Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en

Medusa Mining Ltd

Publié le 09 avril 2015

Co-O Mine Geology & Service Shaft Updates

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   K Street | Philippines | Report |

Co-O Mine Geology & Service Shaft Updates

MEDUSA MINING LIMITED

ABN: 60 099 377 849

Unit 7, 11 Preston Street

Como WA 6152

PO Box 860

Canning Bridge WA 6153

Telephone: 618-9367 0601

Facsimile: 618-9367 0602

Email: [email protected]

Internet: www.medusamining.com.au

ANNOUNCEMENT

9 April 2015

Co-O MINE GEOLOGY & SERVICE SHAFT UPDATES

(ASX: MML)

Medusa Mining Limited ("Medusa" or the "Company"), through its Philippines operating company, Philsaga Mining Corporation ("PMC"), wishes to advise that significant progress has been made with respect to the potential and predictability of the Co-O Mine geology for long term planning.

The Service Shaft to Level 8 (approximately 390 metres below surface) has been approved at a cost of US$10 million (± 20%) with a construction time of approximately 17 months and an estimated payback period of 1.4 years. Surface earthworks and underground Alimak rising have commenced.

Geoff Davis, CEO of Medusa, commented:

"The advances in the geological understanding of the large Co-O vein system greatly enhance our ability to plan for the future, as well as demonstrate the considerable upside beyond the current resources and reserves that will support a long life future. The mine to 30 June 2014 has produced approximately

630,000 ounces, and at the same date had 1.4 million ounces of total resources.

The Service Shaft will greatly improve the efficiency of the Co-O Mine with respect to the transport of men and materials, supervision, safety, and ore haulage. This is an important step in improving our haulage systems for the future."

Co-O MINE GEOLOGY

The key points from the extensive review, re-interpretations and re-modelling of the geology of the Co-O Mine over the last 2 years are:
(i) The 3 main veins, Central, Jeremy and GHV are continuous over a strike length of at least
1.5 kilometres, and are open to the east. Figure 1 shows only the GHV resource model.
(ii) The horizontal length of the best mineralised core of the vein system is approximately 800 metres, and this core plunges to the east at approximately 30°, as depicted on Figure 1. Economic mineralisation does occur outside the core zone, but is less consistent.
(iii) The Co-O diatreme breccia (see 2012 Annual Report) disrupts the up-dip sections of some of the north dipping vein mineralisation in some down-plunge positions (Fig 2). In addition a consistent shatter zone which is approximately 50-100 metres wide has now been identified peripheral to the diatreme, within which the veins' continuity and characteristics dissipate and are generally not economic to mine.
(iv) Proximal to the eastern part of the Co-O vein system, the near surface underside of the diatreme and shatter zone's flare dips shallowly at approximately 10° to the south, and becomes steeper to approximately 50° dip with increasing depth, diverging away from the north-dipping veins, and hence the veins are interpreted to be open down-plunge (Fig 2).
(v) Some resource blocks currently extend (and are open) to beyond Level 12 (550 metres below Level 1). Additional drilling rigs will be added to the underground drilling programme from drill chambers on Level 8 to drill out the zone between Levels 12 and 16 to justify the case for an L16 Shaft to Level 16 (750 metres below Level 1).
(vi) Comparison with other similar epithermal vein systems, such as the Vera Nancy system in North Queensland, currently being mined by Evolution Mining Limited, shows significant similarities as shown in Figure 3. The Vera Nancy system has a 4 kilometre strike length (Co-O has so far been mined over 1.5 kilometres), a similar shallow plunge to its mineralisation, and a similar vertical extent of economic mineralisation.

Figure 1. Co-O Mine long section showing the Resource Model (2014) for the GHV vein, and the projected downplunge continuation of the mineralisation corridor.

Figure 2. Cross-section through the L16 position.

Figure 3. Longitudinal projection showing the Co-O vein system with the superimposed Vera Nancy vein system.

SERVICE SHAFT

Background

The Service Shaft has been approved by the Board at an estimated cost of US$10 million to an accuracy of ± 20%, excluding new mine buildings and other surface support facilities, with a construction time of approximately 17 months. Its position is shown on Figure 1. Initial surface earthworks are in progress and underground Alimak rising work has commenced.
The Service Shaft with a rope-guided cage is being sunk to significantly improve the working efficiency of the mine in lieu of the existing series of external and internal shafts that service the mine workings from Level 3 to Level 8. This improvement will include increased broken rock hoisting capacity of the L8 Shaft through the removal of the current men and materials transport within the L8 Shaft.
The design and ordering of long lead time engineering items is well advanced.
Completion of the Service Shaft will increase the L8 Shaft rock hauling capacity to approximately 1,700 dry tonnes per day (dptd) from 1,400dptd following the recent L8 Shaft upgrade, and the total mine capacity to approximately 2,700dtpd from all shafts, thereby matching the mill capacity subject to the availability of ore from underground operations.

Service Shaft Details

The Service Shaft will provide access for the bulk of the workforce until the commissioning of the conceptual L16 Shaft. The main transport role of the Service Shaft will only decline after nominally ten years as the production below 8L increases to a point when the levels above 8L are only undertaking remnant mining and general maintenance.
Hence, the "centre of gravity" of the Co O Mine's supervision and support personnel that is located at the present Mine Office near the portals and L8 will move to the Service Shaft for a four or more year period, thence to the proposed L16 Shaft over a ten or more year period.
The Service Shaft will:

service the existing working levels between 3L and 8L for a nominal ten year life and is considered within an overall life of mine shaft plan involving the existing Agsao and Baguio Shafts to 5L, the L8 Shaft to 8L, a proposed L16 shaft to 16L and conceptual ventilation shafts;

be collared at the E15 position so that an existing underground 50m vertical shaft and 100 metres of coincident Alimak raises can be incorporated into the new shaft design, thereby reducing cost and completion time;

have outside cage dimensions of 2.65 metres by 2.20 metres with a load capacity of 3 tonnes to allow all current mine equipment to be transported without the need to break down and re-assemble the equipment; and

transport 30 men to and from work each lift thereby reducing dramatically the travel time to and from work places.

Business Case

The business case is based on the increased production rate that can be achieved from the Co- O Mine through improved L8 Shaft broken rock hoisting following the removal of the present men and materials hoisting from the L8 Shaft. This will result in the L8 Shaft being employed solely for broken rock hoisting for which it was originally designed.
The estimated payback period is 1.4 years based on the current production schedule.

DISCLAIMER

This announcement contains certain forward-looking statements. The words 'anticipate', 'believe', 'expect', 'project', 'forecast', 'estimate',

'likely', 'intend', 'should', 'could', 'may', 'target', 'plan' and other similar expressions are intended to identify forward-looking statements. Indications of, and guidance on, future earnings and financial position and performance are also forward-looking statements. Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond the control of Medusa, and its officers, employees, agents and associates, that may cause actual results to differ materially from those expressed or implied in such statements. Actual results, performance or outcomes may differ materially from any projections and forward-looking statements and the assumptions on which those assumptions are based. You should not place undue reliance on forward-looking statements and neither Medusa nor any of its directors, employees, servants or agents assume any obligation to update such information.

Lire la suite de l'article sur www.noodls.com
Données et statistiques pour les pays mentionnés : Philippines | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Philippines | Tous

Medusa Mining Ltd

EXPLORATEUR
CODE : MML.AX
ISIN : AU000000MML0
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Medusa Mining est une société de production minière d'or et de cuivre basée en Australie.

Medusa Mining détient divers projets d'exploration aux Philippines.

Ses principaux projets en exploration sont CO-O, CORPLEX, ABACUS, ANOLING et APICAL aux Philippines.

Medusa Mining est cotée au Canada, au Royaume-Uni, en Australie et en Allemagne. Sa capitalisation boursière aujourd'hui est 125,7 millions AU$ (90,7 millions US$, 89,2 millions €).

La valeur de son action a atteint son plus haut niveau récent le 03 juin 2011 à 8,60 AU$, et son plus bas niveau récent le 27 juin 2017 à 0,27 AU$.

Medusa Mining possède 207 790 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Présentations des Compagnies de Medusa Mining Ltd
05/09/2016Investor Presentation September 2016
14/02/2011Investor Presentation February 2011
18/08/2008Aegis report
16/06/2008 BGF Equities Research Report
12/03/2008Fairfax ResearchContent-class: urn:content-classes:message
31/07/2007 Quarterly Activity Report
11/03/2007Investor Presentation
Dans les médias de Medusa Mining Ltd
17/06/2008Building a low cost production base with blue sky potential
13/03/2007Broker Report
Rapports annuels de Medusa Mining Ltd
: 2013 Annual Report
: 2011 Annual Report
Annual Report and Notice of Meeting
2006 Annual Report
Nominations de Medusa Mining Ltd
31/05/2013: Retirement and Appointment of CFO
25/01/2013: New Board Appointments
09/06/2011Board Restructure Following TSX Delisting to Oversee the Nex...
09/07/2010Appointment of Non-Executive Chairman
15/02/2010Appointment of director
15/09/2009Appointment of Director
Rapports Financiers de Medusa Mining Ltd
21/02/2012: Interim Financial Results
27/04/2011March 2011Quarterly Report
22/02/2011MEDUSA ACHIEVES RECORD HALF-YEAR PROFIT
07/09/2009Records strong 2009 financial results
Projets de Medusa Mining Ltd
08/04/2013(Co-o): Co-O Mill & Mine Expansion Update
21/02/2013(Co-o): Co-O Drilling Update
18/10/2012(Co-o): Co-O Mine Shafts Update
15/08/2012(Co-o): Co-O Mine Geology and Mineralisation Update
10/07/2012(Co-o): Co-O Drilling Update
10/07/2012(Co-o)Limited: Co-O Drilling Update
16/04/2012(Co-o): Co-O Drilling Update
21/03/2012(Co-o): Co-O Operations-Unscheduled Mill Maintenance
05/04/2011(Co-o)Co-O DRILLING CONTINUES HIGH GRADE RESULTS
01/12/2010(Saugon) - Saugon Drilling Expands High-Grade Gold-Silver Potential
30/06/2010(Co-o)Co-O Mine Update
29/03/2010(Co-o)Co-O Mine drilling update
16/03/2010(Co-o)Co-O expanded mill commissionning
17/07/2009(Co-o)Co-O mine reserve now 500 000 ounces
19/01/2009(Co-o) Co-O MINE RESOURCES INCREASED 40% TO 1.2 MILLION OUNCES
01/12/2008MAJOR NEW HIGH GRADE VEIN DISCOVERY
12/08/2008(Co-o)Co-O MINE RESOURCE EXPANSION
07/05/2008(Co-o)WIDE-HIGH GRADE INTERSECTION AT Co-O MINE
26/03/2008(Co-o)Co-O MPSA GRANTED
21/01/2008(Co-o)NEW CATTO VEIN EXTENSIONS DISCOVERED
01/10/2007(Co-o)Co-O Mine Expansion
04/09/2007713,000 resource ounces and growing
15/08/2007CO-O MINE RESOURCE DRILL HOLE RESULTS
09/07/2007New Discoveries
20/06/2007(Anoling)POSITIVE RESULTS FROM ANOLING GOLD PROJECT
16/05/2007(Co-o)Co-O Mine Update
19/03/2007(Anoling)Anoling Gold Project tenements granted
23/05/2006Tambis project exploration, Philippines
Communiqués de Presse de Medusa Mining Ltd
20/06/2016Relocation of Office Premises
09/05/2016Investor Presentation May 2016
06/05/2016Market Briefing May 2016 – Medusa Mining Ltd
02/05/2016Cancellation of Unquoted Securities (Options)
05/04/2016Terms of Appointment of CEO
21/03/2016CEO Appointment
22/01/2016CEO Appointment Update
20/01/2016Exploration Pipeline and Tenement Review
18/01/2016L8 Shaft Upgrade
18/01/2016Mineral Resources and Reserves Statement Addendum to 2014 An...
18/01/2016Cancellation of Unquoted Securities
09/10/2015Notice of Annual General Meeting and Proxy Form
05/10/2015Investor Presentation October 2015
25/09/2015Annual Mineral Resources & Ore Reserve Update Statement
04/09/2015Annual Mineral Resources Update Statement
03/09/2015Asset Impairment of US260M
27/08/2015ASX Appendix 4E and Financial Results for ended year June 30...
27/08/2015Full Year Results 2015
28/07/2015Investor Presentation July 2015
27/07/2015Quarterly Report June 2015
07/07/2015Co-O Mine Service Shaft Update
13/04/2015Investor Presentation April 2015 – Zurich and London
09/04/2015Co-O Mine Geology & Service Shaft Updates
21/01/2015Exploration Pipeline and Tenement Review
16/01/2015L8 Shaft Upgrade
12/01/2015Cancellation of Unquoted Securities
12/01/2015Mineral Resources and Reserves Statement Addendum to 2014 An...
09/12/2014Appendix 3Z – Directors Final Notice (Gary Raymond Powell)
21/11/2014Results of Annual General Meeting November 2014
20/11/2014Executive Appointments
13/02/2014Fatality Underground
13/02/2014Medusa Mining Limited: Fatality Underground
31/01/2014Medusa Mining Limited Quarterly Activities Report: Period En...
28/01/2014Operations Update
28/01/2014Medusa Mining Limited: Operations Update
21/01/2014Operations Update
29/10/2013: Quarterly Activities Report Period Ended 30 September 2013
23/10/2013: SAG Mill Update
04/09/2013: Operations Update-New Mill and Level 8
31/07/2013: Quarterly Activities Report Period Ended 30 June 2013
08/07/2013(Co-o): Co-O Operations Update
02/05/2013: Quarterly Activities Report Period Ended 31 March 2013
15/04/2013: Investor Presentation April 2013
30/10/2012: Quarterly Activities Report Period Ended 30 September 2012
29/08/2012: Full Year Results
06/08/2012(Co-o): Co-O Mine Mineral Resource Update
31/07/2012: Quarterly Activities Report Period Ended 30 June 2012
30/04/2012: Investor Presentation May 2012
24/04/2012: Quarterly Activities Report Period Ended 31 March 2012
10/02/2012: Investor Presentation February 2012
30/01/2012December 2011 Quarterly Report
17/01/2012: Bananghilig Deposit Drilling Update
16/12/2011: Appendix 3B
05/12/2011: Issue of Performance Rights
24/10/2011: Investor Presentation
29/08/2011Achieves Record Full Year Profit
24/08/2011ASX Announcement
22/08/2011(Co-o): Co-O Mine Mineral Reserve Estimate
28/07/2011ASX Announcement - Quarterly Report
25/01/2011- Medusa Quarterly Report
24/05/2010AIM cancellation & admission to the official list
07/05/2010Copper portfolio - Lingig update
08/03/2010Bonus issue of shares
25/01/2010Notice of no corporate associations
09/10/2009Lingig drilling extends mineralisation
12/08/2009ASX Announcement
03/07/2009MML - ASX Ann - S&P/ASX 200 Index
22/06/2009ASX Announcement
01/06/2009MML - ASX Announcement
26/02/2009UNDERWRITTEN A$24.5 MILLION PLACEMENT
28/01/2009Quarterly Report
05/11/2008ASX Announcement
23/09/2008ASX Announcement
19/09/2008Crosby Makes $182 Million Takeover Bid for Medusa Mining
20/08/2008ASX Announcement
25/07/2008ASX Announcement
10/06/2008ASX Announcement
11/04/2008Joint Venture With Bunawan Mining Corporation
14/03/2008Half Year Financial Report – 31 December 2007
25/02/2008IRON ORE TARGETS IDENTIFIED
13/11/2007LINGIG PORPHYRY COPPER DISCOVERY
31/10/2007 QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2007
16/08/2007Ambrian Morning Research
01/08/2007Heads of Agreement and Placement with Sierra Mining Ltd
16/07/2007Barobo Mineralised Corridor
13/06/2007 Acquisition of Co-O Mine Royalty
25/05/2007Equity Research
15/05/2007ASX Announcement
30/04/2007Quarterly Report March 2007
21/03/2007Releases
08/03/2007 Dismissal of motion for reconsideration on CO-o mise
13/06/2006appointement of nominated advisor & broker - AIM London
17/05/2006Acquisition of Apical gold project, Philippines
10/04/2006Alternative Investment Market (AIM) London
16/03/2006half year financial report 31 december 2005
30/01/2006Gold Production started, increasing quickly from here
21/01/2006ANALYSIS : MEDUSA MINING
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (MML.AX)TORONTO (MLL.TO)
0,605-15.38%7,43-0.80%
AUSTRALIA
AU$ 0,605
08/07 11:00 -0,110
-15,38%
Cours préc. Ouverture
0,715 0,615
Bas haut
0,600 0,625
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,605 -%
Volume var. 1 mois
123 619 -%
24hGold TrendPower© : -44
Produit
Développe
Recherche Gold
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 02/03/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
Variation annuelle
DateVariationMaxiMini
2022-14,79%0,950,60
2021-7,79%0,990,66
20200,00%1,070,40
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,52 AU$+0,47%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
12,02 US$-0,25%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,59 GBX+9,83%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,66 CA$+0,76%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,14 CA$+1,89%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,20 AU$-4,76%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,84 CA$-1,60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
51,03 US$+0,33%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+0,00%Trend Power :