Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Redcorp Ventures Ltd.

Publié le 13 février 2008

Tulsequah Chief Mine Update Constuction and Permit Progress

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter

 

 

 

 

February 13, 2008

February 13, 2008 - Vancouver, British Columbia - Redcorp Ventures Ltd. (TSX:RDV) and its wholly-owned subsidiary, Redfern Resources Ltd. (together, the "Company") is pleased to provide an update on mine development and construction activities as well as associated permitting progress for the Tulsequah Chief Mine.

The project detailed engineering is well advanced and approximately 50% complete. However, the permit acquisition process has been slower than anticipated which has led to delays in the implementation of our original construction schedule.  At the same time, we have successfully identified and secured virtually all of the essential long-lead time capital equipment at lower than anticipated costs. As a result we have mandated our engineering and procurement contractor, Wardrop Engineering Inc. ("Wardrop"), to update the capital cost estimate and, with Merit International - our construction manager, to prepare an updated project control estimate and schedule to reflect current procurement knowledge, vendor quotations and contractor rates. We anticipate that the control estimate will be finalized near the end of February and will be used to manage the project through to completion.

Equipment Procurement

We recently completed purchase of the ball mill, the rod mill and the two associated re-grind mills for the primary grind and re-grind circuits of the processing plant. These mills are used equipment which have been selected, tested and confirmed for suitability by Wardrop and our equipment advisor, Westpro Machinery Inc. of Vernon, BC ("Westpro").  We are pleased with the assistance extended by Westpro. The mills and necessary materials, as specified by Wardrop, are being shipped to Westpro's facilities for refurbishment and subsequent shipment to site, inclusive of warranty. Westpro is also supplying a fifth mill for the limestone grinding circuit for the tailings slurry feed. 

We have also provided notice to Carmacks Commercial Corp. of our intention to exercise our option agreement to acquire or lease, on or before February 28, 2008, the diesel generating plant and associated equipment previously announced in our news release of September 18, 2007.  One of the eight generator units will be sent to Finning Canada for installation of a heat-recovery system.  This will allow preparation of field upgrade packages for heat-recovery installation on site for the remaining seven units.

The Company has notified Sandvik Mining and Construction Group of its intention to proceed with purchase or lease of the selected underground mobile equipment fleet, consisting of three LHDs, two 40 tonne haul trucks, two longhole and two jumbo drill rigs and miscellaneous support units. The equipment is scheduled for delivery in two stages commencing in January 2009, with a second delivery in March 2009.

The permanent mine camp facility construction is in progress on a fixed cost basis. Initial deliveries are expected to commence in March 2008. The camp is being designed and constructed by Modular Transportable Solutions, LLC ("MTS") of Yakima, Washington, USA.

Hovertrans Ltd. is handling the design and construction specifications for the Air Cushion Barge ("ACB") and the Amphitrac tow vessel. The ACB is being built at Sundial Shipyards in Portland, Oregon and the amphibious tow vessel construction is in progress in Southampton, England, both managed by Hovertrans. Some delays have been experienced due to final design modifications and attendant vessel certification approvals. The delivery dates for the vessels are under review and are expected to be in late spring. Redfern has also commissioned a re-fit to the Arctic Eagle, our shallow-draft river tug, which will increase its available power from 750 to 1430 BHP for use with the air-cushion and conventional barge operations. The re-fit work is being conducted at Allied Shipyards in Vancouver.

Underground Development Design and Contract

Redfern has completed the detailed design for underground development in close consultation with Procon Mining and Tunneling Ltd. ("Procon"), the selected underground development contractor. The design is being incorporated in a pending Mines Act permit amendment submission. The contract with Procon is being finalized and should be executed by the end of February. The start of the underground development work is scheduled for June 2008.


Permitting Status

We anticipate imminent receipt of the initial Mines Act permit which will allow commencement of construction on the PAG (potentially acid generating) and NAG (non-acid generating) waste pads. On completion of the PAG site the Company will commence re-location of the existing waste material at the mine site, followed by commencement of site preparation for plant construction in the summer of 2008.  A Mines Act permit amendment application is now being finalized which will govern the underground mine development, the upgrade of site roads approved by the previously issued Mineral Exploration (MX) permit and for additional roads. A third Mines Act amendment submission is envisaged for approval of the tailings dam detailed design and construction plan, and the barge site.

A Construction Discharge Approval permit application is required for regulating water management and treatment of discharges during the construction of the mine.  It has been prepared in close consultation with the Ministry of Environment and is due to be released shortly for a 30 day stakeholder comment period prior to finalization. 

Redfern experienced delays in initial permit receipts in 2007 which resulted in slower than expected commencement of construction activities and which have extended the project's estimated completion date to the second quarter of 2009.  We are currently completing an Environmental Assessment ("EA") certificate amendment to permit the operation of the proposed air-cushion barge transportation system on the Taku River. Due to additional information requests the public meeting associated with these permits in Alaska was delayed until February 4. This was completed and the associated public comment period in Alaska was extended to February 21. The EA amendment is now estimated for completion in March 2008. 


In November, we entered into a rigorous review with the Taku River Tlingit First Nation ("TRTFN") of the portion of the MX permit covering road construction from the barge landing site to the proposed limestone quarry area, south of the mine site, covering approximately seven kilometres of new road.  Redfern voluntarily suspended construction on this section of the road in order to cooperate with and address TRTFN concerns. In the interim, construction activities were directed to the airstrip and associated roads north of the mine site. We recently received notice from the TRTFN that they are satisfied with the environmental assessment and design of the southern road section. Accordingly we have supplied the Ministry of Forests ("MoF") with the associated clearing envelope for inclusion as an amendment to the existing License to Cut ("LTC"). On receipt of the LTC amendment approval, and confirmation from the Ministry of Mines, the proposed road construction will be able to proceed under the existing MX permit.

Current Construction Activities

Arctic Construction's crews are currently clearing and building the airstrip at the site and preparing for bridge construction for the Shazah Creek crossing. The new camp at the Shazah airstrip location is being erected and set-up to support continuing construction operations. A second heading of road construction is expected to commence from the barge site connection road towards the Tulsequah Chief Mine site as soon as the MoF LTC permit amendments have been issued, expected to occur imminently.

Redcorp Ventures Ltd. is a Vancouver based mineral exploration and development company with active projects in British Columbia, Canada and Portugal. Further information on Redcorp and the Tulsequah Project can be obtained on the Company's website at
www.redcorp-ventures.com and at Redfern's website at www.redfern.bc.ca or by calling toll-free to Troy Winsor, Manager of Investor Relations or Salina Landstad, Manager of Public Relations at the contact numbers listed below.  

ON BEHALF OF THE BOARD OF DIRECTORS OF REDCORP VENTURES LTD.
"Terence Chandler"
                                                                       
Terence Chandler
President and CEO  

Certain of the statements made and information contained herein is "forward-looking information" within the meaning of the Securities Act (Ontario) and the Securities Act (Alberta.) Forward-looking information includes disclosure regarding possible or anticipated events, conditions or results of operations that is based on assumptions about future economic conditions and courses of action and includes future oriented financial information with respect to prospective results of operations or financial position that is presented either as a forecast or a projection.  Forward-looking information is often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect" and "intend"; statements that an event or result is "due" on or "may", "will", "should", "could", or "might" occur or be achieved; and, other similar expressions.  

More specifically, forward-looking information contained herein includes, without limitation, statements concerning our plans at our Tulsequah Project (inclusive of the Big Bull Project), the net present value of the Tulsequah Project, the timing and amount of estimated future production and mine life, expected future prices of gold, silver, copper, lead and zinc, mineral reserve and mineral resource estimates, estimated capital and operating costs of the project, estimated capital pay-back period, estimated asset retirement obligations, timing of development and permitting time lines; all of which involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information.  

Forward-looking information contained herein is based on material factors and assumptions and is subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from a conclusion, forecast or projection in the forward-looking information. 
These include, without limitation, material factors and assumptions relating to, and risks and uncertainties associated with, the availability of financing for activities when required and on acceptable terms, the accuracy of the interpretation of drill results and the estimation of mineral resources and reserves, the geology, grade and continuity of mineral deposits, the consistency of future exploration, development or mining results with our expectations, metal price fluctuations, the achievement and maintenance of planned production rates, the accuracy of component costs of capital and operating cost estimates, current and future environmental and regulatory requirements, favourable governmental relations, the availability of permits and the timeliness of the permitting process, the availability of shipping services, the ultimate recovery amount, if any, of our investment in third-party asset-backed commercial paper (ABCP) that is currently undergoing liquidity restructuring by the Committee representing the Montreal Accord, the availability of specialized vehicles and similar equipment, costs of remediation and mitigation, maintenance of title to our mineral properties, industrial accidents, equipment breakdowns, contractor's costs, remote site transportation costs, materials costs for remediation, labour disputes, the potential for delays in exploration or development activities, timely completion of future NI 43-101 compliant reports, timely completion of future feasibility studies, the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, continuing global demand for base metals, expectations and beliefs of management and other risks and uncertainties, including those described under Risk Factors Relating to Our Business in our Annual Information Form, filed on SEDAR on April 2, 2007, and in each subsequent Management's Discussion and Analysis. Although we have attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate.  Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from any conclusions, forecasts or projections described in the forward-looking information. Accordingly, readers are advised not to place undue reliance on forward-looking information. Except as required under applicable securities legislation, we undertake no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise. 

 ###

Contacts:

Troy Winsor
Manager, Investor Relations
1-888-225-9662 604-466-8934

Salina Landstad
Manager, Public Relations & Corporate Communications
604-639-0135 / 1-888-669-4775

 


Corporate Head Office
Suite 800, 1281 W. Georgia Street, Vancouver, BC V6E 3J7
Tel: (604) 669-4775 ext109 Fax: (604) 669-5330 Toll Free: (888) 669-4775

Listed on TSX: Symbol RDV


Copyright �2007
info@redcorp-ventures.com

Redcorp Ventures Ltd.

EN DÉVELOPPEMENT
CODE : RDV.TO
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Redcorp Ventures est une société d’exploration minière de zinc et de plomb basée au Canada.

Redcorp Ventures est en développement de projets de zinc, de plomb, d'argent, de cuivre et d'or au Canada, et détient divers projets d'exploration au Canada.

Son principal projet en développement est TULSEQUAH CHIEF au Canada et ses principaux projets en exploration sont LAGOA SALGADA PROJECT et VILA DE REI au Portugal et HAWK au Canada.

Redcorp Ventures est cotée au Canada et aux Etats-Unis D'Amerique. Sa capitalisation boursière aujourd'hui est 2,0 millions CA$ (2,0 millions US$, 1,3 millions €).

La valeur de son action a atteint son plus haut niveau récent le 31 décembre 2007 à 0,93 CA$, et son plus bas niveau récent le 21 septembre 2009 à 0,01 CA$.

Redcorp Ventures possède 398 356 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Rapports annuels de Redcorp Ventures Ltd.
Annual Report 2006
Annual Report 2005
Annual Report 2004
Financements de Redcorp Ventures Ltd.
13/11/2008RECEIVES RECEIPT FOR PROSPECTUS QUALIFYING THE DISTRIBUTION...
21/04/2008$64,000,000 Credit Facility
Nominations de Redcorp Ventures Ltd.
02/12/2008Appointment of Owner's Project Management Team
22/07/2008Appointment of Mill Superintendent
03/04/2008Appointment of Officer
03/01/2008Appointment of Officer
30/08/2007Appointment of New Director
Rapports Financiers de Redcorp Ventures Ltd.
14/11/2008Financial and Operating Highlights for the Third Quarter End...
12/08/2008Financial and Operating Highlights for the Second Quarter En...
17/11/2007Third Quarter Interim Highlights
14/08/2007Second Quarter Interim Highlights for the Three and Six Mont...
Projets de Redcorp Ventures Ltd.
28/02/2009(Tulsequah Chief)ANNOUNCES ARCTIC LITIGATION
17/02/2009(Tulsequah Chief)Tulsequah Chief Mine Project Development Suspension Continue...
26/01/2009(Tulsequah Chief)Asset-Backed Commercial Paper Distribution Update Tulsequah ...
22/12/2008(Tulsequah Chief)Tulsequah Project Construction & Permitting Update
22/09/2008(Tulsequah Chief)Tulsequah Chief Progress Update
19/06/2008(Tulsequah Chief)Redfern Resources Welcomes Honourable Kevin Krueger Minister...
06/06/2008(Tulsequah Chief)Tulsequah Chief Progress Update
03/03/2008(Tulsequah Chief)Receipt of Mines Act Permit and Licence to Cut Amendment?Tul...
13/02/2008(Tulsequah Chief)Tulsequah Chief Mine Update Constuction and Permit Progress
11/02/2008(Lagoa Salgada Project)Commencement of Exploration Drill Program Lagoa Salgada Proj...
04/02/2008(Tulsequah Chief)Tulsequah Chief Mine Update
07/12/2007(Tulsequah Chief)Tulsequah Chief Mine Project Receives Cutting Permit for Sit...
21/08/2007(Lagoa Salgada Project)Resource Estimate Completed For Lagoa Salgada Deposit, Portu...
02/08/2007(Tulsequah Chief)Tulsequah Project Update
Communiqués de Presse de Redcorp Ventures Ltd.
25/05/2009Reductions in Corporate Management
05/03/2009Announces CCAA Filing
03/03/2009KEY APPROVALS RECEIVED FOR TULSEQUAH PROJECT
10/02/2009Update of Asset-Backed Commercial Paper Distribution
19/09/2008Executes Definitive Agreement With Gold Wheaton Gold Corp.
18/09/2008Project Funding Update
22/08/2008$85 MILLION LOAN FACILITY ARRANGED WITH HSBC BANK CANADA
15/08/2008Extension To Closing of Gold Wheaton Transaction
14/08/2008s Progress at Portugal Base Metal and Gold Exploration Proje...
25/07/2008Tuslequah Chief Progress Update
15/05/2008Corporate & Tulsequah Chief Mine Development Update
14/04/2008Constructiion Update
26/03/2008Portugal Exploration Update
17/01/2008Tulsequah Chief Mine Featured on Mining Industry TV
03/10/2007Redfern Receives Approval for Changes to Tulsequah Project D...
18/09/2007Option To Purchase Agreement Concluded For Long lead-time Po...
24/08/2007Announces Corporate Update
16/08/2007Payment of a Portion of Outstanding Short-Term Funds
16/08/2007MX Permit Granted for Tulsequah Project
16/08/2007Short-Term Investment Repayment Delayed
25/06/2007Construction Equipment Scheduled for Delivery to Tulsequah C...
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TORONTO (RDV.TO)Other OTC (RDFVF)
0,005+0.00%0,000+0.00%
TORONTO
CA$ 0,005
21/09 17:40 -
0%
Cours préc. Ouverture
0,010 0,005
Bas haut
0,005 0,005
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,005 -50,00%
Volume var. 1 mois
141 500 -50,00%
24hGold TrendPower© : -15
Produit
Développe Copper - Gold - Lead - Silver - Zinc
Recherche Copper - Gold - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 18/10/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,84 AU$+1,75%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
10,28 US$-0,39%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,71 GBX+4,41%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,62 CA$-1,13%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,06 CA$+0,75%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+2,13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 AU$+7,50%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,89 CA$-5,03%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
50,12 US$-1,44%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$-5,26%Trend Power :