Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Independence Group NL

Publié le 20 octobre 2015

Quarterly Report Q1 September 2015

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Copper | Dollar | K Street | Nickel | Zinc |

Quarterly Report Q1 September 2015

65452f9b2325b802803ff2.pdf


Quarterly Report / Q1 September 2015


  • Q1 gold production of 111,039 ounces at AISC A$863/oz

  • Record quarterly production at Simberi of 29,539 ounces

  • Continued strong cash generation



Executive Summary Operations

˃ Consolidated gold production was 111,039 ounces for the

September quarter (Q4 Jun: 99,359 oz). Consolidated All- In Sustaining Cost1 (AISC) was A$863 per ounce for the quarter (Q4 Jun: A$979 per ounce). The average realised gold price for the quarter was A$1,565 per ounce (Q4 Jun: A$1,478 per ounce).

˃ Leonora (Western Australia) production was 81,500 ounces of gold for the quarter (Q4 Jun: 72,222 oz), with Gwalia production 72,388 ounces (Q4 Jun: 57,208 oz) at AISC of A$692 per ounce, and King of the Hills production 9,112 ounces (Q4 Jun: 15,014 oz) at AISC of A$964 per ounce.

˃ Simberi (PNG) gold production was a record 29,539 ounces for the quarter (Q4 Jun: 27,137 oz), comfortably in excess of the targeted 100,000 oz p.a. run rate. Mining, ore transport and processing all exceeded their targets and delivered record results. AISC was A$1,252 per ounce.

Health & Safety

˃ The Company-wide Total Recordable Injury Frequency Rate (TRIFR), calculated as a rolling 12 month average, was

4.1 to 30 September 2015 (Q4 Jun: 5.0).

Exploration

˃ Gwalia (Leonora) A program directed at extensions to the Gwalia lode system approximately 400m below current underground mine workings has continued with the completion of a daughter from parent hole GWDD13. The hole intercepted the Gwalia mine sequence and returned mineralised lode intervals similar to those encountered higher in the mine. In addition, a new parent hole (GWDD17) was commenced to optimise target coverage during the current program and provide positions from which further deposit extensions could be reached. The full drilling program is aimed at delineating an Indicated Resource to support studies of a potential materials handling system (including consideration of a shaft).

˃ Centenary Project (Leonora) WA Follow up drilling of non- gold mineral anomalies identified from a ground based geophysical program have returned anomalous results from three of the four target areas. Further drilling and


  1. Non-IFRS measure, refer page 12


    geophysical surveys area expected to be completed in the December 2015 quarter.

    ˃ Simberi PNG Trenching at Pigibo North on the Simberi Mine Lease (PNG) was completed during the quarter, targeting oxide mineralisation. Encouraging results were returned including:

    Pigibo North

    ˃ SIMTR932: 50m @ 1.3 g/t Au, including

    10m @ 2.6 g/t Au

    ˃ SIMTR934: 40m @ 1.2 g/t Au, including

    15m @ 1.8 g/t Au

    ˃ SIMTR952: 55m @ 1.0 g/t Au, including

    20m @ 1.4 g/t Au

    ˃ Big Tabar Island PNG Detailed creek mapping and channel sampling continued at Banesa Au-Cu porphyry prospect (EL609) during the September quarter.

    ˃ Pinjin Project (Yilgarn) WA Field work focussed on defining geological/structural, geophysical and gold in bedrock geochemical targets for follow-up aircore drilling.

    Finance (unaudited)

    ˃ US dollar denominated debt was reduced by US$22 million during the quarter to US$249 million at 30 September 2015 (Q4 Jun: US$ $271 million). At 30 September 2015, interest bearing liabilities totalled A$358 million (Q4 Jun: A$347 million).

    ˃ Cash contribution2 from operations for the quarter was a record A$80 million, an increase of A$11 million on the previous quarter, reflecting the increased production at Gwalia and record cash flow from Simberi. Cash at bank as at 30 September 2015 was A$115 million 3 , after repayment of debt and financing costs in the quarter of A$34 million.


  2. Non-IFRS measure, refer reconciliation of cash movements on page 11

  3. Excluding A$2 million restricted cash


St Barbara Limited

Level 10, 432 St Kilda Road, Melbourne VIC 3004

T +61 3 8660 1900 F +61 3 8660 1999

ACN 009 165 066

Locked Bag 9, Collins Street East, Melbourne VIC 8003

W www.stbarbara.com.au


Outlook

˃ Guidance for FY16 is revised as follows:

˃ Forecast Gwalia (Leonora) gold production of between 230,000 and 250,000 ounces (previously 220,000 to 230,000 ounces) at an AISC of between A$875 and A$940 per ounce (previously A$875 to A$950/oz), with capex of between A$30 and A$35 million.

˃ Forecast Simberi gold production of between 90,000 and 110,000 ounces at an AISC of between A$1,275 and A$1,400 per ounce, with capex of between A$8 and A$12 million.

˃ Forecast exploration expenditure of A$10 million.


Bob Vassie

Managing Director and CEO 20 October 2015


St Barbara Gold Production & Guidance


Production Summary

Consolidated

Q3 Mar

FY15

Q4 Jun

FY15

Q1 Sep

FY16

Guidance FY16 [3]


Production

Gwalia

oz

76,954

57,208

72,388

230 to 250 koz

(previously 220 to 250 koz)

King of the Hills

oz

11,836

15,014

9,112

9 koz4

Simberi

oz

22,498

27,137

29,539

90 to 110 koz

Consolidated

oz

111,288

99,359

111,039

329 to 369 koz

(previously 319 to 369 koz)


Mined Grade

Reserve grade [2]

Gwalia

g/t

9.7

8.6

9.7

9.4

King of the Hills

g/t

4.1

4.5

n/a

n/a

Simberi

g/t

1.38

1.28

1.22

1.3

Total Cash Operating Costs[1]


n/a

Gwalia

$/oz

532

729

553

King of the Hills

$/oz

1,177

1,095

893

n/a

Simberi

$/oz

1,193

1,034

1,119

n/a

Consolidated

$/oz

734

868

731


875 to 940

(previously 875 to 950)

All-In Sustaining Cost[1]

Gwalia

$/oz

645

860

692

King of the Hills

$/oz

812

1,106

964

-

Simberi

$/oz

1,310

1,149

1,252

1,275 to 1,400

Consolidated

$/oz

798

979

863

995 to 1,070

(previously 995 to 1,080)

[1] Non-IFRS measure, refer page 12.

[2] Ore Reserve grade at 30 June 2015, refer Ore Reserve and Mineral Resources Statement released 25 August 2015. [3] FY16 guidance issued in the June 2015 Quarterly Report (released 21 July 2015) and refined in this report.

[4] Stockpiled as at 30 June 2015.



AISC (Consolidated)

(A$/oz)


1,344


1,042


FY15 AISC A$1,007/oz


Gold Production

(koz) 98

17


798


111


22

30%

25%

22%

23%

12


979


99


27


863


111


30


FY16 Production Indicative Quarterly Guidance Profile

69 129

13 15

11

69 77 72

57

45



FY 15


FY 15


FY 15


FY 15


FY 16


FY 16


FY 16


FY 16


FY 16

Q1 Sep

Q2 Dec

Q3 Mar

Q4 Jun

Q1 Sep

Q1 Sep

Q2 Dec

Q3 Mar

Q4 Jun

Total

Gwalia King of the Hills Simberi

koz

Figures displayed to nearest thousand ounces. Reported ounces in associated table


Indicative % of annual production (koz)


Gwalia, Leonora, WA

AISC (A$/oz)


1,086


883


860


692

˃ During the quarter work was completed upgrading the support in the main decline between 1380 Level and 1460 Level.


Gwalia Deep Drilling Program


˃ A drilling program directed at extensions to the Gwalia lode system approximately 400m below current

FY15 AISC A$841/oz


Mined grade (g/t Au)


9.0

7.9

645


9.7


8.6


9.7

underground mine has continued with the completion of daughter hole GWDD13H.

˃ Significant results returned from GWDD13H were (all intercepts down-hole, details in Table 2):

˃ Main Lode 1.2 m @ 25.8 g/t Au from 2,104 m

FY15 mined grade 8.9 g/t Au


Production (koz)

77.0

68.6


45.4


57.2


72.4

˃ South West Branch 0.6 m @ 9.6 g/t Au from 2,119 m

˃ West Lode 5.9 m @ 8.5 g/t Au from 2,179 m

˃ This is the fourth separate hole to have intersected the mine sequence below the existing reserve, and reflects accurate modelling by the geology team in predicting the location of the mine sequence and effective execution by the drill team to successfully intercept the target. These results further indicate that the mine sequence continues at this depth, and supports the parallel work on a potential

FY 15

Q1 Sep


Operations

FY 15

Q2 Dec

FY 15

Q3 Mar


koz

FY15

Q4 Jun

FY 16

Q1 Sep

materials handling system (including consideration of a shaft).

˃ Drilling has commenced on a new daughter hole GWDD13I and a new parent hole GWDD17.


˃ Gwalia produced 72,388 ounces of gold in the September quarter due to strong mining performance in volume and grade.

˃ Ore mined for the quarter was a record 254 kt. This record reflects the ongoing implementation of production enhancing techniques such as underground waste storage and an ore pass system.

˃ Ore milled for the quarter was 241 kt, an increase of 16 kt from the previous quarter despite a 9 day plant shutdown for mill relining. The mill plan was adjusted to accommodate the increased volume of ore mined during the quarter. Ore containing an estimated 5,500 ounces of gold was stockpiled at the end of the quarter.

˃ Mined ore grade was higher than expected at 9.7 g/t Au for the quarter. This was due to strong stoping performance delivering improved control of dilution, in addition to the presence of higher grade shoots in the mined areas. The resolution of the grade control drilling is insufficient to accurately estimate the presence and magnitude of these higher grade shoots.

˃ All In Sustaining Cost (AISC) reduced to A$692 per ounce for the quarter, due to the mine cycle having several stopes 'in production' as well as mining taking place in stopes where high grade shoots were present.


West Lode Drilling Program


˃ West Lode constitutes one of the four major lode structures identified within the Gwalia Mine Sequence and is located approximately 80m to the west of South West Branch.

˃ Underground drilling completed during the September 2015 quarter has continued to return significant intersections which include (all intercepts metres below surface, details in Table 1):

West Lode:


˃

UGD2354:

2.3m @ 8.0 g/t Au from 1,717 m

˃

UGD2356:

10.6m @ 5.1 g/t Au from 1,755 m

˃

UGD2358:

1.9m @ 41.5 g/t Au from 1,876 m

˃

UGD2366:

4.2m @ 12.8 g/t Au from 1,835 m

˃

UGD2367:

1.2m @ 32.1 g/t Au from 1,767 m

˃ Results from recent West Lode drilling will be incorporated into the Resource model and mine plan, which is expected to lead to an updated Reserve statement during the financial year.



Gwalia Growth Projects - Materials Handling Study


Production Summary Gwalia

Q3 Mar FY15

Q4 Jun FY15

Q1 Sep FY16

Underground ore mined

kt

250

216

254

Grade

g/t

9.7

8.6

9.7

Low grade development ore & stockpiles milled

kt

11

7

2

Grade

g/t

3.4

1.9

2.6

Ore milled

kt

259

225

241

Grade [1]

g/t

9.6

8.2

9.8

Recovery

%

96

96

96

Gold production

oz

76,954

57,208

72,388

All-In Sustaining Cost [2]

$ per ounce

Mining

353

469

356

Processing

84

99

121

Site services

35

65

52

Stripping and ore inventory adjustments

23

58

(11)


By-product credits

495

691

518

(3)

(2)

(3)

Third party refining & transport

1

1

1

Royalties

39

39

37

Total cash operating costs

532

729

553

less operating development

(73)

(102)

(45)

Adjusted cash operating cost

459

627

508

Corporate and administration

33

36

40

Corporate royalty

23

24

23

Rehabilitation

2

2

3

On-site exploration

-

-

-

Capitalised mine & op

development


103


145


101

Sustaining capital expenditure

25

26

17

All-In Sustaining Cost (AISC)

645

860

692

˃ During the quarter the Company commenced preliminary scoping studies on potential materials handling systems for deeper mining in parallel to the drill program. These studies include assessing a shaft with skip hoisting, a shaft with vertical conveying, and also slurry pumping to surface. Each of the current alternatives requires underground crushing.

˃ Management is seeking to accelerate the materials handling study, now targeting completion of appropriate studies for the Board to have the information necessary for an investment decision in Q2 December FY17.


Outlook


˃ FY16 guidance is refined as follows:

˃ Production of between 230,000 ounces and 250,000 ounces (previously 220,000 to 250,000 ounces)

˃ AISC of between A$875 and A$940 per ounce (previously A$875 and A$950/oz)

˃ Capital expenditure of between A$30 and A$35 million.


Gwalia underground ore mined


231250

205


216

254


FY 15

Q1 Sep

FY 15

Q2 Dec

FY 15

Q3 Mar kt

FY 15

Q4 Jun

FY 16

Q1 Sep


[1] Includes Gwalia mineralised waste [2] Non-IFRS measure, refer page 12


King of the Hills, Leonora, WA

AISC

[A$/oz]

1,407

1,123

812

Production [koz]


12.011.8

10.8


1,106


15.0


964


9.1

Operations


˃ King of the Hills ceased mining in April 2015, and had subsequently been placed on care and maintenance, with the associated capitalised mine development written off during FY15.

˃ Processing of King of the Hills ore was completed in Q1 September 2015.

˃ On 15 October 2015 St Barbara Limited completed the sale of the King of the Hills project and Kailis resource to Saracen Metals Pty Ltd, a wholly owned subsidiary of Saracen Mineral Holdings Ltd. The sale includes certain mine and related assets and rehabilitation liabilities

FY 15

Q1 Sep

FY 15

Q2 Dec

FY 15

Production Summary King of the Hills

Q3 Mar FY15

Q4 Jun FY15

Q1 Sep FY16

Underground ore mined

kt

171

29

-

Grade

g/t

4.1

4.5

-

Ore milled

kt

97

118

76

Grade

g/t

4.0

4.2

3.9

Recovery

%

95

95

95

Gold production

oz

11,836

15,014

9,112

All-In Sustaining Cost [1]

$ per ounce

Mining

996

231

17

Processing

202

200

2

Site services

74

20

-

Stripping and ore inventory adjustments

(117)

622

868


By-product credits

1,155

1,073

887

(17)

(21)

(20)

Third party refining & transport

1

1

1

Royalties

38

42

25

Total cash operating costs

1,177

1,095

893

less operating development

(867)

(129)

-

Adjusted cash operating cost

310

966

893

Corporate and administration

33

36

40

Corporate royalty

23

24

23

Rehabilitation

24

19

-

On-site exploration

-

-

-

Capitalised mine & op development

421

58

-

Sustaining capital expenditure

1

3

8

All-In Sustaining Cost (AISC)

812

1,106

964

Q3 Mar koz

FY 15

Q4 Jun

FY 16

Q1 Sep

located at King of the Hills and Kailis.

˃ Consideration for the sale is A$3 million cash, with A$300,000 paid on Completion and the balance due on the earlier of commercial production of ore at the Kailis project or 4 years from Completion. St Barbara's 30 June 2015 Financial Report noted the present value of the A$2.7 million deferred settlement as A$2.3 million, and that on Completion the present value of the rehabilitation provision of A$13.9 million relating to King of the Hills and Kailis will be reversed to the Income Statement.


[1] Non-IFRS measure, refer page 12


Simberi, Papua New Guinea

Operations


2,205


AISC

[A$/oz]


Production

[koz]


12.7


FY 15

Q1 Sep


1,619


17.3


FY 15

Q2 Dec


1,310


22.5


FY 15

Q3 Mar

koz


1,149


27.1


FY 15

Q4 Jun


1,252


29.5


FY 16

Q1 Sep

˃ Simberi produced a site record 29,539 ounces of gold during the quarter, an increase of 9% on the previous quarter. In the month of July a record 11,695 ounces was produced. Gold production for the quarter again comfortably exceeded the 100,000 oz p.a. target run rate.

˃ The total volume of material and ore mined increased on the previous quarter by 38% to 2.6 Mt, which was a new site record.

˃ Annualised throughput for the quarter was approximately equivalent to the target 3.5 Mtpa.

Production Summary Simberi

Q3 Mar FY15

Q4 Jun FY15

Q1 Sep FY16

Total ore & waste mined

kt

1,618

1,882

2,606

Ore mined

kt

460

725

896

Grade

g/t

1.38

1.28

1.22

Ore milled

kt

750

768

859

Grade

g/t

1.1

1.3

1.3

Recovery

%

83

86

84

Gold production

oz

22,498

27,137

29,539

All-In Sustaining Cost [1]

$ per ounce

Mining

316

345

351

Processing

473

394

448

Site services

361

245

273

Stripping and ore inventory adjustments

-

-

-


By-product credits

1,150

984

1,072

-

-

-

Third party refining & transport

13

14

10

Royalties

30

37

37

Total cash operating costs

1,193

1,035

1,119

Corporate and administration

33

36

40

Corporate royalty

-

-

-

Rehabilitation

21

17

14

On-site exploration

-

-

-

Capitalised mine & op

development


-


-


-

Sustaining capital expenditure

63

61

79

All-In Sustaining Cost (AISC)

1,310

1,149

1,252

˃ AISC for the quarter was A$1,252 per ounce (Q4 Jun: A$1,149/oz). Whilst this is an increase from the previous quarter, it is below the guidance range for FY16. The underlying cash costs per ounce in US dollars increased 2% from Q4 FY15 to Q1 FY16, however, the Australian dollar equivalent was impacted by the devaluation in the Australian dollar. Simberi costs are approximately denominated in US Dollars (40%), Papua New Guinea Kina (40%) and Australian Dollars (20%). In addition:

˃ a number of one off costs were incurred in this quarter, including increased investment in the ore delivery system, plant and mill trommel

˃ improvement in ore delivery tonnage was largely achieved through increased trucking, which is higher cost than the integral ore delivery infrastructure (discussed below).

˃ Operational improvements continue to drive increases in the performance of the Simberi processing plant. Mill throughput of 859 kt (annualised 3.4 Mtpa) was a 12% increase on the previous quarter, with the month of September a record with 299 kt (annualised 3.6 Mtpa) of ore processed.

˃ There is confidence that Simberi can improve further:

˃ a number of initiatives to increase the overall percentage of ore being delivered through the lower cost ore delivery system with the potential to reduce unit costs

˃ a major shutdown of the plant was undertaken during the quarter with significant changes made to the mill and trommel, which are expected to further increase throughput and reduce operating costs.


[1] Non-IFRS measure, refer page 12



Outlook


˃ FY16 guidance is maintained:

˃ production of between 90,000 and 110,000 ounces

˃ AISC of between A$1,275 and A$1,400 per ounce

˃ capex of between A$8 and A$12 million.


Simberi oxide life of mine / sulphide transition


Simberi Ore & Waste Mined



1,710

= 1,618

= 1,401 = 1,389


1,157


1,158


999


905


896


725

402

484

460

= 1,882


= 2,606


˃ During the quarter the prefeasibility study (PFS) for the Simberi sulphide project was further advanced.

˃ As previously noted, areas of Simberi's oxide reserves are within the pit wall pushbacks of the deeper sulphide pits, meaning that a value optimised mine plan needs to include a phased cut-over period between oxide and sulphide mining when both can be processed. Such a phased cutover with both oxide and sulphide processing


FY15

Q1 Sep


FY15

Q2 Dec


FY15

Q3 Mar

kt


FY15

Q4 Jun


FY16

Q1 Sep

streams operating would also optimise recovery when processing transitional ores.

˃ Should the sulphide orebody not be mined, the value optimised oxide mine plan would leave behind some of the oxide ore. At the start of the 2016 financial year, the value optimised oxide mine plan was in the order of four years if the Sulphide project was not progressed.

˃ The sulphide project PFS is being expedited with current

Ore Mined Waste Mined = Total


Simberi Ore Milled

859

750

768


620

536

focus on development of an optimised mine plan incorporating economical and metallurgical parameters as identified through the study to date. Previous metallurgical work identified and then refined a traditional flotation circuit appropriate to yield a marketable concentrate. Development of the optimised mine plan with subsequent evaluation of project economics indicate completion of the PFS in the March 2016 quarter. Further drilling work is being planned to determine the full extent of the sulphide orebody as well as to acquire samples to better evaluate metallurgical variability and use that information to optimise the mine plan.

˃ The existing combined oxide and sulphide reserves indicate a potential long life operation in excess of 15 years with upside potential as the full extent of the sulphide orebody below the oxide is yet to be determined.


FY15

Q1 Sep


FY15

Q2 Dec


FY15

Q3 Mar

kt


FY15

Q4 Jun


FY16

Q1 Sep


Exploration


Gwalia Deep Drilling Program


˃ Resource extension drilling at Gwalia has continued with the objective of providing the required certainty to extend the Gwalia resource and to develop the case for mining below the current base of reserves at 1800 metres below surface (mbs).

˃ The initial parent hole was completed in February 2015 and reported to the ASX on 25 February 2015, while results from the first daughter drill hole were released to the ASX on 7 April 2015 and a second daughter hole (GWDD16C) on 5 August 2015.

˃ Parent hole GWDD13 has been re-opened to complete a new daughter hole. GWDD13H achieved a downhole depth of 2,239m after passing through over 100m of the Gwalia mine sequence which incorporated mineralised intervals equivalent to Main Lode, South West Branch and West Lode. Further daughter hole drilling from this parent is in progress.

˃ Significant results returned from GWDD13H were (all intercepts down-hole, details in Table 2):

˃ Main Lode: 1.2m @ 25.8 g/t Au from 2,104m

˃ South West Branch: 0.6m @ 9.6g/t Au from 2,119m

˃ West Lode: 5.9m @ 8.5g/t Au from 2,179m

˃ A new parent hole (GWDD17) commenced during the September 2015 quarter to optimise target coverage and to provide a position from which further deposit extensions could be reached. At the end of the quarter GWDD17 had reached a depth of 796m aiming to pass through the target position at a downhole depth of 2,050m.

˃ The full drilling program is aimed at delineating an Indicated Resource to support the materials handling studies.


Centenary Project Leonora WA


˃ The Centenary project is approximately 60 km north of Leonora, nearby to the Jaguar and Bentley operations of Independence Group (Figure 3.0).

˃ As previously announced, St Barbara has completed high powered ground electromagnetic (EM) surveys and follow- up rotary mud/diamond drilling of four targets located approximately 200m below surface.

˃ Three anomalies within E37-916 are located close to the interpreted western boundary of the felsic-volcanic dominated stratigraphic package which hosts the Jaguar and Bentley copper-zinc-silver volcanogenic massive sulphide (Cu-Zn-Ag VMS) deposits owned by Independence Group NL (ASX: IGO). These anomalies were

tested by holes CNRD001, CNRD002A and CNRD003. CNRD003 and did not return an intersection and will be redrilled to correctly target the source of the anomaly during the December 2015 quarter. Both CNRD 001 and CNRD002A returned anomalous zinc values associated with intervals of black shale.

˃ A highly conductive anomaly within E37-917, coincident with nickel geochemistry, was targeted by rotary mud/diamond hole CNRD004. Complete analytical results are yet to be received.

˃ Further drilling and geophysical surveys are expected to be completed in the December 2015 quarter.


Pinjin Project Yilgarn WA


˃ Exploration continued on the Pinjin project within the Yilgarn Province, WA. The Pinjin Project is located 150km northeast of Kalgoorlie, comprising a large tenement package of 20 exploration licences (1,358 km2) for 485

blocks (Figure 3.1).

˃ The focus during the quarter was to progress the higher ranked geophysical and bedrock geochemical targets in preparation for future aircore drilling. Two reconnaissance field visits were conducted during the quarter with 31 residual soil samples, 11 outcrop rock chip samples and

194 historical RAB or aircore drill cuttings collected. Samples were analysed for gold and a multi-element suite.

˃ Seven samples of historical drill cuttings sampled in the field returned >50 ppb Au (Figure 3.1). These include:

˃ Target 2446-1 (761 ppb Au)

˃ Target 2446-2 (541 ppb Au)

˃ Target 2447-3 (215 ppb Au)

˃ Target 2447-1 (150 ppb Au)

˃ Target 2447-2 (150 ppb and 83 ppb Au).

˃ 225 sample pulps from a previous 2013 aircore drilling program were analysed for a multi-element suite.

˃ Program of Works (PoWs) involving aircore drilling have been submitted to the Department of Mines and Petroleum. Heritage surveys are planned for the December quarter. Aircore drilling will commence upon successful completion of surveys and approval of PoWs.


Simberi, Tatau & Tabar Islands, Papua New Guinea (ML 136 and EL 609)


˃ Exploration continued on Simberi ML136 and EL609 at Western Simberi Island and Big Tabar Island (Figures 4.0 and 4.1).

˃ On Simberi Island (Figure 4.0), the exploration program is focused on identifying additional near-mine higher grade


oxide resources as potential ore feed sources to extend oxide mine life.

˃ Trenching within ML136 was completed at Pigibo North. A total of 33 trenches (SIMTR917 to SIMTR923; SIMTR927 to SIMTR952) were collected for 2,075 metres and 415 samples. Significant trench sampling results are highlighted in Figure 4.2 and include:

Pigibo North:

˃ SIMTR932: 20m @ 1.1 g/t Au, and

50m @ 1.3 g/t Au, including 10m @ 2.6 g/t Au

˃ SIMTR934: 40m @ 1.2 g/t Au, including

15m @ 1.8 g/t Au

˃ SIMTR935: 30m @ 1.0 g/t Au, including

10m @ 2.0 g/t Au

˃ SIMTR952: 55m @ 1.0 g/t Au, including

20m @ 1.4 g/t Au

˃ Six diamond drill holes of an eight hole program (SDH335 to SDH340) were completed at Pigibo North in September for a total of 393.3m (Figure 4.2). Results are pending.

˃ Drill pads have been established at Patan in preparation for an 8 hole (360m) diamond drill program planned for the December quarter.

West Simberi:

˃ Surface sampling continued on West Simberi Island (EL609) during the September quarter. Ridge and spur soil (n=42) and four hand trenches (SIMTR916 and SIMTR924 to SIMTR926) for 270 metres (n=54) followed up anomalous gold in stream sediment samples (Figure 4.3). No significant results were returned from the recent soil and trench samples (Figure 4.4).

Big Tabar Island:

˃ Detailed creek mapping, trench mapping and channel sampling was conducted at Banesa Au-Cu prospect (EL609) during the September quarter. A total of 6.1 line km of creek and trench mapping were completed and 34 rock chip samples were collected. A total of 64 creek channel and trenches (TABTR108 to TABTR171) for 3,515 metres and 678 samples were collected at Banesa. Au and Cu assay results were received for trenches TABTR079 to TABTR167. Significant trench sampling results are highlighted in Figure 4.5 and include:

Banesa:

˃ TABTR079: 55m @ 0.3 g/t Au and 0.2% Cu, including

5m @ 2.5 g/t Au and 0.5% Cu

˃ TABTR092: 125m @ 0.3 g/t Au and 0.1% Cu, including

10m @ 1.3 g/t Au and 0.2% Cu, and 5m @ 1.9 g/t Au and 0.3% Cu.

˃ During the quarter, a large mining company entered into a confidentiality agreement with the Company to review EL609 exploration data, including the Banesa porphyry target.


Expenditure (unaudited)


˃ Expenditure on mineral exploration for the September 2015 quarter is shown below:


Q1 Sep 2015

Australia

A$0.2 million

(expensed)

Pacific

A$0.9 million

(expensed)

Gwalia Deep Drilling

A$0.5 million

(capitalised)

Total

A$1.6 million

December 2015 Quarter


˃ Exploration in Q2 December 2015 will focus on:

˃ The identification of further extensions to the Gwalia deposit through a phased program of diamond drilling directed at quantifying the resource to approximately 2,000 metres below surface

˃ Follow-up drilling and broader application of high powered electro-magnetic surveys to pursue base metal and nickel targets within the Centenary project area

˃ Conducting heritage surveys at Pinjin over proposed targets in preparation for aircore drilling

˃ Targeting near mine oxide potential within ML136 on Simberi at Pigibo North and Patan

˃ Continuing reconnaissance mapping and surface sampling, targeting oxide potential on West Simberi (EL609) following up anomalous gold results from the stream sediment sampling program

˃ Subject to access, trenching on southwest Tatau Island targeting higher grade oxide potential

˃ Finalise detailed prospect mapping and surface sampling at Banesa Au-Cu prospect on Big Tabar Island

˃ Finalise access at Fotombar prospect on Big Tabar Island for mapping and surface sampling.


˃ The map below shows current and planned target areas for Q2 December 2015.

interest, amounted to A$18 million. St Barbara has now repurchased a cumulative US$67 million (27%) in aggregate principal of the original US$250 million of Notes issued by St Barbara in March 2013. US$183 million of the Notes were on issue at the end of the September quarter.

˃ The first of eight US$9 million quarterly repayments of the Red Kite debt facility was completed during the September 2015 quarter, leaving a balance of US$66 million on this facility at the end of the quarter. Interest and principal repayments to Red Kite amounted to A$16 million for the September quarter.

˃ The consolidated AISC for the quarter was higher than in Q3 March FY15 (A$798/oz) which had a similar production volume. This is in part due to the higher AISC at Gwalia and King of the Hills, and also due to the higher proportion of Simberi production in Q1 of 27% (Q3 Mar FY15: 20%).

Cash movements & balance A$M

(unaudited)

Q3

Mar FY15

Q4

Jun FY15

Q1

Sep FY16

Leonora - operating cash flow [2]

68

59

68

Simberi - operating cash flow [2]

2

10

12

- project capex

-

-

-

Gold Ridge

(1)

-

(1)

Rehabilitation , land management & corporate capex

(1)

(1)

(2)

Corporate costs [3]

(5)

(4)

(4)

Corporate royalties

(2)

(2)

(2)

Exploration (4)

(2)

(3)

(2)

Other project costs (see below)

-

(2)

-

Working capital movement

(16)

(3)

3

Cash flows before finance costs

43

54

72

Net interest and finance costs

(3)

(18)

(4)

US debt repayment

-

(67)

(30)

Net movement for quarter

40

(31)

38

Cash balance at start of quarter

68

108

77

Cash balance at end of quarter[5]

108

77

115

˃ Cash movements for the September 2015 quarter are summarised in the following table:


Health & Safety

˃ The Company-wide Total Recordable Injury Frequency Rate (TRIFR), calculated as a rolling 12 month average, decreased from 5.0 at 30 June 2015 to 4.1 for the twelve months ended 30 September 2015. The improvement reflects a continued focus on safety in response to the slight increase in TRIFR during FY15.

˃ At the recent PNG National Mines Rescue Competition, the Simberi Emergency Response Team won the 'Best Team' for the Multi Casualty event, 'Best Captain' for the Multi Casualty Event and 'Best Medic' for both the Firefighting and Multi Casualty events.

Financials (unaudited)

˃ 109,776 ounces of gold were sold in the September quarter, at an average realised gold price of A$1,565 per ounce (Q4 June 2015: 104,954 oz at A$1,478 per ounce).

˃ Cash at bank at 30 September 2015 was $115 million1 after total payments during the quarter of A$34 million for the repurchase of US Notes and Red Kite interest and principal repayments noted below.

˃ During the September quarter, the Company repurchased US$13 million in aggregate principal of its US Senior Secured Notes at a 7% discount to par value (US$3 million was announced on 26 August 2015 with the financial report presentation, and US$10 million was announced on


˃ Total interest bearing liabilities at 30 September 2015 of A$358 million included US$183 million Senior secured notes and US$66 million Red Kite facility, with the balance comprised of A$4 million of lease liabilities. At 30 June 2015, the interest bearing liabilities balance was A$347

28 September 2015). The corresponding net cash outflow,

including discounted principal repayments and accrued



1 Excluding A$2 million restricted cash

  1. Net of sustaining capex

  2. Includes corporate redundancy payments and restructuring consulting fees incurred in relevant quarters

  3. Includes Gwalia Deep Drilling

  4. Excluding A$2 million restricted cash


Share Capital

Issued shares

Opening balance 30 June 2015

495,102,525

Issued

Nil

Closing balance 30 September 2015

495,102,525

Unlisted performance rights

Opening balance 30 June 2015

20,059,671

Issued

Nil

Lapsed

Nil

Closing balance 30 September 2015

20,059,671

million, with the increase in the September quarter due to the adverse movement in the A$/US$ exchange rate (0.7022 at 30 Sep 2015, 0.7713 at 30 Jun 2015).

˃ The Company manages exposure to the US dollar denominated debt using US dollar revenue from gold sales.

˃ At 30 September 2015, there were 75,150 ounces of gold forward contracts at a strike price of A$1,600 per ounce to be delivered between October 2015 and June 2016. These gold forward contracts were established to secure a stable cash margin on Simberi's forecast FY16 gold production.


Senior Secured Notes US$M


˃ Issued March 2013 250

˃ Repurchased Q4 Jun 2015 (54)

˃

˃

˃

Balance remaining at 30 Sep 2015

Closing bid at 30 September 2015 Coupon

183

US$ 0.93

8.875% p.a.

˃

˃

˃

Redemption date

S&P rating Moody's rating

15 April 2018

B-

Caa1

˃ Repurchased Q1 Sep 2015 (13)


ASX & ADR


The Company's shares are listed on ASX (ASX:SBM) and through American Depositary Receipts (ADR OTC: STBMY) traded in the USA.


Scheduled Future Reporting


Date

Report

27 November

Annual General Meeting

Late January

December 2015 Quarterly Report


Corporate

˃ As advised on 4 September 2015, S&P Dow Jones Indices announced the Company's inclusion in the ASX 300 effective 18 September 2015.

˃ Gold Ridge (Solomon islands) Pursuant to the agreement for the unconditional sale of the Gold Ridge Project which was completed in May 2015, the Company delivered (through a third party) a water treatment plant to the Gold Ridge tailings storage facility during the quarter. The plant is now installed and due to be commissioned in November. This will complete the Company's obligations associated with the sale of the Gold Ridge Project.

[Dates are tentative and subject to change]


Non-IFRS Measures

˃ The Company supplements its financial information reporting determined under International Financial Reporting Standards (IFRS) with certain non-IFRS financial measures, including cash operating costs. We believe that these measures provide additional meaningful information to assist management, investors and analysts in understanding the financial results and assessing our prospects for future performance.

˃ Cash Operating Costs are calculated according to common mining industry practice using The Gold Institute (USA) Production Cost Standard (1999 revision).

˃ All-In Sustaining Cost (AISC) is based on Cash Operating Costs, and adds items relevant to sustaining production. It includes some, but not all, of the components identified in World Gold Council's Guidance Note on Non-GAAP Metrics - All-In Sustaining Costs and All-In Costs (June 2013).

˃ AISC is calculated on gold production in the quarter.


˃ For underground mines, amortisation of operating development is adjusted from 'Total Cash Operating Costs' in order to avoid duplication with cash expended on operating development in the period contained within the 'Mine & Operating Development' line item.

Lire la suite de l'article sur www.noodls.com

Independence Group NL

PRODUCTEUR
CODE : IGO.AX
ISIN : AU000000IGO4
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Independence Group est une société de production minière de nickel et d'or basée en Australie.

Independence Group détient divers projets d'exploration en Australie.

Ses principaux projets en production sont LONG NICKEL et MT MAGNET en Australie, son principal projet en développement est TROPICANA en Australie et ses principaux projets en exploration sont DE BEERS, HOLLETON, LAKE LEFROY, MUSGRAVE, KARLAWINDA, CLUB TERRACE, COOMBERDALE, DUKETON, JEANNIE RIVER, MT ISDELL et BOSTON SHAKER en Australie.

Independence Group est cotée en Australie. Sa capitalisation boursière aujourd'hui est 4,3 milliards AU$ (2,8 milliards US$, 2,6 milliards €).

La valeur de son action a atteint son plus bas niveau récent le 22 janvier 2016 à 1,98 AU$, et son plus haut niveau récent le 20 août 2021 à 9,98 AU$.

Independence Group possède 586 750 016 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Dans les médias de Independence Group NL
01/08/2006Bumper Profit Results. More to come
Nominations de Independence Group NL
29/07/2011Change to Board of Directors
Rapports Financiers de Independence Group NL
27/02/2014Half Yearly Report and Accounts
31/08/20112011 Financial Yr Full Year Results and Final Dividend
Projets de Independence Group NL
26/05/2015Australia's gold miners drive M&A revival
29/11/2011(Tropicana)Tropicana JV Mineral Resource Increase
23/03/2010(Long Nickel)Nickel sulphides intercepted north of the Long Nickel Mine
18/07/2006(Tropicana)Tropicana JV Project update
Communiqués de Presse de Independence Group NL
27/07/2016Institutional Placement and Share Purchase Plan Presentation
27/07/2016Trading Halt
25/07/2016Quarterly Report Presentation - Webcast
25/07/2016Tropicana - Delineation of new high grade shoot
11/07/2016June Quarter and FY16 Production Update
27/06/2016First Ore Mined in Development at Nova
01/06/2016Board Changes
24/05/201613th China Nickel Conference Presentation
06/05/2016Notice of initial substantial holder for ABU
06/05/2016Change in substantial holding
27/04/2016March 2016 Quarter Results Presentation
22/04/2016Quarterly Report Presentation - Webcast
01/02/2016Becoming a substantial holder from NAB
22/12/2015Change in substantial holding from CBA
17/12/2015Appendix 3Y
16/12/20152015 Annual General Meeting Presentation
29/10/2015September 2015 Quarter Results Presentation
29/10/2015Appendix 4G
20/10/2015Quarterly Report Q1 September 2015
12/10/2015Appendix 3X Initial Director's Interest Notice
12/10/2015Appointment of Directors
06/10/2015Company Secretarial changes
06/10/2015ABU: Bumblebee Gold-Copper-Silver-Lead-Zinc-Cobalt Discovery
02/10/2015ALY: Bryah Basin Project Exploration Update
28/09/2015Ceasing to be a substantial holder
25/09/2015Becoming a substantial holder
24/09/2015Ceasing to be a substantial holder
22/09/2015Dividend/Distribution - IGO
22/09/2015FY2015 Final Dividend
17/09/20152015 Annual General Meeting extension
10/09/2015Appendix 3B for Sirius Acquisition Scheme
09/09/2015IGO implements business improvement measures at Long
07/09/2015Ceasing to be a substantial holder
27/08/2015Ceasing to be a substantial holder
24/08/2015IGO Appendix 4E and Annual Financial Report
24/08/2015IGO FY2015 Financial Results presentation
24/08/2015Becoming a substantial holder
17/08/2015Becoming a substantial holder for IGO
12/08/2015Ceasing to be a substantial holder from NAB
07/08/2015Becoming a substantial holder from CBA
05/08/2015Tropicana Presentations clarification
03/08/2015Tropicana site visit presentation August 2015
31/07/2015SIR: Acquisition Scheme Booklet
30/07/2015Correction to 21 July 2015 Appendix 3B
29/07/2015Quarterly Report Presentation Webcast
23/07/2015Ceasing to be a substantial holder
16/07/2015Becoming a substantial holder
03/07/2015Becoming a substantial holder from CBA
25/05/2015Sirius's rags-to-riches story ends with A$1.8bn deal
24/04/2015Becoming a substantial holder
22/04/2015March 2015 Quarterly Activities Report
22/04/2015Quarterly Report Presentation Webcast
10/04/2015March 2015 Quarter Production Results
13/03/2015Ceasing to be a substantial holder from CBA
13/03/2015Becoming a substantial holder from CBA
10/03/2015Becoming a substantial holder
06/03/2015Ceasing to be a substantial holder from CBA
24/02/2015February 2015 Investor Presentation post Half Year Results
18/02/2015Half Year Report, Interim Dividend and Upgraded Guidance
14/02/2015February 2015 Investor Presentation
30/01/2015ABU: High-Grade Nickel, Cobalt and Manganese
12/01/2015December 2014 Quarter Production Results
29/12/2014Retirement of Kelly Ross as a director
18/12/2014Appointment of Keith Spence as a director
27/11/2014Appendix 3B
27/11/2014Results of 2014 Annual General Meeting
20/11/2014Chairman's Address to Shareholders at 2014 AGM
06/11/201405 Nov 2014: Independence enters into farm-in and JV at Brya...
30/10/2014Quarterly Report Presentation Webcast
30/10/2014Stockman Project Proposal Passes Environmental Assessment
27/03/2014Jaguar Operation Update
27/02/2014Half Year Results and Interim Dividend
27/02/2014Independence Group Half Year Results and Interim Dividend
30/01/2014Quarterly Activities Report
30/01/201430 Jan 2014: Independence to Explore and Earn an Interest in...
16/10/2013October 2013 Investor Presentation
24/09/2013Presentation at Denver Gold Forum
05/08/20132013 Diggers and Dealers presentation
31/07/2013June 2013 Quarterly Activities Report
26/03/2012Trafford Enters into Iron Ore Agreement with Independence Gr...
19/12/2011Share Purchase Plan Offer Booklet
19/12/2011Appendix 3B Application for Quotation of Placement Shares
14/12/2011Equity Raising Presentation by Managing Director
14/12/2011Institutional Placement and Share Purchase Plan
05/12/2011on Operations and Financials
02/09/2011Mr Gary Comb
31/08/2011Preliminary Final Report Information Listing Rule 4.3A
26/08/2011Full Year Profit Guidance
19/08/2011Company Secretary Change
29/07/2011Diggers and Dealers 2011 Presentation
26/07/2011(Tropicana)Tropicana Gold Project Reserve Increases to 3.91M Gold Ounce
01/04/2011Jabiru Takeover Offer Declared Unconditional
01/04/2011Jabiru - Second Supplementary Bidders Statement
14/03/2011Musgrave. Minerals Ltd - Priority Offer
28/08/2008Preliminary Final Report 2008 & Final Dividend
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (IGO.AX)
7,27+1.54%
AUSTRALIA
AU$ 7,27
24/04 11:00 0,110
1,54%
Cours préc. Ouverture
7,16 7,19
Bas haut
7,00 7,27
Année b/h Var. YTD
6,78 -  9,10 -20,11%
52 sem. b/h var. 52 sem.
6,78 -  16,12 -47,96%
Volume var. 1 mois
3 408 787 4,30%
24hGold TrendPower© : -44
Produit Gold - Nickel
Développe Gold
Recherche Copper - Gold - Nickel
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 23/11/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
2024-44,38%
2023-2,90%16,1211,64
202217,35%9,9410,12
202179,78%9,9810,08
2020-2,30%7,113,33
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,75 AU$+0,52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
10,92 US$-1,71%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,57 GBX+3,64%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$-8,33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,38 CA$-3,64%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
15,32 CA$+0,46%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$-2,08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,19 AU$+0,00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,77 CA$-1,12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,10 US$-0,89%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+0,00%Trend Power :