Publié le 05 juillet 2011

Starts Up the Nixon Fork Mill

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Canada | Copper | Nixon |
TSX.V: FAU  OTCQX: FVGCF  FSE: FWR

www.firerivergold.com

 info@firerivergold.com

Recent Updates

6 June.
Fire River Gold Announces 107.13 g/t (3.12 opt) Gold and 36.26 g/t (1.06 opt) Silver Over 8.4 m (27.6 ft) At Nixon Fork Gold Mine, Alaska
 
19 May.
Fire River Gold Releases Additional High Grade Results and Explains the Significance to the Mining Program
 
16 May.
Fire River Gold Announces 71.4 g/t (2.08 opt) Gold and 40.1 g/t (1.17 opt) Silver Over 5.9 m (19.4 ft) At Nixon Fork Gold Mine, Alaska
 
12 May.
Timothy G. Smith Joins Fire River Gold as Vice President, Operations
 
28 April.
Fire River Gold Announces 41.0 g/t (1.20 opt) Gold and 33.8 g/t (0.99 opt) Silver Over 9.0 m (29.5 ft) At Nixon Fork Gold Mine, Alaska
 
 

Recent Articles

 

Fire River Gold Corp Starts Up the Nixon Fork Mill
 

July 5, 2011 Vancouver, Canada -- Fire River Gold and Mystery Creek Resources (collectively "the Company") are pleased to provide the following update for the Nixon Fork Mine. It is a thorough document that provides insight into all aspects of operations at site. All photos contained in this release were recently taken and represent current conditions at site.

Start Up Schedule

The mill was started up on July 4th. Only the gravity and flotation circuits are being run, which will achieve approximately 80% recovery of gold from freshly mined ore.

The crushing circuit has already been operating this past week as a commission task and to prepare road surfacing material for construction. See Figure 1 for a picture of the primary jaw crusher in operation.

The start up plan for the plant is to process barren waste for a few days to get the material flowing through the mill. Next, low grade mineralized rock (2 to 8 g/t) will be processed over the next week as a "breaking in" period for the gravity and flotation circuits. After the breaking in period, the mill should be fully operational on gravity and flotation circuits and will start processing higher grade feed.

Completion of the cyanide-in-leach (CIL) circuit will be ongoing during start up, with mechanical completion and commissioning projected for late fall. Adding the third process should bring total recovery up to 96%.

The mine and mill should be fully operational and near capacity at 150 tpd of fresh ore from the mine by the end of October. By late spring of 2012, ore feed from the mine will be supplemented by recovering an additional 100 tpd of tailings from the existing tailings pond, which grades approximately 7.6 g.t (Giroux, 2010).

The key project objectives dates are summarized as follows:

  • July 4 - Mill start up
  • Late July -- First concentrate shipment of 30 tonnes from Anchorage
  • Mid to late August -- First dor� gold pour from gravity concentrate
  • Early September -- Dry stack construction completion
  • September/October -- Mechanical completion of CIL plant
  • Late October -- Commissioning of CIL, start of leaching
  • Late Spring 2012 -- Leaching historic tails from pond


Figure 1: Jaw Crusher in Operation

The Mill

There were several modifications made to the existing mill that were performed concurrent with construction completion of the CIL plant:

  • At the crushing plant, the crush size was reduced from 2 inches to 1 inch passing, which is a standard practice. This should reduce the grinding requirement and could increase the capacity of the mill.
  • The feed to the centrifugal gravity separator used to come from the cyclone overflow. This has been re-routed to draw from the cyclone feed. This should increase gold recovery and system operational reliability. Gravity gold is the cheapest to process and has the highest value, so this will have a strong economic benefit to operations.
  • A slurry storage tank was added between the concentrate thickener and filter to decouple the two processes and make them more efficient. Peristaltic pumps were also installed to maintain a high density and low flow. In past operations moistures as high as 20% were reported in the concentrate. We anticipate a much lower moisture content of in the new concentrate.

The flotation circuit is very simple, using only xanthate and frother. No pH control is required. As such, no improvement to the existing circuit was deemed necessary. Our objective will be to moderate copper content in the concentrate, which varied from 10 to 25% historically.


Figure 2: Gravity and Flotation Circuits at the Mill

The Carbon-In-Leach (CIL) Circuit

Two of the five cyanide leach tanks have been fully installed and a third is partially complete. Though at site, these were delayed so that several smaller installation around the large tanks would not be obstructed.

The main components of the carbon stripping and electrowinning circuits have been installed. Piping and electrical work will start in earnest in mid August. Nearly all remaining equipment is at site, the exception being the agitators for the detox tanks, which are the critical path item for mechanical completion, which is anticipated for mid September.

A cyanide source has been secured for delivery in October.

The Filtered Tailings Disposal Site (Dry Stack)

The original design of the dry stack was for water collection beneath the sand in porous pipes, transferring to a pond for sampling and percolation into the earth. The company elected to line the dry stack and enlarge and convert the percolation pond to a lined collection pond to make this a zero discharge facility. This is the only significant construction activity outside of the mill building in 2011. A fleet of construction equipment is being assembled at site, including an excavator, dozer, front end loader, and articulated truck for this work. A crew of six will complete this construction by the end of August. Completion of the dry stack is necessary prior to the commissioning of the CIL circuit.

The Mine

The mine has been in operation for several months, with mine rehabilitation, ore stockpiling, waste development, and diamond drilling being the primary activities.

All mine rehabilitation work is complete, the largest project being the refurbishing of the ventilation raise which serves as a secondary egress.

Two primary waste headings are being driven: 1) the Crystal Ramp is being extended to depth to access the down-dip extensions of 3000 and 3300 zones and 2) a shallow ramp is being driven from the Crystal Mine to connect it to the Mystery Mine. To-date the Crystal Ramp has been driven 42 m and the Mystery drive has been driven 90 m. A ventilation drift for the Crystal ramp extension has also been completed, a distance of 33 m.

The Mystery Mine connection drift is a shallow ramp, driven at 6% grade from the Crystal Mine, starting at 170 mASL . This connection is crucial to future operations, as it will open up the Mystery Mine for mining operations (current resources in the Mystery Mine are 28,400 tonnes indicated grading 23.7 g/t for a total of 20,900 indicated oz Au using a cut-off grade of 10 g/t, from Giroux, 2010). It will also provide excellent drill platforms to explore the zone between the mines, including the Southern Cross and J5A mineralized zones.

Mining and development activities are still ramping up to full capacity as the manpower expands to its full complement of 90 site employees. Approximately half of the new production mining fleet has arrived at site, including a one-boom Tamrock jumbo, BC2 longhole drill, 4 yd� R1300 scooptram, and a 20 tonnes Dux truck. A second Dux truck and R1300 scooptram are scheduled to arrive early in June. The second scooptram will be remote-capable, expanding stoping method options for the operation. Additional equipment is being considered to enhance productivity, including a rockbolting machine. The mine is expected to achieve its full production target of 3800 ounces per month by October 2011.


Figure 3: Mine Equipment Purchases (L to R: One Boom Jumbo, 4 yd� Scooptram, LH Drill)

Stockpile Management

At present a stockpile of approximately 2300 tonnes of high grade material and 100 tonnes of medium grade material is stored in front of the primary jaw crusher outside of the mill building (Figure 4). In addition, approximately 500 tonnes of low grade material has been stored on a nearby laydown (Figure 5). This material is segregated into piles awaiting grade determination by assay (note the identifying stakes for each pile) before being added to one of the piles or disposed of onto the waste dump.


Figure 4: High Grade Stockpile (left) and Medium Grade Stockpile (right) ahead of Primary Crusher


Figure  SEQ Figure 5: Low Grade Stockpile (to right) and Unclassified Material Piles

Water in the Mine

There is much speculation, but few facts known about the groundwater situation in the mine. At present there is approximately 3 m of water at the bottom of the old ramp and approximately 0.3 m in the new ramp heading. The water level in the mine is known to fluctuate as much as 6 m in the spring after the snow melt.

While the full extent of the groundwater significance is not known, the mine is taking several steps to manage groundwater inflows should they become problematic to the crystal ramp development, including:

  • Locating the drive in tightly healed limestone
  • Installing a 200,000 gallon reservoir at 170 mASL to pump inflow water (completed July 3rd) and a second 70,000 gallon reservoir at 340 mASL for drill water storage
  • Diamond drilling ahead of the development heading to explore groundwater and fracture conditions
  • Acquiring a large capacity grout pump and contracting experts to guide the grouting program should one be required
  • Acquiring four evaporation misting machines to dispose of excess groundwater through accelerated surface evaporation (one unit is already in service at the tailings pond, see Figure 6).


Figure 6: Evaporation Mister at Tailings Pond

Drilling

The mine has two Hagby drills that have been operated underground over the past several months. Drill results have been extensively covered by numerous press releases over that period.

The main objective of recent drilling was ore definition in support of the earliest mining in the upper Crystal Mine, approximating the first six months of production. This work is complete and the drills are now being turned to exploration targets on surface and underground. The most important target for both is the zone between the Mystery and Crystal mines, which houses three targets: the Southern Cross, J5A, and 3100 zones. These will be more effectively drilled once platforms have been provided by the shallow ramp connecting the Mystery and Crystal Mines.

The Company maintains that the property is fairly large and the ability to replenish mining on an annual basis is a probable and appropriate approach to extending the life of the operation.


Figure 7: Hagby Drill Set Up Underground

Assay Lab

One challenge of start up has been to fully staff the assay lab, which has been accomplished with the addition of four assayers.

While the ore is visually discernable, the precise grade is not, and there is enough latitude that the geologists are regularly surprised in both directions -- assays demonstrating higher and lower grade than expectations based on visual examination. Accordingly, a quick turn-around of assays is necessary to properly manage the determination of ore and waste. The number of results per day will increase with mill start up, as the underground testhole, chip samples, and muck pile samples with be joined by numerous daily checks on mill feed, gravity, flotation, concentrate and final tailings determinations.

Diamond drill samples are still assayed independently such that they can be used to support resource and reserve estimations.


Figure 8: Fire Assaying for Stockpile Grade Determination

Marketing Contracts

Negotiation of contracts for the off-take of concentrate and dore bars are under active discussion with a number of major buyers. The concentrate will leave site in 1 tonne totes on pallets aboard a C130 Hercules aircraft. The dor� will be shipped in 25 to 30 kg bars that will be comprised of gold (60%), silver (30%), and impurities (10%). No delay to revenue is anticipated due to completion of either contract.

Security

A contract has been awarded to an independent contractor Doyon Universal Services LLC for continuous surveillance of the mill area and to accompany all shipments from site. The Company is confident that the surveillance equipment installed coupled with the diligence of a third-party security team will protect the operation from losses due to theft.

Logistics

Being an air-support operation, efficient logistics are crucial to the property's success. Our primary fuel supplier, Everts Air Cargo, has successfully built up our inventory at site such that for the first time in our project's history we refused a fuel flight last week. Figure 9 shows the Everts DC-6 offloading fuel into the Nixon Fork tanks. Note that the art on the nose depicts the plane's original owner, Mr. Howard Hughes.


Figure 9: Everts Air Cargo's DC-6 Transferring Fuel

Most of the heavy equipment at site was lifted from Anchorage aboard a Lockheed C-130 Hercules airplane, supplied by Lynden Air Cargo (Figure 10). This plane will also be used for all bulk supply, such as cyanide, lime, cement, and to fly copper concentrate from site. Excess payload capacity is often exploited by offloading wing fuel from the plane to our fuel storage tanks.


Figure 10: Lynden C-130 Hercules Airplane Arriving at Nixon Fork Mine

Anchorage Office

The Company has established an Anchorage office, which is embedded in Lynden's main facility. Project accounting, human resources, and logistics coordination will be managed from this office.

Closing Comments

Needless to say we are all excited about achieving this milestone. I am very proud of our workers and our management and thank each employee, consultant, and contractor whose contribution got us to this point. It has certainly been a team effort with many helping hands.

On behalf of the Board of Directors, I look forward to keeping you updated with our corporate developments.

"Richard Goodwin"

Richard Goodwin
President and COO


Certain information regarding the Company including management's assessment of future plans and operations, may constitute forward-looking statements under applicable securities laws and necessarily involve risks associated with mining exploration and development, volatility of prices, currency fluctuations, imprecision of resource estimates, environmental and permitting risks, access to labour and services, competition from other companies and ability to access sufficient capital. As a consequence, actual results may differ materially from those anticipated in the forward-looking statements. A feasibility study has not been completed and there is no certainty the disclosed targets will be reached nor that the proposed operations will be economically viable. The TSX Venture Exchange or its Regulation Services Provider have not reviewed and do not accept responsibility for the adequacy or accuracy of the contents of this news release, which has been prepared by management. We seek safe harbour.
 


 

Click HERE to unsubscribe to our email list

Données et statistiques pour les pays mentionnés : Canada | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous

Fire River Gold

EN DÉVELOPPEMENT
CODE : FAU.V
ISIN : CA31811Q1063
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Fire River est une société d’exploration minière d'or basée au Canada.

Fire River est en développement de projets d'or et d'argent en USA.

Son principal projet en développement est GOLDEN ZONE PROPERTY en USA et ses principaux projets en exploration sont NIXON FORK, GOLDEN ZONE, KANSAS CREEK et DRAKEN en USA.

Fire River est cotée au Canada. Sa capitalisation boursière aujourd'hui est 3,2 millions CA$ (2,8 millions US$, 2,2 millions €).

La valeur de son action a atteint son plus haut niveau récent le 27 novembre 2009 à 0,75 CA$, et son plus bas niveau récent le 09 octobre 2014 à 0,01 CA$.

Fire River possède 316 160 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Financements de Fire River Gold
20/09/2012Announces Additional Brokered Private Placement with Sunel S...
07/09/2012Announces Closing of Second Tranche of Brokered Financing Fo...
10/08/2012Announces Closing of First Tranche $5.7 Million Brokered Fin...
11/06/2012Annouces $4M Private Placement
18/05/2011Announces Extension of Warrant Expiry Date
26/05/2010Previously Announced Non-Brokered Private Placement Oversubs...
05/05/2010Increases Non Brokered Private Placement to $4 million
19/11/2009Announces $10 Million Brokered Private Placement
Nominations de Fire River Gold
10/01/2014Appoints New Director
10/01/2014Appoints New Director
10/01/2014Appoints New Director
27/03/2013Director Resignation
08/11/2012Appoints New Director
03/10/2012Announces New Directors And Officers
03/10/2012appoints new directors and officers
28/06/2012Appoints Interim President & CEO
16/05/2012Appoints New Director
19/12/2011Appoints Vice President of Finance and CFO
23/06/2011Appoints Fred Sveinson to the Board of Directors
Projets de Fire River Gold
08/01/2013(Nixon Fork)Drills 3.34 Metres Grading 219.1 g/t Gold at Nixon Fork
10/12/2012(Nixon Fork)Drills 7.6 Metres Grading 50.26 g/t Gold at Nixon Fork
16/05/2012(Nixon Fork)Update on the Progress of the Nixon Fork Gold Mine
22/12/2011Provides Updated Resource Estimate
21/12/2011Receives Further Revenue from Concentrate and Dor=E9 Product...
14/12/2011(Nixon Fork)Resumes Full Operations At Nixon Fork Mine
12/12/2011receives 2nd and final drawdown from Sprott Resource Lending...
03/10/2011(Nixon Fork)Announces New Ore Zone Discovered at the Nixon Fork Mine
25/08/2011(Nixon Fork)on Progress of the Nixon Fork Mine Start Up
23/08/2011Announces Further Drill Results
05/07/2011(Nixon Fork)Starts Up the Nixon Fork Mill
19/05/2011Releases Additional High Grade Results and Explains the Sign...
08/04/2011(Nixon Fork)Announces 108.0 g/t (3.15 opt) Gold Over 2.4 m (7.9 ft) At N...
01/04/2011(Nixon Fork)Announces 65.3g/t (1.90 opt) Gold Over 5.5 m (18.0 ft) At Ni...
25/03/2011(Nixon Fork)Announces 125.5g/t (3.66 opt) Gold Over 6.0 m (19.7 ft) At N...
14/03/2011(Nixon Fork)Reports Additional Underground Drill Holes Results: 202.7 g/...
07/03/2011(Nixon Fork)Reports New Underground Drill Holes Results: 92.2 g/t (2.69 ...
17/02/2011(Nixon Fork)Announces Results of Snowden's PEA for the Resumption of Und...
19/08/2010(Nixon Fork)Announces 215 g/t (6.27 opt) Gold Over 0.2 m (0.7 ft) At the...
03/08/2010(Nixon Fork)Announces 20 g/t (0.58 opt) Gold Over 2.5 m (8.2 ft) At the ...
27/07/2010(Nixon Fork)Commences 28,000 Metre Drill Program
06/07/2010(Nixon Fork)Announces 144 g/t (4.2 opt) Gold over 2.5 m (8.2 ft) Nixon F...
30/06/2010(Nixon Fork)Generates Over $1 Million Revenue From Ball Mill Clean Up At...
21/06/2010(Nixon Fork)Announces 498 g/t (14.52 opt) Gold over 3.0 m (9.8 ft) Nixon...
18/06/2010(Nixon Fork)Announces 67 g/t (1.95 opt) Gold over 6.3 m (20.7 ft), Nixon...
23/03/2010(Nixon Fork)produces excellent gold results from geological re-assessmen...
01/02/2010(Nixon Fork)Project Update -- Nixon Fork Gold Mine, Alaska Winter 2010
29/01/2010(Nixon Fork)Lays A Lot Of Geological Love Onto Its Nixon Fork Gold Proje...
Communiqués de Presse de Fire River Gold
25/03/2014Announces Reclassification to Tier 2
11/03/2014Announces New Mailing Address and Phone Number
18/12/2013Announces New Mailing Address and Phone Number
05/12/2013Announces OTCQX Delisting
08/10/2013Receives Default Notice
13/08/2013Misses Payment to Lender
28/06/2013Suspends Operations
28/03/2013Provides Operations Update
29/06/2012Amends Waterton Debt Facility
25/06/2012Accepts Resignations of Senior Management and Board Members
24/04/2012Provides Additional Information Regarding Credit Facility
05/04/2012enters into Gold Stream Credit Agreement with Waterton Globa...
20/03/2012Announces the Completion and Commissioning of the CIL Circui...
06/02/2012Announces Promotion of Timothy G. Smith to Vice President, C...
03/02/2012New Office Address & Phone Number
12/12/2011Announces Temporary Suspension of Operations Due To Inclemen...
14/09/2011Receives First Concentrate Payment
10/08/2011Announces Concentrate Sales Agreement
11/07/2011Announces Refining Contract
07/07/2011(Nixon Fork)Announces Additional Drill Results At Nixon Fork Gold Mine, ...
06/06/2011(Nixon Fork)Announces 107.13 g/t (3.12 opt) Gold and 36.26 g/t (1.06 opt...
16/05/2011(Nixon Fork)Announces 71.4 g/t (2.08 opt) Gold and 40.1 g/t (1.17 opt) S...
12/05/2011Timothy G. Smith Joins Fire River Gold as Vice President, Op...
28/04/2011(Nixon Fork)Announces 41.0 g/t (1.20 opt) Gold and 33.8 g/t (0.99 opt) S...
19/04/2011(Nixon Fork)Announces 16.7 g/t (0.49 opt) Gold and 51.2 g/t (1.49 opt) S...
05/04/2011Announces President's Message
04/03/2011(Nixon Fork)Corporate Update for the Nixon Fork Gold Mine - $7,000,000 N...
02/03/2011Appoints R. David Russell as Chairman and Richard Goodwin a...
09/06/2010Announces 12,000 Metre Drilling Program
07/06/2010closes final tranche of financing for proceeds of a cumulati...
17/05/2010Closes First Tranche of Financing For Proceeds of $3,625,500
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TSX-V (FAU.V)
0,010+0.00%
TSX-V
CA$ 0,010
09/10 15:51 -
0%
Cours préc. Ouverture
0,010 0,005
Bas haut
0,005 0,010
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,010 -%
Volume var. 1 mois
849 310 -%
24hGold TrendPower© : -37
Produit
Développe Gold - Silver
Recherche Copper - Gold - Silver
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 18/11/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,66 AU$+1,46%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,09 US$+0,33%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,59 GBX+9,83%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,61 CA$-1,14%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,19 CA$+2,21%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,20 AU$-4,76%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,84 CA$-1,60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
50,98 US$+0,24%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+0,00%Trend Power :