canada � Kidd operations
Ore mined (t)
Copper head grade (%)
Ore treated (t)
Concentrate produced (t)
Copper in concentrate (t)
Zinc concentrate produced (t)
Zinc in concentrate (t)
Silver in concentrate (oz) |
2,260,452
1.59
2,268,672
134,701
34,375
148,451
78,094
2,877,410 |
2,227,223
1.97
2,238,269
162,758
42,322
134,733
71,497
2,602,232 |
Canada � Horne smelter
Concentrate treated � third party (t)
Concentrate treated - integrated� (t)
Total concentrate treated (t)
Anode copper (t) |
351,938
373,707
725,645
194,819 |
351,507
399,576
751,083
187,410 |
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
Canada - CCR Refinery
Anode copper feed - third party (t)
Anode copper feed� integrated� (t)
Refined copper (t) |
62,715
204,157
265,538 |
61,548
203,745
263,967 |
Chile � Collahuasi**
Material mined (t)
Ore mined (t)
Copper grade in ore milled (%)
Ore milled (t)
Concentrate produced (t)
Copper in concentrate (t)
Copper cathode (t)
Silver in concentrate (oz) |
101,474,116
32,734,874
0.76
19,192,172
411,331
107,928
16,195
1,333,992 |
92,563,211
19,905,585
1.02
21,008,847
675,749
183,604
15,841
1,786,103 |
Chile - Lomas Bayas
Material mined (t)
ROM leach (t)
ROM copper grade (%)
Heap leach (t)
Heap leach copper grade (%)
Copper cathode (t) |
62,556,448
39,536,325
0.24
14,074,124
0.40
73,333 |
66,900,909
42,804,384
0.26
14,502,842
0.37
73,605 |
Chile � Altonorte
Concentrate treated � third party (t)
Concentrate treated - integrated� (t)
Total concentrate treated (t)
Anode copper (t) |
802,627
128,438
931,065
270,247 |
765,631
268,325
1,033,956
311,014 |
Peru - Antamina Copper***
Material mined (t)
Ore mined (t)
Copper head grade (%)
Ore treated (t)
Copper concentrate produced (t)
Copper in concentrate (t)
Silver in concentrate (oz) |
65,292,433
14,619,962
1.10
15,688,109
534,644
150,809
4,203,445 |
53,255,990
13,666,661
1.04
12,688,078
400,253
112,617
3,645,644 |
Peru � Tintaya
Material mined (t)
Ore mined (t)
Ore milled (t)
Copper grade in ore milled (%)
Gold grade in ore milled (g/t)
Concentrate produced (t)
Copper in concentrate (t)
Gold in concentrate (oz)
Copper cathode (t)
Silver in concentrate (oz) |
61,585,646
6,985,865
7,232,875
0.68
0.13
143,267
37,977
16,207
8,844
450,881 |
100,725,107
5,332,950
7,378,509
1.22
0.23
251,987
74,261
33,144
20,969
869,635 |
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
Peru � Antapaccay
Material mined (t)
Ore mined (t)
Ore milled (t)
Copper grade in ore milled (%)
Gold grade in ore milled (g/t)
Concentrate produced (t)
Copper in concentrate (t)
Gold in concentrate (oz)
Silver in concentrate (oz) |
10,143,742
1,195,725
1,494,843
0.51
0.08
19,591
5,027
1,151
50,042 |
-
-
-
-
-
-
-
-
- |
Total mined copper production (t) (contained metal)
Total mined gold production (oz) (contained metal)
Total copper cathode (from mined, integrated and third party material) (t) |
747,042
421,553
630,708 |
888,979
517,861
650,917 |
Average LME copper cash price ($/t)
Average LBM gold price ($/oz) |
7,953
1,668 |
8,826
1,573 |
* ** *** � |
100% consolidated figures Xstrata Copper's pro-rata share of Collahuasi (44%) Xstrata Copper's pro-rata share of Antamina (33.75%) Integrated is defined as feed sourced from an Xstrata mine or smelter (only joint venture ownership share) |
Coal
Total consolidated coal production reached a record 90.4 million tonnes, 7% higher than in 2011.
Thermal coal production from our Australian operations, including semi-soft production, totalled 53.2 million tonnes, an increase of 7% from 2011. Increased volumes predominantly resulted from the restart of mining at Blakefield South, commencement of mining at Ravensworth North, Ulan West and Ulan open cut, and the return to full production at Rolleston following flooding in 2011. The increase was partially off-set by end of mine life closures at Ravensworth West and Westside during 2012 and at Baal Bone in late 2011.
Australian coking coal production was 6.9 million tonnes, 9% lower than the previous year. Increased production at Oaky Creek North was offset by engineering challenges with the new thin seam longwall at Oaky Creek No.1 mine. Remediation works are being finalised by the supplier, and production is ramping up.
Production from our South African thermal coal operations was 18.7 million tonnes in 2012, up 16% on the previous year, primarily due to the ramp up of Goedgevonden. A full year of production from the ATCOM East mine, combined with continued productivity improvements at our Impunzi and Tweefontein open cut mines, also contributed to the increase in production.
Our share of production from the Cerrej�n joint venture in Colombia increased 7% to reach 11.6 million tonnes, mainly as a result of productivity improvements arising from pit re-sequencing and shorter haul distances.
(million tonnes) |
Year ended
31.12.12 |
Year ended
31.12.11 |
Total consolidated production* |
90.4 |
84.3 |
Total export production |
79.7 |
69.9 |
Coking (Australia) |
6.9 |
7.6 |
Semi-soft (Australia) |
4.3 |
5.3 |
Thermal |
68.5 |
57.0 |
Australian thermal |
43.8 |
37.1 |
South African thermal* |
13.1 |
9.1 |
Americas thermal |
11.6 |
10.8 |
Total domestic production |
10.7 |
14.4 |
Australian thermal |
5.1 |
7.4 |
South African thermal* |
5.6 |
7.0 |
Average received export FOB coal price ($/t) |
|
|
Australian thermal |
101.9 |
109.6 |
South African thermal |
100.3 |
101.2 |
Americas thermal |
88.7 |
101.0 |
Australian coking |
198.1 |
265.0 |
Australian semi-soft coking |
158.6 |
202.5 |
Average received domestic FOB coal price (US$/t) |
|
|
Australian thermal |
41.3 |
43.1 |
South African thermal |
21.8 |
22.5 |
* |
South African thermal production in 2011 has been reported exclusive of Mpumalanga tonnes. The Mpumalanga assets were sold effective 31 December 2011 and they produced 1 million tonnes in the 12 month period.
|
Nickel
Total nickel production was a record 106,873 tonnes in 2012, a further increase on the record volumes achieved in 2011. This increase was supported by a full year�s production of 15,186 tonnes of nickel in ferronickel from our Falcondo operation in the Dominican Republic, which operated 7% above its current nameplate capacity.
Production from our Sudbury mines in 2012 increased 3% to 20,425 tonnes of nickel in concentrate compared to the previous year, driven by higher nickel head grades, which improved 10% to 1.61% from 2011. Total copper in concentrate production from our Sudbury mines and mill increased 16% to 57,813 tonnes, reflecting a peak period of increased copper volume from Nickel Rim South, and production from the extension of Fraser mine�s copper zone in partnership with Vale. Nickel in matte from the Sudbury smelter was 4% higher than the previous year at 72,526 tonnes and the second highest level on record as a result of higher capacity utilisation from acquiring and processing additional third-party feed.
Our Raglan mine operated at full capacity and treated 1.3 million tonnes of ore while generating a 5% increase in nickel in concentrate to 28,613 tonnes over the previous year due to a 5% increase in nickel head grade to 2.50%, primarily due to the commissioning of the Kikialik mine in early 2012.
At our Australian mines, we processed 726,029 tonnes of ore in 2012, 7% lower than the previous year, reflecting the decision to place the lower-grade Cosmos mine on care and maintenance in the third quarter of 2012 in response to adverse market conditions. The impact of this move was partly offset by solid performance from the Sinclair mine, where mined production was 21% above plan.
Our Nikkelverk refinery in Norway produced 91,687 tonnes of nickel in 2012, in line with the previous year�s production. Copper metal production of 37,891 tonnes was up 4% from the previous year, reflecting improvements in copper processing capacity.
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
North America � Sudbury operations � mine/mill
Ore mined (t)
Nickel head grade (%)
Copper head grade (%)
Ore treated (t)
Total nickel in concentrate (t)
Nickel in concentrate from own mines (t) Nickel in concentrate from third parties (t)
Total copper in concentrate (t)
Copper in concentrate from own mines (t) Copper in concentrate from third parties (t)
Total cobalt in concentrate (t)
Cobalt in concentrate from own mines (t) Cobalt in concentrate from third parties (t) |
1,480,212
1.61
3.71
2,029,753
26,618
20,425
6,193
57,813
52,544
5,269
563
330
233
|
1,493,005
1.46
3.23
1,883,997
22,716
19,795
2,921
49,887
47,533
2,354
473
344
129
|
North America � Sudbury operations � smelter
Total nickel in matte (t)
Nickel in matte from own mines (t) Nickel in matte from third parties (t)
Total copper in matte (t)
Copper in matte from own mines (t) Copper in matte from third parties (t)
Total cobalt in matte (t)
Cobalt in matte from own mines (t) Cobalt in matte from third parties (t) |
72,526
54,682
17,844
20,475
16,555
3,920
2,193
595
1,598 |
69,459
57,066
12,393
20,041
15,036
5,005
2,209
784
1,425 |
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
North America � Raglan
Ore mined (t)
Nickel head grade (%) Copper head grade (%) Ore treated (t)
Nickel in concentrate (t)
Copper in concentrate (t) Cobalt in concentrate (t) |
1,272,968
2.50
0.68
1,293,678
28,613
7,132
602 |
1,206,360
2.39
0.69
1,299,821
27,274
7,215
562 |
Australia � XNA Ore mined (t)
Nickel head grade (%)
Ore treated (t)
Nickel in concentrate (t) Copper in concentrate (t) Cobalt in concentrate (t) |
685,258
2.12
726,029
11,674
573
322 |
768,843
2.69
778,073
17,034
881
396 |
Dominican Republic - Falcondo
Ore mined (t)
Nickel head grade (%) Ore treated (t)
Nickel in ferronickel (t) |
2,168,636
1.18
1,301,694
15,186 |
1,721,673
1.26
1,142,754
13,498 |
Europe � Nikkelverk
Total nickel metal (t)
Nickel metal from own mines (t) Nickel metal from third parties (t)
Total copper metal (t)
Copper metal from own mines (t) Copper metal from third parties (t)
Total cobalt metal (t)
Cobalt metal from own mines (t) Cobalt metal from third parties (t) |
91,687
52,802
38,885
37,891
16,049
21,842
2,969
825
2,144 |
92,427
59,047
33,380
36,292
13,809
22,483
3,067
948
2,119 |
Total mined nickel production (t) (contained metal) - INO
Total mined copper production (t) (contained metal) - INO
Total mined cobalt production (t) (contained metal) � INO
Total nickel production (t)
Total refined nickel production (t)
Total ferronickel production (t) (contained nickel) |
60,712
60,249
1,254
106,873
91,687
15,186 |
64,103
55,629
1,302
105,925
92,427
13,498 |
Average LME nickel cash price ($/t)
Average LME copper cash price ($/t)
Average Metal Bulletin cobalt low grade price ($/lb) |
17,526
7,953
12.98 |
22,831
8,826
16.01 |
Zinc
Total zinc in concentrate production was slightly higher in 2012 than in 2011. Our Australian operations achieved record volumes in 2012, with an 8% increase in zinc in concentrate production compared to the record volumes reached in 2011. The higher Australian volumes offset lower output at our Brunswick and Perseverance mines in Canada, which was mainly due to lower grades as ore reserves approach the end of their lives, and lower zinc production at Antamina, where the mine plan continues to operate in a predominantly copper ore zone.
Refined zinc metal production at our smelters was in line with 2011 volumes.
Total lead in concentrate production increased by 9% compared to 2011, mainly as a result of record volumes of lead in concentrate production at Mount Isa Mines. Improved lead ore grades at our Australian operations more than offset lower head grades at our Canadian operations.
Total refined lead metal production was 12% higher than 2011, boosted by higher lead production at our Mount Isa operations and improved shipping schedules for lead bullion to our UK lead refinery.
|
Year ended 31.12.12 |
Year ended 31.12.11 |
Australia � Mount Isa |
|
|
Ore mined (t) |
9,445,131 |
9,089,019 |
Zinc head grade (%) |
6.0 |
5.4 |
Lead head grade (%) |
2.7 |
2.4 |
Silver head grade (g/t) |
56.9 |
52.3 |
Ore treated (t) |
9,375,574 |
9,233,581 |
Zinc in concentrate (t) |
390,407 |
357,011 |
Lead in concentrate (t) |
153,116 |
130,697 |
Lead in purchased concentrate smelted (t) |
7,335 |
7,633 |
Lead in lead/silver bullion (t) |
147,177 |
138,629 |
|
Silver in purchased concentrate smelted (k oz) 1,000 1,031
Silver in crude lead (k oz) |
6,878 |
6,546 |
Australia � McArthur River |
|
|
Ore mined (t) |
2,300,133 |
2,338,328 |
Zinc head grade (%) |
11.9 |
11.1 |
Lead head grade (%) |
5.2 |
4.4 |
Ore treated (t) |
2,379,576 |
2,379,565 |
Zinc in concentrate (t) |
202,095 |
194,058 |
Lead in concentrate (t) |
40,372 |
38,284 |
Silver in concentrate (k oz) |
1,820 |
1,594 |
Europe � San Juan de Nieva |
|
|
Zinc metal (t) |
512,321 |
511,092 |
Saleable zinc (t) |
489,549 |
489,103 |
Europe � Nordenham |
|
|
Zinc metal (t) |
149,482 |
154,241 |
Saleable zinc (t) |
143,843 |
148,402 |
Europe � Northfleet |
|
|
Mount Isa sourced lead (t) |
156,930 |
127,507 |
Other lead (t) |
- |
2,548 |
Total lead (t) |
156,930 |
130,055 |
Mount Isa refined silver (k oz) |
7,249 |
5,381 |
Total silver (k oz) |
7,249 |
5,381 |
|
Year ended 31.12.12 |
Year ended 31.12.11 |
North America � Brunswick mine |
|
|
Ore mined (t) |
2,883,157 |
3,102,794 |
Zinc head grade (%) |
7.6 |
7.9 |
Lead head grade (%) |
3.0 |
3.1 |
Silver head grade (g/t) |
92.0 |
97.0 |
Ore treated (t) |
2,941,043 |
3,081,241 |
Zinc in zinc concentrate (t) |
173,196 |
192,237 |
Zinc in bulk concentrate (t) |
17,149 |
16,758 |
Lead in bulk concentrate (t) |
5,868 |
6,932 |
Lead in lead concentrate (t) |
45,969 |
49,830 |
Lead in other feeds to smelter (t) |
31,272 |
42,488 |
Total refined lead (t) |
74,486 |
76,524 |
Silver in bulk concentrate (k oz) |
416 |
474 |
Silver in lead concentrate to smelter (k oz) |
2,335 |
2,506 |
Silver in other feeds to smelter (k oz) |
12,123 |
12,185 |
Total silver in dor� (k oz) |
12,359 |
13,434 |
Copper in concentrate (t) |
8,153 |
8,798 |
North America � CEZ refinery * |
|
|
Zinc metal (t) |
72,566 |
72,425 |
Saleable zinc (t) |
65,927 |
65,824 |
North America � Perseverance |
|
|
Ore mined (t) |
1,099,874 |
1,114,423 |
Zinc head grade (%) |
12.5 |
13.2 |
Ore treated (t) |
1,078,309 |
1,086,760 |
Zinc in concentrate (t) |
125,174 |
135,008 |
Copper in concentrate (t) |
10,926 |
9,752 |
Peru - Antamina Zinc** |
|
|
Ore mined (t) |
14,619,962 |
13,666,661 |
Zinc head grade (%) |
1.9 |
2.3 |
Ore treated (t) |
15,688,109 |
12,688,076 |
Zinc in concentrate (t) |
73,913 |
79,444 |
Total zinc in concentrate production (t) |
981,934 |
974,517 |
Total zinc metal production (t) |
734,370 |
737,758 |
Total lead in concentrate production (t) |
245,325 |
225,743 |
Total lead metal production (t) |
231,415 |
206,579 |
Average LME zinc price($/t) |
1,946 |
2,190 |
Average LME lead price ($/t) |
2,061 |
2,399 |
* ** |
Xstrata Zinc�s pro-rata share of CEZ production (25%) Xstrata Zinc�s pro-rata share of Antamina production (33.75%) |
Alloys
Total attributable ferrochrome production during 2012 was 938,426 tonnes, 8% lower than in 2011. Our furnaces operated at 66% of their capacity in response to weak market demand and as a result of participating in the national energy supplier, Eskom�s, power buy-back programme. Volumes were further reduced during the high electricity tariff winter months, at the end of which industrial action impacted the ramp-up of production.
The average European benchmark ferrochrome price for 2012 of $1.21 per pound was slightly lower than the average price in 2011. The European benchmark price for the first quarter of 2013 has been settled at $1.125 per pound, a 2% increase on the $1.10 achieved for the fourth quarter of 2012.
Tswelopele, our 600,000 tonnes per annum pelletizing and sintering plant, was commissioned on schedule and within budget in October and reached design production capacity within the first month of operation.
During 2012, PGM volumes of 140,381 ounces were 10% lower than in 2011 as Eland continued its transition from an open cast to underground operation and as a result of industrial action. The two shafts at Eland have commenced ramping up and full capacity of 5,400,000 tonnes per annum will be reached in 2018. At our Mototolo joint venture, a record 2,466,362 tonnes was achieved, 7% higher than in 2011 as a result of continued productivity improvements.
Ferrochrome
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
Attributable* saleable production (kt) |
938 |
1,021 |
Indicative average published price (c/lb) (Metal Bulletin) |
121.3 |
125.0 |
* Reflects Xstrata�s 79.5% share of the Xstrata-Merafe Chrome Venture |
Platinum
|
Year ended 31.12.12 31.12.11 |
Year ended 31.12.11 31.12.11 |
Consolidated� saleable production (oz) Platinum
Palladium
Rhodium |
80,199
45,217
13,694 |
92,411
46,968
15,049 |
Average (London Platinum and Palladium Market) Platinum price ($/oz) Average (London Platinum and Palladium Market) Palladium price ($/oz) Average (Johnson Matthey) Rhodium price ($/oz) |
1,552
643
1,276 |
1,720
733
2,022 |
� Consolidated 100% of Eland and 50% of Mototolo |
Ends
Données et statistiques pour les pays mentionnés : Canada | Tous Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous
|
Xstrata plc
|
|
PRODUCTEUR |
CODE : XTA.L |
|
|
| |
ProfilIndicateurs de MarchéVALEUR : Projets & res.Communiqués de PresseRapport annuelRISQUE : Profile actifsContactez la cie |
Xstrata est une société de production minière de zinc et de plomb basée en Suisse. Xstrata est productrice de zinc, de plomb, d'argent, de bauxite, de charbon, de cobalt, de cuivre, de molybdène, de nickel et d'or au Botswana, au Canada, au Chili, au Perou, en Australie, en Argentine, en Colombie et en Jamaique, en développement de projets d'argent, de cobalt, de cuivre, de molybdène, de nickel, d'or, de palladium, de platine, de plomb, d'uranium et de zinc au Canada, au Chili, aux Philippines, en Australie, en Argentine, en Nouvelle-Caledonie et en Republique Dominicaine, et détient divers projets d'exploration au Botswana, au Bresil, au Canada, au Chili, au Groenland, au Mexique, au Panama, au Perou, au Yemen, en Australie, en Afrique Du Sud, en Argentine, en Irlande, en Norvege, en Papouasie-Nouvelle-Guinee et en Turquie. Ses principaux projets en production sont ALUMBRERA en Argentine, KIDD CREEK MINE (MINE D), CRAIG - ONAPING (SUDBURY) MINE, PELLETIER LAKE (STADACONA MINE), LINDSLEY MINE, NORALEX (WEST ANSIL, HORNE, ETC), STRATHCONA, KIDD CREEK DIVISION, BUCKO LAKE, FALCONBRIDGE MINE, RAGLAN, SUDBURY, BRUNSWICK MINE et KIDD au Canada, HYC MCARTHUR RIVER, MOUNT ISA LEAD ZINC SILVER, ERNEST HENRY, BOUNTY MINE, COSMOS MINE, THUNDERBOX, EMILY ANN (LAKE JOHNSTON), MT MCCLURE, MT ISA, SILVER SWAN, MT ISA BLACK STAR, MT ISA ENTERPRISE et EMILY ANN en Australie, LOMAS BAYAS et COLLAHUASI MINE au Chili, TINTAYA, ANTAMINA, ANTAMINA et ANTAMINA ZINC ORE au Perou, PHOENIX MINE (TATI NICKEL) au Botswana, PRODECO en Colombie et ST ANN BAUXITE en Jamaique, ses principaux projets en développement sont LENNARD SHELF, MAGGIE HAYS, CLONCURRY COPPER et LENNARD SHELF en Australie, CERRO DE MAIMON et FALCONDO MINE en Republique Dominicaine, AGUA RICA et EL PACHON en Argentine, HACKETT RIVER, PREMIERE RIDGE, ONAPING DEPTH, FRASER MORGAN, NICKEL RIM SOUTH, ONAPING DEPTH, PERSEVERANCE et PD1 au Canada, LOMAS BAYAS II au Chili, KONIAMBO en Nouvelle-Caledonie et TAMPAKAN aux Philippines et ses principaux projets en exploration sont HORNE SMELTER, ISLAND COPPER, KONRAD, MARY MARCH, MEGATEM, ROBB LAKE, AKWESKWA, MUSK, CEZINC, DONKIN, TROILUS / TORTIGNY, TORTIGNY, SABIN, CHANCE, TULKS NORTH, CATFACE, GREAT BURNT LAKE, WEST ANSIL, TULK SOUTH - DOMINO, TULK EAST B ZONE, TULK SOUTH BOOMERANG, TULK EAST A ZONE, TULK LONG LAKE MAIN ZONE, SKIDDER, MATAGAMI, HEATH STEELE MINES, GASPE MINE et MONTCALM TWP PROP au Canada, BLACK ROCK, TOBY CREEK, MUSGRAVE, MOUNT PEAKE et SINCLAIR en Australie, ELMALAAN en Turquie, MANGABAL au Bresil, KABANGA en Tanzanie, FRIEDA - NENA DEPOSIT en Papouasie-Nouvelle-Guinee, PALLAS GREEN en Irlande et DIKOLOTI au Botswana. Xstrata est cotée au Royaume-Uni et en Allemagne. Sa capitalisation boursière aujourd'hui est 2 893,1 milliards GBX (4 497,6 milliards US$, 3 435,7 milliards €). La valeur de son action a atteint son plus bas niveau récent le 30 avril 2013 à 963,50 GBX, et son plus haut niveau récent le 02 mai 2013 à 999,70 GBX. Xstrata possède 3 002 692 076 actions en circulation. |
Dans les médias de Xstrata plc |
Rapports annuels de Xstrata plc |
Attributions d'options de Xstrata plc |
Nominations de Xstrata plc |
|
Communiqués de Presse de Xstrata plc |
Publication de commentaires terminée |
|
|