Capstone Reports Pre-Feasibility Study Results for Santo Domingo Project in Chile

Santo Domingo PFS Generates After-tax NPV (8%) of US$1.1 billion with a 3 year payback

VANCOUVER, Aug. 15, 2011 /CNW/ - Capstone Mining Corp. (TSX: CS) today announced the results of the Pre-feasibility Study ("PFS") for its Santo Domingo Iron Oxide-Copper-Gold ("IOCG") project ("Santo Domingo" or the "Project") in Region III, Chile.  The Project is owned 70% by Capstone and 30% by Korea Resources Corporation ("KORES").

Highlights

(all amounts in U.S. dollars unless otherwise indicated and reflect 100% of the project)

  • Average annual production of 144 million pounds of copper, 4.1 million tonnes of iron concentrate and 15 thousand ounces of gold.  Copper production will average 255 million pounds in the first five years of the Project.
  • Base Case1 after-tax net present value (NPV), discounted at 8%, of $1.1 billion. Spot Case2 after-tax NPV (8%) of $4 billion.
  • After-tax internal rate of return (IRR) of 22% with a payback period of 3.0 years (Base Case).
  • Expected life of mine total cash production costs are estimated to be $0.11 per pound of payable copper (net of magnetite iron and gold by-product credits and selling costs); $0.32 in the first five years (Base Case).
  • Total capital costs estimated to be $1.24 billion, which includes a 14% contingency on total costs.
  • 18 year mine life with operations expected to commence in late-2015.
  • Nominal plant throughput rate of 63,500 tonnes per day; 70,000 tonnes per day in the first five years.
  • Favourably located close to existing infrastructure, with direct access to Asian markets.
  • Off-take agreements (at market pricing) committed for 50% of the copper and 50% of the iron concentrate, life of mine, as part of the strategic partnership with KORES for development of the Project.

1 Base Case at constant $2.50/lb. copper price, $1.00/dmtu iron price ($65/t conc. at 65% Fe), $1,000/oz. gold price.  All calculations are Base Case except where otherwise specified.
2 Spot Case at constant $4.00/lb. copper price, $2.00/dmtu iron price ($130/t conc. at 65% Fe), $1,400/oz. gold price.

"The positive Santo Domingo PFS has met our economic expectations," said Darren Pylot, President and CEO of Capstone.  "With the buoyancy in the copper market and strong demand for the by-product iron production, we intend to advance this Project towards production.  With our $507 million cash balance at June 30, 2011, and the commitment by KORES to arrange debt financing for 65% of the capital costs of the Project, we have the means to move forward rapidly."

"With the PFS and funding in hand, we will proceed to award the contract for the Feasibility Study ("FS") and we have started the permitting process in Chile, as well as Project staffing under the direction of Gregg Bush, Capstone's Senior Vice President and Chief Operating Officer.  Gregg has over 30 years of experience in large mine operations and development, with over 12 years of that spent in Chile," continued Mr. Pylot.  "We are starting immediately to build the team that will see this exciting new Chilean copper project through to production."

Prefeasibility Study

The Santo Domingo PFS was completed by Ausenco, a global leader in engineering and project management services for the resource and energy sectors.  With 30 offices in 20 countries, Ausenco specializes in the Energy, Environment & Sustainability, Minerals & Metals, Process Infrastructure and Program Management sectors.  Ausenco was chosen for the Santo Domingo PFS because of its expertise and experience with similar sized, large base metal and iron projects, and proven experience with port and slurry pipeline construction.  Significant contributions to the report were made by Scott Wilson RPA (subsequently Roscoe Postle Associates Inc.) (resource model), Arthur H. Winckers & Assoc. (metallurgy), Nilsson Mine Services Ltd. (mine design) and Knight Pi�sold (environmental).

The PFS builds on the Preliminary Assessment ("PA") completed in 20083.  Since the PA, considerable work has been done on the project.  The mineral resource has been increased from 240 to 486 million tonnes, the metallurgical performance, using seawater for copper and iron recovery, has been proven, and a large data set to support grinding characteristics/throughput estimates has been gathered.

The Santo Domingo Project will be an open pit operation, using conventional drilling, blasting, loading with diesel hydraulic shovels, and truck haulage.  The process plant will have an annual average throughput of 63,500 tonnes per day using SAG and ball milling, with conventional flotation utilizing seawater to produce a copper concentrate.  Magnetite iron will be recovered from the copper rougher tailings using Low Intensity Magnetic Separation (LIMS).  A pipeline will bring seawater from the coast, approximately 74 kilometres from the project, and both copper and iron concentrate will be transported to the coast in a slurry pipeline for export.

3   Far West Mining Ltd. Preliminary Assessment  dated May 9, 2008.  Available in the Santo Domingo section of Capstone's website or on SEDAR under Far West's profile.

Location

The Santo Domingo Project is located 50 kilometres west of Codelco's El Salvador copper mine, and 130 kilometres north northeast of Copiap� in Region III, Chile, near the town of Diego de Almagro. Elevation at the site ranges from 1,000 to 1,280 metres above sea level, with relatively gentle topographic relief. Access to the project is 1 kilometre off the paved highway C-17 from Diego de Almagro to Copiap�.  Regional infrastructure is good and highways connect the site to the main regional towns and cities. Regularly scheduled air services are available between Santiago and El Salvador and the Atacama airport located northwest of Copiap�.

Mineral Resource Estimate

Indicated and Inferred Mineral Resources (May 15, 2010)

Zone Mt % CuEq % Cu g/t Au % Fe
Indicated          
SDS 275 0.64 0.41 0.056 27.8
Iris 111 0.50 0.23 0.033 26.3
Iris Norte 99.5 0.47 0.16 0.019 26.4
Total indicated 486 0.57 0.32 0.043 27.2
Inferred          
SDS 30.5 0.46 0.26 0.037 23.7
Iris 5.52 0.47 0.19 0.026 26.0
Iris Norte 25.3 0.47 0.10 0.011 27.9
Total Inferred 61.3 0.46 0.19 0.025 25.7

Notes: CIM definitions were followed for Mineral Resources. Mineral Resources for SDS/Iris are estimated at a cut-off grade of 0.25% CuEq. CuEq grades are calculated using average long-term prices of $2.25/lb Cu, $950/oz Au, and $0.74/dmtu Fe ($50/dmt conc. at 67.5% Fe). CuEq calculations and metallurgical recovery factors are as stated in the Scott Wilson RPA Technical report.  Due to rounding, some figures may not add up to the totals shown.  Mineral resources that are not mineral reserves do not have demonstrated economic viability. See "Quality Assurance and NI 43-101 Compliance" at the end of this news release for further information.

Mineral Reserves

Santo Domingo Open Pit Probable Mineral Reserve

Stage Ore (Mt) Ore Grade Contained Metal
Cu (%) Au (g/t) Cu (Mlbs) Au (kOz) Magnetite Conc. (Mt)
SDS/Iris            
SDS Stage 1 71.8 0.61 0.08 958 193 11
SDS Stage 2 63.7 0.41 0.06 574 113 10
SDS Stage 3 170.5 0.23 0.03 848 173 32
SDS Stage 4 38.8 0.36 0.05 304 60 3
Subtotal SDS/Iris 344.8 0.35 0.05 2,684 539 57
Iris Norte            
IRN Stage 1 21.4 0.23 0.03 108 20 4
IRN Stage 2 28.0 0.13 0.01 78 12 7
IRN Stage 3 23.7 0.11 0.01 60 8 5
Subtotal Iris Norte 73.1 0.15 0.02 246 41 17
Grand Total 418.0 0.32 0.04 2,930 580 73

Notes:  NSR cut-off of $5.79/t (incremental operating cost; does not include mining costs). Mineral Reserves based on Indicated Mineral Resources only. Magnetite concentrate tonnage based on average 65% iron grade.  Due to rounding, some figures may not add up to the totals shown.

Life of Mine Production Schedule

The cash flow model is supported by a mine plan developed to an annual level of detail.  Approximately 50 million tonnes of material would be pre-stripped in the year prior to start-up of operations.  The life of mine plan contemplates mining of 1.7 billion tonnes of material consisting of 1.3 billion tonnes of waste rock and overburden and 0.4 billion tonnes of ore over an 18-year mine life.  The overall strip ratio for the project is 3:1.

The plan developed for the project mines higher copper grades in the first five years of the mine life with progressively lower copper grades and higher iron grades for the remaining 13 years.

A detailed mine plan can be accessed at http://capstonemining.com/i/pdf/NR-AUG-15-2011-Santo-Domingo-Physicals-Summary.pdf.

Processing

The copper and magnetite recovery plant and associated service facilities will process run of mine (ROM) ore delivered to a primary crusher feeding a conventional process of crushing and grinding of the ROM ore, copper flotation (in seawater), and magnetite recovery from copper rougher tailings. Copper and magnetite concentrates will be thickened on site prior to being pumped via a concentrate pipeline to the port. At the port, the concentrates will be washed, dewatered and loaded onto ships for transportation to third-party smelters.

Grinding and flotation testwork has established mill design parameters and copper recovery estimates for the study.  The mill will process a total of 418 million tonnes of ore over an 18-year mine life at an average grade of 0.32% Copper, 0.04 grams per tonne gold, and 27.6% iron.  Mill throughput will vary from 70,000 tonnes per day in the first five years, to 60,000 tonnes per day in the latter years. Average mill throughput over the 18-year mine life is 63,500 tonnes per day.  Metal recoveries for copper and gold are 88.7% and 46% respectively, averaged over the mine life.

Iron recovery was determined from magnetic separation testing on the copper flotation rougher tailings.  Iron recoveries vary directly with the mineralogy of the iron present in the ore.  The present study does not consider any process to recover the specular hematite portion of the iron.  Therefore iron recovery is presented in terms of the total mill feed mass recovery.  For the life of the project this averages 17.5%, and ranges from a low of 10.3% in the first year of the project to a high in excess of 25% in the last two years of the project.  Testing indicates that a magnetite concentrate grading 65% iron can be maintained throughout the life of the project. All metallurgical data used in the development of the recovery and concentrate grade estimates for the cash flow models are based on tests conducted using seawater, which produced results equivalent to, or better than, tests performed in fresh water.

An annual production schedule showing tonnes processed, grades, and recoveries can be accessed at http://capstonemining.com/i/pdf/NR-AUG-15-2011-Santo-Domingo-Physicals-Summary.pdf.

The tailings storage system consists of a tailings storage facility ("TSF") located north of the proposed mine. The TSF is designed to store approximately 353 Mt of conventional thickened tailings - enough for the approximately 18 years of the project life. Storage of both seawater and process water is proposed in lined ponds near the plant site. Water make-up is proposed to be untreated seawater. Based on the conventional thickened tailings disposal method, the estimated water make-up will be approximately 1,450 m3/h (~400 L/s).

Infrastructure

Access to the mine site is 6 kilometres to the south of Diego de Almagro on Highway C-17. This section is paved and in good condition. Due to the location of the Iris Norte pit and process facility, approximately 2 kilometres of the existing road will require diversion and an overpass. The overpass will allow vehicle access to the tailings storage facility without crossing Highway C-17.

High-voltage transmission will be achieved using a 220 kV double-circuit overhead line from Diego de Almagro. The high voltage power line will feed a 220/13.8 kV transformer yard at the project main substation. Correspondence with the Chilean government organisation for the coordination of electrical installations, SDEC-SIC, suggests there is sufficient 220 kV power available on the central grid which services the project area to meet the demands of the project.

Due to the scarcity of fresh water in Region III in Chile, the Project will be designed to use seawater, which will be brought to the site via pipeline from the coast.

The PFS is based on the port facility being located near the coastal township of Cha�aral, approximately 74 kilometres west of the Santo Domingo project. The port facility will receive magnetite and copper concentrate from the project by pipeline.

Both the concentrate and seawater pipelines are anticipated to run together in a pipeline corridor along the north side of the C-57 road and Route 5. The ground is gravel, clay and sand with no high points and a continuous slope.

Capital Cost Estimate

The total project capital cost estimate is summarized below and has �25% accuracy as of July 2011. This estimate is based on a foreign exchange rate of 1 US$ = 466 Chilean Pesos (CLP).

Summary of Capital Costs

Area $M
Mining equipment 172
Pre-strip 54
Process plant 283
Tailings 29
On-Site Infrastructure 27
Off-Site Infrastructure  
     Site Power                                                                             6  
     Concentrate Pipeline                                                          49  
     Seawater Pipeline                                                               76  
     Concentrate Dewatering, Storage and Load Out              121  
Off-Site Infrastructure (Total) 253
Total Direct Costs 818
Indirect Costs 186
Owners Cost 89
Total Indirect Costs 275
Contingency 149
Total Project Cost 1,242

Life of mine sustaining capital, estimated at $495 million over the 18-year mine life including mine closure estimates, are not included in the above figure.

Operating Cost Estimate

The total project operating costs, excluding costs associated with concentrate sales, are summarized below. The costs are presented as life-of-mine ("LOM") averages per tonne of ore processed.

Summary of Average LOM Operating Costs

Cost Centre $M/a $/t ore
Mining 107 4.62
Process plant 101 4.37
Concentrate pipeline 2 0.09
Seawater pipeline 10 0.43
G&A 13 0.55
Port Facility 11 0.46
Total 244 10.52

The operating costs estimate was prepared with a base date of July 2011 to an accuracy level of �25%. The estimate excludes sustaining capital expenditure requirements which have been included as part of the financial model.

The estimated total cash production costs for copper over the life of the project are estimated at $0.11 per pound of payable copper, when including gold and iron credits and selling costs.  The co-product total cash production costs are estimated at $1.12 per pound of payable copper and $30.46 per tonne of magnetite concentrate.

Economics

The overall economic performance of the project (as measured by the IRR, NPV and payback period) is summarized below. Base case and spot price economic models were developed.  These models are based on the commodity prices, and operating and capital costs listed below.

Base Case Economic Analysis

Economic Parameters EBITD&A After Tax
NPV ($M @ 8%) 1,620 1,092
IRR% 29.4 22.0
Simple Payback Period (years) 2.5 3.0
Total Cash Production Costs (per lb of payable Cu) 0.11

Notes:  Total Cash Production Costs (per lb of payable Cu) are inclusive of by-product credits and selling costs.

Spot Price Case Economic Analysis

Economic Parameters EBITD&A After Tax
NPV ($M @ 8%) 5,472 3,985
IRR% 60.2 45.4
Simple Payback Period (years) 1.5 1.7
Total Cash Production Costs (per lb of payable Cu) negative 1.75

Notes:  Total Cash Production Costs (per lb of payable Cu) are inclusive of by-product credits and selling costs.

Summary of Inputs into Economic Model

Parameter Base   Spot
NPV discount rate, % 8
Copper price, $/lb 2.50 4.00
Magnetite price, $/dmtu 1.00* 2.00**
Gold Price, $/oz 1,000 1,400
Capital Cost, $M 1,242
LOM Site Operating Cost, $M 4,403
LOM Sustaining Capital Cost, $M 495
LOM Selling Costs, $M 1,091

*US$65/t conc. at 65% Fe; ** US$130/t conc. at 65% Fe.

Sensitivities

    EBITD&A AFTER TAX
PARAMETER
OR
VARIATION
VALUE IRR
(%)
 
NPV
@ 8.0%
($M)
IRR
(%)
 
NPV
@ 8.0%
($M)
Copper Price ($/lb)        
           
-20% $2.00 21.3 967 15.9 589
-10% $2.25 25.4 1,294 19.0 841
Base Case $2.50 29.4 1,620 22.0 1,092
10% $2.75 33.3 1,946 24.9 1,341
20% $3.00 37.1 2,272 27.7 1,589
Total Operating Costs ($/t LOM average)        
           
-20% $8.42 34.1 2,125 25.6 1,469
-10% $9.47 31.8 1,872 23.9 1,282
Base Case $10.52 29.4 1,620 22.0 1,092
10% $11.57 26.9 1,367 20.1 899
20% $12.63 24.3 1,115 17.9 704
Initial Capital Costs ($M)        
           
-20% $994 37.4 1,882 28.2 1,334
-10% $1,118 33.1 1,751 24.8 1,213
Base Case $1,242 29.4 1,620 22.0 1,092
10% $1,366 26.3 1,489 19.6 971
20% $1,491 23.7 1,357 17.6 850
Magnetite Iron Price ($/dmtu Fe)        
           
-20% $0.80 26.2 1,232 19.3 791
-10% $0.90 27.9 1,426 20.7 942
Base Case $1.00 29.4 1,620 22.0 1,092
10% $1.10 31.0 1,814 23.3 1,241
20% $1.20 32.4 2,008 24.5 1,390

Permitting

The land and territory investigations regarding the project's current footprint indicate there would be no impact on natural parks, biodiversity conservation priority sites, or indigenous development land in the Atacama Region. Additional baseline studies are required for the project in order to achieve a proper characterization of the environmental components that should be included in the future Environmental Impact Study ("EIS").

Next Steps

A project implementation schedule has been developed for a FS with additional test work and engineering, to be followed by procurement and construction of the process plant, related facilities, and infrastructure, with commissioning completed in late-2015.  The plan includes additional environmental baseline studies and the preparation of the EIS and permitting process for the plant and associated infrastructure.  Due to the advanced nature of the testwork, the FS can commence in parallel or slightly ahead of the testwork program and still allow the results to be incorporated in the study.  Capstone is in the process of recruiting key personnel in Chile to move the project forward.

The critical, long-lead items for development of the plant are the grinding mills.  SAG and ball mills delivery is currently forecast to be in excess of 18 months from manufacture to delivery at port of export and timelines will be monitored closely.

The PFS does not include recovery of the hematite iron in the mill feed or the processing of approximately 30 million tonnes of oxide material in the indicated resource category.  The FS has upside potential in the recovery of the hematite iron with an additional processing step.  There is also potential to recover copper from the oxide material in a satellite leaching operation.  In addition, further geotechnical drilling is planned for the FS with the goal of improving the overall strip ratio.

Technical Report

The full Santo Domingo PFS, prepared as a National Instrument 43-101 compliant Technical Report, will be filed under Capstone's profile on SEDAR at www.sedar.com within 45 days.

Conference Call and Webcast

Capstone will host a conference call on Tuesday, August 16, 2011 to discuss the Santo Domingo PFS and second quarter results.  The conference call and webcast details are as follows:

Date: 
Time:  
Dial in:  
Webcast:  
Replay:  
Replay Passcode: 
Tuesday, August 16, 2011
11:30 am Eastern Time (8:30 am Pacific Time)
North America -- 1.888.231.8191, International -- 1.647.427.7450
http://www.newswire.ca/en/webcast/viewEvent.cgi?eventID=3595240
North America -- 1.800.642.1687, International -- 1.416.849.0833
81625702

The conference call replay will be available until August 25, 2011. A transcript of the call will also be made available on Capstone's website (http://capstonemining.com/s/ConferenceCalls.asp) within approximately 24 hours of the call.

About Capstone Mining Corp.

Capstone Mining Corp. is a TSX listed Canadian mining company with two producing copper mines in the Americas: the Cozamin copper-silver-zinc-lead mine located in Zacatecas State, Mexico and the Minto copper-gold-silver mine in Yukon, Canada.

Using its operations as a springboard, Capstone aims to grow organically and through acquisitions in politically stable, mining-friendly jurisdictions, with a focus in the Americas: organic growth through continued mineral resource and reserve expansions as well as expanding operations at its operating mines, development of its large scale 70% owned Santo Domingo copper-iron-gold project in Chile in partnership with Korea Resources Corporation, development of its Kutcho copper-zinc-gold-silver project in British Columbia and exploration at properties in Chile, British Columbia and Australia. Capstone's cash flow and strong balance sheet provide the platform to enhance that growth profile. Capstone is included in the S&P/TSX Composite Index and S&P/TSX Global Mining Index. Additional information is available at www.capstonemining.com.

Quality Assurance and NI 43-101 Compliance

The technical information in this news release has been prepared in accordance with Canadian regulatory requirements by, or under the supervision of, David Brimage of Ausenco, (an independent "Qualified Person") as set out in National Instrument 43-101 Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators ("NI 43-101") and reviewed by John Sagman, P. Eng., a Qualified Person and Vice President, Technical Services, Capstone Mining Corp. In addition, Gregg Bush, Senior Vice President and Chief Operating Officer for Capstone, reviewed all Technical Information in this news release.

The PFS was prepared with input from the following: David Brimage of Ausenco, Dave Rennie of Scott Wilson RPA, John Nilsson of Nilsson Mine Services Limited, Art Winckers of Arthur H. Winckers & Associates, Robert Braun of Ausenco, and Humberto Rivas of Knight Pi�sold, who are responsible for certain sections of the PFS as detailed in the PFS and this release.

Readers are advised that mineral resources that are not mineral reserves do not have demonstrated economic viability.  Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. These mineral resource estimates include inferred mineral resources that are normally considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. Even though test mining has been undertaken in areas with M&I class mineral resources there is no certainty that inferred mineral resources will be converted to measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

Based on the resource estimate, a standard methodology for pit limit analysis, mining sequence, and cut-off grade optimization, including application of mining dilution, process recovery, economic criteria and physical mine and plant operating constraints, has been followed to design the open pit mines and determine the mineral reserve estimate for each deposit as summarized in the Mineral Reserve table.

Cautionary Note Regarding Forward-Looking Information

This document may contain "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking statements"). These forward-looking statements are made as of the date of this document and Capstone Mining Corp. (the "Company") does not intend, and does not assume any obligation, to update these forward-looking statements, except as required under applicable securities legislation.

Forward-looking statements relate to future events or future performance and reflect Company management's expectations or beliefs regarding future events and include, but are not limited to, statements with respect to the estimation of mineral reserves and mineral resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of mineral resources; possible variations in ore reserves, grade or recovery rates; accidents; dependence on key personnel; labour pool constraints; labour disputes; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; and other risks of the mining industry as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, all of which are filed and available for review under the Company's profile on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.  Accordingly, readers should not place undue reliance on forward looking statements.

Alternative Performance Measures

"Cash Production Costs", "Total Cash Production Costs", "Total Project Operating Costs" and "LOM Operating Costs" are Alternative Performance Measures.  These performance measures are included because these statistics are key performance measures that management uses to monitor performance. Management uses these statistics to assess how the Company is performing to plan and to assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with IFRS.

 

 

For further information:

Capstone Mining Corp.
Cindy Burnett, VP, Investor Relations
Telephone: 604-637-8157
Email: cburnett@capstonemining.com
Website: www.capstonemining.com

.
Data and Statistics for these countries : Australia | Canada | Chile | El Salvador | Mexico | All
Gold and Silver Prices for these countries : Australia | Canada | Chile | El Salvador | Mexico | All

VanEck Vectors Global Alternative Energy ETF

PRODUCER
CODE : CS.TO
ISIN : CA14068G1046
CUSIP : 14067U104
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Capstone Mining is a copper producing company based in Canada.

Capstone Mining produces copper, gold, lead, silver and zinc in Canada and in Mexico, develops copper, gold, silver and zinc in Canada.

Its main assets in production are MINTO MINE in Canada and COZAMIN BACIS in Mexico and its main asset in development is KUTCHO in Canada.

Capstone Mining is listed in Canada, in Germany and in United States of America. Its market capitalisation is 457.8 millions as of today (US$ 336.2 millions, € 302.2 millions).

Its stock quote reached its lowest recent point on December 06, 2002 at 0.11, and its highest recent level on June 28, 2024 at 9.96.

Capstone Mining has 47 442 200 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of VanEck Vectors Global Alternative Energy ETF
12/31/2007Corporate Presentation
In the News and Medias of VanEck Vectors Global Alternative Energy ETF
11/26/2018Capstone Mining mulls selling stake in Chile-based copper-ir...
Annual reports of VanEck Vectors Global Alternative Energy ETF
2007 Annual Report
Nominations of VanEck Vectors Global Alternative Energy ETF
5/14/2013Capstone Appoints D. James Slattery as Chief Financial Offic...
6/4/2012Capstone Mining Appoints Director
9/14/2011Capstone Appoints Santo Domingo General Manager and Awards E...
4/14/2011Reports Change to its Board
Financials of VanEck Vectors Global Alternative Energy ETF
7/28/2015Second Quarter 2015 Financial Results
2/21/2014Capstone Mining Reports Financial Results
2/21/2014Reports Financial Results for Pivotal Year
1/13/2014Capstone Mining 2013 Fourth Quarter and Full
10/30/2013Capstone Mining 2013 Third Quarter Continues
10/10/2013Capstone Mining 2013 Third Quarter
7/11/2013Capstone Mining 2013 Second Quarter
5/8/2013Capstone Mining 2013 First Quarter Financial
4/11/2013Capstone Mining 2013 First Quarter
11/8/2012Capstone Reports 2012 Third Quarter Financial Results; Cash ...
8/15/2012Capstone Reports 2012 Second Quarter
5/10/2012Capstone Reports Solid 2012 First Quarter
8/15/2011Capstone Reports Second Quarter 2011
5/25/2011Capstone Reports First Quarter 2011 Financial Results
11/7/2008Reports Financial Results For The Third Quarter
7/23/2008To Release Second Quarter Results
7/9/2008Announces Production and Sales for the Second Quarter of 200...
4/30/2008 Reports Record Operating Profit Of $15.9 Million For The Fi...
4/23/2008To Release First Quarter Results On Tuesday April 29, 2008
4/16/2008 Announces Production And Sales For The First Quarter Of 200...
11/15/2007Year-End and Fourth Quarter Results
Project news of VanEck Vectors Global Alternative Energy ETF
9/22/2014(Minto Mine)Receives Quartz Mining License Amendment for Minto Mine
12/3/2013Capstone Mining Provides Pinto Valley Production Update
10/11/2013Capstone Mining Completes Acquisition of
8/8/2013Capstone Mining Acquires Option on 350,000 Hectare Explorati...
6/11/2013Capstone Mining Provides Update on Pinto Valley Acquisition
10/25/2012Capstone adds 101 Million Pounds of Copper in Indicated Mine...
6/18/2012Capstone Completes Minto Mine Phase VI
2/8/2012Capstone Updates Mineral Resource Estimate for Footwall Zone...
2/2/2012Capstone Completes Another Successful Drill Season at Minto ...
6/20/2011Capstone Announces Initial Mineral Resource
6/17/2011Capstone Completes Acquisition of Far West Mining and Transa...
6/14/2011Capstone Mining and Far West Mining Approve Acquisition and ...
5/30/2011Capstone Adds 219 Million Pounds of Copper in M&I Mineral Re...
5/2/2011Capstone Reports Additional High Grade
4/14/2011Capstone Reports High Grade Intercepts at
3/14/2011Capstone Completes Prefeasibility Study on Phase V Expansion...
2/24/2011(Kutcho)Reports 2011 Prefeasibility Study for Kutcho Copper-Zinc Pro...
2/24/2011Capstone Reports 2011 Prefeasibility Study
2/17/2009(Minto)Reports 5th New High Grade Copper-Gold Discovery at Minto Mi...
2/9/2009Announces Robust Mineral Resource Update for High Grade Kutc...
2/4/2009(Cozamin Bacis)Reports Record Copper Production for 2008 and Increases Fore...
1/10/2008(Cozamin Bacis)Highlights Production and Sales for the Four Months Ended De...
10/16/2007(Cozamin Bacis)Capstone Increases Resources to 8.6 Million Tonnes at the Co...
10/11/2007(Cozamin Bacis) Declares Expanded Commercial Production at Cozamin and High...
Corporate news of VanEck Vectors Global Alternative Energy ETF
7/26/2016Capstone reports 2Q loss
4/26/2016Capstone reports 1Q loss
1/19/2016Capstone Mining to Attend Upcoming Investor Conferences
1/18/2016Capstone Mining 2016 Operating and Capital Guidance
1/18/2016Capstone Extends Pinto Valley Mine Life to 2039
1/6/2016Edited Transcript of CS.TO earnings conference call or prese...
11/25/2015Capstone Mining to Attend Upcoming Investor Conferences
10/27/2015Capstone reports 3Q loss
10/13/2015Capstone Mining 2015 Third Quarter Production Results
9/9/2015Capstone Mining Announces Spending Cuts in Response to Marke...
9/8/2015Capstone Mining to Attend Upcoming Investor Conference
8/27/2015Edited Transcript of CS.TO earnings conference call or prese...
8/5/2015Capstone Mining Receives Water Use Licence for Minto Mine
8/3/2015Zacks Investment Ideas feature highlights: Avino Silver and ...
7/28/2015Capstone Mining Second Quarter 2015 Financial Results
7/13/2015Capstone Mining 2015 Second Quarter Production Results
7/8/2015Capstone Mining Receives Approval of Environmental Impact As...
4/13/2015Capstone Mining 2014 First Quarter Production Results
4/1/2015Capstone Mining Publishes Inaugural Sustainability Report
4/1/2015Publishes Inaugural Sustainability Report
2/19/2015to Attend Upcoming Investor Conferences
12/1/2014to Attend Upcoming Investor Conferences
10/29/2014Capstone Mining Reports Another Quarter of Record Cash Flow
10/14/2014Capstone Mining to Attend Upcoming Investor Conference
9/12/2014Discontinues Planned Offering of $300 million Senior Notes
9/5/2014Announces Launch of $300 million Senior Notes Offering
5/7/2014Reports Operating Cash Flow Increases 134% to $47.1 Million
4/10/2014Record 2014 First Quarter Production Results
3/26/2014Extends Pinto Valley Mine Life to 2026
1/20/2014Capstone Mining to Attend Upcoming Investor Conferences
1/20/2014to Attend Upcoming Investor Conferences
1/20/2014to Attend Upcoming Investor Conferences
1/13/20142013 Fourth Quarter and Full Year Production Results
12/11/2013Capstone Mining Files Updated Technical Report for Pinto Val...
12/11/2013Files Updated Technical Report for Pinto Valley
11/14/2013Capstone Mining to Attend Upcoming Investor Conferences
11/14/2013to Attend Upcoming Investor Conferences
10/7/2013Capstone Mining Provides Update on Pinto
10/7/2013Provides Update on Pinto Valley Acquisition
7/31/2013Capstone Mining Delivers Consistent 2013
7/11/20132013 Second Quarter Production Results
6/13/2013Capstone Mining Files Pinto Valley 43-101 Mineral Resource E...
6/11/2013Provides Update on Pinto Valley Acquisition
5/30/2013Capstone Mining to Attend Upcoming Investor Conferences
5/10/2013Capstone Mining Reports Annual General Meeting Voting Result...
4/29/2013Capstone Mining to Purchase Pinto Valley
4/28/2013to Purchase Pinto Valley Copper Mine
3/13/2013Capstone Mining Reports 2012 Year End
2/18/2013to Present at Upcoming Investor Conferences
1/10/2013Capstone 2012 Fourth Quarter and Full Year Production Result...
1/10/20132012 Fourth Quarter and Full Year Production Results Meet Gu...
10/31/2012Capstone Reports Senior Management Change
10/31/2012Reports Senior Management Change
10/23/2012Capstone Reports Board Change
10/23/2012Reports Board Change
10/11/2012Capstone 2012 Third Quarter Production Results on Track
7/12/2012Capstone 2012 Second Quarter Production Results On Target
5/14/2012Capstone Reports Board Change
4/13/2012Capstone Mining Announces New $200 Million
4/12/2012Capstone 2012 First Quarter Production
3/14/2012Capstone Reports Strong 2011 Results
2/10/2012Capstone Mining Reports Board Change
1/26/2012Capstone 2012 Operating and Capital Guidance
1/17/2012Capstone Fourth Quarter and Full Year 2011 Production Result...
1/16/2012Capstone Awards Contract for Santo Domingo
10/6/2011Capstone Third Quarter Production Results
8/15/2011Capstone Reports Pre-Feasibility Study
8/10/2011to Hold Second Quarter and Santo Domingo PFS Conference Call...
7/6/2011Capstone Second Quarter Production Results
6/20/2011Capstone Mining Board of Director Changes
6/14/2011and Far West Mining Approve Acquisition and KORES Agreement
6/2/2011Independent Proxy Firms Recommend Capstone Shareholders Vote...
5/23/2011Mails Information Circular with Respect to Acquisition of Fa...
5/20/2011Capstone Mining Mails Information Circular
5/10/2011to Hold First Quarter Conference Call May 25, 2011
4/26/2011Capstone Reports First Quarter Production
4/17/2011Capstone Mining to Acquire Far West Mining
4/14/2011Capstone Reports Change to its Board
3/15/2011Capstone Reports Record Revenue and Strong
1/26/2009Commences US$ 3 Million Resource Expansion Drill Program at ...
1/22/2009Reports Debt Repayments, Funding of Debenture Repurchase and...
12/10/2008Reports Final Drill Intercepts of Near Surface Copper-Gold a...
11/25/2008Reports Minto Mine Connected to Yukon Electrical Grid
11/24/2008Sherwood and Capstone Announce Closing of Business Combinati...
11/14/2008Shareholders Overwhelmingly Approve Business Combination wit...
9/8/2008Announce Combination to Create Intermediate Copper Producer
7/29/2008Reports Record Revenues of $35.3 Million and Record Operatin...
7/15/2008Announces Normal Course Issuer Bid
2/28/2008December 31, 2007 Four Month Stub Period Results
2/21/2008to Release 4 Months Ended December 31, 2007 Results on Thurs...
1/17/2008Provides 2008 Expansion And Exploration Plans And Increases ...
11/8/2007 To Release 2007 Year End Results On Wednesday November 14,...
7/19/2007Provides Cozamin Mine Expansion Update
6/28/2007Reports Q3 Results: Operating Profit of $7.8 Million, $0.09 ...
4/5/2007Closes Previously Announced Agreement to Sell Cozamin Silver...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CS.TO)FRANKFURT (OUW.F)
9.65+1.37%5.45-2.68%
TORONTO
CA$ 9.65
09/18 17:00 0.130
1.37%
Prev close Open
9.52 9.51
Low High
9.42 9.88
Year l/h YTD var.
6.02 -  11.20 50.08%
52 week l/h 52 week var.
4.49 -  11.20 65.24%
Volume 1 month var.
1,601,554 0.416%
24hGold TrendPower© : 40
Produces Copper - Gold - Silver
Develops Copper - Gold - Silver - Zinc
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/5/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202449.61%9.9610.05
202330.57%7.254.40
2022-8.52%7.792.25
2021126.89%6.642.41
2020226.03%2.490.33
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.08+0.50%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.91-2.73%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-3.26%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.67+0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+6.25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+2.70%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 1.77-2.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.37-0.22%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
VanEck Vectors Global Alternative Energy ETF profile | VanEck Vectors Global Alternative Energy ETF news | VanEck Vectors Global Alternative Energy ETF market Indicators | VanEck Vectors Global Alternative Energy ETF projects and resources | VanEck Vectors Global Alternative Energy ETF valuation | Go to VanEck Vectors Global Alternative Energy ETF properties | VanEck Vectors Global Alternative Energy ETF corporate presentation | VanEck Vectors Global Alternative Energy ETF annual report | VanEck Vectors Global Alternative Energy ETF management | VanEck Vectors Global Alternative Energy ETF interactive charts | VanEck Vectors Global Alternative Energy ETF free charts | VanEck Vectors Global Alternative Energy ETF TORONTO | VanEck Vectors Global Alternative Energy ETF FRANKFURT | VanEck Vectors Global Alternative Energy ETF Other OTC
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.