LNG Ltd.

Published : May 04th, 2015

Magnolia LNG Project EPCC Phase Status Update

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Magnolia LNG Project EPCC Phase Status Update

Microsoft Word - Release ASX 2015-05-04 EPCC Contract Final.docx

ASX/MEDIA RELEASE

4 May 2015

MAGNOLIA LNG PROJECT EPCC PHASE STATUS UPDATE

Highlights:

EPCC Contract Terms & Conditions agreed with KBR‐SK E&C Joint Venture (KSJV)

Clough‐CH∙IV selected to provide Owner's Engineer Services for MLNG

Project activities being arranged to align with regulatory process calendar

Liquefied Natural Gas Limited (ASX: LNG; OTC ADR: LNGLY) (the Company) is pleased to advise that its wholly owned subsidiary, Magnolia LNG LLC (MLNG) has taken two significant steps in readiness for the engineering, procurement, construction and commissioning (EPCC) phase of the Magnolia LNG Project to be located in Lake Charles, Louisiana, USA.
In early January 2015, MLNG had initialled off on the EPCC contract with SK E&C Group. Kellogg Brown & Root LLC (KBR) then joined the Magnolia LNG project as the lead partner in an integrated joint venture with SK E&C (together, the KBR‐SK joint venture, or KSJV). MLNG and KSJV have now agreed to terms and jointly initialled off on the updated EPCC contract including terms and conditions, full scope of work and all supporting contract schedules and attachments.
Additionally, MLNG has completed a tender process and has selected Clough‐CH∙IV to fulfil the roll of owners engineer for the EPC phase of the project. This will include providing technical and project execution support personnel to MLNG as oversight to the KSJV contractor activities as the project moves through detailed design, construction, commissioning and start‐up in support of delivering LNG from the first of the four planned 2 mtpa LNG trains by the end of
2018.
"The alignment of the project activities and planning with the regulatory process is critical to advancing the project at a pace to meet our commitments to deliver LNG to our customers by the end of 2018," said John Baguley, MLNG Chief Operating Officer. "Our execution plans and activities are established on this basis and also optimized to enable the sequential completion of the full four train, eight mtpa MLNG facility. The agreement with KSJV on the contract terms and conditions marks an important step, in that it forms the basis for the final lump sum turnkey pricing reflecting current market conditions, and timed to initiate site works consistent with the availability of the necessary permits and authorizations. This also allows the project to initiate an early works program to de‐risk the project schedule and maximize the use of the time available until our actual site works can begin."

ABOUT MAGNOLIA LNG:

The Magnolia LNG Project is 100% owned by Magnolia LNG LLC, which is a wholly owned subsidiary of Liquefied Natural Gas Limited. The project comprises the proposed development of an 8‐mtpa LNG project on a 115‐acre site, located on an established LNG shipping channel in the Lake Charles District, State of Louisiana, United States of America. The project is based on the development of four x 2 mtpa LNG production trains using the Company's wholly owned OSMR® LNG process technology.
Magnolia LNG's business model provides liquefaction services to LNG buyers who pay a monthly fixed capacity fee, plus all LNG plant operating and maintenance costs. LNG buyers contract for liquefaction services under two contract models - a Liquefaction Tolling Agreement, whereby the LNG export terminal is only responsible for processing natural gas into LNG, and an LNG Sales and Purchase Agreement under which the customer buys LNG on a free on board basis (FOB).

ABOUT LIQUEFIED NATURAL GAS LIMITED

Liquefied Natural Gas Limited is an ASX listed company (Code: LNG and OTC ADR: LNGLY) whose portfolio consists of 100% ownership of the following companies:
Magnolia LNG LLC (Magnolia LNG), a USbased subsidiary, which is developing an 8 mtpa
LNG export terminal, in the Port of Lake Charles, Louisiana, USA;
Bear Head LNG Corporation (Bear Head), a Canadian based subsidiary, which is developing an 8 mtpa LNG export terminal in Richmond County, Nova Scotia, Canada with potential
for further expansion;

Gladstone LNG Pty Ltd, a subsidiary which is progressing the 3.8 mtpa Fisherman's Landing

LNG (FLLNG) Project at the Port of Gladstone in Queensland, Australia; and

LNG Technology Pty Ltd, a subsidiary which owns and develops the Company's OSMR® LNG

liquefaction process, a mid‐scale LNG business model that plans to deliver lower capital and operating costs, faster construction, and improved efficiency, relative to larger traditional LNG projects.

For further information contact:

Mr Maurice Brand

Mr John Baguley

Mr Michael Mott

Managing Director/CEO

Chief Operating Officer

Chief Financial Officer

Liquefied Natural Gas Ltd.

Magnolia LNG LLC

Liquefied Natural Gas Ltd.

Level 1, 10 Ord Street

1001 McKinney Street, Suite 600

1001 McKinney Street, Suite 600

West Perth, WA 6005

Houston, TX, USA

Houston, TX, USA

+61 8 9366 3700

+1 713 815 6940

+1 713 815 6909

Liquefied Natural Gas Limited

Level 1, 10 Ord Street, West Perth WA 6005

Telephone: (08) 9366 3700 Facsimile: (08) 9366 3799

Email: [email protected]

Website: www.LNGLimited.com.au

Disclaimer

Forward-looking statements may be set out within this correspondence. Such statements are only predictions, and actual events or results may

differ materially. Please refer to our forward-looking statement disclosure contained on our website at www.LNGLimited.com.au and to the

Company's Annual Report and Accounts for a discussion of important factors that could cause actual results to differ from these forward-looking statements. The Company does not undertake any obligation to update publicly, or revise, forward-looking statements, whether as a result of

new information, future events or otherwise, except to the extent legally required.

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Australia | Canada | United States Of America | All
Gold and Silver Prices for these countries : Australia | Canada | United States Of America | All

LNG Ltd.

DEVELOPMENT STAGE
CODE : LNG.AX
ISIN : AU000000LNG0
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

LNG is a producing company based in Australia.

LNG develops natural gas in Australia.

Its main asset in development is GLASSTONE LNG PROJECT in Australia.

LNG is listed in Australia. Its market capitalisation is AU$ 22.1 millions as of today (US$ 17.0 millions, € 14.1 millions).

Its stock quote reached its highest recent level on April 24, 2015 at AU$ 5.00, and its lowest recent point on April 24, 2020 at AU$ 0.04.

LNG has 512 979 968 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of LNG Ltd.
Annual Report 2011
Nominations of LNG Ltd.
8/2/2013Change to LNG Ltd's Board of Directors
Project news of LNG Ltd.
2/20/2014Magnolia LNG Project Update
1/8/2014Magnolia LNG Project Update
12/16/2013Key 2013 milestone achieved at Queensland Curtis LNG project
12/13/2013$10.85 Million Raised To Progress Magnolia LNG Project USA
12/9/2013Equity Placement to Further Progress Magnolia LNG Project
11/29/2013Magnolia LNG Submits Draft Resource Reports on Schedule
11/10/2013Magnolia LNG Project Update
10/15/2013Magnolia LNG Project Files for Additional Export Approvals
10/8/2013Magnolia LNG Project Update - Progress On Track
9/11/2013Magnolia LNG Project Update - On Track
8/14/2013Enterprise Shareholders Approve Acquisition By LNG Energy Lt...
8/6/2013Magnolia LNG Project Approval Process
7/31/2013$10M Capital Raising to Progress Magnolia LNG Project, USA
7/26/2013Stonepeak Strategic Alliance and Project Equity Magnolia LNG
5/15/2013Gladstone Fisherman's Landing LNG Project Gas Supply Update
5/8/2013Magnolia LNG Project Monthly Progress Report No.1
1/28/2013Magnolia LNG Project Site Option to Lease Term Sheet Signed
1/20/2013Magnolia LNG Project
9/13/2012Gladstone Fishermans Landing LNG Project Gas Supply Progress
6/4/2012Gladstone Fisherman's Landing LNG Project Update
12/12/2011Gladstone Fisherman's Landing LNG Project Update
6/2/2008(Glasstone Lng Project)Gladstone "Fisherman's Landing" LNG Project - Arrow/Shell Al...
4/1/2008(Glasstone Lng Project)Gladstone Fisherman's Landing LNG Project
2/5/2008(Glasstone Lng Project)Gladstone LNG Project - Fisherman's Landing
Corporate news of LNG Ltd.
1/18/2016Investor Presentation
12/21/2015Appendix 3Y
12/21/2015Appendix 3B
12/18/2015Gas Natural Rioja to start work this month on installation o...
11/19/2015Chief Development and Chief Technical Officers Appointment
11/19/2015Results of Annual General Meeting
11/19/2015AGM Presentation
10/27/2015Appendix 4C
10/26/2015Australia: Gladstone LNG ships first liquefied natural gas c...
10/19/2015Annual Report 2015 - Shareholders' Version
10/16/201515.09.2015 Contract for purchase of liquefied natural gas fo...
10/14/2015Iran Could Trigger A Resource War On Several Fronts Other Th...
10/5/2015Response to ASX Price Query
9/15/2015Contract for purchase of liquefied natural gas for the purpo...
8/28/2015Appendix 4E
8/18/2015Appointment of General Counsel and Joint Company Secretary
8/17/2015National Energy Board Grants Export Licence to Bear Head LNG
8/10/2015Change in substantial holding
8/7/2015Appendix 3Y
7/30/2015Global Alliance With Chart Industries, Inc.
7/29/2015Appendix 4C
7/28/201550 years of LNG – August 2013: the world’s first transhipmen...
7/21/2015PRESS DIGEST- Canada - July 21
7/20/2015Bear Head Receives DOE Approval of Exports to FTA Countries
7/15/2015Honeywell To Improve Operations For Liquefied Natural Gas Pi...
4/24/2015Appendix 4C
4/23/2015Magnolia LNG Project Tolling Agreement Update - Me
4/20/201550 years of LNG – 1962: the first experiments on transportin...
4/20/2015ExxonMobil President Calls for Urgent Action on U.S. Liquefi...
4/8/2015Shareholder Presentation
4/6/2015DF will carry out the extension to a Liquefied Natural Gas t...
4/2/2015Bear Head LNG Files Updated Registration with NSE
4/1/2015Shareholder Presentations
3/18/2015Magnolia LNG Project Update From FERC
3/15/2015Bear Head LNG Receives Permit to Construct
3/12/2015Investor Presentation
3/6/2015Qatargas to restart LNG production Train 4 in late March aft...
3/3/2015LNG Ltd Plans Dual Listing in USA
3/2/2015Magnolia EPC Contractor Joint Venture Finalized
2/28/2015Lithuania signs non-binding deal for U.S. LNG
2/27/2015Half Year Report and Appendix 4D
2/25/2015US Patent Update for OSMR Technology
2/19/2015GDF SUEZ wins an important liquefied natural gas supply cont...
2/15/2015Bear Head LNG Takes a Major Step Forward in Canadian Process
1/15/2015US Patents Update
1/13/2015GP Strategies Completes Liquefied Natural Gas Trailer Loadin...
1/13/2015Investor Presentation
1/12/2015Gas tanker runs aground off Nigeria -traders
2/6/2014Pivotal LNG and WesPac Midstream LLC Selected to Serve TOTE'...
2/5/2014Magnolia LNG Opens Lake Charles Office
2/4/2014Magnolia LNG Signs EPC MOU with SKEC Group
1/29/2014Magnolia LNG signs Definitive Pipeline Capacity Agreement
11/26/2013Tolling Term Sheet Signed with LNG Holdings Corp for 1.7mtpa
8/20/2013Energy Ltd. Completes Acquisition of Enterprise Energy Resou...
7/19/2013Magnolia LNG - Significant Community and Government Support
7/17/20132 MTPA Tolling Term Sheet Signed with Gunvor - Magnolia LNG
6/25/2013Energy Ltd. to Acquire All of the Shares of Enterprise in Fr...
3/22/2013Magnolia LNG Pre Filing Request Approved
3/13/2013Magnolia LNG Pre Files for Approvals
8/23/2012Market Briefing - LNG Ltd MD on strategic gas supply
12/2/2011Martin Place Securities Report 1 December 2011
11/25/2011Change of Share Register
11/24/2011Results of AGM
10/7/2011Form 604 Notice of change of interests of substantial holder
10/6/2011Form 603 - Notice of initial substantial holder
9/21/2011Queensland Gas Pipeline Interim Feed Agreement
9/5/2011Gas Pipeline Licence Granted
8/1/2011Appendix 3X
8/1/2011Quarterly Report June 2011
7/20/2011Carbon Tax Impact
7/14/2011OSMR Technology Patents Update
7/13/2011HQCEC Share Placement Completed and Appendix 3B
7/11/2011HQCEC Receives Foreign Exchange Approval For Share Placement
2/5/2008Notice of Shareholder Meeting
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
Australia (LNG.AX)
0.043+0.00%
Australia
AU$ 0.043
02/26 10:00 -
0%
Prev close Open
0.043 0.043
Low High
0.043 0.043
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.043 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : 8
Produces
Develops Natural gas
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
Annual variation
DateVariationHighLow
20210.00%0.040.04
2020-77.37%0.210.04
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.52+0.47%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.99-0.50%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59+9.83%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.65+0.38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.07+1.45%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20-4.76%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.83-2.14%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 50.96+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :