VANCOUVER, BRITISH COLUMBIA--(Marketwire - Oct. 31, 2012) - Mr. Harvey Keats, Chief Executive Officer of Donner Metals Ltd. ("Donner" or the "Company") (News - Market indicators)(FRANKFURT:D4M), provides a development update for the Bracemac-McLeod Mine and an exploration update for the Matagami Project as reported to the Company by partner and project operator Xstrata Canada Corporation-Xstrata Zinc Canada Division ("Xstrata Zinc").

Bracemac-McLeod Development:

Development, now standing at 6,430 metres, has reached the Bracemac Main and the Bracemac KT zones and development in ore has already started at the Bracemac Main zone. Ramping continues at Bracemac and in the two ramps to McLeod. There are now 25,000 tonnes of ore in the stockpile on surface from the Bracemac Main Zone. Pre-production activities will commence in January with the objective of having 3 months of ready-to-blast ore to supply the mill at 3,000 tonnes per day early in the second quarter of 2013. Equipment and buildings are being moved from Persévérance to Bracemac-McLeod in preparation for the transition to production from Bracemac-McLeod.

McLeod Deep Drill Program:

Donner and Xstrata have completed planning of an aggressive 35,000 metre drill program on the McLeod Deep Zone discovery that is currently estimated to contain Inferred Mineral Resources of 2.47 million tonnes grading 9.21% zinc, 1.22% copper, 39.81 g/t silver and 1.12 g/t gold (65% Xstrata, 35% Donner). Drilling will be conducted by multiple wedges from seven new pilot holes. The program will consist of both definition and exploration drilling designed to meet the following objectives:

  • Meet the 50-metre drill hole spacing criteria for the estimation and classification of the McLeod Deep Zone as an indicated resource.
  • Assess the continuity and distribution of gold grades within the base metal sulphide mineralization.
  • Identify possible extensions of mineralization to the southeast, northwest and down-dip.
  • Confirm the presence of mineralization between the McLeod Deep Zone and the bottom of the McLeod Zone, which is currently under development.

This program will provide the technical information required to determine if the life-of-mine plan for Bracemac-McLeod should be expanded to include development of the McLeod Deep Zone.

Exploration:

A total of five Diamond drill holes were completed and one hole was deepened since mid-September. Results from each area are described below and assay results are listed in the attached Table 1.

McLeod Up-Dip

Three Diamond drill holes were completed and one hole was deepened as part of the continuing McLeod Zone up-dip exploration program (Figure 1). All holes intersected mineralized chlorite alteration ("Pipe" alteration) with local copper and copper-zinc sulphides. The holes investigated the Key Tuffite Horizon at an approximate spacing of 50 metres.

Three drill holes were completed up-dip and to the east of MCL-12-16 (2.83% copper over 19.4 metres). MCL-12-19 was drilled 37 metres east and up-dip from MCL-12-16. This hole intersected 10 metres of intense Pipe alteration carrying a mineralized zone which returned 1.0 metre grading 8.86% copper, 3.97% zinc, 33.9 g/t silver, 0.18 g/t gold. MCL-12-20 intersected stringer mineralization and patchy chlorite alteration 184 metres up-dip from MCL-12-19 and 61 metres up-dip and east of hole MC-08-35 that returned 10.75% copper over 0.6 metres. MCL-12-21 was drilled 52 metres down-dip from MCL-12-20 where it intersected sheared intrusive rocks at the target followed by 36 metres of Pipe alteration. MCL-12-13, previously reported on September 19, 2012, was deepened to 522 metres. It intersected 14.7 metres of well-mineralized Pipe alteration below the Key Tuffite carrying stringer chalcopyrite and sphalerite. Assays are pending.

Rivière Allard

Two drill holes were completed in the Rivière Allard area in the Central Camp Joint Venture area approximately 11 kilometres from the Matagami Lake Mill. Drill holes RA-12-12 and RA-12-13, drilled 180 metres apart, intersected a weakly mineralized andesite pyroclastic unit at the target horizon. Mineralization consists of disseminated and stringer pyrite, pyrrhotite, magnetite, sphalerite and chalcopyrite. No significant values are expected.

SUPPLEMENTARY INFORMATION

The Bracemac-McLeod deposit contains Proven and Probable Mineral Reserves of 3.7 million tonnes grading 9.60% zinc, 1.26% copper, 28.25 g/t silver and 0.43 g/t gold. Inferred Mineral Resources of 2.6 million tonnes grading 8.79% zinc, 1.31% copper, 38.84 g/t silver and 1.06 g/t gold are located in proximity to the Mineral Reserves. The Company is a fully vested partner with Xstrata Canada Corporation in the extensive Matagami base metal camp located in the Abitibi region of Québec. This joint venture partnership covers six joint venture areas ("the Matagami Project") governing 4,737 square kilometres of prime stratigraphy, which has yielded high-grade base metal production since 1963. Xstrata Zinc is the project operator for the Matagami Project, including the Bracemac-McLeod Mine. Additional information is available at www.donnermetals.com.

Xstrata Zinc is the project operator for the Matagami Project and all of the respective joint ventures. As operator, Xstrata Zinc is responsible for the execution of all development, production and exploration programs on the property. This includes resource evaluation, sampling, submittal of samples for assay, assay verification, metallurgical evaluation and QA/QC. Sample preparation and assaying are conducted by ALS Chemex-Chimitec, of Val-d'Or, Québec (zinc, copper and silver by atomic absorption, and gold by standard fire assay procedures).

Robin Adair (VP of Exploration) is a Qualified Person for Donner Metals Ltd. and is responsible for the technical information reported in this news release.

ON BEHALF OF THE BOARD OF DONNER METALS LTD.

Harvey Keats, Chief Executive Officer

To view Table 1 and Figure 1, associated with this press release, please visit the following link: http://media3.marketwire.com/docs/don-1031-maptable-eng.pdf.

Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Donner Metals Ltd. - Vancouver
604.683.0564 or Toll Free: 1-800-909-8311
or
Donner Metals Ltd. - Montreal
514.286.1665
donner@bed-rock.com
www.donnermetals.com
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Sphinx Resources

EXPLORATION STAGE
CODE : SFX.V
ISIN : CA8484221012
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Sphinx is a zinc and copper development stage company based in Canada.

Sphinx develops zinc, copper, gold and silver in Canada.

Its main asset in development is PD1 in Canada and its main exploration properties are SOUTH VOISEY BAY, WEST RAGLAN and MATAGAMI in Canada.

Sphinx is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 838 700 as of today (US$ 670 585, € 638 839).

Its stock quote reached its highest recent level on August 26, 2016 at CA$ 0.14, and its lowest recent point on December 06, 2022 at CA$ 0.01.

Sphinx has 83 870 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Sphinx Resources
8/8/2013Announces Second Closing of Private Placement
8/8/2013=3A Donner Metals announces closing of private placement
7/9/2013=3A Financing Update
6/24/2013Announces Financing
11/14/2012Announces Closing of C$1,439,000 Final Tranche Private Place...
2/28/2012Increases Private Placement Financing
2/27/2012Announces C$10,000,000 Private Placement Financing
10/27/2011Announces C$2,440,000 of Private Placement Financings
7/27/2011$3 Million Private Placement
7/25/2011Funds Received, Private Placement Closed
7/13/2011Financing News
2/15/2010Additional Private Placement Closings
11/16/2009Private Placements close
5/14/2009Non-Brokered Financing
1/7/2008 $3.2 Million Private Placement Closed
12/17/2007 Private Placement Increased to $3.2 Million
12/7/2007 $2.0 Million Private Placement
Project news of Sphinx Resources
12/10/2013Donner Metals Acquires Option on Valmond Gold Property from ...
10/30/2013(Matagami)Matagami Exploration Joint Ventures Update
9/3/2013=3A Donner Forfeits Interest in Bracemac=2DMcLeod
8/13/2013=3A Donner Metals Bracemac=2DMcLeod Interest
8/13/2013Bracemac-McLeod Interest
7/31/2013=3A Donner Metals Mineralization Extended=2C New Copper Zone...
7/12/2013=3A Donner Metals Update on Production at Bracemac=2DMcLeod
7/12/2013Update on Bracemac-McLeod Production
5/22/2013More High-Grade at McLeod Deep
5/16/2013Production has started!
5/16/2013Production Commences at Bracemac-McLeod
11/1/2012Development and Exploration Update
9/5/2012Bracemac-Mcleod Continues on Target
7/6/2012Provides Exploration Drilling Update
7/6/2012=3A Higher Production at Bracemac=2DMcLeod
7/5/2012Higher Production at Bracemac-McLeod
2/22/2012(Matagami)Ltd=2E: New Drilling Continues to Demonstrate Potential of M...
1/16/2012Ltd=2E: Bracemac-McLeod Mine Development Continues to Track ...
10/25/2011Ltd=2E: Bracemac-McLeod Mine Development Tracking On Budget ...
4/26/2011(Matagami)Completes Earn-In on the Matagami Project
3/6/2011(Matagami)Bracemac-McLeod Ramp Moves Past 660 Metres
2/10/2011(Pd1) Matagami Project Advances as the PD1 Deposit Moves to Feasi...
7/12/2010(Matagami)Drilling Extends McLeod Deep Discovery
3/7/2010(Matagami)Bracemac-McLeod Update
2/16/2010(Matagami)McLeod Deep Discovery Expanded-7.50 Metres Grading 10.27% Zi...
11/23/2009(Matagami)Expanded Winter Drill Progam Initiated at Matagami
10/1/2009(Matagami)Bracemac-McLeod Feasibility Advances as Exploration Continue...
7/15/2009(Matagami) BRACEMAC-MCLEOD advances to feasibility
6/5/2009(Matagami)on BNN and Matagami Project Details
5/25/2009(Matagami)Drilling to Resume at Matagami; Scoping Study Nears Completi...
2/26/2009(Matagami)BRACEMAC-MCLEOD NI 43-101 INDICATED RESOURCE: 3,623,000 TONN...
2/26/2009(Matagami)UPDATED BRACEMAC-MCLEOD NI 43-101
2/11/2009(Matagami)featured on Minesite.com
1/26/2009(Matagami)NI43-101 Resource
1/23/2009(Matagami)INITIAL BRACEMAC-MCLEOD NI43-101 INDICATED RESOURCE
11/12/2008(Matagami)Assays Return High-Grade Zincand Copper from the McLeod Disc...
9/5/2008Provides Initial Results From a Single Drill Hole Program on...
5/27/2008(Matagami)Four New High GradeIntersections at Bracemac/McLeod Includin...
5/9/2008(Matagami)13.47% Zinc, 2.33% Copper Over 6.95 Metres Intersected at Br...
4/11/2008High Grade Discovered Between Bracemac and McLeod
3/3/2008New High Grade Intersections Expand Zones at Bracemac and Mc...
1/9/2008 Drilling Intersects 9.48% Zinc and 2.81% Copper Over 6.00
Corporate news of Sphinx Resources
12/30/2013Announces Completion of Share Consolidation
12/13/2013Announces Results From AnnualGeneral and Special Meeting and...
11/14/2013Annual and Special General Meeting
7/18/2013Announces Closing of C$2,807,010 Placement
7/8/2013=3A Copper Stream with Sandstorm Amended
7/8/2013Donner Metals Copper Stream With Sandstorm Amended
3/14/2013Announces Financial Support from Quebec Institutions
1/15/2013Stock Options Granted
11/1/2012Ltd=2E: Increased Upfront Paymen =?ISO-8859-1?Q?t=20From=20S...
10/22/2012Announces Results from Annual General Meeting, Head Office M...
10/22/2012Announces Results from Annual General Meeting, Head Office M...
10/4/2012Underground photos and video updates from Donner Metals
9/19/2012Ltd=2E: Mcleod Zone Extended Up-Dip: Exploration Drilling In...
8/28/2012=3A President's Message
4/17/2012Normand Champigny Appointed President of Donner Metals
2/23/2012Sandstorm Partners With Donner Metals
2/22/2012Ltd=2E: Development to Reach the McLeod Zone a Year Ahead of...
2/22/2012News Release
1/20/2012Join us at at the Vancouver Resource Show and Exploration Ro...
9/1/2011September Video update from Donner Metals
7/13/2011Sandstorm Provides US$25 Million Senior Financing
4/14/2010Definition Drill Program Completed at Bracemac-McLeod
2/3/2010$2,409,930 Financing Closed
1/30/2010Financing Increased
9/8/2009engineering contract and fast-tracked feasibility
8/24/2009Two Near Term Production Stories
6/22/2009Industrial Alliance Features Report on Donner Metals
5/19/2009A "Green Shoot" Rising
5/14/2009Is At The Starting Gate
2/26/2009Hotsheet
2/18/2009positioned for success
2/9/2009featured in Mining Journal
12/12/2008$1,048,000 Financing Closes
12/4/2008 AND XSTRATA ZINC CANADA WIN INTERNATIONAL EXPLORATION AWARD
11/25/2008$1.0 Million Financing
11/18/2008Donner Metals has fast-track potential says Reinhard
7/31/2008 Drilling Continues toDelineate and Expand Mineralization at...
8/1/2008Hotsheet for 7/31/2008
5/28/2008$3 Million Debenture Offering
5/27/2008Hotsheet for 5/27/2008
4/11/2008Hotsheet for 4/11/2008
3/20/2008March Chairman's Letter
3/5/2008Hotsheet for 3/5/2008
2/1/2008Engages Mau Capital to Provide Investor Relations
1/8/2008Hotsheet for 1/8/2008
12/7/2007Chairman's Letter
11/28/2007Expands Interest in Matagami Camp
11/8/2007Join us at the San Francisco Hard Assets Investment Conferen...
10/22/2007 Hotsheet for 10/21/2007
8/2/20076 New Massive Sulphide =?ISO-8859-1?Q?=20Intersections,=20In...
6/14/2007New Zinc-Copper Discover 9.24% Zinc, 0.99% Copper Over 27.95...
6/7/2007Bracemac Yields Additional Results With New Mineralization I...
4/11/2007Copper-Rich Massive Sulphides Intersected in BRC-07-32 in th...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (SFX.V)
0.010+0.00%
TSX-V
CA$ 0.010
12/06 09:30 -
0%
Prev close Open
0.010 0.010
Low High
0.010 0.010
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.010 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : -9
Produces
Develops
Explores for Copper - Gold - Nickel - Palladium - Platinum - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/23/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :