Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
AnglaisFrancais
Cours Or & Argent en
Dans la même rubrique

Sherwood Copper Corp.

Publié le 25 février 2008

Reports 2007 Production Results & 2008 Production Estimate for Minto Mine

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Canada | Copper | K Street | Zinc |

SUITE 860 - 625 HOWE STREET Ÿ VANCOUVER, BC  Ÿ V6C 2T6  CANADA Ÿ TEL: (604) 687-7545  FAX: (604) 689-5041

PRESS RELEASE

FOR IMMEDIATE RELEASE

 

February 25, 2008                                                                                                                        #08-08

 

Sherwood Reports 2007 Production Results & 2008 Production Estimate for Minto Mine

Higher Production Increases Exposure to Current High Metal Prices while Downside is Protected

 

VANCOUVER, BRITISH COLUMBIA - Sherwood Copper Corporation (SWC: TSX-V) today announced its operating results for 2007, which included production of 9.66 million pounds of copper in concentrate including 5.35 million pounds of copper in the fourth quarter of 2007.  This production level is less than set out in the 2006 detailed feasibility study (?DFS?) but in line with revised forecasts set out in the 2007 pre-feasibility study (?PFS?) as a result of decisions to (1) process lower grades during the commissioning and ramp up of the mill in order to avoid unnecessary metal losses until recoveries reached design levels and, (2) to construct the Phase 2 mill expansion earlier than contemplated in the DFS, resulting in some production being deferred into 2008 as the plant expansion was constructed and tied in.  

 

In addition, Sherwood announced its production estimate for 2008 of approximately 55 million pounds of payable copper and 24,000 oz of payable gold, significantly higher than projected in its 2006 DFS, as a result of (1) completing the Phase 2 mill expansion earlier than planned and (2) further optimization of the open pit schedule for 2008, resulting in higher grade ore being processed sooner.  In fact, for the next several months, grades mined from the pit are forecast to exceed 4% copper, but mill feed will likely be capped at 4% copper in order to not overload the circuit with too much concentrate.

 

?Our copper & gold production from the high grade Minto copper-gold mine was very close to the revised target for the entire year and in the first quarter of commercial production,? said Stephen Quin, President & CEO.  ?This is a tremendous achievement for our operating personnel, especially given the challenges inherent in commissioning a new mine and in tying in the Phase 2 mill expansion while still operating the mine,? he added.  ?Further, Sherwood has been successful in advancing a number of project optimizations to the point that they could be brought into our production plans, boosting metal production estimates for 2008 and beyond.  Additional opportunities for further enhancements and increases in production are still being evaluated as part of Sherwood?s relentless pursuit of value.?

 

Sherwood Objectives

Sherwood?s objective for the Minto Mine is twofold: firstly to aggressively increase reserves and production in a staged manner, resulting in a natural dehedging through increased production and, secondly, to continually optimize and improve the production profile and costs of operation through its relentless pursuit of value.  In both of these areas, Sherwood has made considerable progress since the DFS was published in mid-2006, but continues to strive to extract maximum value from its Minto Mine to the benefit of all stakeholders, as discussed below.  In addition, Sherwood recently acquired a controlling interest in Western Keltic Mines, which owns the high grade Kutcho copper-zinc-silver-gold project in NW British Columbia.  Based on what is a very similar scale of project, this acquisition provides Sherwood with the opportunity to repeat its experience at Minto to repeat the successful optimization, construction and operation at Kutcho.

 


Forward Sales

As a result of the expanded production profile outlined in the recently completed PFS, forward sales now account for approximately 50% of the next four years production and approximately 32% of current life-of-mine production.  This represents a marked decrease in forward sales from the previously forecast 75% of its metal production in the first four years based on production levels set out in the original DFS.  A decrease in forward sales provides Sherwood with increased exposure to current high spot prices for copper, gold and silver.  The percentage forward sold excludes any consideration of potential production from the Kutcho project, which is entirely unhedged.  Details of the current forward sales positions on a quarterly basis are attached to this press release.

 

2007 Operating Results

Key operating statistics for the Minto Mine in the third and fourth quarters of 2007, and for the entire year (including waste stripping for the entire 12 months and limited concentrate production in the second quarter of 2007), are presented below.  All costs and production prior to October 1, 2007 were capitalized, and commercial operations commenced on October 1, 2007.

 

 

Q3/2007

Q4/2007

Total 2007*

Tonnes mined

2,836,571

2,299,882

14,919,032

 - Ore

495,870

131,162

700,398

 - Waste**

2,340,701

2,168,720

***14,218,634

Ore grade

 

 

 

- Copper (%)

1.69%

2.02%

1.70%

- Gold (g/t)

0.45

0.61

0.45

- Silver (g/t)

7.0

7.6

6.8

Mill throughput

 

 

 

- Tonnes processed

117,382

100,811

238,446

- Copper grade (%)

1.90%

2.57%

2.16%

 - Gold grade (g/t)**

N/A

N/A

N/A

 - Silver grade (g/t)

6.9

9.1

7.7

Recoveries

 

 

 

 - Copper

78.1%

93.7%

85.1%

 - Gold*

N/A

N/A

N/A

 - Silver

68.6%

87.7%

77.5%

Concentrate

 

 

 

- Tonnes produced (dmt)

4,965

7,086

12,630

- Copper grade (%)

35.1%

34.3%

34.7%

- Gold grade (g/t)*

N/A

N/A

N/A

 - Silver grade (g/t)

112.4

113.8

113.0

Contained Metal

 

 

 

- Copper (lbs)

3,837,143

5,350,602

9,662,003

- Gold (oz)*

N/A

N/A

N/A

- Silver (oz)

17,940

25,932

45,890

* From June ? December 2007 inclusive, except the mining quantities are inclusive of all pit production

 through the end of 2007

** Gold is not assayed on site, resulting in a significant lag in receiving this data.

*** Includes capitalized pre-stripping treated as pre-production costs in the DFS.

 

The key points related to the 2007 and early 2008 production are as follows:

v      Copper recoveries are now averaging 93-94% on a consistent basis with individual days as high as 98% versus plan of 90-93%, while concentrate grades have averaged 37% versus plan of 30-33% during commissioning of the Phase 2 expansion.

v      As previously disclosed through 2007, mill throughput was hampered in the early months of operation by poor mechanical performance of the flotation cells and limitations in the tailings and concentrate filtration.  By year-end 2007, these issues had been resolved and the plant is currently ramping up to full capacity of 2,400 tonnes per day, with minor on-going tie-ins completed in January and February 2008.  In the meantime, when throughput is less than full capacity, higher than planned grade has been fed to the mill (2.6 - 2.9% versus 1.9 - 2.0% planned) so that copper metal production in each of December 2007 and January 2008 have met budget.

v      Reconciliation of ore mined during 2007, based on blast hole assays, suggest approximately 18-20% more tonnes of ore at similar grades as compared to those estimated in the reserve block model used in the DFS and PFS.  This upside was an opportunity identified in the 2006 DFS.  The higher tonnages are an encouraging trend, but no definitive conclusions can be made until additional data is generated throughout the reserves.

v      Stripping at the Minto pit is accelerated in the early years and decreases thereafter, as set out in the PFS.

v      Sherwood currently has more than 13,000 dmt of concentrate stored between the Skagway ore terminal and its on-site storage facility at Minto, with a ship scheduled to pick up approximately 10,000 tonnes of concentrate in early March.

 

Production Outlook & Forward Sales

As announced December 12, 2007, Sherwood reported details of an independent pre-feasibility (?PFS?) for the Minto Mine that incorporated a Phase 3 expansion of the mill commencing in 2009 and the mining of the Area 2 deposit commencing in 2011.  The following table summarizes the estimated payable metal production set out in the PFS and the quantities forward sold.  This combination provides significant downside protection but considerable upside opportunity as production plans increase.

 

 

 

Pre-Feasibility Study (Dec. 2007)

 

 

 

2008

2009

2010

2011

2012

2013

2014

2015

Total/Ave.

 

 

 

 

 

 

 

 

 

 

 

Payable Copper

000's lbs Cu

57,155

51,778

81,666

42,491

44,527

23,501

37,833

8,951

347,903

 - Copper Forwards

000's lbs Cu

25,190

32,825

27,798

24,251

 

 

 

 

110,064

 - Average forward pricing

US$/lb

$2.85

$2.49

$2.19

$2.41

 

 

 

 

2.5

 - Uncommitted copper

000's lbs Cu

31,965

18,954

53,868

18,240

44,527

23,501

37,833

8,951

237,839

 - Copper committed (%)

 

44.1%

63.4%

34.0%

57.1%

0.0%

0.0%

0.0%

0.0%

31.6%

 

 

 

 

 

 

 

 

 

 

 

Payable Gold

Oz Au

24,504

18,662

35,455

21,059

19,998

8,670

14,982

2,567

145,897

 - Gold Forwards

Oz Au

12,126

14,424

14,025

13,520

 

 

 

 

54,095

 - Average forward pricing

US$/oz

 $653

 $653

 $653

 $718

 

 

 

 

$669.45

 - Uncommitted Gold

Oz Au

12,378

4,238

21,430

7,539

19,998

8,670

14,982

2,567

91,802

 - Gold committed (%)

 

49.5%

77.3%

39.6%

64.2%

0.0%

0.0%

0.0%

0.0%

37.1%

 

 

 

 

 

 

 

 

 

 

 

Payable Silver

000's oz Ag

262.1

262.4

436.1

195.5

180.7

96.4

122.4

32.3

1,588

 - Silver Forwards

000's oz Ag

162.8

156.6

132.0

151.4

 

 

 

 

603

 - Average forward pricing

US$/oz

$11.88

$11.90

$11.90

$13.50

 

 

 

 

$12.30

 - Uncommitted Silver

000's oz Ag

425

419

568

347

181

96

122

32

2,191

 - Silver committed (%)

 

62.1%

59.7%

30.3%

77.5%

0.0%

0.0%

0.0%

0.0%

38.0%

 

Achievement of production levels set out in the PFS in 2008 is dependent on achieving and maintaining design grades, throughput and recoveries, but is achievable with existing permits, while the production levels in years 2009 and beyond are also dependent on amendments to operating permits to increase mill throughput and permit mining the Area 2 deposit.  These forecasts take no account of exploration success in 2007 or the acquisition of the Kutcho project, which could result in increased unhedged production in future years.

 

An unusually long period of cold weather (minus 40 centigrade or below) in January and the first half of February did affect mining operations but, with more than 500,000 tonnes of ore stockpiled, the impact on milling operations was reduced.  On the processing front, the very cold primarily affected crusher operations leading to occasional shortages of feed for the mill, but operations were able to adjust by feeding higher grade ore to the mill, mitigating the impact on January production and, to a lesser extent, February?s production.  However, sufficient high grade ore is expected to be available from the pit to allow overall 2008 goals to be met.  A redesign of the crusher feed mechanism during the summer of 2008 should prevent this from being an issue going forward.

 

Sherwood also advises that the first and last quarters are projected to be lowest production quarters in 2008 due to the ore release schedule from the pit and, in the case of the first quarter, completion of commissioning and ramp-up to full Phase 2 mill capacity during the quarter.

 

Continued Optimization

As reported in the 2006 DFS, a number of opportunities to further optimize the Minto project beyond what was established in the DFS were identified.  Since that study, a number of these opportunities have been incorporated and were addressed in the recent PFS, while several others are ready to implement and others are a matter of on-going work.  The list following identifies these opportunities and updates the status on each.

1.      Accelerate Phase 2 mill expansion to 2,400 tonnes per day of throughput.  Construction was completed at the end of December, more than six months ahead of the feasibility schedule and commissioning is in progress with sustained tonnages of over 2,000 tonnes per day achieved to date.  Included in the PFS.

2.      Access grid power replacing more expensive diesel power.  Construction of the power line commenced late 2007 and is scheduled for completion before the end of 2008.  Line clearing and route survey is well advanced.  Included in the PFS.

3.      Reduce waste stripping by steepening the pit walls.  A geotechnical program completed in early 2007 has allowed steepened pit walls to be utilized since mid-2007.  Included in the PFS.

4.      Utilization of coarser grinding in the mill, allowing increased throughput for minimal capital expenditures.  Extensive metallurgical bench scale test work in 2007 confirmed that mill throughput can be increased significantly by utilizing a coarser grind with minimal impact on recoveries, which is the basis for the Phase 3 mill expansion to 3,500 tonnes per day incorporated in the PFS.  Full scale testing of coarser grinding in the Minto mill will likely occur in 2008.

5.      Rescheduled mining of the open pit bringing grade (and therefore higher metal production) forward.  Given the northern part of the pit has higher copper grades, significantly higher precious metal grades and higher recoveries, and generates a higher grade concentrate (resulting in lower transportation and smelting costs per unit of metal), combined with current high metal prices, developing the pit northward in the early years from the initial cut, as opposed to southward, is expected to result in higher metal production and increased profitability.  A preliminary version of a rescheduled pit is used in the PFS, resulting in increased production in 2008 vs. the DFS (from grade alone, assuming no throughput increase) and in 2009 and 2010 from a combination of higher grade and higher throughput.  An additional iteration of this mining plan is currently being reviewed, with the objective of moving some of the exceptionally high grade production in 2010 forward into late 2008 and 2009.

6.      Benefit from positive reserve reconciliation.  As noted above, the blast hole assay data suggests approximately 18-20% more ore tonnes mined to date versus the reserve block model used in the DFS and PFS.  This is likely due to undersampling of historic core and a number of other factors and was identified as an opportunity in the DFS.  The trend observed to date will continue to be monitored and has not been incorporated in the PFS; Sherwood views this as an unquantified upside opportunity.

7.      Increased reserves.  Given the ability to increase mill throughput for minimal capital, the single biggest opportunity to increase value of the Minto Project is to add reserves.  The 2006 Area 2 discovery was incorporated into the PFS, but the exploration successes of 2007 at Area 118, the southeast corner of Area 2 and Ridgetop offer near term potential for resource additions which were not included in the PFS.  Resource estimates are in process for these areas, and additional drilling in planned in 2008 to more fully evaluate the potential of these and to drill test other areas.

8.      Improved copper recoveries in the southern pit area.  In the DFS, copper recovery for a limited amount of tonnage in the southern area of the Minto pit was assumed to be 75% in the DFS based on historic test work.   Based on bench scale test work conducted during 2007 the recovery for this material has been increased to 85% in the PFS.  Further metallurgical test work conducted in 2007 on all other ore in the pit, aside from this one area, yielded recoveries in the 93-94% range, as used in the PFS.

9.      Gravity gold recovery.  In addition to a base recovery of approximately 74% assumed in the DFS, coarse visible gold has been observed in core during 2006-2007 drilling and a field trial of a gravity gold recovery circuit is planned for mid- to late 2008.  This opportunity has not been incorporated in the PFS.

10.  Waste dump relocation.  The PFS identified possible alternative locations for the waste rock dumps, which could reduce waste haulage costs.  In order to determine the viability of these alternatives, geotechnical drilling is required, which will commence before the end of February.  These geotechnical holes will be extended into bedrock to test buried geophysical targets that could represent additional mineralization not previously evaluated.

 

Kutcho Project

Now that Sherwood has acquired 91.7% ownership of Western Keltic Mines, owner of the high grade Kutcho copper-zinc-gold-silver deposit in northwestern British Columbia, Sherwood has begun its process of reassessing the development options for the deposit.  Sherwood?s objective will be to take a more Minto-like approach to the development of Kutcho, potentially by focusing on the rapid development of a smaller scale, lower capital cost operation that is focused on high grade production up front.  In order to achieve this objective, Sherwood intends to:

1.      Update the current resource estimate;

2.      Re-design the open pit to optimize grade and tonnage production;

3.      Re-scope the project scale to optimize profitability, while reducing capital;

4.      Initiate an in fill drill program to better define near surface mineralization and higher grade trends, and re-optimize the open pit;

5.      Conduct a metallurgical program focused on optimizing process design and recoveries to feasibility standards and explore opportunities to increase recoveries;

6.      Continue the permitting process with the relevant authorities;

7.      Engage local stakeholders, including First Nations, through community consultations.

 

More definitive information on the scope and timing of these activities will be provided as they are developed.

 

Sherwood

Sherwood?s successful consolidation of the ownership of the Minto Project provides a unique investment opportunity ? participation in a high-grade, open pit copper-gold mine located in Canada with tremendous exploration potential on the property.   Aggressive exploration, in parallel with successful mine development and operations, provides Sherwood the opportunity to grow from within through resource and reserve additions in pursuit of further production expansions.  Sherwood plans to continue this "growth from within" strategy, along with further operational optimizations and the pursuit of merger & acquisition opportunities, in its relentless pursuit of value.  In parallel, Sherwood aims to repeat its success with the Minto project at the Kutcho project.

 

Quality Assurance

The technical information in this news release has been prepared in accordance with Canadian regulatory requirements set out in National Instrument 43-101 and reviewed by Stephen P. Quin, P. Geo., President & CEO for Sherwood Copper Corporation.  The exploration activities at the Minto project site are carried out under the supervision of Brad Mercer, P. Geol., Exploration Manager with Sherwood.  The operational information relating to the Minto Mine in this release have been carried out under the supervision of Ian Berzins, P.Eng., General Manager of the Minto Mine and Kevin Weston P.Eng., Chief Operating Officer for Sherwood Copper.

 

Additional Information

Additional information on Sherwood and its Minto Project can be obtained on Sherwood?s website at http://www.sherwoodcopper.com.

 

On behalf of the board of directors

SHERWOOD COPPER CORPORATION

?Stephen P. Quin?

Stephen P. Quin

President & CEO

 

 

 

 

 

For further information please contact Stephen Quin, President of Sherwood Copper Corp.

or Brad Kopp or Kristy Reynolds at (604) 687-7545 or (888) 338-2200

** INTERNET ADDRESS: www.sherwoodcopper.com **

 

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this press release.

 

This document may contain "forward-looking statements" within the meaning of Canadian securities legislation and the United States Private Securities Litigation Reform Act of 1995. These forward-looking statements are made as of the date of this document and the Company does not intend, and does not assume any obligation, to update these forward-looking statements.

 

Forward-looking statements relate to future events or future performance and reflect management's expectations or beliefs regarding future events and include, but are not limited to, statements with respect to the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of resources; possible variations in ore reserves, grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, all of which are filed and available for review on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.


Accordingly, readers should not place undue reliance on forward-looking statements.

 


Sherwood Copper Corporation

Summary of Forward Sale Contracts (as of February 20, 2008) to Accompany Press Release Dated February 25, 2008

 

COPPER

 

 

 

GOLD

 

 

SILVER

 

 

Weighted Average

 

 

 

Weighted Average

 

Weighted Average

 

Year

Tonnes

Lbs

Price (US$/t)

Price (US$/oz)

Year

OZS

Price (US$/oz)

Year

OZS

Price (US$/oz)

2008 Q1

1,233

2,718,300

6,500.40

2.95

2008 Q1

2,291

653.42

2008 Q1

31,733

11.90

2008 Q2

4,261

9,393,897

6,401.23

2.90

2008 Q2

4,358

652.83

2008 Q2

61,514

11.87

2008 Q3

3,357

7,400,918

6,322.63

2.87

2008 Q3

2,220

653.98

2008 Q3

34,881

11.86

2008 Q4

2,575

5,676,903

5,957.85

2.70

2008 Q4

3,257

653.48

2008 Q4

34,664

11.90

Total 2008

11,426

25,190,018

6,288.92

2.85

Total 2008

12,126

653.33

Total 2008

162,792

11.88

 

 

 

 

 

 

 

 

 

 

 

2009 Q1

3,624

7,989,552

5,768.53

2.62

2009 Q1

3,959

653.45

2009 Q1

40,636

11.90

2009 Q2

4,184

9,224,141

5,572.36

2.53

2009 Q2

3,883

653.46

2009 Q2

42,017

11.90

2009 Q3

3,700

8,157,104

5,381.96

2.44

2009 Q3

3,291

653.42

2009 Q3

36,963

11.90

2009 Q4

3,381

7,453,829

5,184.07

2.35

2009 Q4

3,291

653.42

2009 Q4

36,963

11.90

Total 2009

14,889

32,824,626

5,484.62

2.49

Total 2009

14,424

653.44

Total 2009

156,579

11.90

 

 

 

 

 

 

 

 

 

 

 

2010 Q1

3,381

7,453,829

5,036.62

2.28

2010 Q1

3,291

653.42

2010 Q1

36,963

11.90

2010 Q2

3,381

7,453,829

4,895.54

2.22

2010 Q2

3,414

653.44

2010 Q2

34,693

11.90

2010 Q3

3,015

6,646,937

4,757.50

2.16

2010 Q3

3,660

653.49

2010 Q3

30,153

11.90

2010 Q4

2,832

6,243,491

4,620.02

2.10

2010 Q4

3,660

653.49

2010 Q4

30,153

11.90

Total 2010

12,609

27,798,087

4,838.48

2.19

Total 2010

14,025

653.46

Total 2010

131,962

11.90

 

 

 

 

 

 

 

 

 

 

 

2011 Q1

2,832

6,243,491

4,541.62

2.06

2011 Q1

3,660

653.49

2011 Q1

30,153

11.90

2011 Q2

3,352

7,389,895

5,405.54

2.45

2011 Q2

3,620

727.58

2011 Q2

40,005

13.83

2011 Q3

3,612

7,963,097

5,704.59

2.59

2011 Q3

3,600

765.25

2011 Q3

44,931

14.47

2011 Q4

1,204

2,654,366

5,655.37

2.57

2011 Q4

2,640

727.69

2011 Q4

36,327

13.26

Total 2011

11,000

24,250,849

5,308.66

2.41

Total 2011

13,520

717.58

Total 2011

151,416

13.50

 

 

 

 

 

 

 

 

 

 

 

TOTAL

49,924

110,063,580

5,466.74

2.48

TOTAL

54,095

669.45

TOTAL

602,749

12.30

 

 

Données et statistiques pour les pays mentionnés : Canada | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous

Sherwood Copper Corp.

CODE : SWC.V
CUSIP : 82442N 103
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Sherwood Copper est une société développant des projet miniers de cuivre basée au Canada.

Sherwood Copper est cotée au Canada et aux Etats-Unis D'Amerique. Sa capitalisation boursière aujourd'hui est 56,5 millions CA$ (46,4 millions US$, 36,8 millions €).

La valeur de son action a atteint son plus haut niveau récent le 31 décembre 2007 à 8,26 CA$, et son plus bas niveau récent le 21 novembre 2008 à 1,01 CA$.

Sherwood Copper possède 53 853 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Rapports annuels de Sherwood Copper Corp.
2007 Annual report
Financements de Sherwood Copper Corp.
29/02/2008 Signs Committed Term Sheet for Corporate Credit Facility wi...
15/02/2008 Announces $7.2 million Flow-through Financing
Nominations de Sherwood Copper Corp.
01/04/2008Makes Key Appointments to its Board & Management
16/01/2008 Appoints Kevin Weston as Chief Operating Officer
Rapports Financiers de Sherwood Copper Corp.
27/08/2008Reports Continued Strong Financial Results for the Three Mon...
22/07/2008Reports Increased Copper Production & Reduced Costs in Secon...
30/05/2008Reports Strong Results from Operations in First Quarter 2008
Projets de Sherwood Copper Corp.
26/01/2009(Minto Mine)Capstone Mining Corp. Commences US$ 3 Million Resource Expan...
10/12/2008(Minto Mine)Capstone Mining Corp. Reports Final Drill Intercepts of Nea...
13/11/2008(Kutcho Creek)Increases Continuity of High Grade Copper Trend at its Kutch...
07/11/2008(Minto Mine)Raises US$37.5 million from Minto Precious Metal ProductionT...
04/11/2008(Minto Mine)Reports New Copper-Gold Discovery at Minto Mine and possible...
22/09/2008(Kutcho Creek)Reports Further High Grade Intercepts from its Kutcho Copper...
18/09/2008(Minto Mine)Reports Thick Intervals of Near Surface Copper-Gold Minerali...
02/09/2008(Kutcho Creek)Reports Multiple High Grade Intercepts from its Kutcho Coppe...
28/08/2008(Minto Mine)Reports High Rainfall temporarily restricts access to its Mi...
21/08/2008(Minto Mine)Reports Further High Grade Copper-Gold Results From Areas 2 ...
17/07/2008(Minto Mine)Releases Further High Grade Copper-Gold from Area 2 & Area 1...
14/07/2008(Kutcho Creek)Reports High Grade Intercepts from the Kutcho Drill Program
17/06/2008(Minto Mine)Announces Significant Increase in Copper-Gold Resources at M...
17/04/2008(Minto Mine)Reports Minto Copper-Gold Mine Achieves & Exceeds Design Cap...
10/03/2008(Kutcho Creek) Completes Funding Arrangements for Kutcho Project & Begins ...
25/02/2008(Minto Mine)Reports 2007 Production Results & 2008 Production Estimate f...
13/02/2008(Minto Mine)Intersects High Grade Copper-Gold Mineralization in 4 Separa...
14/01/2008(Minto Mine)Intersects High Grade Copper-Gold Mineralization at Area 118...
18/12/2007(Minto Mine) Reports Phase 2 Mill Expansion at Minto Copper-Gold Mine Co...
12/12/2007(Minto Mine) Reports Results of Pre-feasibility Study for Expansion of M...
07/12/2007(Minto Mine)Reports Groundwork has Commenced on Carmacks to Stewart Tran...
03/12/2007(Minto Mine)Intersects High Grade Copper-Gold Mineralization at Ridgetop...
29/10/2007(Minto Mine) Intersects High Grade Copper-Gold Mineralization at Area 11...
25/10/2007(Minto Mine) Ships first Minto Mine Concentrates from Skagway
25/09/2007(Minto Mine)Receives Encouraging Results From 2007 Gradient IP Geophysic...
19/09/2007Discovers High Grade at Airstrip & Expands High Grade at Are...
05/09/2007(Minto Mine)Reports "On budget & Ahead of Schedule" Phase 1 Construction...
25/07/2007(Minto Mine)Delivers First Concentrates from Minto Mine to Port of Skagw...
15/06/2007(Minto Mine)Phase 2 Exploration Program Underway at Minto Copper-Gold Mi...
12/06/2007(Minto Mine)Reports Excellent Metallurgical Test Results from Area 2 at ...
24/05/2007(Minto Mine)Discovers High Grade Copper-Gold Mineralization in Minto 'Ga...
24/04/2007(Minto Mine)Awarded Funding from the Yukon Government to Advance Area 2 ...
12/04/2007(Minto Mine)Expands Scope of Pre-feasibility Study on Minto Copper-Gold ...
11/04/2007Accelerates Phase 2 Mill Expansion at Minto Copper-Gold Mine...
Communiqués de Presse de Sherwood Copper Corp.
23/01/2009Capstone Mining Corp. Reports Debt Repayments, Funding of De...
24/12/2008Capstone Mining Corp. Mails Offer to Purchase to its Debentu...
24/11/2008Reports Cash Flow from Mining Operations of $29.9 million in...
21/11/2008Announces Closing of Precious Metal Transaction
19/09/2008sets Shareholder Meeting Date for Capstone Combination
05/08/2008Reports Higher Copper Production Forecast for 2009 & Updated...
25/07/2008Reports Phase 3 Mill Throughput Increase to 3,200tpd Approve...
30/06/2008Finalizes Exploration Agreement with Northern Tiger Resource...
12/06/2008Reports Results of Preliminary Economic Assessment for Kutch...
05/06/2008Holds Successful Annual Meeting & Reports on Strategic Objec...
28/05/2008and Western Keltic Announce Closing of Business Combination
07/04/2008and Western Keltic Mines Inc. Announce Planned Business Comb...
06/03/2008 Increases Holdings to Approximately 93% of Western Keltic S...
03/03/2008Signs Exploration Memorandum of Understanding with Firestone...
22/02/2008Acquires 91.7% of Western Keltic Shares & Extends Offer for ...
12/02/2008Takes up 85.6% of Western Keltic Shares & Extends Offer for ...
30/01/2008Extends Offer for Western Keltic Mines to February 11, 2008
24/12/2007 Mails Offer for Western Keltic Mines
26/11/2007 Announces Agreement for Acquisition of Western Keltic Mines
29/10/2007 Appear on BNN TV
12/10/2007 Holds the Official Opening Ceremony for the Minto Mine, Yuk...
04/10/2007 Reports that Minto Mine Declares Commercial Production
17/07/2007Identifies Two Extensive Copper-Gold Systems at Minto Projec...
16/07/2007Reports Geotech Program Results in Improved Pit Slopes at Mi...
29/05/2007reports Yukon Utilities Board Approves Revised Power Purchas...
15/05/2007reports Yukon Government Support for Revamped Power Purchase...
10/05/2007Nominates Industry Leader for election to its Board of Direc...
02/05/2007Announces Yukon Utilities Board Turns Down Provisions of the...
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TSX-V (SWC.V)
1,05-7.89%
Dernières informations avant suppression de la cote
Cours préc. Ouverture
1,14 1,04
Bas haut
1,02 1,12
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  1,05 -%
Volume var. 1 mois
0 -%
Produit
Développe
Recherche
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 07/09/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,70 AU$-0,65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,94 US$+9,34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,54 GBX-2,55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,69 CA$+13,03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
15,60 CA$+1,83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,20 AU$+2,63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,87 CA$+5,65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,61 US$+0,98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :