Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Kettle River Resources Ltd

Publié le 25 juin 2008

DO-27 DIAMOND PROJECT INDICATED MINERAL RESOURCE

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Canada |

News Release

 

June 24, 2008

DO-27 DIAMOND PROJECT INDICATED MINERAL RESOURCE:

19.5 MILLION TONNES, 94 CPHT, 18.2 MILLION CARATS

 

Kettle River Resources Ltd. (the "Company") announces that Joint Venture partner, Peregrine Diamonds Ltd., the operator, has reported to DHK Diamonds Inc. that they have received a Canadian NI-43-101-compliant report. DHK Diamonds Inc. ("DHK") a privately owned corporation, (Dentonia Resources Ltd. 43.37%, Horseshoe Gold Mining Inc. 13.26% and Kettle River Resources Ltd. 43.37%) owns a participating 10.78% interest in the project.  

"Mr. Eric Friedland, Chief Executive Officer, and Mr. Brooke Clements, President of Peregrine Diamonds Ltd. ("Peregrine" or "the Company") are pleased to report a Canadian NI-43-101-compliant indicated mineral resource of 18.2 million carats in 19.5 million tonnes of kimberlite for the nine hectare DO-27 kimberlite. The estimated grade of the indicated resource is 94 carats per hundred tonnes ("cpht"). The resource estimate was prepared by AMEC Americas Ltd. ("AMEC"), an internationally recognized engineering firm with extensive experience in evaluating advanced diamond projects. An additional 6.5-8.5 million tonnes of kimberlite below the indicated resource was classified as a potential mineral deposit and DO-27 remains open at depth.

 

DO-27 is situated on the 15,000 hectare WO property in the Northwest Territories, Canada, approximately 27 kilometres southeast of the DiavikTM Diamond Mine and 11 kilometres east of the Tibbitt to Contwoyto Ice Road used to supply the two diamond mines in the area. Ownership interests in the WO property are as follows: Peregrine 71.74%, Archon Minerals Limited 17.48% and DHK Diamonds Inc. 10.78%. Peregrine holds 97.92% of the diamond marketing rights.

 

In addition to the resource calculation, AMEC completed an internal preliminary technical assessment ("PTA") study of DO-27 where a number of mining engineering parameters were examined in conjunction with the resource estimate, currency exchange rates, fuel and other consumable prices, diamond valuations and capital cost trends in the mining industry, to determine the current economic potential of DO-27. Both a "scrub-only" and "stand-alone" operation were investigated. For a "scrub-only" operation, a kimberlite concentrate with a grade up to ten times that of run of mine material would be produced at DO-27 by conventional open-pit mining, crushing and scrubbing techniques. The resulting concentrate would be transported elsewhere for final diamond recovery. For a "stand-alone" operation, rough diamonds would be recovered at the site by way of a conventional open-pit mining and diamond processing facility. The economics of a potential "scrub-only" project were determined by the PTA to be currently more favourable than a "stand-alone" operation.

 

AMEC investigated whether the DO-27 indicated mineral resource had the potential to pay back capital on an undiscounted cash flow basis. A preliminary financial analysis for a "scrub-only" mining operation was performed which achieved this objective, supporting the resource classification.

Although Peregrine management has concluded that the development of the DO-27 project is currently not economically justifiable, both the Company and AMEC believe that there is a reasonable chance that DO-27 could support a mining operation in the future. Factors that could enhance the economics of a mining operation at DO-27 include:

         Higher rough diamond prices.

         Possible underestimation of the average DO-27 diamond value because the current estimate is based on a parcel of only 2,075 carats.

         More favourable Canadian-US currency exchange rates.

         A diamond processing arrangement with one of the nearby diamond mines.

         Increased revenue potential from downstream cutting and polishing of DO-27 diamonds.

         Mining and processing technology advances.

         Regional infrastructure developments.

         An ultimate run of mine grade greater than the current grade estimated by reverse circulation ("RC") drill samples.

Eric Friedland, CEO of Peregrine stated "This independent resource calculation and associated PTA is the result of over three years of hard work by many people, much of it under harsh conditions with difficult technical challenges. We were successful in proving that the diamond grade of DO-27 is almost three times higher than previously estimated and the work was to a standard and quality that allows for the formal classification of a resource. Data from the resource and engineering studies in combination with future diamond valuations will give Peregrine the ability to efficiently assess the economic potential of DO-27 on an ongoing basis. At a time of projected future shortfalls in diamond supply and expected increases in rough diamond prices, the diamond resource at DO-27, which is contained within one large kimberlite, close to existing diamond mining infrastructure, is well-positioned as a candidate for future development."

 

DO-27 Resource Statement

The reported mineral resource for the DO-27 kimberlite extends to a depth of approximately 325 metres below surface. Canadian Institute of Mining and Metallurgy ("CIM") standards and securities commission disclosure requirements require that a resource can only be declared on a mineral deposit that has "reasonable prospects of economic extraction". AMEC determined that DO-27 met these criteria by generating a Lerches-Grossman ("LG") economic pit shell for a "scrub-only" operation, using the Whittle software package. Following are the assumptions used by AMEC in their analysis:

 

         Diamond Prices:  On December 17, 2007, Peregrine reported that the modelled diamond value for a 2,075 carat parcel ranged from US $43-70 per carat, with a base case of US $51 per carat. The valuation is summarized in Table 1. The valuation was completed in Antwerp Belgium in late 2007 under the supervision of WWW International Diamond Consultants Ltd. ("WWW"), an internationally recognized diamond valuation and consultancy company. The "High" diamond price of US $70 per carat was used for pit shell generation. There is a high degree of uncertainty in the modelled value of the larger stones that would be expected in a production scenario in a parcel of only 2,075 carats. The values of large stones typically have the most significant impact on overall average diamond value. WWW has stated that it is highly unlikely that the ultimate average price of DO-27 goods will be lower than the "Low" values and that the "High" values should not be considered maximum values.

Table 1: DO-27 Diamond Valuation Results

Weight Of Valuation Sample (Carats)(1)

Largest Diamonds (Carats)

"Base Case" Diamond Price Model (US$/Carat)(2)

"High" Diamond Price Model (US$/Carat)(2)

"Low" Diamond Price Model (US$/Carat)(2)

2,075(1)

9.45, 7.03, 7.11, 6.03, 5.17, 4.84, 4.35, 4.19

$51

$70

$43


(1) Sample weight represents the total carat weight of diamonds larger than the 1 DTC sieve size (approx. 0.85 mm) presented for valuation following the combination of individual sub-samples from the 2005, 2006 and 2007 bulk sampling programs and after acid cleaning.

(2) As determined by WWW International Diamond Consultants Ltd. from their October 31, 2007 price book

         Grade: The average estimated diamond grade within the LG pit shell is 94 cpht. At DO-27, there is a lack of sample data from actual mined material or drill core with which to compare the RC results. AMEC stated that in their experience, RC drilling commonly underestimates the diamond content of kimberlites being sampled and grade increase factors as high as 150 to 200 percent have been encountered. For the purposes of this resource estimate however, no adjustment has been made to the estimated grade.

         Confidence Category: AMEC has treated the DO-27 resource as a bulk mining scenario with a consistent grade of 94 cpht and no internal waste. Local variations in block grades may not be fully reflected in the resource block estimates. The indicated mineral resource can only be converted to a mineral reserve using no cut-offs or selectivity assumptions.

         Metallurgical Recovery: 100 percent.

         Mining Costs: US $2.05 per tonne of ore or waste incremented by US$0.02 per per tonne per ten metre depth.

         Operating Costs: US $19.96 per tonne, for a "scrub-only" operation including an estimate for trucking to and processing by a third party diamond recovery facility in the area and general and administrative costs.

         Stripping Ratio: Life of mine 6.3:1

         Capital Costs: US $400-500 million for a "scrub-only" operation.

         Pit Slopes: Granite pit slope inter-ramp angles ranging from 45� to 53�.

Mineral Services Canada Inc. provided AMEC with a three dimensional model of DO-27. An external pipe shell was defined and the internal geology of the pipe was established; the dominant pipe infill, which comprises approximately 86 percent of the pipe volume, is primary pyroclastic kimberlite ("KIMB 1"). AMEC then produced a block model with 10 metre by 10 metre by 5 metre blocks. The tonnage for each block was calculated by multiplying the volume of each block by a density determined from a three dimensional density model developed by AMEC. The density model was based on 507 specific gravity measurements on drill core from throughout the body performed by Teck Cominco's Global Discovery Labs in Vancouver. There is a trend of increasing density with depth and towards the margins of DO-27 as the near-surface material and the kimberlite in the central part of the pipe is highly weathered, making this material very amenable to mechanical reduction to a high diamond grade kimberlite concentrate. The reported tonnage for the indicated resource and the potential mineral deposit is restricted to those blocks that fall within the KIMB-1 wireframe.

 

The three dimensional model of the DO-27 kimberlite and the tonnage and resource estimates are based on data from 66 core holes totalling 17,300 metres and 46 large diameter (35-61 cm) RC holes totalling 8,800 metres. A cumulative 3,200 dry tonnes of bulk sample material collected from the RC holes was processed for final diamond recovery at the bulk sample test facility at BHP Billiton's Ekati(tm) Diamond Mine. A geological model of DO-27 can be viewed at http://www.pdiam.com/i/pdf/DO27.pdf.

 

A NI 43-101-compliant Technical Report on the DO-27 project that contains the details of the resource estimate is in preparation by AMEC and will be posted on SEDAR and Peregrine's website within 45 days.

 

DO-27 Potential Mineral Deposit

AMEC considers an additional 6.5-8.5 million tonnes of kimberlite for DO-27 to be a potential mineral deposit based on an analysis of the drill hole data and the three dimensional model. This potential mineral deposit consists of the continuation of the diamondiferous kimberlite at depth below the limits of the indicated resource, from approximately 325 to 425 metres below surface, and it is currently delineated by eight core holes and two RC holes. DO-27 remains open at depth and additional tonnage could be defined with subsequent drilling. A grade of 90-100 cpht was assigned to the 6.5-8.5 million tonnes by extending the approximate grade of the indicated resource. The potential quantity and grade of this potential mineral deposit is conceptual in nature and there has been insufficient exploration to define the potential mineral deposit as a mineral resource. It is uncertain whether further exploration will result in this potential mineral deposit being delineated as a mineral resource

 

Preliminary Technical Assessment Study

In early 2007, AMEC was awarded the contract to assist with Peregrine's internal PTA of the DO-27 project. The PTA included a conceptual model of a potential diamond mine based on the preliminary geological model available in 2007. The study examined several operating scenarios and development concepts, focusing on kimberlite processing, waste rock and processed kimberlite disposal, water management and overall project footprint. AMEC provided some order-of-magnitude capital and operating cost estimates that might be realized for different project development scenarios. These studies were conceptual in nature and not prepared to a standard of detail that would allow disclosure under Canadian NI 43-101 guidelines. Following is a summary of the engineering work that has been completed to date.

 

In 2006 Peregrine retained EBA Engineering Consultants Limited ("EBA") to undertake a geotechnical assessment of potential DO-27 pit slopes to assist with the design of the conceptual open pit mine scenarios. Using the geotechnical data provided by EBA, a preliminary Whittle open pit optimization study was undertaken by AMEC in 2007 as part of the PTA in order to establish the potential size of a conceptual one million tonne per year and two million tonne per year mining operation and associated waste dump and site layout. An optimal pit shell was selected, conceptual mine production schedules were developed and an equipment fleet was selected to match the proposed mine output.

 

Processing test work was completed at SGS Lakefield for both the "stand-alone" and a "scrub-only" operation. The "stand-alone" plant would be a typical open pit kimberlite mining and diamond processing operation where rough diamonds are recovered at the site. For a "scrub-only" operation, a kimberlite concentrate, with grades as high as 940 cpht, would be produced and trucked elsewhere for diamond recovery. The DiavikTM and EkatiTM Diamond Mines are located 27 kilometres northwest and 57 km north of DO-27 respectively. Scrubbing tests were completed and 890 kg and 270 kg of core were subjected to low pressure and high pressure scrub tests respectively. As the DO-27 kimberlite is relatively soft and highly weathered, especially in the upper portions of the pipe, a large amount of the kimberlite was washed away as -1.00 mm fines after only three to four minutes of scrubbing at normal water pressures. Kimberlite collected from 61-121 metres depth had a scrubbing concentration factor of 10:1 from run of mine material. More competent material collected from depths of 121-181 metres and 181-275 metres depth had concentration factors of approximately 3.3:1 and 2.3:1 respectively. Therefore, under these conditions, kimberlite with a grade of 94 cpht in the upper 121 metres of the pit could be upgraded to a concentrate with a grade of 940 cpht. Tests showed that the addition of a tertiary crushing circuit and high pressure washing would achieve even higher concentration ratios. Pre-concentrating the kimberlite has the benefit of reducing the amount of material that would need to be transported to and processed by a third party diamond recovery facility. In addition, the capital and operating costs for a "scrub-only" processing plant would be significantly less than for a full diamond recovery circuit. A summary of the scrubbing test was reported by Peregrine in a news release dated July 24, 2007.

 

AMEC examined the infrastructure requirements for a conceptual project at DO-27 based on analogous diamond mine configurations consistent for a remote site in the Arctic. Using the conceptual mine plan, processing plant and infrastructure layouts, AMEC calculated order-of-magnitude ranges of capital and operating costs.

 

Future Work

Peregrine will, on an on-going basis, continue to evaluate the economics of DO-27 in the context of changes to rough diamond prices, mining and processing technology developments, the state of nearby diamond mines, US-Canadian currency exchange rates and factors affecting capital and operating costs. The existing 2,075 carat diamond parcel is available for valuation in the future should diamond prices increase. The wealth of engineering and geological data that was generated from the bulk sampling programs, the PTA and the resource estimation, provides an excellent foundation from which a future decision to advance the project to the feasibility stage can be made.

 

Diamond prices continue to rise and industry experts predict that without significant new discoveries in the coming years, the global demand for diamonds could outstrip supply as early as next year with associated accelerated increases in rough diamond prices.

 

DO-27 is situated within three mining leases totalling 1,500 hectares on the WO property that are in good standing until 2023. The leases are renewable for multiple additional 21 year terms after 2023. Peregrine is committed to keeping local First Nations groups informed on project developments and the Company has an excellent record of employing individuals from the local communities.

 

In addition to the WO property, which also hosts the four hectare, diamondiferous DO-18 kimberlite, 700 metres north of DO-27, Peregrine holds an additional 165,000 hectares of highly prospective mineral claims in the region. Concurrent with ongoing evaluation of DO-27, Peregrine will continue to systematically explore its mineral claims in the area in an effort to make a diamondiferous kimberlite discovery that could complement a potential mining operation at DO-27.


 

Qualified Person Statement

Jennifer Pell, (Ph.D., P.Geo.), Chief Geoscientist for Peregrine Diamonds Ltd., is the Qualified Person under NI 43-101, for work on the DO-27 kimberlite. Mr. Howard Coopersmith (B. Sc.,P.Geo.), an internationally recognized consultant to the diamond industry, was Peregrine's external Qualified Person for the 2005, 2006 and 2007 bulk sampling programs. Dr. Pell and Mr. Coopersmith have reviewed this press release and approve of its contents.

 

Mr. Ken Brisebois (B.A.Sc.,P.Eng.) and Mr. Ted Eggleston (PhD., P. Geo.) of AMEC are the independent Qualified Persons who supervised the preparation of the mineral resource estimate for the DO-27 kimberlite. Mr. Brisebois has 22 years of worldwide experience in mining resource and reserve assessments and related work and has worked on several diamond resource estimates in North America. His specialties include technical resource and reserve risk assessment, resource and reserve audits, geostatistical and geological modelling, ore and grade control and resource classification. Mr. Eggleston has more than 30 years of worldwide experience in exploration and development of mining properties including work on several diamond projects in North America. Messrs. Brisebois and Eggleston have reviewed the statements regarding the mineral resource estimate in this press release and approve of its disclosure.

 

For further information, please contact Brooke Clements, President, Eric Friedland, CEO, or Peregrine Diamonds Investor Relations, at 604-408-8880 or at investorrelations@pdiam.com."

 

 

 

 

 

ON BEHALF OF THE BOARD

 

'signed'

 

 

Ellen Clements, Director

President & CEO

 

Contact Larry Widmer 250 878 5099 or Ellen Clements 1 800 856 3966

 

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this news release.

 

Données et statistiques pour les pays mentionnés : Canada | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous

Kettle River Resources Ltd

EXPLORATEUR
CODE : KRR.V
ISIN : CA4927051082
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Kettle est une société basée au Canada.

Kettle détient divers projets d'exploration au Canada.

Ses principaux projets en exploration sont TAM O'SHANTER, BLUEBELL (ORO DENERO), RAINBOW JV et GREENWOOD AREA au Canada.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Projets de Kettle River Resources Ltd
10/09/2008(Greenwood Area)Final Drill Results from Greenwood Area properties
23/08/2008(Greenwood Area)Drill program results for Greenwood Area Properties
18/07/2008(Arcadia (skylark))News Release
Communiqués de Presse de Kettle River Resources Ltd
05/11/2015IIROC Trading Halt - KRR; EMT
21/07/2015New Nadina Explorations Limited to Acquire Kettle River Reso...
25/06/2008DO-27 DIAMOND PROJECT INDICATED MINERAL RESOURCE
07/05/2008Work starts on Greenwood Area Properties
21/02/2008Kettle River News
19/02/2008RECEIVES SOIL SAMPLE RESULTS AND ADDITIONAL TRENCH ASSAYS
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TSX-V (KRR.V)Other OTC (KRRSF)
0,005+0.00%0,001-50.00%
TSX-V
CA$ 0,005
06/11 15:45 -
0%
Cours préc. Ouverture
0,005 0,005
Bas haut
0,005 0,005
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,005 -50,00%
Volume var. 1 mois
45 000 -50,00%
24hGold TrendPower© : -2
Produit
Développe
Recherche Copper - Nickel - Platinum
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,49 AU$+0,13%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,76 US$+1,29%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,54 GBX-0,92%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,59 CA$-0,38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
15,15 CA$+0,80%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$-7,84%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 AU$+0,00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,79 CA$-2,72%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
50,54 US$+0,40%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+0,00%Trend Power :