VanEck Vectors Global Alternative Energy ETF

Published : November 24th, 2009

Receives Optimized Definitive Feasibility Study - Significantly Improved Economics -

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Canada | Copper | Debt | Gold | Lead | Palladium | Platinum | Silver | Storage | Water |

Marathon Receives Optimized Definitive Feasibility Study - Significantly Improved Economics -

TORONTO, Nov. 24 /CNW/ - Marathon PGM Corporation ("Marathon" or "the Company", MAR-TSX) received the optimized Definitive Feasibility Study ("DFS") covering its 100% owned Marathon PGM-Cu Project (the "Project"), located 10 km north of Marathon, Ontario. A summary of the DFS will be filed on SEDAR and posted on the Company's website upon receipt from Micon International Limited ("Micon"), within 45 days of this press release.

"The economics of the Marathon Project have been significantly improved due to a combination of factors. Improved metallurgical recoveries, increased reserves, a much improved mine plan and overall CAPEX reduction totaling C$92 million are the key drivers in this improvement," said Phillip Walford, Marathon's President and CEO. "The PGM metallurgy jumped by 3% for Pd, 7% for Pt and 7% for Au, which has improved the economics of the project as a whole and lead to additional reserves. The new mine plan has a higher efficiency which reduced the amount of mining equipment required. This superior set of economics sets the stage for our next phase of developing the Marathon Project. Everyone involved in the revision has given considerable effort in improving the feasibility study."

    -------------------------------------------------------------------------
    Summary highlights of the DFS are:                             Base Case
                                                    (3 year trailing average)
    -------------------------------------------------------------------------
    Undiscounted cash flow (pre-tax)                           C$847 million
    -------------------------------------------------------------------------
    Undiscounted cash flow (after tax)                         C$596 million
    -------------------------------------------------------------------------
    NPV @ 6% (after tax)                                    C$251 million
    -------------------------------------------------------------------------
    IRR (pre-tax)                                                        21%
    -------------------------------------------------------------------------
    IRR (after tax)                                                      17%
    -------------------------------------------------------------------------
    Payback period                                                 4.4 years
    -------------------------------------------------------------------------
    Proven and probable reserves contained
    -------------------------------------------------------------------------
      Copper                                                  497,233,000 lb
    -------------------------------------------------------------------------
      PGM+Au                                                    3,392,000 oz
    -------------------------------------------------------------------------
      Silver                                                    4,235,000 oz
    -------------------------------------------------------------------------
    Average annual metal production 1st 5 years
    -------------------------------------------------------------------------
      Copper                                                  37 million lbs
    -------------------------------------------------------------------------
      PGM+Au                                                      234,000 oz
    -------------------------------------------------------------------------
      Silver                                                      182,000 oz
    -------------------------------------------------------------------------
    Cash cost per PGM+Au oz (net of credits)
     life of mine                                       Negative US$14.40/oz
    -------------------------------------------------------------------------
    Cash cost per Cu lb (net of credits) life of mine    Negative US$0.25/lb
    -------------------------------------------------------------------------

The DFS examined the economics of developing and mining the Marathon PGM-Cu Project, a large polymetallic deposit in Northern Ontario, at a rate of 22,000 tpd. The project will produce a single concentrate containing copper, platinum, palladium, gold and silver.

Presented below are three different economic cases and metal price forecasts, used in the study.

    -------------------------------------------------------------------------
                         Base Case (3 Yr     Bank Variable   5 Year Trailing
                            Tr Prices)(1)       Forecast(2)         Prices(3)
    -------------------------------------------------------------------------
    Undiscounted cash flow
    -------------------------------------------------------------------------
      Pre-tax              C$847 million     C$816 million     C$637 million
    -------------------------------------------------------------------------
      After tax            C$597 million     C$577 million     C$453 million
    -------------------------------------------------------------------------
    Net present value
     @ 6% discount rate
    -------------------------------------------------------------------------
      Pre-tax              C$383 million     C$373 million     C$259 million
    -------------------------------------------------------------------------
      After tax            C$251 million     C$245 million     C$164 million
    -------------------------------------------------------------------------
    Average annual cash
     flow (pre tax)         C$74 million      C$71 million      C$55 million
    -------------------------------------------------------------------------
    Internal rate of return
    -------------------------------------------------------------------------
      Pre-tax                        21%               21%               17%
    -------------------------------------------------------------------------
      After tax                      17%               18%               14%
    -------------------------------------------------------------------------
    Capital investment
    -------------------------------------------------------------------------
      Pre-production       C$351 million     C$351 million     C$351 million
    -------------------------------------------------------------------------
      Life-of-mine         C$495 million     C$495 million     C$495 million
    -------------------------------------------------------------------------
    Payback period             4.4 years         4.2 years         5.2 years
    -------------------------------------------------------------------------
    Cash costs, net of
     credits
    -------------------------------------------------------------------------
      Per PGM+Au oz     Negative US$14.4            US$124           US$21.4
    -------------------------------------------------------------------------
      Per lb copper     Negative US$0.25  Negative US$0.96           US$0.00
    -------------------------------------------------------------------------
    1.  Base Case - Three Year Trailing Price, as of October 31, 2009: US
        $2.91/lb Cu; US$321/oz Pd; US$1,347/oz Pt; US$819/oz Au, US$14.10/oz
        Ag, US$/C$ exchange rate = 1.099.
    2.  Variable Forecast as at November 2009: US$2.50/lb Cu in 2013, US
        $2.00/lb Cu Long Term (LT), US$400/oz Pd LT, US$1,750/oz Pt LT, US
        $900/oz Au LT, US$13.00/oz Ag and US$/C$ exchange rate =
        1.10 from Bloomberg
    3.  Five Year Price Trailing Prices, as of October 31, 2009: US$2.63/lb
        Cu; US$293/oz Pd; US$1,206/oz Pt; US$695/oz Au, US$12.04/oz Ag, US$/C
        $ exchange rate = 1.131.

The DFS was managed and compiled by Micon and reserve estimates, mine design, scheduling and mine costing with support by Met-Chem Canada Inc. for process engineering and costing of the process and infrastructure and AMEC for the design and costing of the process solids (tailings) management systems. The DFS cost estimates are considered to be of an accuracy of +/-15%.

The DFS included modeling of an optimized engineered open pit design that resulted in a proven and probable mineral reserve estimate of 91 million tonnes containing 497 million pounds of copper and 3.394 million ounces of PGM and gold.

Mineral Reserve Estimate

Mineral reserves were based on a Whittle based open pit optimization and subsequent mine design, undertaken by Micon using the measured and indicated mineral resources, which were estimated by Micon and reported by Marathon in a press release dated October 9, 2008. The optimal pit shell produced by the Whittle software was used as a guideline for the design of the engineered pit. These final reserves have been modified slightly as a result of final mine plan changes. The table below shows the reserve statement for the Marathon deposit:

    -------------------------------------------------------------------------
                                         Pd      Pt      Au     Cu       Ag
    Classification          Tonnes     (g/t)   (g/t)   (g/t)    (%)    (g/t)
    -------------------------------------------------------------------------
    Proven                76,461,000   0.910   0.254   0.090   0.268   1.464
    Probable              14,986,000   0.435   0.147   0.060   0.138   1.318
    Total                 91,447,000   0.832   0.237   0.085   0.247   1.440
    -------------------------------------------------------------------------
    
    -----------------------------------------------------------------
                              Cu lbs  Pd Ozs  Pt Ozs  Au Ozs  Ag Ozs
    Classification             (X1M)  (000's) (000's) (000's) (000's)
    -----------------------------------------------------------------
    Proven                       452   2,237     625     222   3,600
    Probable                      46     209      71      29     635
    Total                        497   2,447     696     251   4,235
    -----------------------------------------------------------------

Open pit mining reserves were developed under the direction of Sam Shoemaker Jr., MAusIMM of Micon. Mr. Shoemaker is a Qualified Person ("QP") within the context of NI43-101.

The DFS base case demonstrates that the Marathon PGM-Cu Project generates strong cash flow under appropriate metal price assumptions. There is excellent potential to expand the resource and reserve base of the project by further exploration on the Company's extensive land position in the Marathon area and will add to mine life.

The two largest areas for adding resources are located immediately outside the Marathon designed pit and at the 100% owned Geordie Lake Deposit, located 14 km west of Marathon. Large blocks of PGM-Cu extend well beyond the current Marathon designed pit. These blocks were not included in the reserves due to economic constraints, but may represent future mining potential in later stages of mining. In addition, there are several known PGM-Cu mineralized zones on strike from the Marathon deposit that have not been fully explored.

The Geordie Lake Deposit has an existing measured and indicated resource of 25.99 mt grading 0.55 g/t Pd, 0.03 g/t Pt, 0.05 g/t Au, 0.35% Cu and 2.35 g/t Ag representing 456,800 oz Pd, 28,400 oz Pt, 45,800 oz Au, 195.7M lb Cu and 1,938,400 oz Ag. Mineralization at Geordie Lake is open down dip and to the north and south, which bodes well for open pit mining potential. The potential for additional PGM-Cu zones is high.

Location

The Marathon PGM-Cu Project is located 10 km north of Marathon, Ontario. The deposit is easily accessible from the Trans Canada Highway and is also close to the CP railway. Electrical power is easily accessible with the deposit being located within 1km from two spurs of OPG's electrical power grid. The region also benefits from a strong contractor and supplier base to the mining industry and an experienced mining workforce.

Capital Investment Program

The initial capital investment program amounts to C$351.1 million and is summarized below.

    -------------------------------------------------------------------------
                                                                  C$ million
    -------------------------------------------------------------------------
    Processing plant and infrastructure                                261.7
    -------------------------------------------------------------------------
    Tailings and water management                                        8.7
    -------------------------------------------------------------------------
    Owner's cost                                                         7.2
    -------------------------------------------------------------------------
    Pre-strip and other mining                                          24.3
    -------------------------------------------------------------------------
    Contingencies                                                       49.5
    -------------------------------------------------------------------------
    -------------------------------------------------------------------------
    Total Pre-production capital                                       351.1
    -------------------------------------------------------------------------
    -------------------------------------------------------------------------
    Life-of-mine CAPEX including Total Pre-production capital
     (net of salvage)(1)                                               494.6
    -------------------------------------------------------------------------
    -------------------------------------------------------------------------
    (1) Includes $120.8 million in Mining equipment that would be leased
        assuming 10% down payment and financing of the balance over 5 years
        at 9% p/a.

These updated pre-production and life of mine capital estimates are C$35 million and C$92 million lower than the 2008 Feasibility Study estimates, respectively. The main differences are lower plant equipment costs, removal of the process solids (tailings) thickening system, lower cost option for the process solids disposal management system and reduced mining capital due to a new mine design and schedule.

There are two solids disposal options for the Marathon Project. Both are technically and environmentally viable and will be presented in the NI 43-101 report and in permitting documents. The option used in the base case is the lowest cost of the two. The other option will cost C$50 million more over the life of the mine and will reduce the NPV of the base case to C$211 million.

Mining

The Marathon PGM Deposit will be mined utilizing conventional open pit mining equipment and practices with a total fleet of fourteen 228 tonne capacity haul trucks, two 27 m(3) diesel-hydraulic shovels, four production drills, a pre-shear drill and one 25 m3 wheel loader, and various ancillary equipment to support the mining operations, to be acquired over four years on a lease/purchase plan.

The open pit will operate on a year round basis and provide ore feed to an on-site processing plant and low-grade ore stockpile. The feed rate to the processing plant is designed to be 22,000 tpd ore. The pit will require the removal of a total of 3.6 mt of overburden and a total of 259.9 mt of waste rock (total 263.5 mt) over a mine life of 11.5 years. The overall waste tonnes to ore tonnes stripping ratio is estimated to be 2.88:1. The pit design includes inter-ramp pit slope angles that range from 48 to 55 degrees with the majority at 55 degrees.

The waste rock storage facility has been designed to hold the life-of-mine waste rock production and has a storage volume of 114 million m3 with a footprint area of 241 hectares.

Mineral Processing

The plant design comprises a sulphide flotation facility with a nominal throughput capacity of 22,000 tpd (8 mt per annum) based on 90% plant availability. Metallurgical recoveries are estimated at 90.8% for Cu, 71.0% for Pt, 80.1% for Pd, 79.9% for Au and 74.5% for Ag.

The process flowsheet and design criteria are based on extensive metallurgical testwork programs that were conducted at various laboratories, including SGS Lakefield located in Lakefield, Ontario and Xstrata Process Support based in Falconbridge, Ontario. The process includes primary and secondary crushing using conventional crushers, tertiary crushing using high pressure grinding rolls (HPGR), ball milling, conventional flotation and concentrate dewatering. Approximately 90,000 tonnes per year of a single bulk concentrate containing copper and high values of PGM, gold and silver will be shipped to a third party smelter.

Operating Costs

Total on-site cash operating costs are estimated at C$13.39 per tonne milled. Estimated average life-of-mine unit operating costs per tonne of ore processed are C$5.67/t for mining, C$6.85/t for processing and C$0.87/t for general and administration. The cost of mining ore and waste is C$1.48 per tonne.

Financing and Cash Resources

As at September 30, 2009, Marathon had $11.2 million in its treasury. The Company is examining a variety of different methods of securing the required funding to develop the Marathon Deposit, including joint ventures, royalty arrangements, project equity and debt instruments.

Technical Report

A NI 43-101 F1 Technical Report summarizing the DFS will be filed within 45 days on SEDAR and posted on the Company's website upon receipt from Micon.

Qualified Person

The revised Marathon DFS was prepared by Micon under the supervision of Richard Gowans, P.Eng., the independent QP. Mr. Gowans is President and Principal Metallurgist with Micon. Mr. Phillip Walford, President and CEO of Marathon, is the Company's designated QP for the purpose of the DFS. Mr. Gowans and Mr. Walford have reviewed and approved the contents of this press release.

About Marathon PGM Corporation:

Marathon is exploring resource development potential in the immediate vicinity of the Marathon deposit to expand mine life of the planned large tonnage, open pit mining operation. The Marathon deposit is one of the largest PGM-Cu reserves in Canada and is expected to grow with development of additional nearby resources. Marathon's optimized P+P reserve contains 2.447 million ounces of Pd, 696,000 ounces of Pt, 251,000 ounces of Au, 497 million lbs of Cu and 4.235 million ounces of Ag. Marathon also has development and exploration stage properties in southeastern Manitoba and western Newfoundland, respectively. Marathon's management plans to build on its experience through the advancement of its properties and by examining other strategic opportunities.

Cautionary Notes Concerning Estimates of Mineral Resources

This news release uses the terms measured, indicated and inferred resources as a relative measure of the level of confidence in the resource estimates that occur separate from the quoted mineral reserves. Readers are cautioned that Marathon's mineral resources associated with the Geordie Lake Deposit are not economic mineral reserves and that the economic viability of resources that are not mineral reserves has not been demonstrated. In addition, inferred resources are considered too geologically speculative to have any economic considerations applied to them. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies or economic studies except for Preliminary Assessment as defined under NI 43-101. Readers are cautioned not to assume that that further work on mineral resources will lead to mineral reserves that can be mined economically.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Except for statements of historical fact relating to Marathon, certain information contained herein constitutes "forward-looking statements". Forward-looking statements include statements that are predictive in nature, depend upon or refer to future events or conditions, or include words such as "expects", "anticipates", "plans", "believes", "considers", "intends", "targets", or negative versions thereof and other similar expressions, or future or conditional verbs such as "may", "will", "should", "would" and "could". We provide forward-looking statements for the purpose of conveying information about our current expectations and plans relating to the future and readers are cautioned that such statements may not be appropriate for other purposes. By its nature, this information is subject to inherent risks and uncertainties that may be general or specific and which give rise to the possibility that expectations, forecasts, predictions, projections or conclusions will not prove to be accurate, that assumptions may not be correct and that objectives, strategic goals and priorities will not be achieved. These risks and uncertainties include but are not limited to those identified and reported in Management's Discussion and Analysis for the year ended December 31, 2008.

Other than as specifically required by law, we undertake no obligation to update any forward-looking statement to reflect events or circumstances after the date on which such statement is made, or to reflect the occurrence of unanticipated events, whether as a result of new information, future events or results otherwise.

%SEDAR: 00020574E For further information: David Leng, P.Geo:. Tel: (416) 849-3432, Fax: (416) 861-1925, dleng@marathonpgm.com

.
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

VanEck Vectors Global Alternative Energy ETF

EXPLORATION STAGE
CODE : MAR.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Marathon PGM is a nickel and zinc exploration company based in Canada.

Marathon PGM holds various exploration projects in Canada.

Its main exploration properties are BIRD RIVER - PAGE BLOCK, MARATHON, BIRD RIVER - NI ZONE, BIRD RIVER - ZN & CU ZONE and GEORDIE LAKE in Canada.

Marathon PGM is listed in Canada and in United States of America. Its market capitalisation is 24.7 millions as of today (US$ 19.1 millions, € 15.9 millions).

Its stock quote reached its lowest recent point on August 14, 1998 at 0.02, and its highest recent level on June 03, 2011 at 7.50.

Marathon PGM has 47 442 200 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of VanEck Vectors Global Alternative Energy ETF
12/18/2009 Closes First Tranche of Non-Brokered Private Placement Flow...
Nominations of VanEck Vectors Global Alternative Energy ETF
8/8/2007 appoints Raymond Mason as VP of Operations
Financials of VanEck Vectors Global Alternative Energy ETF
8/15/2008Announces 2008 Q2 Financial Results
11/14/2007 Announces 2007 Q3 Financial Results
8/2/2007 Announces 2007 Q2 Financial Results
5/15/2007Announces 2007 Q1 Financial Results
Project news of VanEck Vectors Global Alternative Energy ETF
9/12/2013(Marathon)Marathon Trenching Adds 300m Strike-length to Mineralized Zo...
7/27/2010Cu Project Advances: Permitting, Financing and Metallurgy
7/21/2010(Marathon)Hits 33.54 g/t (uncut) Gold Across 4 m (0.98 oz/ton uncut ac...
3/22/2010(Geordie Lake)Excellent Geordie Lake Drill Results
11/24/2009(Marathon) Receives Optimized Definitive Feasibility Study - Significa...
10/7/2009(Geordie Lake)Development Plans for Geordie Lake Deposit
9/29/2009(Marathon) Wraps Up 2009 Campaign with 4.31 g/t PGM+Au and 0.19% Cu ov...
9/16/2009(Marathon)Drilling Program Hits High Grade Outside Pit Shell
9/10/2009(Marathon)Announces Analyst Day at Marathon PGM-Cu Project
9/8/2009(Marathon)Marathon's Drilling Pushing New Boundaries
7/6/2009(Marathon)Project DFS Being Optimized
6/10/2009(Marathon)Completes Purchase of Bamoos Land Package
6/12/2009(Bird River - Page Block)Marathon Intersects Sulphide Lenses at Coppermine Zone
6/1/2009(Marathon)Better Metallurgy and Economics
3/11/2009(Bird River - Page Block) Reports Positive Drill Results at Bird River
2/27/2009(Bird River - Page Block)Bird River Resource Expansion Continues
2/3/2009(Bird River - Page Block)Marathon Files Technical Report on Feasibility Study and Res...
1/15/2009(Bird River - Page Block) Develops Two Resources on Bird River Project
12/19/2008(Marathon)Project Receives Positive Feasibility Study
11/6/2008(Marathon)Project Receives Support from Pic River First Nation
8/12/2008Definitive Feasibility Study Update
7/29/2008(Marathon)Hits Thickest Ever Intersection of PGM-Cu Mineralization, 18...
7/16/2008(Bird River - Page Block)Ore Fault Drilling Hits 4.5m of 1.32% Ni, 0.14% Cu, and 1.31...
1/28/2008(Marathon) Entering into Option and JV Agreement with Benton Resources...
12/12/2007(Bird River - Page Block)Reviews Progress of 2007 and Plans for 2008
10/24/2007(Marathon)reports final holes of 2007 campaign and hits thickest ever ...
9/11/2007 intersects 44 m of 1.48 g/t PGM and gold and 0.36% copper o...
7/26/2007(Marathon)Drilling intersects 14.6 g/t PGM and gold and 0.18% copper o...
4/18/2007(Marathon)drills 8 m of 3.1 g/t PGM+Au in W Zone
4/4/2007(Marathon)drilling continues to expand W and RD Zones
3/21/2007(Marathon)Drilling Expands High Grade W Zone and Establishes New Poten...
2/17/2007(Marathon)hits high-grade Palladium, Platinum and Rhodium in 2 holes, ...
Corporate news of VanEck Vectors Global Alternative Energy ETF
7/28/2015Marret Resource Corp. Releases Q2 2015 Financial Statements
7/17/2015Marret Asset Management Inc. - Issuance of Early Warning Rep...
7/7/2015Marret Resource Corp. Announces Record Date and Distribution
6/29/2015Marret Resource Corp. Announces Results of Annual and Specia...
5/12/2015IIROC Trade Resumption - MAR
5/12/2015Marret Resource Corp. announces shareholder proposal
5/12/2015IIROC Trading Halt - MAR
5/6/2015Marret Resource Corp. Releases Q1 2015 Financial Statements
4/20/2015Marret Resource Corp. provides update
3/31/2015Marret Resource Corp. Releases 2014 Year End Financial State...
12/1/2014IIROC Trade Resumption - MAR
12/1/2014Marret Resource Corp. suspends dividend; Provides update
8/20/2014Marret Resource Corp. Announces Monthly Dividend
8/20/2014Marret Resource Corp. Announces Monthly Dividend
12/11/2013Completes Financing with Rambler and Announces Exploration P...
5/1/2013(Marathon)Marathon Intersects Multiple High-Grade Intervals while Unde...
1/16/2013Marret Resource Corp. announces participation in Cline Minin...
1/16/2013Marret Resource Corp. announces participation in Cline Minin...
10/6/2011(Marathon)Marathon Intersects Best Interval at the Leprechaun Gold Dep...
10/3/2011(Marathon)Marathon Continues to Expand the Leprechaun Gold Deposit wit...
8/11/2010Receives Initial Metallurgical
5/13/2010Announces 8,000 Meter Drilling
5/4/2010New Geordie Lake Resource: Increased Metals, Grade and
4/27/2010Joseph G. Spiteri Appointed to Marathon PGM
3/17/2010Drilling Confirms Near Surface Gold Mineralization at Leprec...
12/23/2009Enters Option and JV Agreement for Mountain Lake's Valentine...
8/26/2009Marathon Converting Waste to Ore
7/15/2009Improving Resources Classifications at Marathon
12/11/2008Project accepted into MPMO Projects List
9/4/2008Completes 2008 Drilling Program on BCF JV Property, Intersec...
8/27/2008Acquires Remaining Discovery Shares Pursuant to Compulsory A...
8/19/2008Growth Continues, Ore Fault Property Acquisition Completed
2/4/2008Cabo Awarded Marathon PGM Corporation Contract
1/7/2008 Fault Agreement Approved by Bird River Mines Shareholders, ...
11/1/2007Finalizes Option Agreement for Ore Fault and Plans Drill Cam...
10/11/2007and Bird River Mines Inc., Announce an Option Agreement for ...
10/4/2007 completes 40,000 m drilling campaign and expects new minera...
10/3/2007: CEO Interview
10/2/2007signs Memorandum of Understanding with the Ojibways of Pic R...
9/21/2007 Samples 7.09 g/t PGM and gold,
8/29/2007extends mineralized zone to 800 m at the Coppermine Zone, Bi...
8/24/2007acquires PGM-Ni-Cu property in the Steel Mountain Complex, N...
8/16/2007- CEO Interview
8/13/2007hits 6 m of 7.48 g/t PGM and gold and 0.06% copper in W Hori...
7/12/2007discovers additional mineralization outside perimeter of exi...
6/28/2007drilling discovers mineralization outside of resource open p...
6/25/2007drilling hits mineralization at WD zone 3 km south of Malach...
6/11/2007Promising First Results from Bird River Property for Maratho...
5/11/2007Drilling Continues Expansion of W Zone and Southern Resource
4/18/2007acquires Bird River Ni-Cu+PGM Property through option
1/25/2007Measured and Indicated In-Pit Resource Grows 39%
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (MAR.TO)Other OTC (MRPGF)
0.520+18.18%4.52+4.63%
TORONTO
Prev close Open
Low High
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  - -100.00%
Volume 1 month var.
-100.00%
Produces
Develops
Explores for Copper - Gold - Nickel - Palladium - Platinum - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/3/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.04-0.21%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.91-2.73%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-3.26%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.67+0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+6.25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+2.70%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 1.77-2.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.37-0.22%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.