Endeavour International Corporation

Published : September 20th, 2017

Launches Construction of Ity CIL Project Based on Optimization Study

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
     


https://www.endeavourmining.com/_themes/design2015/img/endeavour-mining.png?v=1437585204NEWS RELEASE � TSX: EDV All amounts in US$    

ENDEAVOUR LAUNCHES CONSTRUCTION OF ITY CIL PROJECT BASED ON OPTIMIZATION STUDY

 

View News Release in PDF Format

View Presentation in PDF Format

HIGHLIGHTS     

  • Optimization Study significantly improves the previous Feasibility Study results (published in November 2016) and positions the Ity CIL Project as Endeavour's next long-life low-cost flagship asset
    • Long 14-year mine life based on current reserves which increased by 1.0Moz to 2.9Moz
    • Average annual production over the first 5 years increased by 42% to 235koz and AISC decreased by 3% to $494/oz
    • Average annual production over the first 10 years increased by 51% to 204koz and AISC decreased by 2% to $549/oz
    • Robust economics with after-tax NPV5% of $710m, a 73% increase, based on a gold price of $1,250/oz
  • Ity CIL Project has entered the construction phase following Board approval
    • Endeavour's in-house construction team has begun to transition from Hound� to Ity and has commenced mobilisation to site
    • $412 million initial capex, fully funded from existing sources of capital with the recent Revolving Credit Facility upsize
    • 20-month construction duration with the first gold pour expected for mid-2019

 

Abidjan, September 20, 2017 - Endeavour Mining Corporation ("Endeavour") (the "Company) (TSX:EDV) (OTCQX:EDVMF) is pleased to announce that its Board of Directors has approved the construction decision for its Ity CIL project at its mine in Cote d'Ivoire following the robust results obtained from its Optimization Study.   

The Ity CIL Project Feasibility and Optimization studies have been conducted to analyze the economic viability of constructing a straight forward gravity circuit/Carbon-In-Leach ("CIL") plant as an alternate processing route to the current heap leach process. Following the publication of the November 2016 Feasibility Study ("FS"), an Optimization Study ("OS") was prepared to better capture the value created from the recent exploration success which has led to increasing the plant name-plate design from 3.0Mtpa to 4.0Mtpa. In addition, several changes have been made to leverage construction and operating synergies between Ity, Agbaou and Hound�.

The production profile and economics have significantly improved, as summarized in Table 1 below:

Table 1: Summary of 2016 CIL Feasibility Study vs. 2017 Optimization Study

(On a 100% basis)

2017
OPTIMIZATION STUDY

2016

FEASIBILITY STUDY

VARIANCE
(OS VS. FS)

M&I Resources (inclusive of Reserves)

3.8Moz

2.3Moz

+65%

P&P Reserves

2.9Moz

1.9Moz

+53%

Average production (first 5 years)

235koz

165koz

+42%

Average AISC (first 5 years)

$494/oz

$507/oz

(3%)

After-tax NPV5% based on $1,250/oz

$710m

$411m

+73%

After-tax IRR based on $1,250/oz

40.3%

35.9%

+12%

After-tax IRR based on $1,000/oz

23.2%

19.5%

+19%

S�bastien de Montessus, President & CEO, stated:  "Today's study clearly positions Ity as our next flagship asset with robust project economics, a strong long-life production profile, and significant exploration upside. Its average annual production in the first five years of 235koz with AISC below $500/oz and an after-tax IRR  of +20% even at a low gold price of $1,000 per ounce are proof of the compelling economics of the project.

With the upcoming first gold pour at Hound� and Ity CIL construction expected to be completed within 20-months, we remain on track to achieve our strategic milestones of becoming a +800,000 ounce per year gold producer with group AISC below $800 per ounce and mine lives above 10 years by 2019."

Jeremy Langford, COO, added: "We have optimized the Ity CIL project by maximizing the construction and operational synergies between Agbaou, Hound� and Ity, and by leveraging the same designs, components, equipment and spare parts where possible from one project to the other, along with incorporating our extensive construction expertise. The construction team is excited to transition from Hound� to Ity and to continue to build on its construction track-record."  

 

SUMMARY OF KEY CHANGES FROM PREVIOUS FEASIBILITY STUDY

The Ity CIL Project Optimization Study has been managed by Endeavour's in house development team and independently prepared by Lycopodium Minerals Pty Ltd ("Lycopodium") with the support of six globally recognized engineering firms, with the key operational and financial results summarized in the table below:

Table 2: Detailed Summary of 2016 CIL Feasibility Study vs. 2017 Optimization Study

 

2017
OPTIMIZATION
STUDY

2016

FEASIBILITY
STUDY

VARIANCE
(OS VS. FS)

LIFE OF MINE PRODUCTION

 

 

 

Strip ratio, w:o

1.9

2.1

(10%)

Tonnes of ore processed, Mt

57..0Mt

41..0Mt

+39%

Grade processed, Au g/t

1.57 g/t

1.42 g/t

+10%

Gold content processed, Moz

2.87 Moz

1.88 Moz

+53%

LOM Average Gold recovery, %

86%

83%

+3%

Gold production, Moz

2.47 Moz

1.56 Moz

+58%

Mine life, years

14..3 years

13.7 years

+4%

Average annual gold production, koz

173 Koz

114 Koz

+52%

Cash costs, $/oz

$554

$528

+5%

AISC, $/oz

$580

$603

(4%)

AVERAGE FOR YEARS 1 TO 5:

 

 

 

Gold production, kozpa

235 koz

165 koz

+42%

Cash costs, $/oz

$472/oz

$446/oz

+6%

AISC, $/oz

$494/oz

$507/oz

(3%)

AVERAGE FOR YEARS 1 TO 10:

 

 

 

Gold production, kozpa

204 koz

135 koz

+51%

Cash costs, $/oz

$523/oz

$488/oz

+7%

AISC, $/oz

$549/oz

$559/oz

(2%)

CAPITAL COST

 

 

 

Initial capital cost, $m

$412m

$307m

+34%

  - of which equipment lease, $m

$61m

$25m

+160%

Upfront capital cost, $m

$351m

$282m

+24%

ECONOMICS (BASED ON $1,250/OZ)

 

 

 

After-tax IRR

40%

36%

+12%

After-tax NPV  ( 0% discount rate)

$990m

$607m

+63%

After-tax NPV  ( 5% discount rate)

$710m

$411m

+73%

Payback period

1.8 years

2.1 years

(17%)

The key changes made in the Optimization Study include:

  • CIL process plant increased from 3Mtpa to 4Mtpa to better capture the value created from the recent exploration success which has discovered the Bakatouo deposit and increased resources at notably Daapleu and Mont/Ity Flat.
  • Simplified and optimized the process plant design to maximize the replication of the Hound� design, where applicable, to capture working capital inventory synergies.
  • Improved recoveries based on additional metallurgical testwork, namely on the Daapleau primary material.
  • Addition of a diverter/flop-gate system which allows the Ball Mill to run independently during periods when the SAG mill is shut down. This operability allows the plant to maximize utilization and effectively ensure process milling all year round. 
  • Addition of a 26MW full back up power station, identical to that installed at the Hound� project.
  • Optimized upfront capital cost and sequenced overall build time with a higher percentage of "Self-Perform" works.
  • Optimized the site layout, which allows the current heap leach operation to run independently of the CIL project. As such, the construction of the CIL project is not expected to impact the heap leach operation.

 

RESERVES INCREASED BY 1.0Moz, UP 53%

The updated Mineral Reserve estimates were undertaken by Snowden Mining industry Consultants (Snowden). Changes from the previously reported Mineral Reserves are largely due to revised and updated Mineral Resource estimates on the Daapleu, Ity and Bakatouo deposits and revised operating costs largely associated with revised processing capabilities from a 3 Mtpa facility to a 4 Mtpa treatment facility.

Compared to the 2016 Feasibility Study reserves, a total of 1.0Moz were added, with the main increases coming from the discovery of Bakatouo (+532koz), and additional resource to reserve conversion at Mont Ity/Ity Flat (+211koz), Teckraie/Verse Ouest (+187koz), and at Daapleu (+79koz) following additional drilling, as shown in the table below. The Colline Sud deposit is expected to be mined during the heap leach phase and therefore has been excluded from CIL Mineral Reserves.  

Table 3: CIL Project Reserves Comparison

Deposits
on a 100% basis

Optimization Study Reserves,
as at September 1, 2017

 

Feasibility Study Reserves,
as at October 1, 2016

 

Variance
(koz)

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

 

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

 

Open Pits

                 

Bakatouo

6.9

2.40

532

 

-

-

-

 

+532

Colline Sud

-

-

-

 

-

-

-

 

-

Daapleu

18.4

1.72

1,015

 

19.3

1.51

936

 

+79

Mont Ity / Ity Flat

7.4

2.03

479

 

3.8

2.19

268

 

+211

Gbeitouo

2.5

1.37

111

 

2.6

1.35

112

 

(1)

Walter

1.2

1.07

41

 

1.9

1.22

73

 

(32)

Zia NE

6.2

1.06

210

 

4.8

1.24

192

 

+18

Sub-total

42.5

1.75

2,390

 

32.4

1.52

1,580

 

+810

Existing Stockpiles

 

 

 

         

 

Aires

5.8

1.09

202

 

5.8

1.09

202

 

-

Teckraie/ Verse Ouest

8.7

1.02

284

 

2.8

1.07

97

 

+187

Sub-total

14.5

1.05

486

 

8.6

1.08

300

 

+186

Total

57.0

1.57

2,876

 

41.0

1.42

1,880

 

+996

Mineral Reserve estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") definitions standards for mineral resources and reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Notes are provided in Section "About the Mineral Reserve and Resources" of this Press Release, with effective date September 1, 2017. Full details on the 2016 Feasibility Study Reserves are available in the Company's published press release dated November 10, 2016.

 

INDICATED RESOURCE INCREASED BY 1.5Moz

The updated Indicated and Inferred Mineral Resource estimates were undertaken by Cube Consulting (Cube), and incorporate all validated RC, DC and AC drilling completed at the Ity CIL Project up to May 1, 2017.  

There is a total of 10 deposit areas included in the updated Mineral Resource for the Ity CIL Project including four in situ gold deposits that have been or are currently in production, comprising Mont Ity, Ity Flat, ZiaNE and Walter, plus three near-mine in situ deposits comprising Gbeitouo, Daapleu, Colline Sud and Bakatouo, and two rock waste dumps at Teckraie and Verse Ouest and a discontinued heap leach pad Aires.

Compared to the resource inventory used to build the 2016 Feasibility Study, a total of 1.5Moz of Indicated Resources were added, with the main increases coming from the discovery of Bakatouo (+704koz), and additional Indicated resources outlined at Daapleu (+384koz), Mont Ity / Ity Flat (+189koz), and Verse Ouest (+187koz), as shown in the table below.

Table 4: Resource Comparison

 

2017 OPTIMIZATION STUDY INVENTORY

 

2016 FEASIBILITY STUDY INVENTORY

Deposits
on a 100% basis

Indicated Resources

 

Inferred Resources

 

Indicated Resources

 

Inferred Resources

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

 

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

 

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

 

Tonnage
(Mt)

Grade
(Au g/t)

Content
(Au koz)

Open Pits

               

 

 

 

 

 

 

 

 Daapleu

28.1

1.50

1,349

 

0.7

0.92

22

 

19.9

1.51

965

 

4.3

1.15

160

 Mont Ity / Flat

10.1

2.20

716

 

9.7

1.40

436

 

7.5

2.19

527

 

11.1

1.92

684

 Gbeitouo

2.9

1.35

124

 

0.3

1.48

13

 

2.9

1.35

124

 

0.3

1.48

13

 Walter

1.6

1.23

65

 

0.6

1.35

26

 

2.1

1.21

81

 

0.7

1.32

28

 Zia NE

6.7

1.28

274

 

4.0

1.40

178

 

7.7

1.31

325

 

4.0

1.39

179

 Bakatouo

10.2

2.14

704

 

0.6

2.27

44

 

-

-

-

 

-

-

-

 Colline Sud

1.0

2.14

66

 

0.4

2.11

28

 

-

-

-

 

-

-

-

 Sub-total

60.6

1.69

3,298

 

16.3

1.43

747

 

40.1

1.57

2,022

 

20.4

1.62

1,064

Existing Stockpiles

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 Aires

5.8

1.09

202

 

0.2

0.78

6

 

5.8

1.09

202

 

0.2

0.78

6

 Teckraie

2.8

1.07

97

 

0.1

0.55

2

 

2.8

1.07

97

 

0.1

0.55

2

 Verse Ouest

5.9

0.99

187

 

2.3

0.50

37

 

-

-

-

 

8.4

0.85

230

 Sub-total

14.5

1.04

486

 

2.6

0.54

45

 

8.6

1.08

300

 

8.7

0.85

238

Total

75.1

1.57

3,784

 

18.9

1.30

792

 

48.7

1.48

2,322

 

29.1

1.39

1,302

Resource estimated to the Indicated status, as such no Measured Resources available. Mineral Resource estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") definitions standards for mineral resources and reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Notes are provided in Section "About the Mineral Reserve and Resources" of this Press Release, with effective date September 1, 2017. Full details on the 2016 Feasibility Study Inventory are available in the Company's published press release dated November 10, 2016.

 

MINING OPERATIONS, PROCESSING, AND METALLURGY

MINING AND PROCESSING STRATEGY

A number of schedules were completed to test the impact of limiting stockpile size and it was found that there was limited benefit to allowing for large stockpiles. As such, the mining sequence and stockpile management has improved in the Optimized Study compared to the Feasibility Study. Whereas previously the mining period was 9 years followed by the processing of stockpiled low-grade ore for another 5 years, the current mine plan is based on 12 years of mining followed by the processing of stockpiled low-grade ore for another 2 years.

A combination of strategic pit staging and stockpiling allows gold production to be brought forward, with about 1.2 Moz mined in the first 5 years from commissioning and 1.5 Moz in the last 10 years. The overall grade profile declines gradually over the life of mine as higher grade deposits such as Bakatouo, Daapleu and Mont Ity / Flat are mined upfront.

 

Mining Operations

The mine planning, resource and cost estimation for the Feasibility Study is based on an owner-operated mining operation using 90-tonne haul trucks and a maximum mining movement of 16Mt per year with a vertical advance of approximately 40 metres per year. The Company sees these figures as conservative in nature due to the annual rainfall at the Ity project.  Mining is scheduled to commence three months before the start of the processing plant to pre-strip the pits and stockpile ore. The mining fleet contract has been awarded to Komatsu to benefit from synergies relating to minimizing spare parts inventory and maintenance costs, as both Hound� and Karma have a similar fleet.

Table 5: Mine Plan

 

Total

Y-1

Y-2

Y-3

Y-4

Y-5

Y-6

Y-7

Y-8

Y-9

Y-10

Y-11

Y-12

Total material moved, Mt

167

15.6

16.0

16.0

16.0

16.0

16.0

13.8

12.7

15.9

13.6

10.1

5.1

Total ore mined, Mt

57

4.6

5.8

5.9

4.7

4.8

5.1

4.3

3.8

5.4

5.9

4.9

1.9

Stripping ratio, w:o

1.9

2.4

1.8

1.7

2.4

2.3

2.1

2.2

2.3

1.9

1.3

1.1

1.7

Grade mined, g/t Au

1.57

1.70

2.05

1.78

1.87

1.65

1.88

1.20

1.37

1.38

1.30

1.12

1.08

Contained gold mined, koz

2,883

250

380

340

284

256

310

166

168

241

246

176

66

 

Processing Operations

Following updated resource and reserve estimates, the key change to the design basis is an increase in throughput from 3 Mtpa feed to 4 Mtpa feed based on a blend of primary and oxide ore with a conventional primary crushing followed by SAG and Ball milling circuit (SABC) with recycle pebble crusher,  gravity circuit and conventional CIL (Carbon-In-Leach) plant. Soluble copper from the Bakatouo asset is blended with the low copper Daapleu ore into the plant process schedule until depletion of Bakatouo. A maximum process plant feed limit of 200ppm cyanide soluble copper constraint has been set, to manage cyanide consumption within the CIL plant and detoxification circuit.

The process plant will notably be composed of a single stage primary crushing to produce a crushed product size of 80% passing (P80 of 166 mm) and a two stage SAG (with pebble crusher recycle)/ Ball milling in closed circuit with hydrocyclones to produce a P80 grind size of 75 micrometers. A gravity concentrator and Intensive Leach Reactor (ILR) have been included in the design as per the FS. The CIL circuit comprises eight CIL tanks (up from six in the FS) containing carbon for gold and silver adsorption with oxygen sparged from two 25 tonne PSA Oxygen plants  and a 18 tonne split Anglo (AARL) elution circuit. Electrowinning and induction furnace smelting completes the gold dor� production process. A cyanide detoxification and arsenic removal circuit is included in the process facility design, for treatment of process residue before discharge to the fully lined 57Mt Tailings Storage Facility (TSF), located adjacent to the processing facility. Feed water for the processing facility will come from various sources such as pit dewatering bores, the Cavally River for (make-up) and decant return from the TSF.

Table 6: Processing Schedule

 

Total

Y-1

Y-2

Y-3

Y-4

Y-5

Y-6

Y-7

Y-8

Y-9

Y-10

Y-11

Y-12

Y-13

Y-14

Ore processed, Mt

57.2

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

4.0

Grade processed, g/t Au

1.57

2.26

2.32

2.21

1.87

1.99

1.80

1.37

1.57

1.84

1.32

1.45

0.98

0.72

0.53

Recovery rate, %

86%

86%

84%

84%

88%

87%

87%

85%

80%

80%

93%

90%

90%

84%

86%

Recovered gold, koz

2,467

250

250

238

212

223

201

151

161

189

159

167

113

77

59

 

Metallurgy

The overall life of mine recovery rate increased from 83% in the Feasibility Study to 86% in the Optimized Study due to the addition of high-recovery Bakatouo oxide and fresh ore, Mont Ity ore and better recovery on Daapleu Sulphides following additional testwork.

Table 7: Gold Recovery Rate by Deposit

 

Bakatouo
Oxides/Fresh

Bakatouo
Transition

Daapleu
Sulphides

Daapleu
Oxides

Gbeitouo

Mont
Ity/Flat

Walter

Zia NE

Stockpiles

Total

LOM Tonnage, Mt

6.07

0.8

7.8

10.6

2.5

7.4

1.2

6.2

14.5

57.0

% of LOM Tonnage

11%

1%

14%

19%

4%

13%

2%

11%

25%

100%

Gold Grade, g/t Au

2.28

3.29

2.41

1.21

1.37

2.03

1.08

1.06

1.04

1.57

Gold Recovery rate, %

95/97%

84%

66%

85%

88%

89%

96%

97%

92%

86%

For the economic model, payable silver in the dor� ingots has been estimated on a conservative ratio of 2 to 1. A detailed investigation of the metallurgical response of the Bakatouo deposit was undertaken. Most samples showed high gold extractions but soluble copper levels were also high, particularly in the transition ore. As such, Endeavour has elected to blend in the soluble copper ore constraining it to 200ppm per feed blend. The Daapleu Primary ore can be considered refractory, with elevated Arsenic levels in the fresh ore, however it has negligible copper. Further detailed testwork has shown improvements, allowing the reported recovery for the higher Arsenic fresh material to increase to from 60% in the Feasibility Study to 66% in the Optimization Study. 


Low Operating Costs

The operating cost estimates have been re-scoped based on most recent available cost information and based on a 4mtpa processing operation. 

Table 8: Life of Mine Operating Costs in US$, estimated at � 15% accuracy

 

2017
OPTIMIZATION
STUDY

2016
FEASIBILITY 
STUDY

VARIANCE
(OS VS. FS)

Open Pit Mining and Rehandling, $/tonne moved

$2.89/t

$2.45/t

+18%

Processing, $/t milled

$11.96/t

$10.56/t

+13%

G&A costs, $/t milled

$2.23/t

$2.79/t

(20%)

Operating Cost, $/t milled

$22.90/t       

$20.56/t       

+11%       

Operating costs have been based on a delivered diesel price of $1.00/L and are in line with current local pricing. Following the connection to the grid, electricity costs have been estimated based on $0.1243/kWh.

 

PROJECT CAPEX SUMMARY

The optimized and fully scoped upfront capital cost has been re-estimated to reflect the upgrade project scope at $412 million, inclusive of $49 million for the owner-mining fleet and $34 million for contingencies, as summarised in the table below. The upfront capital is expected to be $351 million as a $61 million lease financing is expected to be put in place for the mining fleet and power station.

Table 9: Initial Capital Cost Estimate Summary (US$, �15%)

 

2017
OPTIMIZATION  STUDY

2016
FEASIBILITY STUDY

Treatment Plant

94

63

Reagents and Services

14

9

Infrastructure and Tailings

71

46

Mining (includes pre-striping and $49m for equipment)

84

59

Construction Distributables

26

24

Management Costs

17

16

Owners Project Costs

66

59

Owners Operations Costs

5

4

Sub-Total

378

282

Contingency

34

26

Total

 412

307

Capital costs include the construction of a 58 km, 91kv overhead power line, which connects to the national grid at Danane and terminates with a substation at Ity which will be owned by C�te d'Ivoire Energie ("CIE"). A full 26MW full high speed diesel back-up power station provides 100% redundancy. The infrastructure in place will be improved with roads upgraded to an all-weather and free draining carriageway to provide access for the delivery of equipment, materials and services to the site. A new camp will be built approximately 1 kilometer north-west of the process plant and will provide accommodation for 200 employees, and provisions have been made to construct a suitable airstrip.

A Cavally River diversion will be installed to allow development of the Daapleu pit, with a second diversion upstream of the Walter pit. Pit protection bunds will also be installed and a bridge/culvert road structure from Daapleu over the Cavally River will also be built.

The proposed approach to project implementation is similar in nature to the current execution methodology of the Endeavour Project Services In-House team in that Endeavour will engage a suitably qualified Engineering, Procurement and Construction Management (EPCM) Engineer for design and construction management of the process plant and infrastructure, which will then be handed over to an Owner's operating team. Endeavour will self-perform the development of the mine infrastructure and provision of ongoing drill and blast and mine operating services under an Owner's mine technical team.

The schedule anticipates the project being completed within 20 months from EPCM award.

 

PROJECT ECONOMICS

The results of the financial model show robust results. Applying a long term gold price of $1,250/oz on a flat line basis from the commencement of production, the after-tax NPV5% is $710 million, IRR is 40.3% and project payback period is 1.8 years. 

Table 10: Gold Price Sensitivity

Gold Price
 ($US/oz)

After-tax NPV ($m)

After-tax IRR

0%

5%

10%

$1,000/oz

520

343

221

23.2%

$1,050/oz

613

416

280

26.7%

$1,100/oz

707

489

339

30.2%

$1,150/oz

801

563

399

33.6%

$1,200/oz

896

636

458

36.9%

$1,250/oz

990

710

518

40.3%

$1,300/oz

1,072

773

569

43.1%

$1,350/oz

1,166

847

629

46.4%

$1,400/oz

1,260

920

688

49.6%

 

PROJECT IS FULLY FUNDED

As shown in Figure 1 below, the Ity CIL Project is fully funded with significant headroom available based on liquidity and funding sources available which include cash and undrawn upsized Revolving Credit Facility ("RCF"), the future cash generation from existing operating mines the upcoming proceeds from the sale of the Nzema mine, potential Ity power station and equipment financing, and the upcoming La Mancha anti-dilution equity placement.

Figure 1: Funding Sources

As was successfully implemented during the Hound� construction period, Endeavour will study the opportunity to put in place a short-term Gold Revenue Protection Strategy, consisting of Gold Option Contracts on only a portion of its production, to mitigating risk and increase the certainty of its upcoming free cash flow during its peak investment phase.

HEAP LEACH OPERATION

It is envisaged that the heap leach operation will run during the construction period and that heap leach activities will cease once the CIL plant is commissioned. Endeavour will reassess the risk and opportunity of running both operations in parallel once the CIL project has been developed.   

COMMUNITY AND SOCIAL RESPONSIBILITY ACTIONS

Endeavour recognizes that an active CSR program is the foundation of long-term success and its social license to operate. Baseline studies for the ESIA from 2013 to 2016 have been completed and an ESIA report was published in March 2016 and a Resettlement Action Plan ("RAP") has been completed.

Three environmental permits have been granted covering the mining and process plant, Daapleu and Gbeitouo exploitation and mining and surface infrastructure.

Full CSR team complement is now in place and working on establishing CSR best practices and reporting.

EXPLORATION POTENTIAL  

The Ity area has significant exploration potential with several deposits located within 5 kilometers of one another in addition to several exploration targets identified as per the blue dashed area in the Figure below. This area represents a small portion of the 80km corridor controlled by Endeavour.

Figure 2: Ity Mine Area and Surrounding Exploration Targets

 

ABOUT THE MINERAL RESERVES AND RESOURCES

The in situ Mineral Resources, which include Daapleu, Mont Ity / Ity Flat, Bakatouo, Gbeitouo, Walter, Zia NE and Colline Sud, have been reported inside optimised pit shells and above a 0.5 g/t Au cut-off. Reporting within an optimised pit shell satisfies the requirement for the Mineral Resource to have reasonable prospects for future economic extraction. The pit optimisation assumes a US$1,500/oz Au price.

The Mineral Resource for the rock dumps, which include the Teckraie and Verse Ouest Mineral Resources and also the Aires heap leach pad, have not been reported inside an optimised pit shell. These deposits have been built up above the existing topography and the associated shallow laterite located directly below, therefore satisfying the requirement for the Mineral Resource to have reasonable prospects for future economic extraction. The Teckraie and Verse Ouest rock dump Mineral Resources and Aires leach pad Mineral Resources have been reported above 0.0 g/t Au because there is unlikely to be any grade selectivity during mining. The underlying laterite Mineral Resources for each of the deposits has been reported above 0.5 g/t Au given the possibility for some mining selectivity. The Colline Sud deposit is expected to be mined during the heap leach phase and therefore has been excluded from CIL Mineral Reserves. All Mineral Resources are current as at April 30, 2017. Mineral resources which are not mineral reserves do not have demonstrated economic viability.

Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers.

The statistical analysis, geological modelling and resource estimation for Colline Sud were prepared by Kevin Harris, CPG. Mr. Harris is Endeavour Mining's Group Resource Manager and is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

The statistical analysis, geological modelling and resource estimation for Bakatouo, Mt Ity/Ity flat, Daapleu and Verse Ouest were prepared by Mark Zammit, CPG. Mr. Zammit is a principal consultant geologist with Cube Consulting Pty Ltd and is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

The statistical analysis, geological modelling and resource estimation for Bakatouo, Mt Ity/Ity flat, Daapleu, Gbeitouo, Walter, Zia NE. Aires and Verse Ouest were prepared by Mark Zammit, CPG. Mr. Zammit is a principal consultant geologist with Cube Consulting Pty Ltd and is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

The Qualified person for the Ity Mineral Reserve estimation is Mr Allan Earl AWASM FAusIMM. Mr. Earl is an executive consultant with Snowden Mining industry Consultants Pty Ltd and is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

A gold price of US$1,250/oz was used in the pit optimizations for Mineral Reserves. The estimation of break-even cut-off grades are based on net revenue (gold price x process recovery) and the throughput (ore related) costs.

QUALIFIED PERSONS

Jeremy Langford, Endeavour's Chief Operating Officer - Fellow of the Australasian Institute of Mining and Metallurgy - FAusIMM, is a Qualified Person under NI 43-101, and has reviewed and approved the operational analysis, operating and capital estimates, and other technical information in this news release.

 

 

 

CONFERENCE CALL AND LIVE WEBCAST FOR ITY CIL PROJECT

Management will host a conference call and live webcast today at 9:30am Toronto time (EST) to discuss the results of the Ity CIL Project Optimization Study.

 

The conference call and live webcast are scheduled at:

9:30am Toronto time

6:30am in Vancouver

9:30am in Toronto and New York

2:30pm in London

9:30pm in Hong Kong and Perth

 

The live webcast can be accessed through the following link:

https://edge.media-server.com/m6/p/44r6ckra

 

Analysts and interested investors are also invited to participate and ask questions using the dial-in numbers below:

International: +1646 254 3360

North American toll-free: 1877 280 2342

UK toll-free: 0800 279 4992

 

Confirmation code: 5815693

 

The conference call and webcast will be available for playback on Endeavour's website.

 

Click here to add Webcast reminder to Outlook Calendar

 

 


 

CONTACT INFORMATION

Martino De Ciccio

VP - Strategy & Investor Relations
+44 203 640 8665
mdeciccio@endeavourmining.com

DFH Public Affairs in Toronto

John Vincic, Senior Advisor
(416) 206-0118 x.224
jvincic@dfhpublicaffairs.com


Brunswick Group LLP in London

Carole Cable, Partner
+44 7974 982 458
ccable@brunswickgroup.com

 

ABOUT ENDEAVOUR MINING CORPORATION

Endeavour Mining is a TSX-listed intermediate gold producer, focused on developing a portfolio of high quality mines in the prolific West-African region, where it has established a solid operational and construction track record.

Endeavour is ideally positioned as the major pure West-African multi-operation gold mining company, operating 5 mines across C�te d'Ivoire (Agbaou and Ity), Burkina Faso (Karma), Mali (Tabakoto), and Ghana (Nzema). In 2017, it expects to produce between 500koz and 530koz at an AISC of US$855 to US$900/oz, following the full-year deconsolidation of the discontinued Nzema mine. Endeavour is currently building its Hound� project in Burkina Faso, which is expected to commence production in Q4-2017 and to become its flagship low-cost mine with an average annual production of 190koz at an AISC of US$709/oz over an initial 10-year mine life, based on reserves. The development of the Hound� and Ity CIL projects are expected to lift Endeavour's group production to +900kozpa and decrease its average AISC to circa $800/oz by 2019, while exploration aims to extend all mine lives to +10 years.

Corporate Office: 5 Young St, Kensington, London W8 5EH, UK   

This news release contains "forward-looking statements" including but not limited to, statements with respect to Endeavour's plans and operating performance, the estimation of mineral reserves and resources, the timing and amount of estimated future production, costs of future production, future capital expenditures, and the success of exploration activities.. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "expected", "budgeted", "forecasts", and "anticipates". Forward-looking statements, while based on management's best estimates and assumptions, are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the successful integration of acquisitions; risks related to international operations; risks related to general economic conditions and credit availability, actual results of current exploration activities, unanticipated reclamation expenses; changes in project parameters as plans continue to be refined; fluctuations in prices of metals including gold; fluctuations in foreign currency exchange rates, increases in market prices of mining consumables, possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; delays in the completion of development or construction activities, changes in national and local government regulation of mining operations, tax rules and regulations, and political and economic developments in countries in which Endeavour operates. Although Endeavour has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Please refer to Endeavour's most recent Annual Information Form filed under its profile at www.sedar.com for further information respecting the risks affecting Endeavour and its business. AISC, all-in sustaining costs at the mine level, cash costs, operating EBITDA, all-in sustaining margin, free cash flow, net free cash flow, free cash flow per share, net debt, and adjusted earnings are non-GAAP financial performance measures with no standard meaning under IFRS, further discussed in the section Non-GAAP Measures in the most recently filed Management Discussion and Analysis.


MINE PLAN

 



View News Release in PDF Format
View Presentation in PDF Format
View Funding Sources
View Ity Mine Area and Surrounding Exploration Targets
View Mine Plan




This announcement is distributed by Nasdaq Corporate Solutions (One Liberty Plaza, 165 Broadway, New York, NY 10006. Tel: +1 212 401 8700. www.nasdaqomx.com) on behalf of NASDAQ OMX Corporate Solutions clients. Source: Endeavour Mining, c/o Intertrust Corporate Services Limited 190 Elgin Avenue, George Town, Grand Cayman KY1-9005s, United Kingdom
If you would like to unsubscribe and stop receiving these e-mails click .

.
Data and Statistics for these countries : Burkina Faso | Ghana | Hong Kong | Mali | All
Gold and Silver Prices for these countries : Burkina Faso | Ghana | Hong Kong | Mali | All

Endeavour International Corporation

DEVELOPMENT STAGE
CODE : END
ISIN : US29259G2003
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Endeavour is a and oil development stage company based in United states of america.

Endeavour develops natural gas in U.k., and holds various exploration projects in Norway.

Its main asset in development is COLUMBUS in U.k. and its main exploration properties are NOATUN and ROCHELLE DISCOVERY in Norway.

Endeavour is listed in United States of America. Its market capitalisation is US$ 7.3 millions as of today (€ 5.8 millions).

Its stock quote reached its highest recent level on January 13, 2012 at US$ 9.99, and its lowest recent point on October 10, 2014 at US$ 0.15.

Endeavour has 47 200 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Endeavour International Corporation
9/3/2010Endeavour Merchant Bank Becomes Gold Producer
Financings of Endeavour International Corporation
7/11/2016Closes C$144 million Bought Deal Financing
Nominations of Endeavour International Corporation
10/3/2016appoints two new independent non-executive directors
6/5/2013Mining Reports Election Of Directors
4/2/2013Mining Appoints Ian Henderson to Board of Directors
3/22/2013Mining Announces Director Resignation Following Integration ...
6/8/2012Mining Appoints VP Investor Relations
11/7/2008announces resignation of U.S Global and appointment of new c...
Financials of Endeavour International Corporation
4/21/2016and True Gold Shareholders Approve Acquisition Transaction
11/6/2013Announces 2013 Third Quarter Financial and Operational Resul...
8/6/2013Announces 2013 Second Quarter Financial and Operational Resu...
7/30/2013Schedules 2013 Second Quarter Conference Call and Web Cast
5/9/2012Mining Delivers Strong First Quarter Results Including 49,53...
3/14/2012Mining Reports 2011 Financial Results
3/14/2012Mining Reports 2011 Financial Results And Demonstrates Signi...
8/10/2011Mining Reports Q2 2011 Cash Flow From Mine Operations
6/13/2011Mining Reports Q1 2011 Cash Flow From Mine Operations
3/22/2011Mining Reports Net Income Of $9.6 Million
2/9/2009REPORTS FINANCIAL RESULTS FOR QUARTER ENDED DECEMBER 31, 20...
11/13/2008REPORTS FINANCIAL RESULTS FOR QUARTER ENDED SEPTEMBER 30, 20...
8/22/2008Release Financial Results
Project news of Endeavour International Corporation
4/26/2016Completes Acquisition of True Gold
1/27/2014Mining Declares Commercial Production at Agbaou and Signs Co...
11/29/2013Mining Pours First Gold Bar at Agbaou Mine Ahead of Schedule
11/13/2013Completes Sale and Forms Joint Venture with Samson Explorati...
11/13/2013Mining Reports Record Q3 Gold Production of 88,445 oz and Al...
11/6/2013Mining Announces Positive Feasibility Study ForHound=E9 Gold...
8/6/2013Mining Reports Delivery of Mining Equipment at Agbaou Gold M...
6/25/2013Mining Reports Tabakoto Mill Expansion Achieves Design Capac...
6/12/2013Mining Reports Delivery of Mills at Agbaou Gold Mine and Ach...
4/24/2013Mining Reports Agbaou Gold Mine Construction Progress
1/22/2013Mining Delivers 310,000 Oz Gold Production and Provides 2013...
1/22/2013Mining Delivers 310,000 Oz Gold Production Exceeding 2012 Gu...
10/18/2012Mining closes Avion Acquisition and announces new Board Memb...
10/1/2012Mining Announces ISS and Glass Lewis Recommend in Favour of ...
9/20/2012Mining Announces Full and Final Settlement With Gold Reserve
9/7/2012Mining Drilling At Agbaou Demonstrates Potential For Pit Exp...
7/16/2012Mining Delivers 102,691 Oz of Gold Production in First Half ...
7/13/2012Mining Files Technical Report For Agbaou Gold Project
6/11/2012Agbaou Gold Project enters construction with planned 103,000...
6/11/2012Agbaou Gold Project Enters Construction
5/11/2012Mining Discovers New Oxide Zones at Nzema Gold Mine
5/3/2012Expands Nzema Sulphide Program And Initiates Preliminary Eco...
3/20/2012Goals Met, New Targets Set: Endeavour Mining Earns an A+ For...
3/20/2012Canaccord Genuity Issues $4.00 Target on Endeavour Mining
3/6/2012Mining Sells 40% Interest in Finkolo JV for US$20 Million Ca...
2/23/2012Near-Mine Exploration Programs Yield Strong Results for Ende...
12/19/2011Mining And Adamus Resources Complete Merger
12/5/2011Mining Merger With Adamus Resources Has Become Effective
9/12/2011Mining Reports Positive Drill Results at Agbaou Including 10...
9/12/2011Mining Reports Positive Drill Results at Agbaou
8/22/2011Mining and Adamus Resources to Merge
8/3/2011Mining Reports Exploration Results At C=F4te D'Ivoire Develo...
Corporate news of Endeavour International Corporation
7/26/2016to Announce its Q2 Results on Thursday July 28, 2016
5/9/2016Announces Governance Changes
2/26/2014Issues Statement Regarding Nomination Notice by Stockholders
1/30/2014Mining Delivers 324,275 oz in 2013 and Forecasts 400,000 to ...
1/27/2014Announces Closing of $255 Million Senior Secured First Lien ...
1/6/2014Announces Intention to Refinance Revolving Credit Facility a...
12/3/2013Mining Files Technical Report For Hound=E9 GoldProject Feasi...
11/4/2013Mining to Release Q3 Results on November 12, 2013
10/28/2013Mining Closes Sale of Non-Core Finkolo JV and Receives $16 M...
10/22/2013Announces Completion of Strategic Review, Organizational Cha...
10/15/2013Mining Initiates Mining at Agbaou and Completes Power Line I...
8/7/2013Mining To Release Q2 Results On August 14, 2013
7/24/2013Mining Increases And Extends Debt Facility To Strengthen Fin...
7/18/2013Business Excellence features Endeavour Mining in July 2013 i...
5/15/2013Mining Reports Q1 All-In Sustaining Margin Of $39 Million An...
5/6/2013Mining to Release Q1 Results on May 14, 2013
4/30/2013Mining Sells Non-Core Rare Earths Shareholding For US$5.3M C...
3/27/2013Mining Reports 2012 All-In Margin of $130 Million and Update...
3/20/2013Mining To Release 2012 Year-End Results On March 28, 2013
3/13/2013Mining's Agbaou Construction Continues on Schedule
3/12/2013Mining Files Hound=E9 PEA=2C Completes In-FillDrilling And ...
1/22/2013Mining Announces Positive PEA for Hound=E9 GoldProject
11/8/2012Mining To Release Q3 Results On November 14, 2012
10/12/2012Mining Shareholders Approve Avion Acquisition to Grow Gold P...
8/27/2012Receives Encouraging Drill Results from PEA-Stage Ouar=E9 Pr...
8/27/2012Bids for Avion
8/15/2012Mining Granted Mining Permit for Agbaou Gold Project
8/8/2012MINING TO ACQUIRE AVION GOLD
8/8/2012Mining Reports Strong Q2, with Cash Flow of $47.6 Million fr...
8/3/2012Mining Q2 Webcast Moved To August 9
8/1/2012Mining to Release Q2 Results on August 7
6/28/2012Completes Ouar=E9 Drilling and Commences Resource Update for...
6/21/2012Mining in Gold Newsletter
6/1/2012Digs Deeper, Brings Strong Gold Results from Youga
5/28/2012Positive Drilling Results from Endeavour's Youga Gold Mine
5/4/2012Mining To Release Q1 Results On May 8th, 2012
5/2/2012Expands Nzema Sulphide Program
4/30/2012Strong drilling results from Endeavour Mining's Youga Gold M...
4/19/2012Buy Recommendation for Endeavour Mining
4/2/2012Mining Commences Trading in the U.S. on OTCQX International
3/26/2012Mining Corp. on the Way Up with 3 Mines and 3 Triangles
3/22/2012Five Things to Love About Endeavour Mining
3/8/2012Mining to Release Year End Results on March 13, 2012
3/7/2012VIDEO CORRECTION - Endeavour Mining CEO on BNN
3/7/2012Mining CEO on BNN
3/4/2012Mining Completes Salman Village Resettlement In Ghana
2/2/2012Mining Meets 2011 Gold Production Targets
1/30/2012Mining Reports Q4 and Full Year 2011 Gold Production and 201...
1/30/2012Mining Reports Q4 and Full Year 2011 Gold Production
1/27/2012Mining in Globe and Mail
1/10/2012Mining in Gold Newsletter
11/29/2011Mining Closeout Of Youga Gold Hedge Book
11/28/2011Mining on BNN's Market Call
11/25/2011Mining Shareholders Approve Merger With Adamus
10/13/2011Mining Reports Closing of Sale of Non-Core Diamond Assets an...
10/13/2011Mining Reports Closing Of Sale Of Non-Core Diamond Assets
9/20/2011Mining In Gold Newsletter
9/19/2011Mining Reports Positive Exploration Results at Youga Includi...
9/8/2011Mining in Winston's Growth Stock Report
8/31/2011Two West African Gold Producers Merge - Endeavour Mining
8/26/2011MD/CEO Mark Connelly discusses Adamus' Merger of Equals with...
8/25/2011Mining To Merge With Adamus
8/18/2011Junior Gold Producers Rising to the Occasion - Endeavour Min...
8/15/2011Mining's Profit Rises on Higher Gold Output, Prices
8/11/2011Mining Corp. is Moving Toward Mid Tier Gold Producer Status
8/8/2011Mining - A Deep Discounted Emerging Gold Producer
8/4/2011Mining To Release Second Quarter 2011 Results On August 10, ...
6/10/2011to Release First Quarter 2011 Results on June 13, 2011
6/28/2010ANNOUNCES SIGNING OF $100 MILLION ACQUISITION FACILITY WITH...
6/11/2010and Severstal Find Synergy In Crew Gold: MineralSTOX
6/2/2010Severstal & Endeavour Reach Agreement for Building Value in ...
10/14/2009Appointed as Project Finance Advisor
2/23/2009Financing Highlights Investors Moving into Gold - Midas Lett...
1/19/2009DECLARES MONTHLY DIVIDEND FOR JANUARY 2009
12/17/2008DECLARES MONTHLY DIVIDEND FOR DECEMBER 2008
11/3/2008to Release Q1 Results November 12, 2008
9/4/2008REPORTS NET INCOME OF US$56.5 MILLION FOR YEAR ENDED JUNE 30...
8/12/2008Declares Monthly Dividend for August 2008
7/14/2008Declares Monthly Dividend for July 2008
5/12/2008 DECLARES MONTHLY DIVIDEND FOR MAY 2008
4/12/2008Declares Monthly Dividend for April 2008
3/13/2008Declares Monthly Dividend for March 2008
5/24/2007Acquires Remaining 49% Interest In Guanacevi Mines Project, ...
5/2/2007 Closes Acquisition of Bolanitos Exploitation Contracts; Ann...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AMEX (END)
0.155-16.26%
AMEX
US$ 0.155
10/07 16:07 -0.030
-16.26%
Prev close Open
0.185 0.180
Low High
0.150 0.190
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.155 -3.12%
Volume 1 month var.
415,127 -3.12%
24hGold TrendPower© : -34
Produces
Develops Natural gas - Oil
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.84+1.75%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.28-0.39%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.71+4.41%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.65+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.18+1.47%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22+7.50%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.91-4.02%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 50.06-1.54%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04-5.26%Trend Power :