Orsu Announces Positive Definitive Feasibility Study for the Karchiga VMS Copper Project in Kazakhstan
Published : February 29, 2012
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

LONDON, UNITED KINGDOM--(Marketwire - Feb. 29, 2012) - Orsu Metals Corporation (News - Market indicators)(AIM:OSU) -

Highlights:

  • Post-tax NPV7.5 of US$150 million, IRR of 30% (based on price of US$3.25/lb Cu);
  • Initial capital expenditure of US$115 million;
  • Payback period of 2.75 years (on initial capital expenditure);
  • 11.5 years mine production of 149kt (328 Mlb) payable copper:
    • average annual production of 13kt (28.6 Mlb) of copper from sulphide and oxide ore;
    • at a processing rate of 750,000 tonnes of sulphide ore per annum, a total of 136.3kt (300 Mlb) of copper in 27.9% concentrate;
    • at a heap leach processing rate of 360,000 tonnes of oxide ore per annum (over 4.5 years), a total of 12.7kt (27.9 Mlb) of cathode copper;
  • Life of mine cash operating cost (pre tax) of US$1.47/lb Cu;
  • Net smelter revenue over the life of mine of US$971 million.

Orsu Metals Corporation ("Orsu", or the "Company") (News - Market indicators)(AIM:OSU), the London-based base and precious metals exploration and development company, is pleased to announce the positive results of a Definitive Feasibility Study ("DFS") for its 94.75% owned Karchiga Volcanogenic Massive Sulphide ("VMS") copper project in northeast Kazakhstan (the "Karchiga Project"). The purpose of the DFS was to determine the viability of open pit copper mining at Karchiga and has been prepared by the Company's lead mining consultant SRK Consulting (UK) Limited ("SRK"), which is independent of Orsu, based on Mineral Reserve Estimates, prepared by SRK and reported according to Canadian Institute of Mining, Metallurgy and Petroleum Standards on Mineral Resources and Mineral Reserves (the "CIM Standards").

Mineral Reserves

On the 8th of December 2011, Orsu reported Indicated Mineral Resources for its Karchiga Project comprising 10.8Mt of combined sulphide and oxide mineralisation grading 1.73% Cu for 187,200t (412.7 Mlb) of contained Cu and an Inferred Mineral Resource of 0.02Mt of sulphide mineralisation grading 1.28% Cu for 300t (0.7 Mlb) of contained Cu (see the Company's press release dated 08 December 2011).

Using only the Indicated Mineral Resource Estimates, the DFS supports a Probable Mineral Reserve estimate of 8.5 million tonnes of sulphide ore in the Central and North East pits containing 145,227t (320 Mlb) of copper at an average grade of 1.71% Cu to be amenable to flotation ("FL") and additional 1.5 million tonnes of ore in the Central pit containing 21,399t (47.2 Mlb) of copper at an average grade of 1.43% Cu to be amenable to heap leaching ("HL").

Table 1. Probable Mineral Reserves Estimates as of 18 February 2012
Orebody  
Ore Type
  Tonnes (Mt)   Cu %   Au g/t   Cu Metal (kt)  
Cu Metal (Mlb)
  Au Metal (Koz)
Central   HL   1.5   1.43   0.06   21.4   47.2   3.0
Central   FL   3.8   1.78   0.12   68.2   150.2   15.2
North East   FL   4.7   1.64   0.18   77.0   169.8   27.4
Total       10.0   1.67   0.14   166.6   367.2   45.6
 All figures are on a 100% ownership basis

Pit designs and the final National Instrument 43-101 Mineral Reserve estimate dated 18 February 2012 were completed using two types of software; Whittle 4X optimisation software was used to generate optimal pit shells which were designed in detail using Vulcan software. Key optimisation parameters are presented in Table 2 below.

Table 2. Whittle Input Parameters
OVERALL SLOPE ANGLES PARAMETER
  CENTRAL PIT  
    HANGING WALL 49°
    FOOTWALL 47°
  NORTH-EASTERN PIT  
    HANGING WALL 51°
    FOOTWALL 45°
    NORTHERN WALL 47°
MINING & PROCESSING  
  MINING RECOVERY 95%
  MINING DILUTION 5%
  FRESH CU PROCESSING RECOVERY 94.0%
  OXIDE CU PROCESSING RECOVERY 55.0%
COSTS  
  MINING COST  
    ORE 1.80 USD/t
    OXIDE 1.30 USD/t
    WASTE 1.60 USD/t
  FRESH PROCESSING COST 9.00 USD/t ore
  OXIDE PROCESSING COST 22.57 USD/t ore
  GENERAL & ADMINISTRATIVE COST 5.00 USD/t ore
  ROYALTY 5.7% of RoM Metal Value (above 0.7% Cu head grade)
PRICE  
  CU SELLING PRICE 6,600 USD/t Cu
  NSR 83% (For Fresh Rock only)

Capital Expenditure

The estimated total project capital expenditure ("CAPEX") over the mine life of US$147 million, including the solvent extraction with electrowinning ("SXEW") plant to treat the oxide ores, is made up as follows:

  • US$21.5 million for mining equipment
  • US$40.1 million for copper in concentrate processing plant and equipment
  • US$26.3 million for SXEW plant
  • US$21.7 million for mine site facilities and infrastructure
  • US$26.3 million for sustaining capital & closure costs
  • US$11.3 million for contingency

The estimated initial CAPEX is US$115 million, which excludes the SXEW plant, sustaining capital & closure costs but includes pre-production development costs.

The initial CAPEX estimate is comparable to the initial capital cost estimate of US$100 million contained in the technical report entitled "Preliminary Assessment of the Karchiga Copper Project, East Kazakhstan Region, Kazakhstan" dated May 25, 2010 and prepared by Micon International Co. Limited (the "Karchiga Preliminary Assessment Study") (see Company's press-release dated 25 May 2010). The Company estimates that a 12 to 15 month period is sufficient for the construction of the processing facilities and pre-production development at the Karchiga Project.

Mine Plan

The open pit mining schedule produced by SRK calculated a producing mine life of 11.5 years. The mining schedule envisages the mining of 10 Mt of sulphide and oxide ore and 124 Mt of waste with a stripping ratio of 1:12.4 over the mine life. The average mining rate of the operation is 750kt per annum.

For the first 2.25 years of the mine life, the mining schedule includes open pit mining of the Central sulphide ore body alone in order to maximise the sulphide copper grade and hence sulphide copper recovery. The optimised mine schedule has been developed to minimise the stripping ratio in the initial three years of the mine life. In addition, the use of stockpiling has enabled the Company to increase the processed ore grade. From Year 4 until Year 7, sulphide ore will be mined from both the Central and North East open pits. From Year 8 until the end of mine life in Year 12, all mining will continue in the North East pit.

The average mining cost over the mine life is US$1.7 per tonne of material moved.

Processing Plan and Economic Model

The plant is designed to process approximately 750,000 tonnes per annum of sulphide ore. A conventional processing route was chosen using relatively fine grinding and selective sulphide flotation to produce a 27.9% bulk concentrate. The first production has been scheduled for Q4 2013 through to final production in 2025.

Copper from the oxide ore will be extracted using SXEW process. The oxides will be treated over a period of 4.5 years starting in 2018 at an annual production rate of 360,000 tonnes and is expected to produce an average of 2.8kt (6.22Mlb) of copper cathode per annum over that period. Production of cathode copper will continue until 2022.

In order to reduce the initial CAPEX, the SXEW plant construction has been delayed until after the initial CAPEX payback period (which is anticipated to be 2.75 years). The plant has been designed to treat an average of 30,000 tonnes of leachable oxide ore per month.

The results of the DFS demonstrate that economically the best option is to delay the SXEW construction until 2017, allowing the cost of construction to be financed from the revenue generated by the sulphide ore treatment.

The project key performance indicators are shown in Table 3 below.

Table 3. Key Performance Indicators
Parameter Units   Key Performance Indicator
Average annual mining rate Tonnes   750,000
Average mining cost US$/t of ore   22.99
Annual processing rate (FL) Tonnes   750,000
Mine life (FL) Years   11.5
Processing cost (FL) US$/t of ore   8.91
Metallurgical recovery (FL) %   93.4
Average annual copper production, over 11.5 years (FL) '000 tonnes   11.82
Average annual copper production (FL) Mlb   26.1
Annual processing rate (HL) Tonnes   360,000
Mine life (HL) Years   4.5
Processing cost (HL) US$/t of ore   18.7
Metallurgical recovery (HL) %   61.1
Average annual copper production, over 4.5 years (HL) '000 tonnes   2.8
Average annual copper production (HL) Mlb   6.2
Cash operating cost over the mine life (pre tax) US$/lb Cu   1.47

The mine is expected to produce a total of 149kt (328 Mlb) of payable copper, with an average of 12,957t (28.57 Mlb) of copper production per annum. Figure 1 below shows the production scenario on a 100% owned basis for the two types of payable copper products from the Karchiga Project.

To view Figure 1. Production Profile of Copper in Concentrate and Cathode Copper, please visit the following link: http://media3.marketwire.com/docs/OSU0229.pdf.

The Karchiga Project site is located 10 km from the main road and a 110 kV national power grid and is expected to be connected to the same as part of construction. An adequate supply of water can be sourced from the River Kalzhir as well as from aquifers in the immediate vicinity of the designed project facilities.

The project key economic indicators are shown in Table 4 below.

Table 4. Key Economic Indicators
Parameter Units   Key Economic Indicator
Total project CAPEX US$m   147
Initial CAPEX US$m   115
Total Net Smelter Revenue US$m   971
Sulphide and Oxide Case @ US$3.25/lb Cu:       
- Post-Tax NPV7.5
US$m   150
- Post-Tax IRR %   30
- Payback period   Years    2.75
Sulphide and Oxide Case @ US$3.00/lb Cu:      
- Post-Tax NPV7.5
US$m   113
- Post-Tax IRR %   25
- Payback period Years   3.0
All figures are on a 100% ownership basis

The Environmental and Social Impact Assessment Study for the Karchiga Project was successfully completed by Wardell Armstrong International on 31 January 2012. The Company expects to receive the necessary construction permitting approvals from the Kazakh authorities by the middle of 2012.

A copy of the DFS will be available on the Company's website and on www.sedar.com in due course. 

Dr Sergey V Kurzin, Executive Chairman of Orsu, commented: "I am pleased with the successful completion of the DFS, a key milestone in the development of Orsu as a company. The DFS demonstrates that Karchiga is a technically feasible project, which can be developed as a high grade, medium cost open pit copper mine with robust project economics and a rapid payback period. The Company has been working on the DFS in parallel with local Kazakhstan consulting companies in order to complete the local Technical Project required under Kazakhstan laws and regulations and we have already started the process of obtaining the necessary approvals and permits for project construction and development, which should accelerate the commencement of construction. In addition, the Company, together with their consultants Endeavour Financial have been working on project debt finance options with a number of commercial and development banks with a view to enabling commencement of project construction in Q3 2012."

Qualified Persons

The "qualified person" (as such term is defined in National Instrument 43-101) who supervised the preparation of the Mineral Reserve estimates for the Karchiga Project disclosed in this press release is Dr Alexander Yakubchuk, Chief Operating Officer, Orsu Metals Corporation. Dr Yakubchuk has reviewed and approved the contents of this press release.

The "qualified person" (as such term is defined in National Instrument 43-101) who supervised the preparation of the Mineral Reserve estimates for the Karchiga Project disclosed in this press release from SRK is Mr Michael Beare, Corporate Consultant, an employee at SRK Consulting UK Ltd, and independent of Orsu. Mr Beare was responsible for review and compilation of the Karchiga Project DFS and has reviewed and approved the contents of this press release.

Dr Mike Armitage, CEng, CGeol, Group Chairman and Corporate Consultant (Resource Geology) with SRK, Ms Tracey Laight, MSc, CGeol, FGS, Principal Consultant (Mining Geology) of SRK, both "qualified persons" (as such term is defined in National Instrument 43-101) and independent of Orsu, are the persons responsible for the preparation and verification of the Mineral Resource estimates for Karchiga Project disclosed in this press release.

Forward-looking information

This press release contains forward-looking information which is not comprised of historical facts. Forward-looking information involves risks, uncertainties and other factors that could cause actual events, results, performance and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking information contained (or referred to) in this press release includes, but may not be limited to, the Karchiga Project's expected life of mine and estimated net present value and rate of return, forecasts relating to future production and processing and the timing thereof, expected copper grades, estimates relating to key performance and economic indicators for the Karchiga Project, anticipated costs/expenditures relating to operations and capital, estimates relating to the future price of copper, future revenues, cash flows and capital payback, mineral resource and mineral reserve estimates, anticipated construction at the Karchiga Project and the timing related thereto, the Company's mine plan and processing plan and the expected results thereof, the Company's expectation that it will receive necessary construction and development permits and approvals and the timing related thereto, and management's expectations relating to the potential of the Karchiga Project.

Factors that could cause actual results to differ materially from those described in such forward-looking information include, but are not limited to, risks normally incidental to the development of mineral properties and operating hazards, the possibility that future development or mining results will not be consistent with expectations, uncertainty of mineral resource and mineral reserve estimates, technical and design factors, the Company's inability to obtain, maintain, renew and/or extend required licences, permits, authorizations and/or approvals from the appropriate regulatory authorities, including (without limitation) the Company's inability to obtain (or a delay in obtaining) the necessary construction and development permits and approvals from Kazakh authorities, and other risks relating to the regulatory and/or legal framework in Kazakhstan, the Company's inability to obtain financing for the development of the Karchiga Project on favourable terms or at all, fluctuations in the price of copper, as well as certain other risks set out in the Company's public documents, including its annual information form dated March 24, 2010, filed under the Company's profile on SEDAR at www.sedar.com.

The forward-looking information in this press release reflects the current expectations, assumptions and/or beliefs of the Company based on information currently available to the Company. In connection with the forward-looking information contained in this press release, the Company has made certain assumptions about the Company's business, the economy and the mineral exploration industry in general, future capital, operating and production costs, the future price of copper, the accuracy of the Company's anticipated timing for construction at the Karchiga Project, anticipated mining and processing rates, the key performance and economic indicators relating to the Karchiga Project, the regulatory framework in Kazakhstan with respect to, among other things, the Company's ability to obtain, maintain, renew and/or extend required permits, licences, authorizations and/or approvals from the appropriate regulatory authorities, including the necessary construction and development permits and approvals from Kazakh authorities required to develop the Karchiga Project as anticipated, the Company's ability to continue to obtain qualified staff and equipment in a timely and cost-efficient manner to meet the Company's demand, and has also assumed that no unusual geological or technical problems occur, plant and equipment work as anticipated and no significant events occur outside of the Company's normal course of business. Although the Company believes that the assumptions inherent in the forward-looking information are reasonable, forward-looking information is not a guarantee of future performance and accordingly undue reliance should not be put on such information due to the inherent uncertainty therein.

The mineral resource and mineral reserve figures contained to in this press release are estimates only and no assurances can be given that the indicated levels of copper will be produced. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. While the Company believes that the mineral resource and mineral reserve estimates contained herein are well established, by their nature, mineral resource and mineral reserve estimates are imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable. If such mineral resource and mineral reserve estimates are inaccurate or are reduced in the future, this could have a material adverse impact on the Company. Due to the uncertainty that may be attached to inferred mineral resources, it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration.

Any forward-looking information speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking information, whether as a result of new information, future events or results or otherwise.

GLOSSARY of technical terms:

  • Au - a chemical symbol for gold
  • Cu - a chemical symbol for copper
  • Cut-off grade - the lowest grade, or quality, of mineralised material that qualifies as economically mineable and available in a given deposit. May be defined on the basis of economic evaluation, or on physical or chemical attributes that define an acceptable product specification
  • g/t - grammes per tonne, equivalent to parts per million
  • Indicated Mineral Resource - that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics, can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.
  • Inferred Mineral Resource - that part of a Mineral Resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.
  • lb - pound (=453.59237 grammes)
  • Massive sulphide - a large, usually stratiform, conformable orebody composed mainly of iron sulphide, usually pyrite +/- pyrrhotite, and other base metal sulphides, such as chalcopyrite, along interfaces between volcanic units and sediments
  • Mineral Reserve - an economically mineable part of a Measured and/or Indicated Mineral Resource. It includes diluting materials and allowances for losses, which may occur when the material is mined. Appropriate assessments and studies have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified. Mineral Reserves are subdivided in order of increasing confidence into Probable Ore Reserves and Proved Ore Reserves.
  • Mineral Resource - a concentration or occurrence of natural, solid, inorganic or fossilized organic material in or on the Earth's crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge.
  • Mlb - million pounds
  • Moz - million troy ounces
  • Oxide Mineral Resource - A Mineral Resource comprising mineralisation formed by the chemical interaction of an element or elements with oxygen, usually affected by surface waters
  • oz - troy ounce (=31.103477 grammes)
  • Probable Mineral Reserve - an economically mineable part of Indicated Mineral Resource. It includes diluting material and allowances for losses which may occur when the material is mined. A Probable Ore Reserve has a lower level of confidence than a Proved Ore Reserve but is of sufficient quality to serve as the basis for a decision on the development of the deposit.
  • Proved Mineral Reserve - an economically mineable part of a Measured Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments and studies have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified. A Proved Ore Reserve represents the highest confidence category of reserve estimate. The style of mineralisation or other factors could mean that Proved Ore Reserves are not achievable in some deposits.
  • Sulphide - a mineral composed of a chemical compound between a metal and sulphur
  • t - tonne (=1 million grammes)


Orsu Metals Corporation
Dr Sergey V Kurzin
+44 (0) 20 7518 3999
or
Orsu Metals Corporation
Dr Alexander Yakubchuk
+44 (0) 20 7518 3999
or
Orsu Metals Corporation
Raymond Oates
+44 (0) 20 7518 3999
or
Orsu Metals Corporation
Tania Tchedaeva
Company Secretary
+44 (0) 20 7518 3999
or
Canaccord Genuity Limited
Ryan Gaffney
+44 (0) 20 7050 6500
or
Canaccord Genuity Limited
Andrew Chubb
+44 (0) 20 7050 6500
or
Vanguard Shareholder Solutions
+ 1 604 608 0824
Data and Statistics for these countries : Kazakhstan | All
Gold and Silver Prices for these countries : Kazakhstan | All

Orsu metals corporation

EXPLORATION STAGE
CODE : OSU.TO
ISIN : VGG3192Y1007
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Orsu is a gold and copper development stage company based in United kingdom.

Orsu holds various exploration projects in Kazakhstan.

Its main exploration properties are TOKHTAZAN, TADYBULAK and TALAS in Kyrgyzstan and KARCHIGA in Kazakhstan.

Orsu is listed in Canada, in Germany, in United Kingdom and in United States of America. Its market capitalisation is CA$ 6.4 millions as of today (US$ 4.9 millions, € 4.6 millions).

Its stock quote reached its highest recent level on October 19, 2007 at CA$ 1.83, and its lowest recent point on March 04, 2016 at CA$ 0.01.

Orsu has 182 696 049 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Orsu metals corporation
2/5/2009investor presentation
Annual reports of Orsu metals corporation
Annual report 2007
Nominations of Orsu metals corporation
4/22/2013Extension of East Balkhash 2 Agreement and Appointment of Te...
5/2/2012Announces the Appointment of Mr Kevin Denham as CFO
5/1/2012Announces Appointment of New Chief Financial Officer and Upd...
7/8/2008Announces Board and Committee Appointments
6/24/2008Results of the AGM and Director Appointments
6/23/2008Director Appointment
Financials of Orsu metals corporation
5/21/2013Re-filing of 2012 Annual Financial Statements
1/11/2013Filing of Revised Interim Financial Reports
8/14/2012Interim Results for the Period Ended June 30, 2012 (Unaudite...
5/14/2012Interim Results for the Period Ended March 31, 2012 (Unaudit...
8/11/2011Releases Interim Results for the Period Ended June 30, 2011
8/11/2011Interim Results for the Six Months Ended June 30, 2011 (Unau...
6/2/2011Interim Results for the Three Months Ended March 31, 2011 (U...
Project news of Orsu metals corporation
4/7/2015(Tokhtazan)New Exclusivity Agreement for Potential Sale of Akdjol-Tokht...
8/20/2012(Karchiga)Announces Approval from the Kazakh Authorities for the Devel...
7/17/2012(Talas)Gold Fields to Buy Remaining 40% Interest in Orsu's Talas Pr...
5/25/2012(Talas)Provides Update on the Talas Project in the Kyrgyz Republic
3/29/2012(Karchiga)Filed Definitive Feasibility Study on SEDAR for the Karchiga...
3/19/2012Develops Copper Mine on Chinese Border
3/14/2012A Step Closer to Production
2/29/2012(Karchiga)Announces Positive Definitive Feasibility Study for the Karc...
12/21/2011Expands Copper Resource On Chinese Border
9/29/2011(Karchiga)Karchiga Definitive Feasibility Study Update-Results of 2011...
5/11/2011(Karchiga)Announces Updated Mineral Resources for its Karchiga Project
4/28/2011(Karchiga)Karchiga Metallurgy Testwork Results
4/12/2011(Karchiga)Increases its Share in Karchiga Project to 94.75 per cent an...
3/3/2011(Tadybulak)Builds Kyrgyzstan Asset
2/24/2011(Karchiga)Drill Results Confirm High Grade Single Lode At Karchiga
2/10/2011(Karchiga)Assay Results for 2010 Infill Drilling Programme on the Karc...
5/26/2010(Karchiga)Completion of Preliminary Assessment Study
5/25/2010(Karchiga)N 43-101 technical report
4/6/2010(Tokhtazan)Provides Update on Extension of Tokhtazan Project Licences
3/23/2010(Karchiga)Resource Calculations on both Taldybulak Gold Asset & Karchi...
2/23/2010(Talas)Gets Approval of Class Action Claim Settlement/ Announces Co...
11/18/2009(Talas)Provides Update on Mineral Exploration Projects
6/15/2009(Varvarinskoye Mine)Sale of Varvarinskoye Project
1/30/2009(Varvarinskoye Mine)Mineral Reserves and Resources at Varvarinskoye Mine
12/11/2008completes 6,334m infill diamond drilling at the Taldybulak c...
5/9/2008(Varvarinskoye Mine)Reports Additional Resources at Varvarinskoye Project
Corporate news of Orsu metals corporation
8/3/2016Orsu Metals Corporation Reports Its Unaudited Results for th...
8/2/2016Orsu Metals Corporation Announces Sale of its Akdjol-Tokhtaz...
6/24/20162016 Annual Shareholders’ Meeting
5/31/2016Notice of Annual and Special Meeting of Shareholders and Pos...
5/12/2016Orsu Metals Corporation Reports its Unaudited Results for th...
5/10/2016Orsu Metals Corporation Reminder on Cancellation of Admissio...
5/5/2016Orsu Metals Corporation Update on Conditional Sale of Karchi...
4/11/2016Orsu Metals Corporation Announces Conditional Sale of Karchi...
3/30/2016Orsu Metals Corporation Reports its Audited Annual Results f...
1/26/2016Orsu Metals Corporation Update on Akdjol-Tokhtazan Project
1/25/2016Orsu Metals Corporation: Update on Akdjol-Tokhtazan Project
1/6/2016Update on Exclusivity Agreement for Potential Sale of Akdjol...
1/4/2016Orsu Metals Corporation: Update on Exclusivity Agreement for...
9/3/2015Orsu Metals Corporation Announces Grant of Options
9/2/2015Orsu Metals Corporation: Grant of Options
8/12/2015Orsu Metals Corporation Reports Its Unaudited Results for th...
8/12/2015Orsu Metals Corporation results for the period ended June 30...
7/14/2015Notification of Holding in Company
7/13/2015Orsu Metals Corporation: Notification of Holding in Company
6/23/20152015 Annual Shareholders’ Meeting
6/22/2015Orsu Metals Corporation: 2015 Annual Shareholders' Meeting
4/21/2015Orsu Metals Corporation: Expiry of Options
4/7/2015Orsu Metals Corporation Announces a New Conditional Exclusiv...
4/7/2015Orsu Metals Corporation: New Exclusivity Agreement for Poten...
3/27/2015Orsu Metals Corporation Reports its Audited Annual Results f...
3/27/2015Orsu Metals Corporation annual results for the year ended De...
3/24/2015Orsu Metals Corporation Announces Lapse of Mandate with UniC...
3/23/2015Lapse of Mandate With UniCredit and Barclays
3/23/2015Orsu Metals Corporation: Lapse of Mandate With UniCredit and...
1/29/2015Orsu Metals Corporation Announces Change in Senior Managemen...
1/29/2015Orsu Metals Corporation: Change in Senior Management
12/18/2014Orsu Metals Corporation Announces Assay Results for the Kogo...
12/18/2014Orsu Metals Corporation: Assay Results for Kogodai Licence A...
11/17/2014IIROC Trading Halt - OSU
11/17/2014Orsu Metals Corporation: New Exclusivity Agreement for Poten...
11/17/2014IIROC Trade Resumption - OSU
11/13/2014Orsu Metals Corporation Results for the Quarter Ended Septem...
10/14/2014Orsu Metals Corporation: Update on Exclusivity Agreement for...
10/6/2014Orsu Metals Corporation: Update on Exclusivity Agreement for...
9/24/2014Orsu Metals Corporation: Suspension of Joint Exploration of ...
9/19/2014Orsu Metals Corporation: New Exclusivity Agreement for Poten...
8/13/2014Orsu Metals Corporation: Results for the Quarter Ended June ...
8/4/2014Orsu Metals Corporation: Grant of License to Explore the Kog...
7/7/2014Orsu Metals Corporation: Update on the Potential Sale of Akd...
7/7/2014Orsu Metals Corporation: Update on the Potential Sale of Akd...
7/3/2014Orsu Metals Corporation: Extension of Exclusive Agreement to...
7/3/2014Orsu Metals Corporation: Extension of Exclusive Agreement to...
1/10/2014(Tokhtazan)=3A New Exclusivity Agreement for Potential Sale of Akdjol=2...
9/20/2013Exclusive Agreement to Continue Joint Exploration of the Eas...
9/12/2013(Tokhtazan)New Exclusivity Agreement for Potential Sale of Akdjol-Tokht...
8/13/2013Results for the Quarter Ended June 30, 2013 (Unaudited)
7/24/2013Completion of the Gold Fields Subscription
6/28/2013Annual Shareholders' Meeting Statement
6/28/2013Annual Shareholders' Meeting Statement
6/5/2013Notice of Annual Meeting and Posting of Circular
5/15/2013Results for the Quarter Ended March 31, 2013
5/15/2013Results for the Quarter Ended March 31, 2013 (Unaudited)
3/27/2013Annual Results for the Year Ended December 31, 2012
11/12/2012Grant of Exclusive Right to Explore the East Balkhash 2 Lice...
11/1/2012(Tokhtazan)on Sale of Akdjol-Tokhtazan
7/31/2012Appoints Barclays and UniCredit to Arrange a Senior Debt Fac...
7/24/2012(Talas)Completion of the Sale of Talas to Gold Fields
7/17/2012(Talas)sells Talas to Gold Fields for $10-million (U.S.)
6/19/2012Corrective Announcement of Extension of Endeavour Agreement
6/19/2012Extension of Endeavour Agreement
5/30/2012Notice of Annual General Meeting and Posting of Circular
3/30/2012Annual results for the year ended December 31, 2011
3/5/2012Hits The Sweet Spot In Kazakhstan
3/2/2012(Karchiga)Karchiga Feasibility Lifts Orsu Metals
12/8/2011(Karchiga)Announces An Increased Mineral Resource for its Karchiga Pro...
12/8/2011As Part the Ongoing Definitive Feasibility Study, Orsu Annou...
9/21/2011Receives US$6.83 Mil in Cash for Deferred Consideration and ...
9/21/2011Receives US$6.83 Million in Cash in Early and Final Settleme...
9/1/2011Completes Infill Drilling Programme in Connection With Ongoi...
7/27/2011in Growth Stocks Weekly
7/25/2011Receives US$5.5 Mil In Early and Final Settlement of Deferre...
7/25/2011to Receive US$5.5 Million Cash in Early and Final Settlement...
7/18/2011Commences Infill Drilling Programme in Connection With Ongoi...
3/23/2011Holding(s) in Company
8/6/2010Kyrgyzstan Project Updates: James Winston
7/22/2010Confirms Copper Deposit in Kazakhstan
7/21/2010Provides Update on Mineral Exploration Projects in Kyrgyzsta...
5/27/2010James Winston on Orsu Metals
5/20/2010Enters into Agreement to Increase Share in Karchiga to 94.75...
5/18/2010Interim Results for the Period Ended March 31, 2010
4/23/2010Holding(s) in Company - Sprott Holds 7.2 per cent
2/4/2010Completion of 1st Phase
11/27/2009Agreement to Settle Class Action Claim
11/24/2009Completes Share Consolidation
10/14/2009Provides Update on Sale of Varvarinskoye Project
10/2/2009The Speculative Investor Updates Orsu Metals
9/14/2009Sale of Varvarinskoye Project
7/13/20092009 Annual and Special Meeting Statement
6/24/2009Notice of 2009 Annual and Special Meeting of Shareholders
1/27/2009Winston updates Orsu Metals
1/14/2009Varvarinskoye Update
1/8/2009Announces Update on Extension of Principal Payment Deadline
12/3/2008announces completion of joint venture agreement with Gold Fi...
11/21/2008Crisis or Opportunity?
11/13/2008Corp: Interim Results for the Period Ended 30 September 2008...
11/3/2008poised to evolve into major gold producer, says Roulston
9/26/2008announces update on Varvarinskoye and exploration projects, ...
9/19/2008Winston Updates Orsu Metals Corp
9/9/2008' Denver Gold Forum presentation is available online
9/5/2008Director Share Purchase
8/19/2008Interim Results for the Period Ended 30 June 2008
7/30/2008The Speculative Investor Updates Orsu Metals
7/14/2008European Minerals name change to Orsu; symbol change
7/10/2008Completes First Sale of Copper-Gold Concentrate from the Var...
6/27/2008 Announces the Issue of Shares Pursuant to Acquisition
3/31/2008Varvarinskoye Quarterly Update, Litigation Update, and Finan...
12/27/2007Achieves First Gold Pour on 22 December
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (OSU.TO)LSE (OSU.L)
0.035-12.50%1.25-10.71%
TORONTO
CA$ 0.035
01/31 15:27 -0.010
-12.5%
Prev close Open
0.040 0.035
Low High
0.035 0.035
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.035 -12.50%
Volume 1 month var.
202,000 -12.50%
24hGold TrendPower© : 44
Produces
Develops
Explores for Copper - Gold - Molybdenum
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 12/28/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.05+0.43%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.91-2.73%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-3.26%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.67+0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+6.25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 1.77-2.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.37-0.22%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.