Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Mundo Minerals Limited

Publié le 04 février 2008

Update on Engenho & Exploration

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter

 

Mundo Minerals Limited (ASX: MUN)

 

ASX Release                                  4 February 2008

 

Update on Engenho & Exploration

 

 

Date of lodgement: 4-Feb-2008

Title: Open Briefing�. Mundo Minerals. Update on Engenho & Exploration

Record of interview:

 

corporatefile.com.au

Mundo Minerals Limited (ASX code – MUN) is expecting to commission its Engenho Gold Project (MUN 100%) in Brazil in March 2008. The final capital cost is expected to be A$13 million and is approximately 21% below the Bankable Feasibility Study (BFS) numbers. What are the risks to meeting that budget? Can you outline the ramp-up schedule? How have you been able to reduce the capital expenditure relative to the BFS? To what extent is the capital expenditure estimate locked in?

 

CEO John Langford

We see the risks of not achieving our capital expenditure budget as minimal. At this late stage of development all major components of the construction are locked

in and costs are known. Any variances will be not significant to the overall budget.

 

As part of our ramp up strategy we commenced mining in November, allowing the development to expose the ore body and a stockpile of ore to be available as soon

as the treatment plant has been commissioned. This will enable us to move pretty much into full production immediately. The treatment plant is a straightforward

CIL plant and we have the advantage of having had 170,000 tonnes of ore from the mine previously treated when AngloGold Ashanti had the mine, so we know

metallurgically that the ore has no complications. This gives us a significant degree of confidence that the commissioning process should not be overly time consuming or complicated.

 

We have been able to reduce the capital expenditure essentially from two areas. We managed the construction process with an internal project manager who was

able to achieve significant cost reductions, for instance by purchasing steel direct from the manufacturers and then commissioning fabrication, as well as close management of all purchasing etc. We also achieved great reductions through being able to acquire a second-hand mill and second-hand mining equipment which has now been completely refurbished. In many ways it has been like establishing a project in the same manner as could be achieved in Australia in the early 1990’s when efficiencies could be achieved.

 

corporatefile.com.au

Can you explain how other key project variables for Engenho differ from the BFS numbers?

 

CEO John Langford

We have revised our mine plan and the capacity of our treatment facility is more robust than we anticipated. This has allowed us to increase our forecast mining rate and annual production. While increasing the mining rate effectively reduces the mine life, we are less concerned about this as the orebody remains open at depth and has only been drilled to approximately 230 metres. In addition, we have great exploration targets on the tenement, so we are confident we will not be compromising the integrity of the mine. It makes absolute sense to be taking advantage of the current gold price to bring forward production. Operating costs are about 5% below the BFS expectations. We have undertaken a robust budgeting process and, subject of course to external factors beyond, our control we are confident that these are achievable milestones.

 

corporatefile.com.au

You have forecast EBITDA from Engenho at A$17 million per annum. How robust do you expect operating costs to be? What are your assumptions for gold price and currency? What EBITDA could you generate at current spot prices?

 

CEO John Langford

As mentioned before, our budgeting has been robust. I have personally discussed the operating costs with both our mine manager and metallurgist. Both are confident they can deliver to the budget. We have used a gold price of US$750/oz for the budget. The A$/US exchange rate was 88 cents and the A$/Brazilian Real was 1.57. The exchange rates remain current and the gold price has improved significantly since we prepared the budget – which all adds to the EDITDA.

 

corporatefile.com.au

Can you put in context the forecast production from Engenho relative to your broader plans for the Company?

 

CEO John Langford

In context of the broader corporate plan, Mundo has a medium term strategy of developing a sustainable annual production base of around 250,000 ounces of

gold. We expect 50-60,000 ounces pa from Engenho (which will be driven largely from the existing mine and anticipated exploration potential from the tenements);

50-70,000 ounces pa are from Torrecillas in Peru (a mine with a proposed mill grade of around 20g/t does not require a significant scale of operation to deliver the proposed production, so we do not see this as a stretch target subject to the success of the current work we are doing); and we hope to deliver about 110,000 ounces pa from Tocantins in Brazil, which is a major greenstone belt. We need to undertake a strong exploration programme and achieve further success, but the early results from all of our assets suggest at this stage that we can deliver to our targets. These are targets and we do need to do the work so any assumptions are subject to exploration success and not yet based on proven resources, but we are confident that the targets have solid foundations based on the exploration results we are seeing.

 

corporatefile.com.au

Can you give more detail on the mining progress at Engenho and the reconciliation with the resource model and the implications for the project?

 

CEO John Langford

Mining has progressed since November on two fronts. We are driving the decline to access the main ore body and we are also progressing with the development of

an adit to access approximately 170,000 tonnes of ore that has been left in the pit wall. Ground conditions are excellent and the quality of the mining being undertaken is very high. At this early stage we are extremely pleased with the reconciliation between the resource model and what is being achieved in the mine. We have no reason to anticipate that we will have any issues. Of course it would be foolish to anticipate that the model will be perfect as the mine develops, but we certainly have a high degree of confidence that, should there be any ore losses arising from any reconciliation, these will be replaced from ore exposed and not in the model. Time will tell, but to date we are very happy with progress.

 

corporatefile.com.au

The Engenho resource is open at depth. What are your plans - and the potential - to extend the resources within the Engenho tenements including the Mazoca anomaly?

 

CEO John Langford

Development of the resource at the bottom of the current ore body is not our immediate priority. That will just extend the end of the mine plan. The immediate

priority will be to test anomalies on our tenement such as Mazoca and test some anomalies that suggest there may be parallel orebodies to Engenho. We are

currently undertaking a full mapping and soil sampling exercise over the tenements. We have 711 hectares of tenements and Engenho only takes up 12 hectares so there is a lot of ground to look at. We would hope to be drilling the Mazoca anomaly around April. We won’t test the parallel targets maybe for 18 months when we can get appropriate access to drill from underground. Because of the large number of opportunities ahead of us, we have established a dedicated exploration team responsible for Engenho.

 

corporatefile.com.au

Mundo recently reported two significant drill intercepts from different anomalies at the Concei��o target within the Tocantins Gold Project (MUN 51%). You’ve stated that two separate mineralised zones are developing and are respectively 1.2 kilometres and 400 metres in length. Can you explain what you know so far about the geometry of the structures? What are your plans for Concei��o?

 

CEO John Langford

While Conceicao has been talked about for approximately 6 months, it remains in a reasonably early stage of development as it is a target that keeps developing. We need to do a fair bit more drilling to properly understand the potential, but we feel it has a real chance of developing into something significant. We have achieved some great drilling intersections and the correlation between the drilling and soil sampling is excellent. Towards the latter stage of 2007 we had the rigs working on the 400 metre area, but when we reviewed our strategy in December, it has become clear that the central zone with a strike now of in excess of 2.5 kilometres is where we need to focus to get an understanding of the potential of a resource. The 400 metres region will feed into this larger potential. As such our focus over the next 6 months will be to develop our understanding of this region, the geometry of the structures and the resource potential. While this may sound a little frustrating to some people, we are a focused company and we will drive our exploration strategy to maximise the potential of the asset rather than just driving to deliver short term results. This is an exciting region and we are looking forward to seeing how the potential develops in the forthcoming months.

 

corporatefile.com.au

During the quarter, Mundo advised its joint venture partner in the Tocantins Project that it would be selecting the tenements that would form the ongoing joint venture. Can you describe your current understanding of the geology of these tenements?

 

CEO John Langford

Tocantins is really two separate areas. In the northern section of the tenements the gold is associated with quartz while the southern areas, near Conceicao, are Banded Iron Formations. We have selected the tenements that form the current joint venture and we are assessing other regional opportunities, but it is premature to discuss this further.

 

corporatefile.com.au

The exploration decline to access the vein structure and to undertake development work is advancing at the Torrecillas Gold Project in Peru (100%). What is the timetable and tasks planned before making a decision on whether to proceed to commercial production? When do you expect to decide whether you will proceed to commercial production?

 

CEO John Langford

At Torrecillas we are progressing with the development of the exploration decline to intercept the vein structure from the decline. At the same time we are developing along existing levels that were developed from previous mining operations. The decline and existing development will connect in the next few months. Once the existing decline has connected with the existing development and accessed the vein structure, the contractors will focus on driving out to another vein system so we can assess a third vein structure while our existing mining team will focus on developing along the vein structure with the view of opening up mineralised structures. This will be the primary focus of work at Torrecillas over

the next 18 months.

 

In the quarterly report we announced that existing development has recently opened up strong sulphide structures on both the 6 and10 levels and geologically they are projected to join up. This is consistent with what we expect to achieve through this development exercise and represents the type of development success we expect to encounter to enable us to commit to developing Torrecillas as an economic mining operation.

 

In addition to development work, we will in the next few months start looking at logistics associated with developing a plant on site. The production levels we

would expect with the grade anticipated suggest we are not looking at a major treatment facility and we have developed a strong understanding and database for the logistics of establishing a treatment facility from our experience in developing Engenho. We will obviously transpose what is applicable to our assessment of Torrecillas.

 

We are also looking at mechanical ore sorting which hopefully will allow us to focus on more bulk mining techniques in Peru, rather than the labour intensive approach to mining the narrow veins previously used. Labour costs are low in Peru, but if we can get productivity benefits from bulk mining, there are obvious benefits. We had a small sample of ore tested at an ore sorting laboratory in Germany late in 2007. The initial tests were encouraging and we are looking at sending a larger sample of rock (ore and waste) from Torrecillas to Germany possibly in April depending on availability of the laboratory. This is not a critical path matter, but if we can get the testing done then, we will do so.

All of this is part of the overall project assessment that hopefully will enable us to commit to developing Torrecillas as a commercial mining operation in 2010. At this early stage all is looking promising.

 

corporatefile.com.au

Can you summarise Mundo’s overall project development plans and how you will build the Company? Where do you see greatest value for Mundo shareholders?

 

CEO John Langford

We have a medium term strategy to develop Mundo as an emerging sustainable gold production company heading towards 250,000 ounces per annum. Our

development plan to date is to get Engenho into production in March 2008, hopefully to commit to developing Torrecillas in 2010 and be able to commit to

our first project at Tocantins in 2012. At the same time we will be developing the exploration potential at Engenho and seeking to enhance the annual production

there. This is an ambitious programme, but from what we are seeing, our assets are showing strong potential to deliver to this programme. We need to do a lot of work

to achieve the goal, but in addition to the quality that the assets are showing, we have an experienced technical team located in Brazil and Peru, a good cash

position and an emerging cash flow to draw on – and we have no debt or hedging, so we benefit from the evolving gold price we are seeing. This does not take into

account new opportunities and that remains the crystal ball. We will however remain focussed and our primary goal is to develop a strong business with appropriate fundamentals. While that may sound boring, shareholder wealth has a strong chance of evolving in a sustainable manner if we take this approach to building our company.

 

 

corporatefile.com.au

Thank you John.

 

For further information on Mundo Minerals Ltd visit

http://www.mundominerals.com/ or contact John Langford on 08 9429 8889.

To read, or to receive, future Open Briefings by email, please visit

www.corporatefile.com.au

 

DISCLAIMER: Corporate File Pty Ltd has taken reasonable care in publishing the information contained in this Open Briefing�.

It is information given in a summary form and does not purport to be complete. The information contained is not intended to be

used as the basis for making any investment decision and you are solely responsible for any use you choose to make of the

information. We strongly advise that you seek independent professional advice before making any investment decisions.

Corporate File Pty Ltd is not responsible for any consequences

 

READ CORPORATE
Public Relations Corporate Communications
T: (+61-8) 9388-1474 | F: (+61-8) 9388-1472 | E: info@readcorporate.com.au | Web: www.readcorporate.com.au 

PLEASE NOTE:

This e-mail and any attachments may contain confidential and/or privileged material and is for the intended addressee(s) only. If you are not an intended addressee, you must not use, copy, retain, disclose or distribute this information. Please notify the sender immediately by return e-mail and delete the message from your system. If you believe that this message constitutes a Commercial Electronic Message (CEM) under the Spam Act 2003 and you wish to unsubscribe please contact the originator of this message with the subject line of unsubscribe.

Note: Virus scanning is carried out on all incoming and outgoing email, but cannot be guaranteed to be timely, secure, error or virus-free. To protect against computer viruses, e-mail programs may prevent sending or receiving certain types of file attachments. If you are having problems please check your e-mail security settings to determine how attachments are handled.

 

Mundo Minerals Limited

EXPLORATEUR
CODE : MUN.AX
ISIN : AU000000MUN9
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Mundo Minerals Limited est une société d’exploration minière d'or basée en Australie.

Son principal projet en développement est CRISTA au Bresil et ses principaux projets en exploration sont JAQUEIRA, TOCANTINS et ENGENHO au Bresil et TORRECILLAS au Perou.

Mundo Minerals Limited est cotée en Australie. Sa capitalisation boursière aujourd'hui est 9,7 millions AU$ (9,8 millions US$, 7,5 millions €).

La valeur de son action a atteint son plus haut niveau récent le 29 février 2008 à 1,02 AU$, et son plus bas niveau récent le 10 août 2012 à 0,03 AU$.

Mundo Minerals Limited possède 201 375 177 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Présentations des Compagnies de Mundo Minerals Limited
17/09/2009Expecting Major Progress in FY10
29/04/2008Eagle Research Report
Nominations de Mundo Minerals Limited
18/08/2010Senior Executive Appointment and Project Financing Update
01/12/2008Appointment of Chief Operating Officer
14/06/2007Update on Torrecillas Project, Peru and Key Appointment
Projets de Mundo Minerals Limited
27/05/2010(Engenho)Broker Report from Eagle Research
17/03/2010(Engenho)Second Satellite Gold Discovery Confirmed at Engenho
19/02/2010(Engenho)Production on Track as Peru Trial Mining Delivers Record
12/02/2010(Torrecillas)Project Development Update
14/01/2010(Engenho)Production Resumes at Engenho Gold Mine
09/09/2008(Engenho)Open BriefingR. CEO Gives Engenho Production Update
08/09/2008(Engenho)Engenho Production Update, Funding Facility and Project Reso...
15/08/2008(Engenho)Third Priority Gold Target Identified at Engenho
04/08/2008(Engenho)Crista Anomaly Channel Sample Assays and Widths
31/07/2008(Engenho)Significant Gold Results from Crista, Engenho Tenements
30/07/2008(Engenho)Open Briefing®. Mundo Minerals. Engenho Production & Other P...
03/06/2008(Engenho)Engenho Plant Commissioning Update
05/05/2008(Engenho)Open Briefing®. Mundo Minerals. Engenho Commissioning & Grow...
01/05/2008(Engenho) Engenho Gold Production Commences
08/04/2008(Engenho) Projects Update - Engenho Exploration Potential Upgraded
04/12/2007 Significant Diamond Drilling Intersection at Tocantins
10/09/2007Spectacular RAB Drilling Results From Tocantins
Communiqués de Presse de Mundo Minerals Limited
11/04/2011(Crista)Update on Crista Approvals following key resolution on propo...
04/03/2011Announces $10-15M capital raising to drive gold production a...
04/06/2010Projects and Development Update, June 2010
22/04/2010March 2010 Quarterly Report
08/02/2010Capital Raising
29/01/2010Quarterly Report December 2009
23/11/2009AngloPacific Group agrees A$5million funding for Mundo Miner...
28/10/2009September 2009 Quarterly Report
16/09/2009Exploration and Market Update
23/07/2009June 2009 Quarterly Report
17/07/2009Corporate Weekly Wrap
13/07/2009Crista Update: Resource Drilling Commences Following Further...
09/06/2009Encouraging Results from Initial Drilling at Crista
09/06/2009CEO on Corporate Production Plans
15/06/2009Fat Prophets Research Report
25/05/2009Company Update - Operations and ProductionGrowth
04/03/2009Market Update and Financial Guidance - March 2009
02/02/2009Open BriefingR.Operating Performance & Ramp-up
28/01/2009December 2008 Quarterly Report CORRECTED*
28/01/2009Quarterly Activities Report December 2008
28/07/2008June 2008 Quarterly Activities Report
18/06/2008Completes First Engenho Gold Pour
13/06/2008Announces Key Board Transition
28/04/2008 Quarterly Activities Report
25/03/2008 Expands and Enhances Asset Base in Brazil
11/02/2008Mundo Minerals - Tocantins Joint Venture Update
08/02/2008 Engenh's Revving Up - Lodge Partners Research Report
04/02/2008Update on Engenho & Exploration
31/01/2008Upgrades Gold Production Forecast From South American Mine
29/01/2008Quarterly Activities Report
13/11/2007 Project Progress Report November 2007
03/09/2007Open Briefing - Outlines Upside at Projects
17/08/2007August 2007 Project Progress Report
18/07/2007$18M Capital Raising to Secure Developments of South America...
09/07/2007RAB Drilling Upgrades Discovery Potential at Tocantins
18/04/2007Additional Significant Assay Results - Torrecillas Gold Proj...
16/04/2007Go-Ahead for South American Gold Mine
10/04/2007Significant Underground Sampling Assays at Torrecillas
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (MUN.AX)
0,0480
AUSTRALIA
AU$ 0,048
14/09 14:03 -
0%
Cours préc. Ouverture
0,050 0,045
Bas haut
0,045 0,048
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,048 -%
Volume var. 1 mois
1 414 899 -%
24hGold TrendPower© : 18
Produit
Développe
Recherche Gold
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 17/12/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,63 AU$-1,04%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,04 US$-0,74%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,63 GBX-1,56%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,38 CA$-3,25%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,34 CA$-3,71%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+1,25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 AU$+0,00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
2,60 CA$-0,38%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
47,19 US$-3,52%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,03 AU$+0,00%Trend Power :