POSITIVE FEASIBILITY STUDY FOR THE HASSA=C3=8F MINE: LA MANCHA SET TO BOOST PRODUCTION BY 2013

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Argentina | Australia | Barite |
   

POSITIVE FEASIBILITY STUDY FOR THE HASSA� MINE: LA MANCHA SET TO BOOST PRODUCTION BY 2013


Please find attached the most recent La Mancha Resources press release.

 

.................

 

Veuillez trouver ci-joint le plus r�cent communiqu� de presse de La Mancha Resources.

 

 

POSITIVE FEASIBILITY STUDY FOR THE HASSA� MINE  

�TUDE DE FAISABILIT� POSITIVE � LA MINE HASSA�

 

 

 

NEWS RELEASE

 

Paris, May 16, 2011  

All amounts are in US dollars and for 100% of the project, unless otherwise indicated.

 

POSITIVE FEASIBILITY STUDY FOR THE HASSA� MINE:
LA MANCHA SET TO BOOST PRODUCTION BY 2013

 

FEASIBILITY STUDY HIGHLIGHTS INCLUDE:

  • Hassa�'s proven and probable reserves increase to 1.1M oz of gold (up 233%)  
  • Average gold production of 161,647 oz of gold per year 
  • Average cash cost of US $571/oz (excluding silver credits) 
  • After- tax Internal Rate of Return (IRR) of 36%  
  • NPV at 5% is $116.3 M (quick 1.8 year payback) 
  • Expected commissioning: Early 2013 
  • Initial capital requirement: $187.0 M 
  • The project is fully permitted 

 

SIGNIFICANT UPSIDE REMAINS:

  • Metallurgical testwork recovered significant quantities of silver from the heap leach tails 
  • 1.2Mt of inferred resources in the heap leach tails remain to be converted  

 

La Mancha Resources Inc. (TSX: LMA, hereinafter "La Mancha" or the "Company") is pleased to announce that it has received a positive Definitive Feasibility Study ("DFS") for the proposed upgrade of its present heap leach plant to Carbon-In-Leach ("CIL") technology at its Hassa� gold mine in North-Eastern Sudan.

 

As shown in Table 1 below, the CIL plant should provide two major advantages to the mine: A) it should allow the processing of ore that cannot currently be economically processed with the heap leach method, thus increasing the mine's reserves by 233% to 1,088,000 ounces of gold, and B) the increased capacity (3.0 Mtpa vs. 0.8 Mtpa) should allow the mine's average gold production to increase by 136% to 161,647 ounces of gold per year while significantly reducing cash costs per ounce.  

 

Table 1: Positive impact of upgrading the current plant to CIL technology

 

 

Current Operation

(as of December 31, 2010)

CIL Upgrade

(as of March. 31, 2011)

Processing Plant

 

 

  Process type

Heap leaching

CIL

  Capacity per year (Mtpa)

0.8 - 1.0

3.0

  Design metallurgical recovery

Non-tailings: 70%, Tailings: <30%

Non-tailings: 90%, Tailings: 63%

Production

 

 

  Gold reserves (oz)

327,000

1,088,000

  Yearly production (oz)*

68,434

161,647

  Mine life (years)

Until 2014

2013-2018

  Average cash cost ( US $/oz)**

731

571

*Current operation: Realized 2010 production shown; CIL: Excludes low production projected in last year of operation;

** Current operation: Realized 2010 cash cost shown, CIL: Cash cost excludes capitalized mining costs associated to acidic ore stockpiles  

 

Dominique Delorme, President and CEO of La Mancha, noted that: "This positive feasibility study reconfirms the robust economics outlined in the September 2010 Preliminary Economic Assessment and forms a good basis for the mine's successful long-term commercial viability. It is important to highlight the low mining risk associated with this project, as 75% of the intended feed for the plant is already stockpiled in proximity to the planned plant location. We remain confident that construction will start in the fall, once an agreement on project financing and ownership is finalized with our Sudanese partner. This would allow the plant to start operating in the fall of 2012, with full commissioning planned for early 2013. The Hassa� CIL project is instrumental to La Mancha's objective of increasing its consolidated gold production to 200,000 ounces per year by 2013."

 

The DFS was compiled by Sedgman Ltd. with the collaboration of CSA Global Pty Ltd., Golder Associates, Arethuse Geology and Wardell Armstrong. The key consultants involved in the studies and their respective areas of responsibility are described at the end of this press release, in the "Qualified Persons and Data Verification" section. Table 2 below provides the highlights of Sedgman's financial model for the CIL project based on all the available operating assumptions.

 

Table 2: Highlights of the DFS include:

Definitive Feasibility Study Highlights

Economic assumptions*

 

Gold price

2013: $1,200/oz

2014: $1,100/oz

>=2015: $1,000/oz

Gold royalty fee

5%

Corporate tax rate

10%

Production:

 

Commissioning

2013

Yearly mill run rate, Mtpa

3.0

Gold recovered, '000 oz

698

Metallurgical recovery      

72%

Yearly production**, oz

161,647

Mine life, years

4.7

Financials:

 

Initial capital cost

$187.0 M

Total sustaining capital

$4.2 M

Average cash costs per year***

$571/oz

Internal rate of return

36%

NPV @ 0% discount

$148.8 M

NPV @ 5% discount

$116.3 M

Payback**** , years

1.8

*Applicable corporate tax rate and gold royalty fee are currently 15% and 7% respectively; **Excludes low production projected in last year of operation; ***CIL cash cost excludes capitalized mining costs associated to acidic ore stockpiles; ****Calculated from the commencement of production

 

MINERAL RESERVES

Today's positive DFS has allowed for the conversion of 761,000 ounces to mineral reserves, representing an increase of 233% over reserves published as of December 31, 2010.

 

Table 3 below compares the new upgraded reserve estimate dated March 31, 2011, to the estimate dated December 31, 2010.

 

Table 3: Hassa� Property Gold Resource (excluding VMS deposits)

 

(resource shown inclusive of reserves)

As at Dec. 31, 2010

As per feasibility study

(March 31, 2011)

Tonnes

g/t Au

Ounces

Tonnes

g/t Au

Ounces

Proven Reserves

-

-

-

2,456,000

2.15  

169,700

Probable Reserves

2,895,000

3.51

327,000

11,640,000

2.45  

918,300

Subtotal

2,895,000

3.51

327,000

14,096,000

2.40  

1,088,000

Measured Resource

2,374,000

2.16

165,000

2,456,000

2.15

170,000

Indicated Resource

10,840,000

3.34

1,163,000

13,611,000

2.88

1,262,000

Total M&I

13,214,000

3.12

1,327,000

16,067,000

2.77

1,432,000

Inferred Resource

6,244,000

2.32

466,000

4,329,000

2.77

385,000

 

It is important to highlight that an extra 1.2Mt of heap leach residue grading 2.06 g/t Au (for 79,475 oz of gold contained) remained in the inferred category as of March 31, 2011, as the access required to conduct the necessary drilling was impeded by the active heaps and the tonnage, grades and recoveries were therefore not supported by sufficient testwork to meet the requirements of a feasibility study according to the NI 43-101 standard. In the DFS, however, Sedgman outlines this potential as an "Improvement Opportunity" with sufficient data to make an estimate of the scope of its possible improvement benefit. Sedgman's preliminary economic assessment of this 1.2Mt inferred resource establishes that processing this additional tailings material through the plant to extend the project's life could increase the NPV of the project by $15.9 million to $132.2 million using a gold price of US $1,000 per ounce and a 5% discount rate.

 

PROCESSING, METALLURGY AND PRODUCTION

The CIL mill throughput schedule, as outlined in the DFS, is based on the expected mineral reserve estimate as at commissioning of the mill in early 2013. As such, it is based on the expected December 31, 2012, mineral reserve estimate, which takes into account planned mine production for the period between March 31, 2011, and December 31, 2012.

 

Hassa�'s gold reserve is composed of three different ore types: traditional gold ore, acidic gold ore and heap leach residue accumulated since the mine's start-up. Table 4 below provides a breakdown of the ore types comprised in the DFS reserve base for the CIL mill throughput.

 

Table 4: CIL throughput as per DFS

As of December 31, 2012

Tonnes

g/t Au

Ounces

Traditional Ore*

1,940,000

3.87

241,000

Heap leach residue (tailings)

11,629,000

1.67

626,000

Acidic Ore

530,000

6.06

103,000

Total

14,099,000

2.14

971,000

*Traditional ore is composed of silica-barite rock ("SBR") and Quartz ore

 

The CIL processing facility has been designed to process 3.0 Mtpa using conventional processes. As shown in Figure 1 of the appendix, the plant is set to be strategically located in proximity to the heap leach residue stockpiles.

 

Metallurgical testing indicated that gold recovery rates would differ according to Hassa�'s various ore types, as described above. As such, the gold recovery rate over the life of the CIL phase is expected to average 72%, with rates varying over time depending on ore throughput composition. Metallurgical gold recovery rates for the traditional ore, heap leach residue and acidic ore are 85%, 63% and 95% respectively.

 

Moreover, metallurgical testwork carried out on a total of 23 composite samples taken from the tailings during the preparation of the DFS showed recoveries of significant quantities of silver (on average 4.4 ounces of silver per ounce of gold recovered). It is important to note that the tailings have never before been tested for silver content and silver recoverability. Further analysis is required to quantify the silver as a resource since tonnage, grades and recoveries are not supported by sufficient testwork to meet the requirements of the NI 43-101 standard. In the DFS, Sedgman outlined this potential as another "Improvement Opportunity", and the carbon circuit of the plant has been scaled to allow the recovery of silver and gold by increasing its carbon loading.

 

Table 5 below shows the gold production expected over the life of CIL phase, with the corresponding cash cost per ounce.

 

Table 5: CIL-Phase Production Schedule  

 

 

2013

2014

2015

2016

2017

Tot /Avg

Tonnage Milled (t)

3,000,000

3,000,000

3,000,000

3,000,000

1,982,152

13,982,152

Gold Grade (g/t)

2.58

2.61

2.28

1.75

1.28

2.16

Recovery (%)

75.2%

73.8%

73.5%

66.5%

63.0%

71.9%

Gold Production (oz)

187,198

185,691

161,464

112,235

51,513

698,099

Cash Cost (US $/oz)

498

509

565

681

839

571

 

Since the mine is already in production and water pipeline permits were granted on April 5, 2010, no additional permits are necessary.

 

CAPITAL COSTS

The total capital development budget is $191.2 million, which includes Sedgman's estimates of $187.0 million for the upgrade of the plant and infrastructure, and $4.2 million for replacement of mining equipment. The main capital items are presented in Table 6 below.

 

Table 6: Capital Cost Estimate

Capital Cost Estimate

Plant

$83.8 M

Nile pipeline

$44.5 M

Power

$18.7 M

Indirect costs

$26.4 M

Contingencies

$13.9 M

Subtotal

$187.0 M

Mining equipment

$4.2 M

TOTAL

$191.2 M

Estimated to �15% accuracy

 

As shown above, one of the main capital investments addresses the need for water. As the mine is located in the Red Sea Desert, nearby water sources are limited. Strict management of the underground water sources found around the mine have met the water requirements of the existing heap leaching operation but would not be sufficient for a CIL plant. In order to meet the water requirements of the upgraded plant, a 160 km pipeline is planned. With a projected capacity of 7.7 million cubic metres of water per year, the pipeline is designed to provide sufficient water for an eventual addition of the 5 Mtpa flotation plant required to process Hassa�'s VMS deposits, which would consume 4.1 million cubic metres of water per year. The construction of a single, final pipeline (rather than two smaller lines over time) is planned to reduce overall capital requirements.

 

The DFS is based on power supply from the construction of a fixed 16 MW Heavy Fuel Oil on-site power station. As a result, capital costs for power supply are $6.7 million lower than for the connection to the National Power Grid provided for in the September 2010 Preliminary Economic Assessment. The planned power station is designed to generate 11 kV and should consist of 12 generators in a 10-operating/2-spare configuration, each rated at 1.6 MW (continuous).

 

PROJECT ECONOMICS

Sedgman built a financial model for the project, using the financial parameters and available operating assumptions provided by La Mancha. The results shown are based on conservative gold price assumptions ranging from $1,200 to $1,000 per ounce of gold.

 

The net present value (NPV) and Internal Rate of Return (IRR) are presented for the after-tax scenario. Table 7 below presents the financial highlights associated with the plant upgrade.

 

Table 7: Financial Highlights

 

DFS Financial Highlights

Main assumptions

 

Gold price

2013: $1,200/oz

2014: $1,100/oz

>=2015: $1,000/oz

Royalties: Gold

5%

Corporate tax rate

10%

Financials:

 

Revenues

$753.5 M

Operating income

$146.1 M

Net earnings

$131.2 M

Cash flow from operations

$339.9 M

Free cash flow to equity

$148.8 M

Investment analysis:

 

Initial capital cost

$187.0 M

Total sustaining capital

$4.2 M

After-tax internal rate of return

36%

Payback*, years

1.8

After-tax NPV @ 0% discount rate

$148.8 M

After-tax NPV @ 5% discount rate

$116.3 M

*Calculated from the commencement of production

 

Although the corporate tax rate and gold royalty fee are currently 15% and 7% respectively, assumptions of 10% and 5% respectively were used in the DFS, based on La Mancha management's best estimates of future rates. Should the rates remain at current levels, the NPV discounted at 5% would be $98.0 million and the IRR would be 31%.  

 

The sensitivity of the project's NPV/IRR to changes in the gold price was tested and is presented in Table 8 below.

 

Table 8: Gold Sensitivity

Change in
gold price

 Gold price forecast (US $/ oz)

NPV @ 5%

IRR

2013

2014

>=2015

-10%

1,080

990

900

$58.1 M

21%

+0%

1,200

1,100

1,000

$116.3 M

36%

+10%

1,320

1,210

1,100

$173.8 M

49%

+20%

1,440

1,320

1,200

$231.1 M

62%

+30%

1,560

1,430

1,300

$288.4 M

75%

+40%

1,680

1,540

1,400

$345.7 M

87%

 

UPDATE ON CURRENT OPERATIONS

As shown in Table 3 above, as of December 31, 2010, there was still a total of 2,895,000 tonnes in reserves at the Hassa� mine that could be treated with the current heap leaching facility. These reserves come mainly from the last two deposits of traditional ore identified to date on the property. As the mine's extraction and processing capacity are now stabilized at around 800,000 - 900,000 tonnes per annum, Hassa� can continue its current operations until mid-2014. Table 9 below shows the mine's theoretical operating profile without the upgrade to CIL technology.

 

Table 9: Highlights of the Current Operation

 

 

2011

2012

2013

2014

Total

Tonnage Milled, t

900,000

853,000

700,000

442,000

2,895,000

Gold Grade, g/t

3.89

3.65

3.45

2.57

3.51

Recovery, %

70%

70%

70%

70%

70%

Gold Production, oz

78,857

70,115

54,351

25,582

228,905

 

The rapidity with which the CIL plant can be commissioned should not be overlooked; it has a significant impact on this scenario, as all the planned ore feed would be re-directed towards the CIL plant as soon as it became operational. It is also worth mentioning that the Company has been very successful at identifying new pockets of traditional ore over the past years, virtually replacing reserves as they are mined. Future exploration success of that nature could positively impact both the current operations scenario and the CIL scenario.

 

NEXT STEPS

Based on the results of the DFS, La Mancha's Board of Directors is aiming to start developing the new project in the third quarter of 2011. The Company must meet two conditions by the end of June to achieve this time line:

A.             Successful ownership discussions - La Mancha considers that the successful development of an industrial project of this nature requires a corporate structure with operational and financial flexibility. The Company is currently in discussion with its Sudanese partner to determine an ownership structure that supports the success of the project. 

B.             Full project financing - Once the ownership structure has been determined, La Mancha will finalize the structure of the project funding required. As of December 31, 2010, La Mancha had a cash position of $38.4 million and was debt free. The Company also has the option of monetizing its $7.2 million investment in long-term notes. Lastly, the Company is currently in discussions with AREVA, its major shareholder, to extend and increase the line of credit set up in the fall of 2008. 

 

QUALIFIED PERSONS AND DATA VERIFICATION

The DFS summarized here for the Hassa� CIL project will be incorporated into an NI 43-101 compliant Preliminary Assessment Report to be available on SEDAR and the La Mancha Resources website within 45 days of the date of this news release.

 

The mineral resource estimate upon which the DFS was based was carried out by or under the direction of R�mi Bosc, an independent geologist, Simon McCracken of CSA, and Jean-Jacques Kachrillo of La Mancha, all Qualified Persons under NI 43-101. The DFS financial model included only Measured and Indicated Resources.

 

La Mancha is not aware of any environmental, permitting, legal, title, taxation, socio-political, marketing or other issue that might materially affect this estimate of mineral resources. The projections, forecasts and estimates presented in the DFS that will form part of the Technical Report constitute forward-looking statements, and readers are urged not to place undue reliance on such statements. Additional cautionary and forward-looking statement information is provided at the end of this press release.

 

The Qualified Persons (QPs) for the purpose of National Instrument 43-101 "Standards of Disclosure for Mineral Projects" for the DFS are show in the following table:

 

Qualified Persons

Section

Company

Qualified Person

Mineral Resources

Arethuse Geology

Remi Bosc*

CSA

Simon McCracken*

La Mancha Resources

Jean-Jacques Kachrillo*

Mining and Mine Operating Costs

CSA

Clayton Reeves*

Metallurgy, Processing Facilities,
Capital Cost Estimate, Operating Cost Estimate

Sedgman

Aaron Massey^

Heap Leach Mine Life

La Mancha Resources

Nigel Tamlyn

* Have visited the site for this function

^ A qualified company representative has visited the site for this function

 

Remi Bosc - Geological Engineer, Director and Principal Consultant - Arethuse Geology. Remi is a member of the European Federation of Geologists and has spent several weeks on site over a three-year period during the various stages of resource evaluation. Remi is responsible for resources estimates. The resources of the Heap Leach Residue were jointly estimated with CSA and La Mancha.

 

Simon McCracken - MAIG, Principal Geologist, CSA Global. Simon is a member of the Australian Institute of Geoscientists. Simon is responsible for part of the heap leach resource estimate by mass balance based on cyanidable gold assay.

 

Clayton Reeves - BSc. Engineering Hons. (Mining), Principal Mine Engineer - CSA Global. Clayton is a member of the South African Institute of Mining and Metallurgy. Clayton has spent in excess of seven weeks on site at Hassa� over a period of approximately one year. Clayton is responsible for mining and mine operating costs.

 

Aaron Massey, B.Eng. (Chemical), Senior Process Engineer, Sedgman Ltd. - Metals Engineering Services. Aaron is a member of the Australian Institute of Mining and Metallurgy, and is responsible for the metallurgy, processing facilities and the capital and operating cost estimates.

 

Nigel Tamlyn, Chartered Engineer (UK), - Chief Operating Officer of La Mancha Resources Inc., is a member of the IMMM, a Professional Engineer (South Africa), and member of the SAIMM. Nigel is responsible for the current heap leach operation section.

 

Jean-Jacques Kachrillo, Ph.D. in Geology - Vice President of Exploration for La Mancha Resources Inc., is a registered Geoscientist with Ordre des Geologues du Quebec. As Vice President of Exploration for La Mancha Resources, he regularly visits the Hassai Mine property. He is responsible for the partially treated ore portion of the resource estimate from January 1, 2008, until March 31, 2011.

 

Each of these qualified persons has reviewed and approved the information relevant to their part of the study contained in this press release.

 

 

INVESTOR MEETING / CONFERENCE CALL

La Mancha will hold an investor meeting / conference call on Tuesday, May 17, 2011, at 4:00 PM (Montreal time) to discuss the results of the DFS and respond to questions from interested parties.

 

Interested parties can access the conference call by dialling:

1-416-981-9000 or toll free for North America 800-768-2481 or by accessing the webcast through our web site at www.lamancha.ca.

 

An instant replay of the conference call will be available until May 31 at the numbers below:

416-626-4100 or toll free for North America 800 558 5253 code #21523626.

 

An archived recording of the conference call will be available at www.lamancha.ca

 

ABOUT THE HASSA� MINE

The Hassa� mine is located in the Red Sea Hills desert of north-eastern Sudan, some 450 km from Khartoum. Inaugurated in 1992, it is Sudan's first and only gold mine in production. Twelve pits have been mined over the years, generating a cumulative production of more than 2.1 million ounces of gold. La Mancha owns 40% of the mine through a subsidiary and is the mine operator.. The Hassa� exploration licenses effectively encompass the entire geological district that extends over 24,000 square kilometres.

 

ABOUT THE HASSA� VMS PROJECT

La Mancha's VMS project involves development of the volcanogenic massive sulphide (VMS) deposits underlying the mined-out pits of the Hassa� mine in Sudan. To date, the VMS resource delineated on the Hassa� property includes an Inferred resource of 51.4MT (20.6MT attributable to La Mancha) at 1.31 g/t Au and 1.23% Cu. This Inferred resource has been delineated in the VMS lenses found under the Hassa� South and Hadal Awatib pits. The Hassa� property is a mining complex consisting of 18 mined pits, of which six have visually-identified VMS potential. Following the publication of a positive PEA on September 7, 2010, a 12-month, 100,000-metre drilling program was launched with the intent of upgrading the Inferred resource to the Measured and Indicated category, increasing the current resource at the first two targets, and testing the potential of the VMS structure identified at the third target, Hadayamet. As of April 30, 2011, the campaign remained on schedule, with a total of 41,715 metres drilled. A total of seven drill rigs are currently in operation, with three rigs each at Hassa� South and Hadal Awatib carrying out development and infill drilling and the seventh having started target delineation drilling at Hadayamet.

 

ABOUT LA MANCHA RESOURCES Inc.:

La Mancha Resources Inc. is an international gold producer based in Canada with operations, development projects and exploration activities in Africa, Australia and Argentina. La Mancha's shares trade on the Toronto Stock Exchange (TSX) under the symbol "LMA". For more information, visit the Company's website at www.lamancha.ca.

 

Caution Concerning Forward-Looking Statements

This press release contains certain "forward-looking statements", including, but not limited to, statements regarding the Company's strategic plans, future commercial production, sales and financial results, development, construction and production targets and timetables, mining costs; statements regarding capital expenditures, development plans, and exploration programs, objectives and budgets; statements regarding the Company's expectations; statements regarding the capital costs associated to the development of the CIL project of the Hassa� property, and its economic viability and profitability. Forward-looking statements express, as at the date of this press release, the Company's plans, estimates, forecasts, projections, expectations or beliefs as to future events and results. Forward-looking statements involve a number of risks and uncertainties, and there can be no assurance that such statements will prove to be accurate. Therefore, actual results and future events could differ materially from those anticipated in such statements. Risks and uncertainties that could cause results or future events to differ materially from current expectations expressed or implied by the forward-looking statements include, but are not limited to, factors associated with fluctuations in the market price of precious metals, mining industry risks, exploration risks, risks associated with foreign operations, environmental risks and hazards, uncertainty as to calculation of mineral reserves, requirement of additional financing or additional permits, authorizations or licences, risks of delays in construction and production and other risks referred to in La Mancha's 2010 Annual Information Form filed with the Securities Commissions, as well as the Toronto Stock Exchange.

 

For additional information, please contact:

La Mancha Resources Inc.

Martin Amyot

Nicole Blanchard

Vice President Corporate Development       

Investor Relations

Tel: (514) 987-5115 ext 25

(514) 961-0229

Email: info@lamancha.ca

 

Figure 1: Property Map



�TUDE DE FAISABILIT� POSITIVE � LA MINE HASSA�
POSITIVE FEASIBILITY STUDY FOR THE HASSA� MINE





.
Data and Statistics for these countries : Argentina | Australia | Canada | South Africa | Sudan | All
Gold and Silver Prices for these countries : Argentina | Australia | Canada | South Africa | Sudan | All

La Mancha Resources

PRODUCER
CODE : LMA.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

La Mancha Res. is a gold producing company based in Canada.

La Mancha Res. holds various exploration projects in Argentina and in Australia.

Its main assets in production are WHITE FOIL, ITY, HASSAÏ and FROG'S LAKE in Australia, its main asset in development is FETEKRO in Australia and its main exploration properties are LA ORTIGUITA, BONDOUKOU, HUALILAN and ARIAB in Argentina and HASSAI VMS and PARK DAM in Australia.

La Mancha Res. is listed in Canada and in United States of America. Its market capitalisation is CA$ 499.5 millions as of today (US$ 500.2 millions, € 391.6 millions).

Its stock quote reached its lowest recent point on October 31, 2008 at CA$ 0.04, and its highest recent level on March 09, 2012 at CA$ 4.03.

La Mancha Res. has 142 716 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of La Mancha Resources
Annual Report
Nominations of La Mancha Resources
4/2/2012ANNOUNCES CHANGES TO ITS BOARD OF DIRECTORS
5/4/2011Appoints New COO and CFO
2/26/2007New Appointments to the Board of La Mancha
Financials of La Mancha Resources
3/28/2012POSTS RECORD NET EARNINGS OF $36.1 M AND RECORD OPERATING C...
8/8/2011POSTS RECORD NET EARNINGS FOR THE SECOND QUARTER
5/18/2011NET EARNINGS DOUBLE ON RECORD CASH FLOW FROM OPERATING ACTIV...
Project news of La Mancha Resources
2/11/2013Group implements its growth strategy in Australia: Gold prod...
11/13/2012ANNOUNCES COMPLETION OF COMPULSORY ACQUISITION BY WEATHER I...
3/27/2012MEASURED AND INDICATED RESOURCES MORE THAN DOUBLE TO 4.8 MI...
1/19/2012MEETS ITS 2011 GOLD PRODUCTION FORECAST
5/16/2011(Ity)POSITIVE FEASIBILITY STUDY FOR THE HASSA=C3=8F MINE: LA MANC...
5/9/2011(Ity)ITY MINE RESUMES OPERATION
3/29/2011(Frog's Lake)A Record Year for La Mancha in 2010 as Production Increases ...
2/24/2011(Ity)ITY Mine Update
8/23/2010(Fetekro)Intersects Grades of Up to 135 g/t Au at Its Fetekro Propert...
8/3/2010First Stages of Frog's Leg Drilling Extension Program Return...
7/29/2009(Hassaï)New Longhole Drilling Doubles the Length of La Mancha's Hass...
7/20/2009(Frog's Lake)Frog's Leg Mine to Boost its Average Annual Gold Production ...
5/26/2009(Hassaï)Confirms the Presence of a Second Enriched Zone at the Hassa...
2/17/2009(Frog's Lake)Plans to Increase Production to up to 100,000 oz of Gold in ...
1/22/2009(Frog's Lake)2008 Year End Production Increases 33% to 71,550 Ounces
1/7/2009(Hassaï)Hassai Mine Tailings Begin Adding to La Mancha's Gold Resour...
1/5/2009(Ity)Resource at La Mancha's Ity Mine Jumps 50% on Excellent Dril...
12/10/2008(Hassaï)Recent VMS Drilling Suggests the Presence of a Supergene Zon...
7/30/2008(Hassaï)Preliminary Drill Results at La Mancha's Hassai Mine Suggest...
8/8/2008(Frog's Lake)Posts its Highest Quarterly Gold Production to Date
5/13/2008(Frog's Lake)Obtains a First Gold Pour From New Australian Frog's Leg Min...
4/23/2008(Frog's Lake)Reports Wide High-Grade Intercepts 150 Meters Below Current ...
7/5/2007(Frog's Lake)Frog?s Leg?s Resource Nearly Doubles
Corporate news of La Mancha Resources
11/13/2012Offer Update
8/28/2012ACKNOWLEDGES WEATHER II TAKEOVER OFFER SUCCESSFUL AND DECLAR...
8/3/2012SECOND QUARTER GOLD PRODUCTION JUMPS 21% FROM THE PREVIOUS Q...
7/31/2012Offer Update - La Mancha TSX:LMA
7/20/2012Offer Document Posted - La Mancha TSX:LMA
7/13/2012REACHES DEFINITIVE AGREEMENT TO BE ACQUIRED BY WEATHER II AT...
6/21/2012DISCOVERS A SIGNIFICANT VMS LENS BELOW THE ODERU
6/15/2012(White Foil)WHITE FOIL PROPERTY SHOWS UNDERGROUND POTENTIAL WITH MINERA...
6/11/2012(Ity)New Drill Results at La Mancha's Ity Mine Indicate That Mine...
5/15/2012REPORTS Q1 NET EARNINGS OF $7.9 MILLION
4/9/2012ANNOUNCES CHANGES TO ITS BOARD OF DIRECTORS
3/22/2012Proven and Probable Reserves Grow by 36% at La Mancha's Frog...
3/14/2012ANNOUNCES AUCTION PROCESS
2/22/2012VMS Resource Increases to 81MT Indicated and 37MT Inferred
1/31/2012Discovers a Mineralized Structure Extending Over 800M at Sis...
9/12/2011HASSA=C3=8F VMS DRILLING UPDATE: INTERSECTS 3.30M @ 94 g/t G...
7/11/2011HIGHLIGHTS IMPORTANT STEP FORWARD FOR SUDAN
6/27/2011Hassai Mine's Third Quarter Production Impacted
6/17/2011(Ity)Clarification on CIL Feasibility Study
5/3/2011NOMME UN NOUVEAU CHEF DES OPERATIONS ET UN NOUVEAU CHEF DES ...
1/14/2011RECORD GOLD PRODUCTION IN 2010
7/22/2010Confirms the Discovery of a New Gold Mineralised Zone at its...
5/12/2010Continues to Generate Profits Into 2010
11/11/2009Reports Another Strong Quarter
8/7/2009Posts Record Quarterly Net Earnings As Gold Production Rises...
2/4/2009Takes Advantage of Strong Gold Prices
2/5/2008 to Spend $10.6 Million on Exploration in 2008
5/28/2007Completes the Renewal of the Ity Mine's Mining Permit
5/16/2007Frog's Leg Results Exceed Expectations
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (LMA.TO)Other OTC (LACHF)
3.50+0.00%3.48+0.00%
TORONTO
CA$ 3.50
11/08 12:07 -
0%
Prev close Open
3.50 3.50
Low High
3.50 3.50
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  3.50 -%
Volume 1 month var.
1,500 -%
24hGold TrendPower© : 18
Produces Gold
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/20/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.92-1.71%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+0.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.38-3.64%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.32+0.46%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.77-1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.10-0.89%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :